Professional Documents
Culture Documents
Presentation On T4S
Presentation On T4S
Presentation
AMPY Pipeline Solutions LLP
Adding Values through Audits & Inspections
Critical Observations / Findings (PPL)
Non-availability of construction related documents
The detail of dwelling unit or permanent structures is available for ROW but
not for 15M either side of the pipeline
There is no provision of station limit valve in NGPL like PPL to isolate the
complete station during any emergency- Regulation is to be amended
A time limit should be fixed for first audit from the date of Notification of a
T4S Regulation
6th Capability Building workshop on
PNGRB T4S and IMS Regulations for
Empanelled TPIAs
Entity has not confirms Impact value for 2 NPS Pipe
At Railway crossing, observed TLP PSP reading was taken
on one side as second side not accessible.
Domestic consumers, condition of rubber hose to the burners
was found very bad and in brittle condition. Also, observed
validity of the rubber hose has expired.
Laid steel network at CGS including DRS - Material & NDT
records not traceable to ascertain integrity of pipeline
sections in conformity to design standards.
Observations / Findings – for 2018-19
SINCE 1950
For PE fittings, test certificates following records not evidenced,
1. Polyethylene resins used for thermoplastic fittings is virgin,
2. Cadmium free pigmented compound.
3. Anti-oxidant and UV Stabilizers should not exceed 0.3 and
0.5 percent respectively
Recommendations
SINCE 1950
7 Earth pit resistance i.e. for individual electrode and for grid was mentioned on the cover plate.
The grid resistance was different on different Plates. It could not be verified on site.
8 Double earthing was not found on 3-phase, 415 V Motor connected to Air Compressor.
12 Odoriser dosing rate at CGS found non constituent. To ensure to get desired ethyl mercaptan
smell at the farthest point.
13 Approach road from road to CGS station not properly maintained.
21 DMP Organogram with roles & responsibilities not displayed at CNG Station.
23 Identification of Emergency push button of compressor-1 and compressor-2 was not mentioned
at CNG Station Control Room.
24 Hydro test plate on all the CNG Vehicles not checked for validity of Cylinders before filling gas.
25 First Aid box not properly maintained. List of items not available.
29 The pipe through wall was not passing through sleeve in many Commercial Customers.
30 Gas detectors with hooter/siren not provided in DRS located in residential area.
34 CO2 Cylinders of both CNG Compressors at some of CNG Station -Weight Gauge Glass is
blurred and needs replacement.
35 Cross-over to be provided over the Incoming header PL to DRS Inlet.
Markers / Warning Signs – Not installed in urban areas and industrial parks.
Observations / Findings
Critical observations for CGD-
At City Gas Station:
•Online odorization equipment is installed and maintained by OEM. As per record, 10 ppm is
dozed but display is not available. Shade is not provided for online odorization equipment.
Odorant absorber such as activated carbon saw dust and odorant neutralizer are not available.
Industrial Consumers :
• Fencing is not provided for IPRS installation.
• Warning sign board is not provided.
Instead of City Gas entities float their separate tenders, PNGRB should provide
the single platform or web portal to all the City Gas entities where they can share
the requirement for conducting the T4S audit.
Audit duration (number of days) should be specific for each entity based upon the
the assets available. Some methodology should be developed to calculate the
minimum number of days required to conduct the T4S audit.
MOODY INTERNATIONAL INDIA PVT. LTD.
INDUSTRY SERVICE DIVISION
Third Party Inspection Service in T4S Audit of CGD &
NGPL
by:
SIBENDRANATH ROY, J N AGRAWAL & AJAI SRIVASTAV
28 Jan 2021
Major Recommendations for CGD
Sl No Recommendations
1 Gas detectors should be provided inside DRS/IDRS installations
2 GIS based asset management system should be available for CGD network
4 Off potential measurement should be taken once in a year for steel pipeline
5 Earthing of chain link fencing and gate should be done at installations
6 Valves should be placed at an interval of 1 Km for PE pipe
Boundary wall height should be extended to minimum 3 meter and 0.3 meter barbed wire on top of
7
boundary wall should be provided
8 Surge diverters should be provided across IJ
NABL accreditation for outsourced agencies engaged in calibration of instruments and masters should be
9
available with the entity
10 Coating repair should be done on the basis of CIPL and DCVG survey
Major recommendations for NGPL
Sl No Recommendations
1 Continuity of flanges should be maintained
3 The minimum distance of 5 meter should be maintained from boundary wall to QOEC and scrapper
barrel.
4 Painting of above ground piping should be done
5 QOEC line should be replaced or risk assessment should be done for pressure classification as it is
lesser than minimum one third of main line.
