Professional Documents
Culture Documents
07
24.MAY.2022
FOR QUOTATION
PROJECT :
EMPLOYER :
CONSULTANT :
CONTRACTOR :
APPENDIX #1 : 13.0
5 11-FEB-2022 APPENDIX #1 : 9.0 Updated
7.13.3
6 08-APR-2022 Updated
Appendix-1 : 6.0, 9.0, 13.0
7 24-MAY-2022 APPENDIX #1 : 7.0 Updated
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
VOLUME 5-PART 2- CHAPTER VII-SECTION 7.
GENERATOR AND ELECTRICAL EQUIPMENT
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 1 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
7.5 GENERATOR CIRCUIT BREAKER (GCB).............................................. 82
General .............................................................................................................. 82
Generator Circuit Breaker parameter requirements .......................................... 83
7.6 ISOLATED PHASE BUSBAR (IPB) ............................................................ 92
General .............................................................................................................. 92
Scope of supply and specification ..................................................................... 93
7.7 EMERGENCY DIESEL GENERATOR (EDG).......................................... 98
General .............................................................................................................. 98
Type of Plant ..................................................................................................... 98
Design and Selection ......................................................................................... 98
Rating ................................................................................................................ 99
Operating Philosophy ...................................................................................... 100
In-Service Testing ........................................................................................... 101
D.C. Auxiliaries for the Diesel Generators ..................................................... 101
Extent of Supply .............................................................................................. 101
Particulars of Plant .......................................................................................... 102
7.8 PROTECTION AND METERING SYSTEM ........................................... 117
General ............................................................................................................ 117
500kV EHV OHL protection .......................................................................... 125
Generator Protection ....................................................................................... 126
Unit Overall differential Protection (87O) ...................................................... 130
Generator Step-Up Transformer Protection .................................................... 130
Unit Auxiliary Transformer Protection ........................................................... 132
Auxiliary Power Transformers protection....................................................... 134
Emergency Diesel Generator Protection ......................................................... 135
11 kV Distribution System (Unit Auxiliary and Station) ................................ 135
400 V Distribution System (Unit Auxiliary and Station) ........................... 137
400 V Motor Control Centre (Unit Auxiliary and Station Services).......... 138
Motor Protection ......................................................................................... 138
Revenue/Tariff Metering ............................................................................ 139
Measurement system .................................................................................. 142
Drawings to be provided by the Contractor during the Contract ............... 142
7.9 AC SYSTEM .................................................................................................. 143
General ............................................................................................................ 143
Medium Voltage Switchboards (11kV) .......................................................... 144
Low Voltage Switchboards, Motor control center (400/230 V) ..................... 150
Medium and Low voltage switchboard control and supplies.......................... 154
7.10 DC AND UPS SYSTEM ............................................................................... 156
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 2 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
DC system................................................................................................... 156
UPS system ................................................................................................. 164
Tests ............................................................................................................ 168
Requirements for Battery Rooms ............................................................... 169
Battery Installation Safety Requirements ................................................... 169
Drawings to be provided by the Contractor during the Contractor ............ 170
7.11 CABLING, WIRING, CABLE SUPPORT SYSTEM ............................... 171
Standards .................................................................................................... 171
Scope of work ............................................................................................. 171
Planning and Setting Out of Work ............................................................. 171
Cable management system (CMS) ............................................................. 172
Cable – manufacture ................................................................................... 173
Cable – Installation ..................................................................................... 177
Cables - Termination .................................................................................. 183
Testing of Cables after Installation............................................................. 185
Fire and smoke stopping ............................................................................. 185
Wiring and its Accessories ...................................................................... 186
Terminal Block........................................................................................ 189
Power and Control Cables....................................................................... 190
Information to be provided...................................................................... 193
7.12 EARTHING, LIGHTNING PROTECTION SYSTEM ............................ 193
Applicable standards................................................................................... 193
General........................................................................................................ 193
Methods of installation ............................................................................... 195
Below grade earthing system ...................................................................... 195
Above grade earthing system ..................................................................... 197
Specific earthing conditions ....................................................................... 198
Lightning protection system ....................................................................... 202
7.13 MOTORS ....................................................................................................... 203
General........................................................................................................ 203
Relevant standards ...................................................................................... 203
Duty, rating and motor clarification. .......................................................... 203
Insulation systems ...................................................................................... 205
Windings ..................................................................................................... 205
Stator ........................................................................................................... 206
Rotor ........................................................................................................... 206
Motor enclosure and cooling ...................................................................... 207
Bearings ...................................................................................................... 207
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 3 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Anti-Condensation Heaters ..................................................................... 207
Winding temperature detectors ............................................................... 208
General construction ............................................................................... 208
Terminal Boxes - General ....................................................................... 208
Power cable terminal boxes and terminals .............................................. 209
Secondary Terminal Boxes and Terminals ............................................. 209
Brushgear, Sliprings and Commutators .................................................. 210
Name plate............................................................................................... 210
7.13.18 Motor Starting Current………………………………………………….210
7.13.19 Motor Speed Protection………………………………………...……….210
7.14 LIGHTING AND SMALL POWER ........................................................... 210
General........................................................................................................ 210
General requirements on lighting ............................................................... 212
Illuminated Exit Signs and emergency lightings ........................................ 214
Small power and maintenance box (Single and Three phase supply) ........ 215
Other requirements. .................................................................................... 216
Distribution board ....................................................................................... 217
7.15 CATHODIC PROTECTION SYSTEM ..................................................... 217
General and standards................................................................................. 217
Description.................................................................................................. 218
Design criteria............................................................................................. 218
Protection voltage ....................................................................................... 219
Designed lifetime ........................................................................................ 219
Galvanic Anode/Impressed Current Systems ............................................. 219
Voltage reference points ............................................................................. 220
Control and Instrumentation ....................................................................... 220
Portable testing equipment ......................................................................... 221
Auxiliary protection ................................................................................ 221
Interconnection cables ............................................................................. 221
Underground pipework auxiliary cathodic protection system ................ 222
7.16 TEST AND INSPECTION ........................................................................... 223
General........................................................................................................ 223
Generator and auxiliaries ............................................................................ 224
500kV EHV Overhead line ........................................................................ 233
Power Transformers ................................................................................... 235
Generator Circuit Breaker (GCB)............................................................... 237
Isolated Phase Busbar (IPB) ....................................................................... 239
Emergency Diesel Generator (EDG) .......................................................... 240
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 4 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Protection and metering system.................................................................. 241
AC system (11kV switchgears and 400/230V Switchboards) ................... 242
DC and UPS system ................................................................................ 243
Cabling, wiring, cable support system .................................................... 244
Earthing, lightning protection system ..................................................... 245
Motor ....................................................................................................... 246
Lighting and small power........................................................................ 247
Cathodic protection system ..................................................................... 248
Current Transformer/ Voltage Transformer ............................................ 249
Surge Arrester ......................................................................................... 249
Auxiliary Power Consumption ................................................................ 250
7.17 SPECIAL TOOLS AND SPARE PARTS ................................................... 250
General........................................................................................................ 250
Essential Spares .......................................................................................... 251
Optional Spares........................................................................................... 253
Special and Maintenance Tools .................................................................. 254
Consumables ............................................................................................... 255
[APPENDIX]
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 5 of 255
QUANG TRACH I THERMAL POWER PLANT
2.
