Issuance of Environmental Sanitation Clearance (ESC)
Environmental Sanitation Clearance (ESC) is issued by the DOH Regional Office
allowing the collection, handling, transport, treatment and disposal of domestic sludge or septage for mobile and/or stationary.
Office or Division: Local Health Support Division
Classification: Highly Technical Type of G2B – Government to Business and Transaction: G2G – Government to Government Who may avail: All entities / Owners/Operators/Developers who wanted to establish collection, handling, transport, treatment and disposal of domestic sludge or septage (mobile and/or stationary). CHECKLIST OF REQUIREMENTS WHERE TO SECURE For both Mobile Service and Stationary Service 1. Notarized application Requesting Party (1 original, 3 photocopy) 2. Report of Inspections, Local Health Office recommendations and findings from the LGU concerned (through local health office) (1 original, 3 photocopy) 3. Report of validation and site evaluation DOH Regional Office and Provincial Health Office conducted by the CHD Regional Office in coordination with the concerned Provincial Health Office (1 original, 3 photocopy) Representative Authorization Letter (1 original) Owners / Operators/ Developers Any government valid ID both from the Post Office, DFA, PSA, SSS, GSIS, Senior owner and the representative Citizen’s Office, Pag-ibig, COMELEC, LTO, PRC, (1 original, 1 photocopy) NBI, PhilHealth, BIR AGENCY FEES TO PROCESSING PERSON CLIENT STEPS ACTIONS BE PAID TIME RESPONSIBLE 1. Coordinate and 1.1 Receives and None 40 minutes Designated Staff Submit Notarized evaluates the EOH Application Form application for its including correctness and documentary completeness of requirements the necessary (c/o Local Health documents Office) forwarded by the local health office 1.2 Receives and None 5 minutes Administrative logs Aide VI Central Receiving 1.3 Tabletop None 5 days Regional Sanitary evaluation of the Engineer application EOH
1.4 Schedules the None 3 days Designated Staff
inspection/ EOH evaluation and prepares Office Order/ travel documents and inform the establishment of the inspection 1.5 Conducts None 1 day Regional Sanitary inspection/ (excludes travel Engineer evaluation visit time) EOH
1.6 Prepares and None 2 days Regional Sanitary
process inspection/ Engineer evaluation report EOH
1.7 Issues Order of None 10 minutes Designated Staff
Payment EOH 2. Pays the amount 2.1 Accepts and Clearance 20 minutes Administrative due reflected in issue official Fee: Assistant III the Order of receipt based on Mobile and Cashier Payment to the the amount Stationary - Cashier’s Office reflected in the PHP Order of 2,800.00 Payment Combined- PHP 3,000.00 3. Submits copy of 3.1 Receives and None 5 minutes Designated Staff Official Receipt logs EOH of payment at the EOH office 3.2 Prepares None 1 day Regional Sanitary Environmental Engineer Sanitation EOH Clearance (ESC) 3.3 Recommends None 1 day Medical Officer V the Approval of LHSD Chief ESC Office 3.4 Signs the ESC None 10 minutes Regional Director RD’s Office 4. Receives 4.1 Releases the None 15 minutes Administrative Approved ESC Approved ESC Aide VI Records Section TOTAL Clearance 13 days, 1 Fee: hour, 45 Mobile and minutes Stationary - PHP 2,800.00