6 Point support for piping should be rectified
7 NABL accreditation for outsourced agencies engaged in calibration of instruments and masters should
be available with the entity
8 Gate and barbed wire fencing should be earthed.
9 LEL detectors should be provided at IP stations and terminals
10 Pipe of thickness lesser than minimum 6.4 mm is required to be replaced.
Key concerns and suggestions for strengthening the
certification/ compliance process
Sl No Concerns Suggestions
Time is a constraint for quality audit as Benchmark should be made for minimum time to carry out
1 schedule is not mentioned in tender by clients audit of installations
A time bound rectification measures is not at A time bound rectification process or taking deviation
2 place. Audit observations are carried forward should be in place and carried out before next audit.
or no deviation is taken Defaulter entity should be penalized.
Design documents and records are mostly not In such cases, guidelines may be issued or amended as
3 available for old pipelines per requirement.
Extent of checks ( % of Qty ) of the installation In such cases, guidelines may be issued or amended as
4 is not mentioned by Clients in most of the cases per requirement.
Non-compliance to T4S regulations emerge TPIA engaged in supervising construction work should also
5 from lapses in TPIA supervision of construction be checked by PNGRB for quality output
work
PHISTREAM CONSULTING PRIVATE
LIMITED
• The Pressure Reduction skid at CGS does not have Active/monitor combination with a minimum 50% redundancy
•NC- including slam shut valve for over-protection (Ref Schedule 1D, iv) of PNGRB T4S Standards).
01:
• The On-line odourization equipment designed to minimize fugitive emissions during loading, operation and
NC- maintenance is not installed at the CGS (Ref Schedule 1D, iv) of PNGRB T4S Standards).Hence, the 2.7 Km Steel
02: Pipeline is without odorant.
• Gas Detectors are not installed at CGS (Ref Schedule 1D of PNGRB T4S Standards, Network
NC- Design Requirements, City Gate Stations)
03:
NC-
04:
• Gas Detectors, Flame Detectors and Carbon-di-oxide flooding system installed in the CNG
NC-05 Compressors at Mother Station are not in working condition.
(a):
37
NON – CONFORMITY
• Gas Detectors and Flame Detectors are not installed at the CNG Booster Compressors. Carbon-di-oxide flooding system at CNG
NC-05 Booster compressors is not in working condition (Ref Point No 12 of PNGRB Approved Check List TPCA for CNG Stations).
(b):
• No evidence of external safety audit found (Ref Point No 13 of PNGRB Approved Check List
NC- TPCA for Safety).
06:
• Internal Audit observations of internal audit are not closed (Ref Point No 12 of PNGRB
NC- Approved Check List TPCA for Safety).
07:
AREA OF IMPROVEMENT
38
• The TCP system of the 2.7 Kms Pipe line needs to be converted to PCP system for better control of the CP system
• As the Pipeline is more than 15 years old Caliper survey, CAT/DCVG survey are required to be done for assessment of
internal condition & external Coating condition of the Pipeline
• General housekeeping & condition of Electrical panel room in dealer maintained DBS (inspected by the Audit team) needs to
be improved
• Critical F/F equipment i.e. CO2 flooding system is not operational, requires immediate restoration
• Gas Detectors and Flame Detectors are not installed at the CNG Booster Compressors. Carbon-di-oxide flooding system at
CNG Booster compressors is not in working condition (Ref Point No 12 of PNGRB Approved Check List TPCA for CNG Stations).
Quality Services and Solutions Pvt Ltd
By Jayant Nabar
Observations / Findings
• Critical Observation for PPPL
1. Few valves at inlet manifold of Booster pump house and pig launching valves (HOV)are with welded ends
in Pump Station
2. It has been observed that mitre bends are used at suction line of booster pump area in PL. Since, Pipeline
is old pipeline before PNGRB T4S regulations.
3. As per test record of DCP Fire extinguisher no. D1, D6, D7, D13 & D19 failed in HT, carried out on
17.01.19.
4. Test record for radiography, ultrasonic test or other applicable NDT methods (as carried out before
commissioning) was not available.
Hydro-test (as carried out before commissioning) Report was not available.
5. Inter distance between Booster Pump Shed and Scrapper Launcher or Receiver not maintained as per
PNGRB regulation also found two nos. air receiver vessels between these two sheds, making the area mostly
hazardous.
Quality Services and Solutions Pvt Ltd
7. LPBS for MOV 211, MOV 104., 63 Amp Welding switch socket Body earthing is provided, but terminated at
LPBS Canopy instead of LPBS BODY; It is not effective earthing for the LPBS. More over LPBS Canopy is badly
corroded, earth connections are badly rusted.