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Scope of Work
This Section of the Specification details the technical requirement for the
electrical plant and equipment systems to be designed, manufactured, factory
tested, inspected, supplied, delivered, unloaded at Site, installed, tested,
commissioned and guaranteed by the Bidder/Contractor as part of this Contract
to ensure the safe, efficient and reliable operation of the Plant.
Training on Site, and/or in the manufacturer’s works for the Owner shall also
be included for major items of electrical plant and systems.
The scope of work also includes and refer to Electrical System at: Volume 2-
Part 2-Chapter 7-Section 1 (P2C7S1)- General Technical Requirements
The scope of work further includes the supply of all necessary documentation
to fully describe the plant and equipment as finally put to work including but
not limited to:
(1) Design Calculations,
(2) Operational Characteristics,
(3) General Arrangement Drawings,
(4) ITP and Method of Installation, Commissioning procedure
(5) Fixing Details,
(6) Single Line Diagrams,
(7) Schematic, Logic Diagrams,
(8) Wiring Tables,
(9) Cable Schedules,
(10) Equipment Schedules,
(11) Technical Literature,
(12) Type Test Certificates,
(13) Factory Acceptance Test (FAT),
(14) Site Acceptance Test (SAT)
(15) Operating and Maintenance Manuals, Catalogues
(16) Shop/ Manufacturer’s Drawing and document
(17) As-built drawings and document (including setting value, …)
Moreover, documentation submitted during the various phases of the Project
(e.g.: design, manufacture, installation, commissioning) shall clearly identify
any modifications carried out at that time by an approved method subject to the
approval of the Engineer (e.g.: clouds with an adjacent revision number in a
triangle and an explanation in the drawings revision box)
The scope of electrical plant and equipment shall include all requirements to
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 6 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
fully complete the Power Plant regardless of whether these requirements are
specified herein or not including Site Construction Power and Commissioning
Power ready for commercial operation.
The Bidder shall also be responsible under the Contract for the design and sizing
of the whole and every portion of the proposed electrical plant and any items
which are missing from this Request for Proposal but which can be inferred to
be necessary for the safe, efficient and reliable operation of the Plant shall be
deemed to be included by the Bidder in the Bid price.
The Contractor shall supply complete electric equipment and associated
auxiliaries including but not limited to the following:
a) 500kV EHV Overhead Line Connections from the Generator Step-Up
Transformer Gantry to the 500kV EHV Switchyard Gantries via
intermediate tower (or gantries) fully complete in all respects
b) Two generators, neutral earthing transformers and auxiliaries.
c) Two generator circuit breakers (GCB) and auxiliaries
d) Isolated Phase Busduct (IPB), support system and auxiliaries.
e) Two Generator Step-Up transformers with OLTC and auxiliaries.
f) All Unit Auxiliary Transformer (UAT) with OLTC and auxiliaries
g) All 11kV Switchgears & MCC
h) All 400V switchboards & MCC
i) 11kV Non-Segregated Phase Busduct and Busduct Support System.
j) 400V Non-Segregated Phase Busduct & Busduct Support System
(Shall be applied at appropriated location if required)
k) All 11kV and 400V motors
l) Protection system (Generator Protection, Generator Step-Up Transformer
Protection, Unit Auxiliary Transformer Protection, 500kV EHV Overhead
Line Protection, Other Protection Relay Panels )
m) Low Voltage Auxiliary Transformer
n) 220V DC, batteries, chargers
o) 400/230V UPS.
p) 400V Emergency Diesel Generator system
q) Cabling and Cable support system
r) Lighting and small power system
s) Earthing and lightning protection
t) Cathodic Protection System.
u) Synchronization System.
v) Tariff Metering System.
w) Metering and Measuring System.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 7 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
x) Etc.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 8 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
All 500kV EHV electrical plant and equipment supplied for this Project shall
fully comply with the following requirements of the associated Transmission
System:
The following information for 500kV EHV system shall be considered:
500kV EHV System
Description
(Solidly Grounded)
Nominal System Voltage 500kV
Maximum System Voltage 550kV
Minimum System Voltage 450kV
Short-Circuit Level 50kA/1s
Required creepage distance for outdoor shall be 31mm/kV according to IEC
60137. Larger clearances may be required due to polluted environment
influences such as salt atmosphere, high humidity areas to ensure the safety
clearance.
