Professional Documents
Culture Documents
HIRA
No.: HIRA 026 RISK ASSESSMENT: Working at Height AREA / PROJECT: Mohammed Bin Salman City- Al Mishraq
All tasks related to working at height i.e. concrete pouring, TOOLS & CLIENT: Mohammed Bin Salman City
TASK / OPERATION / Various hand tools, power tools, steel cutters, concrete
ACTIVITY DESCRIPTION: steel fixing, formwork, precast panel placing, erection of EQUIPMENT IN
USE: vibrators, electrical equipment, etc. IMPL. DATE: 2023.02.15
scaffold and platforms, etc.
Risk Assessment Committee (To consist of OHS&E The purpose of this Risk Assessment is to identify all possible hazards and risks associated with the works
Manager, CM, Site Engineer and representative for CONSEQUENCE (C) and to identify mitigation and preventative control measures.
workforce) RISK RATING =
LIKELIHOOD x
CONSEQUENCE
Name Signature 5 4 3 2 1
Ammar Alali 4 20 16 12 8 4
CJ Dempers 3 15 12 9 6 3
Rajesh Marath 2 10 8 6 4 2
1 5 4 3 2 1
Approved By Project
Signature
Manager/Coordinator
Omar Balkhi
5 CONTINUOUSLY (DAILY) 5 DISASTER MORE THAN ONE DEATH LOSS OR INJURY ≥ SR 100K
1|Page
Document Reference
Saudi Constructioneers Ltd.
MC-SC-HSE-HIRA-026
Dated: 2023.02.12
A B C A B C
TASK HAZARDS ASSOCIATED WHO CAN BE AFFECTED BY
RISK RATING
RISK RATING
Ser
(What one does in logical WITH EACH TASK THE RISKS (per hazard and HARM / CONSEQUENCE WITH CONTROLS
CONSEQUENCE
CONSEQUENCE
No.
LIKELIHOOD
LIKELIHOOD
RISK SCORE
RISK SCORE
steps) (What can cause harm?) risks identified) (What can happen /
go wrong?)
High
Low
1. 5 5 25 3 2 6
permanent / vehicle Collision with Workers and fatality. • ADDITIONAL & or SITE CONTROLS
temporary constructed scaffold and platform. Visitors Property damage. • Conduct TBT training to include the use of scaffolding.
horizontal surfaces,
• Hard / Sufficient protection of scaffold / platform areas and braces
etc.
be protected from vehicular movement.
• Prevent the movement of mobile equipment adjacent to erected
scaffold / platforms.
• Only competent scaffold erectors allowed to erect scaffolding.
• Support scaffolding for temporary works to be designed and
checked by competent personnel.
• Weekly inspections, check sheets and scaffold tags to be in place /
Client, Consultants Lacerations, cuts, conducted.
Failure or collapse of • Scaffold inspector to inspect scaffolding before use, and weekly
Supervision fracture, disability
High
Low
scaffold platform on 5 5 25 2 2 4
Workers and fatality. when in use. "Scafftag" marker use to be communicated.
work surface.
Visitors Property damage. • Support scaffolding to be inspected and approved / signed-off by
scaffold inspector / engineer before concrete pours.
• Re inspect scaffold if any changes/ modifications were done.
• Re inspect after heavy rains or inclement weather
• Re inspect after any contact with crane/load or mobile plant.
• Entry and exit points to be well marked.
• Intermediate landings required for stairways. Proper access ways to
Insufficient or poor be maintained.
Client, Consultants
access and egress to Lacerations, cuts, • Sufficient / appropriate edge protection in place.
Supervision
High
Low
scaffold platform or fracture, disability 5 5 25 2 3 6
Workers • Toe boards to be installed on ladder landings.
work area. and fatality.
Visitors • Ladders and stairways to be firmly secured with clamps, Not rope or
Slip, trip and fall.
wire
• Ensure good lighting for all access and working area.
2|Page
Document Reference
Saudi Constructioneers Ltd.
MC-SC-HSE-HIRA-026
Dated: 2023.02.12
Med
fracture, disability 5 5 25 3 3 9
High
from height. Workers certified safe prior to use.
and fatality.
Visitors • Scaffold to be tagged accordingly.
• Regular toolbox talks on the use of scaffolding is required.
• Manual handling techniques to be taught to workers.
• Regular TBT's regarding working at height and use of safety
harnesses.
• Ensure 100% tie-off at all times.
• Minimise people in the scaffolding area trough sufficient
demarcation.
• Include screens and safety nets where suitable / required.
• Toe boards to be on all used platforms.
Client, Consultants Lacerations, cuts, • Keep platforms and walk area clean and free of obstacles.
Falling objects / Supervision fracture, disability • Tools and equipment to be tied up.
High
Low
5 5 25 3 2 6
material from height Workers and fatality. • Use tool retainers and lanyards to prevent tools from falling from
Visitors Property damage. scaffold.
• Conduct TBT regarding working at height and risk related to falling
objects / material.
• Employees not to walk under or directly adjacent to such areas.
• Ensure adequate signage and barricade where applicable
Burrs, nails, sharp Client, Consultants • Ensure good housekeeping round formwork / scaffold. Regular
objects/edges, etc. Supervision Laceration, Cuts and inspection for sharp edges and removing the hazards.
Med
Low
5 3 15 3 1 1
protruding from Workers bruises. • Abrasive gloves to be worn by formwork workers.
scaffold planks. Visitors
Std PPE: Hard Hat, Safety Glasses, High Vis Vest, Additional PPE: Solid barriers / fencing / red and green
Coverall, Steel-cap Safety Shoes. flags / tower lights.
3|Page