JSA (Job Safety Analysis) Sheet

Activity Name:-Welding works Ref-

Location:- Date :

Sr.No. Sub-Activity Name Type Of Hazard Risk(s) Involved Risk Control measures
Only inducted worker shall be deputed at the work place.
1 Manpower Mobilization Untrained worker Personal injury
Given Tool Box Talk to all workers.
Use of proper PPEs as per SPCL safety norms- shoes safety helmet safety goggle
Barricading of work highlighter jacket
2 Personal injury Major burns
area Whole area under working will be properly barricaded
No any unauthorized material to be kept inside barricading area
Use of proper PPEs as per SPCL norms.Only SPCL approved scaffolds to be used for
working at height, Trained persons to be deployed at work competent supervisor to be
present at all time.
For continuous protection double lanyard belt to be used. worker to tie his safety belt to
lifeline or nearest scaffold.
Electric Shock, Fire Use of good insulation of welding supply & erecting cable.
Connection of welding
Burns,Toxic Joint free cable to be used
3 cable to power socket Injury/Death
Fumes,Explodification Approved welding machine to be used
earth & welding work.
Hot work permit to be taken from concern project and safety dept.
Proper earthing to welding machine.
Remove all flammable & combustible materiel from work area.
Fire bucket to be kept available near by working area.
Welding shield to be used for welding
Night work permit to be taken from concern engg.and safety dept.
Darkness, fall of
Work during dark Personal injury, Ensure proper illumination during dark hours.
4 person, fall of
hours damage to property Electrical cable should lead min 2 m height. No exposed electrical wire.Earthing.
machinery
Route shall be illuminated.

Name & Signature of Site Engineer / Supervisor :___________ Name & Signature of Site In-charge :___________