Only equipment which has been fully type tested by a recognised and approved
international testing centre with independent witnessing will be considered and
all relevant type test certificates shall be included by the Bidder in the Bid as
evidence.
In no case shall equipment be dispatched from the manufacturer's works prior
to completion of the Routine Factory Tests in accordance with the requirements
of the appropriate codes and standards as amended and supplemented by this
Request for Proposal and the prior submission and approval of the Factory Test
Report by the Engineer.
The Engineer reserves the right to attend all tests and the Bidder will be required
as part of the Contract to give at least two (2) months prior notice of all such
tests accompanied with the manufacturers Factory Test Protocol documentation
which shall be subject to approval by the Engineer.
The Bidder shall form a design group with a mixture of expert knowledge in the
electrical systems in coal fired power plant to carry out all design activities of
contract program.
The Bidder shall submit details of the make-up of the engineering team as well
as resumes of personnel to be provided and demonstrate their capabilities in
these processes. The Bidder's design group shall meet on a regular basis with
Owner at site or at other mutually agreed location in Vietnam.
Owner will review and comment on the Bidder's design proposals. The Bidder
shall prepare the final design documents and drawings which includes the
product of all the design activities which shall become the design reference.
The Bidder shall develop and submit for Owner approval his standards for Coal
Fired power plant electrical systems. Submission of the Bidder's standard's does
not waive the obligation of the Bidder to further develop these standards at his
own expense if Owner determine to be deficient compared to international best
practice for Coal Fired power plant design.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 9 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Switchgear rooms, relay rooms, electronic rooms and control rooms shall all be
air conditioned and where these rooms are continuously manned and/or where
the equipment in these rooms is essential for the continuous and reliable
operation of the Power Plant.
The CTs, VTs and meter for tariff metering system shall be sampled, verified
and calibrated in accordance with the appropriate test Codes and Standards by
an approved independent testing authority in the local country (Circular No.
23/2013/TT-BKHCN dated September 26th 2013 issued by Ministry of Science
and Technology and current relevant regulation)
Electrical equipment shall be verified the technical safety by an approved
independent testing authority in the local country (Circular No. 33/2015/TT-
BCT dated November 27th 2015 issued by The Ministry of Industry and Trade
and current relevant regulation)
The color of Busbars, Cables shall be complied with the Viet Nam Standards
Vietnam Electrical Equipment Regulation 2006 (Part I)
Circular No. 40/2009/TT-BCT of Ministry of Industry and Trade dated 31
December 2009 regarding the National Technical Codes (Volume 7)
TCXD 9207-2012 “Installation of electrical wiring in dwellings and public
building- Design standard”
The Contractor shall be responsible to coordinate with, EVNNPT/CPMB,
EVNNPT/PTC2 to negotiate, design, provide and complete the connection
interface between Quang Trach I and 500kV Switchyard for synchronization,
control, protection relay coordination, house load, interlocking, status of
(500kV CB, 500kV DS, 500kV ES, 500kV CVT ), communication and
SCADA…. The documents for terminal point shall be included at least
(construction drawing of terminal point, layout, conductors, wirings, fiber-
optical cable connection, Fiber Optic Media Converter, Junction Box, Method
statement for installation, connection, protection relay coordination,
interlocking, control, communication,..)
Based on the documents as listed below, the Contractor shall be responsible for
contacting these agencies (EVNNPT, EVNEPTC, NLDC) to update,
supplement the specifications of the relevant equipment, modification
concerned (if any) in this section and complete the necessary
procedures/requirements before power receiving / power energizing:
Grid connection Agreement No.2097/EVNNPT-TTĐN on June 07th, 2017
signed between National Power Transmission Corporation (EVNNPT) and
Thermal Power Project Management Board No.2 (Current name is Vietnam
Electricity Power Project Management Board No.2 - EVNPMB2);
Tariff Metering Agreement No. 1012/EPTC-KT&CNTT-KDBĐ on March
26th, 2018 signed between Electricity Power Trading Company (EVNEPTC)
and TPMB2 (Current name is EVNPMB2);
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 10 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
SCADA/EMS and Communication Agreement No. 215/ĐĐQG-CN+PT on
31st January 2018 signed between National Load Dispatch Centre (NLDC-
A0) and TPMB2 (Current name is EVNPMB2).
Protection relay and automation Agreement shall be approved by NLDC. The
Contractor shall make a report of above mentioned agreement and submit to
NLDC (with the support of the owner) for approval. Getting NLDC’s approval
is the Contractor‘s scope of work.
Codes and Standards
The Work shall be designed, manufactured, erected and tested according to the
current relevant codes, standards, accident prevention regulations and legal
regulations.
All Materials, Plant and Works carried out including calculation sheets,
drawings, quality and class of goods, methods of inspection, constructional
peculiarities of equipment and parts and acceptances of partial plants, as far as
these are beyond the special requirements of the Specifications, shall comply in
every respect with the relevant technical codes.
The Contractor must comply with the current relevant compulsory Vietnamese
codes and standards, International standards, comprises the following standards:
IEC 60038 Standard Voltages
IEC 60076 Power transformer
IEC 60214 On Load Tap Changer (OLTC)
IEC 60296 Specification for unused Mineral Insulating Oils for
Transformers and Switchgear
IEC 60345 Guide on On – Load for Oil – typed transformer.
IEC 60551 Determination of transformer sound level
IEC 60542 Application Guide for On-Load Tap-Changers
IEC 60056 High-voltage alternating-current circuit-breakers
IEC 60470 HV AC Contactors and Contactor-Based Motor-Starters.
IEC 60420 and IEC 62271-105 High-voltage switchgear and controlgear -
Part 105: Alternating current switch-fuse combinations
IEC 60408 LV air circuit breaker, DS, ES and fuse combination.
IEC 60129 DS and Earthing switches.