8. Three Marshalling JBs are installed & are in service, Flame Proof /EXD Type. No any tag identification on the
JBs. Middle JB, One No cable entry is open/unplugged. One of the JB Cover is half closed
9.JB cover for all the JBs are almost 75 % open, No earthing Provided, No any type tags provided for identification
and supporting frame is badly rusted.
10. All other Electrical Motors, MOVs in the same area Power cables are connected without any kind of straight
through joint. The MOVs located are hardly 350-400 Meter distance from Electrical Substation.
11. Amp flame proof Switch socket installed near MOV 305 , found with No Identification Tag , Input power source
also not mentioned , Allen bolts missing, Spare cable entry hole found unplugged.
Quality Services and Solutions Pvt Ltd
4.QOEC line has been observed lesser than 1/3rd of main line.
5.None of the earth pits were painted with the test date every 6 months with date and resistance value ,
so could not be identified.
8.Thickness measuring locations on the piping and pressure vessels are not marked and numbered
9.Pipeline flanges of PCV -102 ,kickoff line are short bolted and one stud of PSV -102 flange is missing
Quality Services and Solutions Pvt Ltd
1. Air Compressor rooms within Fenced area of CGS’s, and other electrical
fittings are with Non FLP equipment and accessories.
2. Original Pipe Book pertaining to the commissioning of GA’s not available
3. Most of the Cascade LCVs in all GA areas not fitted with spark arrestors
4. Fire Extinuishers maintenance and records are grossly inadequate
5. ERDMP manuals are required to be LOCATION specific not GA specific
6. Gas receipt /dispatch balancing not being done at all
7. Odourant reconciliation not being done/ records not available
8. Lightening arrestors provided at are in adequate. Equipment protection not
available. To be provided in line with IS 2039
9. For domestic connections , in buildings , Secondary pressure of approx. 4 bar
is taken upto the building, UG, and crimped to risers upto the regulator
reducing pressure from 4 bar to 21 mbar with no regulator inside the customer
premises. This is unsafe , and pressure at appliance should be ensured a
pressure of 21mbar , even if only 5 floors height are involved. As per PNGRB
tertiary lines to be of 100mb only
10. Boundary walls at all location not as per MHA guidelines
11. Checking of gas leakages in Steel/MDPE pipelines in congested areas not
being done .
12. All Equipment earthing not at two independent points , with proper earthng
strip and not flexible.
Quality Services and Solutions Pvt Ltd
WAY FORWARD
1. In CGD networks PCP has not been installed even after completion of 2 years.
2. Proper maintenance of API 6D/ API 600 Gate/ Ball/ Plug valves is not carried out.
4 Work Permit System to be followed strictly in line with the regulatory requirements.
48
Way Forward
49
SGS Presentation
WORKSHOP ON CAPACITY BUILDING OF
THIRD PARTY INSPECTION AGENCIES
■ SOP for Odorization Unit, Do’s and Don’ts at Odorization Unit is not displayed.
■ PPEs is not available at All Odorant Station as per PNGRB T4S Requirements.
■ GAP Analysis of CGD System of Gasified Areas are not done after commissioning.
■ High Consequential Areas of Various GAs are not identified location wises.
■ No internal audit has been done after commissioning.
Key Observations/Findings of IMS audit of CGD
Network
■ Most of the MDPE Valve Chamber observed without any Tagging on it. Valve Chamber tagging to
be done as GIS Mapping and Final As-Built Drawing.
■ Fire Mock drill with fire in tea shop opposite RO was carried out and major observations are given
below:
■ Action to be taken in such scenario was not known to the In-charge of RO.
■ There is no role clarity.
■ Such Mock Drill has not been carried out by BPCL / SGL any time in the past.
■ ERV response time: 45 mins.
■ Incoming vehicle entry barrier placed after 10 mins.
■ Fuel filling was not stopped.
Recommendations for CGD
Entities shall impart T4S & IMS related awareness training to all his
employees as well as Contractor’s employees also
Regular monitoring shall be done for pipeline corrosion, painting of
aboveground p/l & replacement of galvanized fasteners.
Entity should use megaphone at every CNG Station for communication
during emergency.
Entity should provide proper technical training to all contractor’s operators
as well as evaluating their skills after training completion.
Highly congested areas shall be surveyed using gas detectors at least once
in 03 months.
Continuous monitoring shall be done to avoid temporary encroachment on
P/L route & near railway crossings.
Recommendations for CGD
CGD shall ensure the 100% usage of Reinforced
rubber hoses conforming to IS 9573 Type II for all
domestic, commercial customers.
CNG Filling operators shall be rigorously trained to
verify CNG kit nameplate & hydrotest due date of
CNG cylinder.