IEC 60298 AC metal-enclosed switchgear and controlgear for rated
voltages above 1kV and up to and including 52kV
IEC 62271 High-voltage switchgear and controlgear
IEC 61439 Low-Voltage Switchgear and Controlgear Assemblies
IEC 60898 Electrical accessories- Circuit-breakers for
overcurrent protection for household and similar installations
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 11 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
IEC 60282 HV fuses
IEC 60269 LV fuses
IEC 60787 Application guide for the selection of fuse-links of high-
voltage fuses for transformer circuit application
IEC 60529 Degrees of protection provided by enclosures (IP Code)
IEC 60947 Low-voltage switchgear and controlgear
IEC 60034 Rotating electrical machines
IEC 60623 Secondary cells and batteries containing alkaline or other
non-acid electrolytes
IEC 60228 Conductors of insulated cables
IEC 60502 Power cables with extruded insulation and their accessories
for rated voltages. form 1kV top to 30kV
IEC 61386 Conduit system for cable management
IEC 60889 Hard-drawn aluminum wire for overhead line conductors
IEC 61089 Round wire concentric lay overhead electrical stranded
conductors
IEC 60888 Zinc coated wires for overhead line conductors.
IEC 61395 Overhead electrical conductors - Creep test procedures for
stranded conductors
IEC 61394 Characteristics of greases for aluminum, aluminum alloy
and steel bare conductors"
IEC 61232 Aluminum-clad steel wires for electrical purposes
IEC 61089 Round wire concentric lay overhead electrical stranded
conductors
IEC 61395 Overhead electrical conductors - Creep test procedures for
stranded conductors
IEC 60076-1 Power transfomer
IEC 60137 Insulated bushings for alternating voltages above 1 000 V
IEC 60168 Tests on indoor and outdoor post insulators of ceramic
material or glass for systems with nominal voltages greater than 1000 V
IEC 60273 Characteristic of indoor and outdoor post insulators for
systems with nominal voltages greater than 1000 V.
IEC 60529 Degrees of protection provided by enclosures (IP Code)
IEC 61869-1 Instrument transformers - Part 1: General requirements
IEC 61869-2 Instrument transformers - Part 2: Additional requirements
for current transformers
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 12 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
IEC 61869-3 Instrument transformers - Part 3: Additional requirements
for inductive voltage transformers
IEC 61869-5 Instrument transformers - Part 5: Additional requirements
for capacitor voltage transformers
IEC 60551 Determination of transformer and reactor sound levels
IEC 60726 Dry- type Power Transformer
IEC 60947 Low Voltage Switchgear and Controlgear.
IEC 61439.1 Low Voltage Switchgear and Controlgear Assemblies
IEC 60408 Low Voltage Air Break Switches, Air Break Disconnectors,
Air Break Switch Disconnectors and Fuse Combination Units.
IEC 60269.1 Low Voltage fuses - General Requirements
IEC 60529 Degrees of Protection Provided by Enclosures
IEC 60255 Electrical Relays
IEEE-Std 80-2000: “Guide for safety in AC Grounding System”
IEEE 81 Guide for Measuring earth resistivity, ground impedance & earth
surface potential of a ground system
IEEE C37.23 Standard for metal-enclosed bus
IEEE C37.013 Standard for AC high-voltage generator circuit breaker rated
on a symmetrical current basis
IEEE C62.92 Guide for the application of neutral grounding in electrical
utility systems. Part II - Grounding of synchronous generator systems
Circular No 25/2016/TT-BCT of Ministry of Industry and Trade dated 30
November 2016 regarding to the Regulations on Electricity Transmission
system
Vietnam Electrical Equipment Regulation 2006 (Part I, II, III, IV)
Decision No. 1232/QĐ-EVN dated on 21 Dec, 2011" Regulation of Metering
Management at Terminal Point for Tariff metering points.
Circular No. 42/2015/TT-BCT of Ministry of Industry and Trade dated 01
December 2015 regarding to the Regulation on Power metering in Power
system
Circular No. 23/2013/TT-BKHCN dated 26th September, 2013 Regulation
Calibration, verification and testing for group 2 measuring instruments
TCXD 9385-2012 “Protection of Structures Against Lightning - Guide for
design, inspection and maintenance
Circular No. 40/2009/TT-BCT of Ministry of Industry and Trade dated 31
December 2009 regarding the National Technical Codes (Volume 5,6,7)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 13 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Circular No. 04/2011/TT-BCT of Ministry of Industry and Trade dated 16
February 2011 regarding the National Technical Code for Testing,
Acceptance Test for Power Facility (Volume 8)
Decision No. 52/QĐ-ĐTĐL dated on 04 August 2015 regarding the
procedure for measurement of Generator Characteristic of Coal Thermal
Power Plant in the Vietnam Competitive Generation Market
Decision No 1361/QĐ-EVN dated 07th November 2018 regarding the Test
and Commissioning Procedure for Surge Arrester/ Lightning Arrester
Decision No 1362/QĐ-EVN dated 07th November 2018 regarding the Test
and Commissioning Procedure for AC Circuit Breaker
Decision No 1363/QĐ-EVN dated 07th November 2018 regarding the Test
and Commissioning Procedure for Earthing system
Decision No 25/QĐ-ĐTĐL dated 26th March 2019 issued by Electricity
Regulatory Authority of Vietnam (ERAV) regarding Testing procedure and
Testing supervision
Electrical system studies
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 14 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Where actual impedance values are not known the impedance values used in the
studies shall be reduced in accordance with the applicable negative tolerance in
the relevant IEC standards.
The studies shall demonstrate that the worst case maximum symmetrical and
peak asymmetrical short-circuit currents which can occur together with a safety
margin of ten (10) percent is less than the proposed symmetrical and peak
asymmetrical fault ratings for the offered equipment.
Short-Circuit Studies shall also be carried out to establish the minimum 2-phase
and minimum 1-phase short-circuit currents which can occur for selecting the
settings of protective devices and for protection co-ordination purposes.
Earthing system study
An Earthing System Design Study shall be carried out strictly in accordance
with the latest edition of IEEE 80, IEEE 665 and Viet Nam Standards to
determine (i) the minimum permissible conductor size for above and below
grade earthing system conductors (ii) the required quantity of above and below
grade earthing system conductors (iii) the tolerable step voltage (iv) the
tolerable touch voltage (v) the maximum step voltage (vi) the maximum mesh
(touch) voltage and (vii) grounding resistance.
The study shall demonstrate that with the proposed above and below grade
earthing system design and the worst case single phase short-circuit current that
can occur that the tolerable step and touch voltages are not exceeded anywhere
within the boundary of the Power Plant and within 1 meter distance at outside
area of the boundary fence.
A design margin of not less than ten (10) percent shall apply throughout.
Following completion of the installation the Bidder will be required as part of
the Contract to carry out tests on Site to verify the results of the design
calculations and in the event that the tolerable step and/or tolerable touch
voltages are exceeded to install additional earthing conductors and/or earthing
rods as appropriate to reduce the measured values below the tolerable safe
values making due allowance for the aforementioned design margin.
Load Flow Study (Voltage Drop/Voltage Dip Study)
Load Flow Studies shall be carried out for all the critical system conditions that
can occur. The load flow studies shall include all branch power flows (i.e.:
MW’s, MVAr’s and MVA) and the resulting voltage levels at all switchboard
busbars and at selected critical MV and LV motor drives.
The voltage variation at each switchboard busbar shall also be included and
based on the foregoing recommendations shall be made for transformer on-load
and transformer off-circuit tapping steps and tapping ranges for approval by the
Owner.
The studies shall demonstrate that under the worst case operating conditions for
the Unit and Station MV and LV power distribution systems that the voltage at
the terminals of consumers lies well within the tolerance allowed by the
equipment Manufacturer’s and in no case exceeds 0.90Un - 1.10Un for steady
state conditions and 0.85Un for transient conditions (i.e.: largest motor starting)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 15 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
with all other normally running loads and motors in service at full nameplate
rating and with all transformers on their rated tap.
Load consumption calculation for unit and station auxiliary system must be
detailed in this stage.
Cable Sizing Study
Cable Sizing Studies shall be carried out to determine:
The minimum power cable size for short-circuit current based on the tripping
time of the back-up protective device.
The minimum power cable size for load current based on the consumer full
nameplate rating and type of installation.
The minimum power cable size for voltage drop/dip based on the consumer
full nameplate rating and route length.
The studies shall demonstrate that under all operating conditions the proposed
power cables can carry full rated current continuously and short-circuit current
for the total clearing time of the back-up protective device without exceeding
the maximum permissible operating temperature for the cable.
The studies shall also demonstrate that the power cables are adequately sized to
maintain the terminal voltage at consumers within the required tolerances.
Protection Coordination Study
A Protection Co-ordination Study shall be carried out to select the settings for
all Unit and Station protective devices and to ensure that with the selected
settings and under all fault conditions that the protective devices will operate
correctly to clear the fault while at the same time disconnecting the minimum
number of plant items.
The protection relay system shall ensure: selectivity, speed, sensitivity,
reliability, simplicity, economy to release the fault and miss-operation
The report shall include a comprehensive description of the proposed relay types
and their setting ranges. Full details of the supplying CT, CVT and VT
parameters together with supporting evidence and calculations to confirm their
adequacy for use with the proposed relays shall also be included.
Frequency Limits
The Facility must be capable of operation at frequencies below:
Frequency Range (Hz) Minimum Sustainable Operation
46.0 to 47.5 No requirement
>47.5 to 48.0 10 min
>48.0 to <49 30 min
49 to 51 Continuous
>51 to 51.5 30 min
>51.5 to 52 01 min
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 16 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The Main Generator is connected by an Isolated Phase Bus duct to the Generator
Circuit Breaker input terminals and connected via Generator Step up
Transformer and 500kV EHV Overhead Line to 500kV Switchyard supplied by
EVN. The Generators shall be synchronized to the 500kV grid by the GCBs or
500kV line Circuit Breakers.
The output terminals of the Generator Circuit Breaker are connected by an
Isolated Phase Busduct (IPB) to:
Low voltage terminal of the GSUT
High voltage (HV) terminals of the UAT
High voltage terminal of the Excitation Transformer
The HV terminals of the GSUT are connected to the 500kV switchyard by
overhead ACSR conductors strung from the power facility to 500kV switchyard.
Neutral of Generator shall be connected to earthing by Neutral Grounding
Transformer / Resistor Cubicle of Generator.
The High voltage side of Unit Transformer shall be connected to the tap-off of
Isolated Phase Busduct. Low voltage terminal of the UATs is connected to 11kV
Unit switchgear bus via busduct. The 11kV MV Unit Switchgears shall be
supplied from their respective Unit Auxiliary Transformers. The 11kV MV
Common Switchgears shall be supplied from their respective 11kV Unit
switchgear bus via busduct or cable. Each 11kV Bus section shall be supplied
from two (02) respective power supply.
The 400V Unit switchgears shall be supplied from the respective 11kV Unit
switchgears via 11kV /0.42kV dry type transformer. Inter-connector circuit-
breakers and/or coupler circuit-breakers between the 400V Unit switchboards
shall normally be open
The 400V Auxiliary Switchboards and the 400V Station Auxiliary
Switchboards shall be supplied from the 11kV Station Auxiliary Switchgears
through their respective 11kV /0.42kV dry type transformer. Inter-connector
circuit-breakers and/or coupler circuit-breakers between the 400V Auxiliary
Switchboards and the 400V Station Auxiliary Switchboards shall normally be
open.