Safety Guards shall be provided for the dispenser units
at CNG stations.
Recommendations for NG Pipeline
Entities shall ensure continuous monitoring to avoid temporary
encroachment on P/L route & near railway crossings.
Entities shall maintain Cathodic Protection system for complete
pipeline.
Required distance shall be maintained between two isolation valves.
Pipeline construction records i.e. RT films, pipe book, as-built
drawings, hydrotest reports shall be maintained in all respect.
Way forward
Key suggestions for strengthening the certification/
compliance process
TPIA should have enough past experience in Pipeline laying of CGD/NG(Cross Country),
Procurement inspections of CGD/NG network.
TPIA should follow the competency criteria set by PNGRB/NABCB for audit team.
Vendors are not observing, in some cases, the requirements of PNGRB Pipelines
should not be laid within specified distance from Electrical Wires/ Installations.
In such cases, they are putting Insulation material around pipeline and offering
installation for clearance. There is no PNGRB guidelines to resolve such
situations.
Welders deployed by vendors in CGD Pipelines, are having cards in which
details like Position, Diameter, Procedure , welding parameters used during
their qualification, are missing. These details are required to be verified during
progress,of actual erection work.
General Observations / Findings /Recommendations
Vendors are generally avoiding the stage of Hydro test before installation
under Railway Lines, Road crossings etc. as per PNGRB regulations.
Vendor is not arranging Pressure and Time recorder for TPI review during 24
HRS. Hydro testing of NGPL Pipelines, which is a requirement as per PNGRB
regulations.
Vendor tend to use ASME Section IX for welding whereas specified as per
PNGRB , API Code is applicable.
Pneumatic Testing of RF pads is generally not specified in drawings and also
not in procedures, which should be tested to ensure leak-proof sound material
below RF Pad Plates at branch locations.
Way forward
More workshops on auditing as per requirements of PNGRB and it’s
revisions.
Spread more awareness about PNGRB regulation requirements in
industry.
Add requirements for training and qualification of contractor’s
personnel regarding PNGRB and Standard requirement.
Providing structured document flow / linkage information about various
PNGRB , Code and Standard requirement.
Indian industry should come with indigenised products for gas networks.
6th Workshop on Capacity Building
TÜV SÜD South Asia 21-01-11 Slide
Recommendation / Suggestion
in PNGRB Workshop
• Mandatory stock for spare hoses, nozzles & DCP are not
available.
• CP monitoring records for Cathodic protection was not made
available.
• Report on effect of interference of Pipelines on Pipelines and
was not made available.
Key Concerns for T4S CGD Audit -
• Audit Man days estimation is concern for T4S audits for some of the CGD
networks more than 10 years old because of their size of operations.
• The T4S CGD audit scope for construction activities is a concern. For auditing
Construction scope, whether to audit construction activities only for the
period from the last audit or from the start of CGD.
Ship Berthing Safety Checks in field Cleaning pigging to be done as per recommended periodicity
Unloading Arm Hook/Emergency Release Coupler fixing as per
gas discharge through vent lines are to be made vertically upwards
Standard SOP
Avoid Roll over during filling into LNG Tanks by density Alternate communication for remote valve isolation in case of OFC
measurement Cable snapping .
Emergency Shutdown System Checking before unloading for Jetty Station venting QOEC piping to be made of atleast 1/3rd of Station
Operations maximum dia piping
Valve passing in the pig launcher/ receiver barrel Surge divertors at IJ to be tested for its working condition
Piping external corrosion at locations of pipe support SOP for various field equipments to be displayed at field
Incident reporting / Investigation/ Analysis/ Safety Interlocks Change Management Procedure and P & ID updation
Any metal pipeline waiting for commissioning filled with pressurized water dosed with corrosion inhibitors (Cathodic
protection in service) should be monitored by 2 different departments so that line integrity is maintained till full
commissioning takes place
Observations and Recommendations– CGD Sector
Observations and Recommendations– CGD Sector
Gas detectors are to be installed at DRS.
At Odorisation unit & industrial connection, observed that the electric cable was laid on the walkway – Cable tray to be provided.
PNGRB not defined guidelines on mandays to be spent sector wise during onsite visit for T4S and IMS audits
PNGRB should allow TPIAs if they want to depute full time working employee of mutual aid firm of client of TPIA to visit and
carryout onsite visit on behalf of TPIA.
Recertification Period of three years is long period it should be reduced to as much as possible to strengthen certification
process.
Entities are not able to approach TPIAs as their contact details are not posted on PNGRB website.
PNGRB should directly give work order to TPIAs to cross audit or carryout surprise Audits if they feel that particular entity is not complying to
safety minimum safety standards
THANK YOU