The 400V, 3 phase Emergency Diesel Generator (EDG) is provided to supply
safe shut down loads for shutting down both units simultaneously. The EDG
power shall supplies for each essential bus.
The rating parameters and plant specifications based on IEC Standards and that
voltage levels of 11kV and 400 V be adopted as follows:
11kV, 3 phase, 3 wire for motors rated from including 200 kW and for bulk
power distribution;
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 17 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
400 V, 3 phase, 3 or 4 wire for motors rated less than 200 kW and for other
3 phase loads;
230 V A.C, 2 wire for small loads requiring single phase power;
400/230 V A.C. UPS for essential control circuits and emergency drives.
220VDC, 2 wire for control circuit.
In the event of any substantial increase in auxiliary system loading (for example
the installation of a Flue Gas Desulphurization system), the following
conditions must be met after inclusion of the additional load:
Voltage regulation - Stating largest 11 kV motor with full auxiliary load (one
unit plus half the station load) must maintain a minimum of 85% of
switchgear rated fault level under all system operating conditions.
Actual 11 kV circuit breaker and busbar currents shall not exceed 95% of
their ratings.
The Unit Auxiliaries Transformers shall have a maximum rating of 60 MVA.
In the design requires transformer ratings more than this figure a higher
voltage system design is to be submitted for approval by Owner.
Under steady-state conditions the voltage may vary between ± 5% of nominal
voltage.
The voltage drop at equipment load terminals due to cable impedance shall
be a maximum of 5% of nominal voltage.
During the starting of large motors, longest motors, short-term voltage
excursions of up to 10% may be experienced at the source of supply. The
total allowable voltage drop at equipment load terminals under these
conditions including cable impedance volt drop shall be limited to 15% of
nominal voltage. Especially, Contractor shall be responsible to calculate the
cable and other necessary solution to ensure the stability and safety operation
of Coal Ship Unloader (CSU) at Coal jetty during the starting of motors to
avoid the voltage drop exceed the allowable value and trip CSU.
Contractor shall be responsible to calculate and consider the conditions as
power cable cross-section, spare capacity, starting solutions,… to ensure the
total voltage drop at equipment load terminals within allowable range as well
as do not impact the normal operation of other electrical equipment/system
of Quang Trach I Power Plant during the starting of large motors, longest
motors as Circulating water pump motor (CWP), Condensate water pump
motor, Forced draft fans (FDF) & Induced draft fans (IDF) & Primary air
fans (PAF) motors,…
Primary features of the a.c. system are as follows:
a) 11kV system resistance earthed (to limit fault damage)
b) 400V system solidly earthed (necessary for reliable protection)
c) One 400V emergency power (diesel generator) supply system is required to
protect each boiler/turbine-generator plant and to maintain essential power
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 18 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
necessary for the safety of personnel in the event of loss of normal AC
supplies. The prospective capacity of diesel generator is 1000kW for each
Unit which will be calculated in detailed design phase. The diesel generators
will be rated for the shutdown requirements of the generating unit.
d) The impedance of each transformer shall be such that voltage regulation
shall be within the specified limits. “Voltage Distribution and Regulation”
and shall be such that the fault withstand capability of its connected
equipment is not exceeded.
The Auxiliary Power consumption load of each Unit is 7.49% at RO
System Configuration Interlocking
Generator Design
The generator shall be of the horizontal, three phase synchronous machine, with
rotating field, cylindrical rotor and totally enclosed, shall be designed and
manufactured to comply with this Specification, IEC 60034-3 and the relevant
other parts of IEC 60034, and shall be suitable in every respect for operation in
the Vietnamese supply system in accordance with the specified conditions
which follow, including the applied standards.
IEC 60034 Rotating Electrical Machines
IEC60085 Electrical insulation—Thermal classification
IEC 60146 Semiconductor Converters
IEC 62053 Electricity metering equipment
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 20 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Circular No. 25/2016/TT-BCT dated November 30, 2016 by the Ministry of
Industry and Trade..
And other current relevant standards.
Generator auxiliaries.
The generator comprises of, but is not limited to the following associated
devices:
Excitation system, Excitation-Transformer.
Supervisor and Direct-online Control System
Automatic Voltage Regulator System (AVR)
Lightning Arrester (LA) or Surge Arrester (SA).
Main generator racking panel (and other equipment)
Generator cooling devices, including the noise filter and the noise decreasing
device to assigned level
All the connecting cables
Internal wiring, include wiring to the correlative clamp rows of all the
supplied boards.
The terminals of wires connecting to the outgoing feeders by IPB.
Current transformers and voltage transformers used for metering, electric
meters must meet the Precision level obeyed to current Vietnamese
regulations, IEC 61869 Standard, IEC 62053 standard or other correlating
standards.
Generator Protection equipment.
Auxiliary devices
Starting up devices, start – up motors associated with required devices to
drive the generator to start – up speed.
Current transformers and metering voltage transformers, rectifiers,
measuring meters system, cables and other correlating devices to fully meet
the operation requirements of the plant.
Heat sensors for sensing the generator temperature.
Sensors to detect vibration at the terminals of coils and glandings Internal
discharge monitoring system
Generator heaters.
Hydro-producing station with dry – making system, pipelines system and
parts connecting to generator
Oil-glanding system.
Protection system to prevent the Sub- Synchronous Resonance (SSR)
Automatic and manual network synchronizing devices.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 21 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
All other electrical devices to ensure for the operation of the generators.
Rating
The generator shall be continuously rated to enable Gross Output of 648.8 MW
and a Net Output of 600 MW (delivery to power grid) after deduction of
excitation power and corresponding Auxiliary power load under the following
conditions:
0.85 Lagging Power Factor
0.9 Leading Power Factor.
Characteristics
The generator shall be designed to have the following characteristics:
A short circuit ratio of not less than 0.5.
A direct axis transient reactance (saturated) should not be less than 19% and
ensure that total impedances of generator and generator transformer must be
complied with Circular 25/2016/TT-BCT are at least 40%.
The overload ability of Generator is 1.5 rating current in at least 30 sec.
Industrial withstand voltage: 50kV
Lightning impulse withstand voltage 125kV
These limits shall not be exceeded when the applicable tolerances are
considered. The applicable tolerances shall not be greater than that allowed by
IEC 60034-3.
A generator capability curve is required to be provided during the Contract
showing expected generator MW/MVAR operating limits at rated hydrogen
pressure (or TEAC) and lower.
Rated speed: 3000 rpm, corresponding to 50Hz frequency
Insulation class: F
Temperature raising range is B level
Excitation system: static excitation.
Voltage and Frequency
(1) The generator shall be rated for 50 Hz operation. The generator shall be
designed to remain operation in the range of 47.5 Hz to 52Hz
(2) Preferred value for generator voltage is 23.5kV but it may be nominated by the
Bidder to optimize the design of all equipment operating at generator voltage.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 22 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(3) The generator and generator transformer tap changer will be operated to
maintain at the HV busbars a scheduled voltage which will be varied from time
to time. Steady-state generator terminal voltage will vary continuously within a
range of plus and minus 5% of rated voltage at any output within the generator
capability, to satisfy these HV conditions.
Stator
Casing
(1) The casing of the stator shall be of fabricated construction gas-tight, and
sufficiently robust to withstand the maximum forces set up in the event of an
explosion of a hydrogen and air mixture in the casing.
(2) Access into the generator casing for inspection of stator end windings shall be
by removal of bolted covers and shall not require the removal of coolers or other
ancillary equipment.
(3) Liquid drains shall be provided from the casing, suitably enlarged, and
connected to plates bolted to the generator frame so that on disconnection of
any external drain there will be a hand hole for clearing material which may
lodge in the internal drain. Liquid detectors, fitted with alarm contacts, shall be
fitted in each separate drain and not in a common line.
(4) It is acceptable for the casing and core to be separate or integral according to
suitability for transport and heavy lift arrangements.
Core
(1) The stator core shall be made up of high permeability low loss stampings,
bonded and tightly clamped together to reduce noise and vibration to a
practicable minimum. Attention shall be given to the prevention of excessive
100 Hz vibration being transmitted to the generator casing, foundations, pipes
or associated equipment. The Contractor shall provide a description of the
bonding used to prevent vibration of the end teeth, during the Contract.
(2) Should the proposed method of transport require a beam to be threaded through
the bore of the stator core then the full length of the bore shall be lined with a
tube of leatheroid or similar material to prevent damage to the laminations
during insertion and removal of the beam, and during transport.
Winding
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 23 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
exceed that nominated in IEC 60034-1 for Class B insulation.
(2) The winding shall be effectively braced and blocked to withstand short circuits
at the terminals under any operating condition and to prevent vibration which
may lead to gas leakage. Materials liable to shrink in the course of time and on
heating shall not be used for packing and wedging, and the general construction
of the stator and the bracing of the winding overhaul shall be such as to provide
adequate cooling surface and avoid "hot sports".
(3) Provision shall be made for preventing the formation of condensation during
shutdown periods.
Terminals
The windings shall be star connected and the ends of each phase of the stator
windings shall be brought to terminals accessible from a space in the foundation
block. Adequate provision shall be made in the design of the foundation block
for accommodation of the metering, protective and other current transformers
required for operating the unit. It may be taken that the current transformers will
not be in contact with the terminals and will be supported independently of the
generator. Creepage distances shall be equivalent to those specified in IEC
60137 for medium polluted atmospheres as defined in IEC 60815.
The windings must be in star configuration, and the terminals of each stator
phase winding must be conducted to connection boxes on racks. All the (6)
connection points for each generator must be able to be taken apart from the
generator and can link with outside connections. Generator connection boxes
will be installed below stator. Connection boxes must be non – ferrous material
type to hinder overheating because of Foucault currents. Three supporting
porcelains must be installed for the either side of phase line and neutral and
concurrently, supporting porcelains of voltage/current transformer required for
measuring devices, protection relays and AVR must be designed.
Connection to Busbars and Earthing Transformer
(1) On the line side, provision shall be made for disconnection of the generator from
the phase isolated busbars to enable the establishment of safety clearances
between the two plants during high voltage testing of either.
(2) On the star point side, provision shall be made for disconnecting the star point
from the generator terminals to enable the establishment of safety clearances
between the generator and the earthing transformer and to enable testing of
individual phase windings.
Rotor
Winding
The design of the rotor shall be such that earth and interturn faults in the
windings will not occur in service. Insulation shall be of Class F temperature
classification. The limit of winding insulation temperature rise shall not exceed
that nominated in IEC 60034-1 for Class B insulation.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 24 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The Contractor shall incorporate all latest design features to avoid permanent
deformation of the winding during service. Packing blocks used in the rotor
winding shall be of approved material and entirely suitable for the high
temperatures and mechanical forces occurring in large rotors. Attention shall be
given to the insulating and securing of the rotor winding connection leads to
avoid vibration and the possible failure of either the lead or its insulation.
Shaft
(1) The rotor shall be made of one solid forging with high mechanical strength
characteristics. The forging shall be fully examined by radiographic and
ultrasonic techniques to determine its soundness.
(2) The Contractor shall incorporate suitable features in the rotor design to reduce
the variation in rotor stiffness about the direct and quadrature axes, and thus
minimize the resultant twice-per-revolution vibration levels. During the contract,
design calculations shall be furnished to show that a rotor critical speed will not
exist in the region of twice rated speed.
(3) The shaft shall have a reference mark of known relationship to the location of
the magnetic poles which can be detected in-service for synchronism of shaft
position with portable test equipment. The mark shall be located such that it is
always accessible notwithstanding shaft expansion and provision shall be made
for mounting of a detecting device.
Slip Rings
Slip rings where necessary shall be mounted on the shaft in a separate enclosure
at the outboard end of the generator.
Generator Earthing
Neutral Point
The generator stator winding, which will be star connected, shall be suitable for
earthing through a single-phase distribution-type double-wound transformer,
the secondary winding of which will be shunted by a non-inductive resistance.
The Bidder shall supply details of the capacitance to earth of the stator windings,
which is necessary for selection a final resistance value, as part of the
commissioning report. The Bidder shall nominate the expected value of
capacitance.
Casing
(1) Earthing terminals or bolts shall be provided at two positions on the stator
bedplate for earthing the generator casing. These positions shall be connected
at two different locations on the station earthing system.
(2) Major turbine generator components shall be electrically bonded together and
connected to the generator earth terminal to provide a low impedance return
path for possible radio frequency (RF) voltage transients generated by thyristor
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 25 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
switching in the generator static excitation circuit.
Turbine/Generator Shaft Voltage/Current Control
(1) The shaft shall be earthed at one position between LP turbine and generator
bearings by suitable multiple (at least two) shaft earthing devices.
(2) The shaft earthing devices shall be protected from the effects of oil, dust, steam
and other contaminants.
(3) Each shaft earthing device shall have 0.01 to 0.1 Ω in-service contact resistance
to the shaft at the rated speed and within permissible shaft vibration levels.
(4) The contact element of each shaft earthing device shall be able to be replaced
with the generator in service without safety risk either to a person or to the
machine.
(5) Each shaft earthing device shall be connected to the turbine/generator earth
bonding conductors or lower bearing case via suitably sized low impedance
current measuring shunt.
(6) The generator outboard bearings and preferably HP turbine bearing No. 1 shall
be electrically insulated from the generator earth.
(7) Shaft voltage test terminals grouped in one single easily accessible location shall
be provided for checking the voltages and insulation integrity for the following:
(a) Insulated bearings
(b) Insulated hydrogen seals
(c) Insulated oil piping
(d) Other insulated components as necessary.
(e) Shaft voltages shall be measuring during the commissioning of Unit.
(8) A continuous on-line shaft earthing monitor shall be provided as a integral part
of the shaft earthing system.
The monitor shall measure earthing current and shaft voltage, and display these
at a local panel adjacent to the generator. It shall also activate at least one "clean"
changeover alarm contact.
(9) A "Shaft Earthing Abnormal" alarm, displayed in the Central Control Room
(CCR), shall be generated for the following conditions:
(a) "Loss of power supply" to the monitor
(b) "Shaft earthing current low" (deterioration of shaft earthing device)
(c) "Shaft insulation low" (loss of insulation integrity)
Each alarm condition above shall be indicated by local LED and shall latch the
local manually resettable alarm contact.
The monitor shall have an analogue 4-20 mA output for each parameter
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 26 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
displayed on the local panel.
Analogue outputs shall be displayed in the CCR (CCR).
(10) The Bidder shall provide details of shaft voltage/current control scheme
monitors the bearing insulation, shaft coupling insulation, shaft earthing devices
and the like during the contract.
Generator Condition Monitoring
(1) General
Each Generator shall be equipped one (01) completed set of Generator on-line
partial discharge monitoring system for generator stator, generator rotor and
generator stator end-winding vibration monitoring system. The system shall be
designed in accordance with NEMA, IEC and any other relevant codes and
standards.
This system shall be composed of sensors, data acquisition units, software,
control system.
All cables including signal cables and communication cables and required
installation materials shall be provided
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 27 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
On-line partial discharge monitoring system shall detect the abnormal
conditions in the electrical insulation system and monitor partial discharge
activity in generator stator windings and vibrations in generator end windings
to monitor continuously the Surface Discharge, Internal Discharge,… and
vibration in generator. The system shall generate alarms in case of excessive
partial discharge or end winding vibrations (EWV). The system should have the
capability to acquire partial discharge patterns and determine partial discharge
quantities as apparent charge, quadratic rate and average discharge current for
each phase.
The system shall be standalone type with facility for storage of trend data and
patterns, The system shall have facility to download patterns and trends on to
PC or LAN, visualization software, noise suppression circuitry for input and
signal transfer.
(2) The system shall include at least the following equipment and comply with the
following requirements:
Sensor shall be detected the abnormal conditions on the surface discharge,
internal discharge,…vibration in generator.
Alert levels of increase in Partial Discharges and vibration in generator shall
be recommended to monitor.
The local analyzer shall be a micro-processor based unit with filtering
&conditioning of the partial discharge signal. The local analyzer shall include
a local keyboard and display for direct checking of the status of monitored
equipment and itself. The cabinet shall be provided. It will be mounted in the
NEMA 4 enclosure.
One (1) computer with a LCD monitor (24 inches) and one (1) logging
printer,… shall be provided to indicate abnormal and alarm status of Partial
Discharges and vibration in generator .
All analyzers shall be connected to the computer for local monitoring and
shall also be connected to the Distributed Control System (DCS)/ Integrated
Control & Monitoring System (ICMS) for the remote monitoring.
The special software required for partial discharge analyzing shall be
provided together with the system. The monitor settings and configurations
shall be available for changing by operator.
Software and on-site training in the use of the software and using the
analyzing shall be provided.
A11 data will be recorded in the local analyzer, will be available to be
downloaded to the computer, and shall be suitable for examination of
historical data.
Operation Manual, Technical Specification for Generator On-line partial
discharge (OLPD) monitoring shall be provided.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 28 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Generator Excitation
General
Equipment for the complete excitation requirements of the generator shall be
provided; including all excitation transformers, thyristor bridges, field
suppression equipment, excitation control equipment and all connections
between these items.
The required excitation system shall be of a static system in which the excitation
power is provided by a transformer connected to the generator side of the
generator circuit breaker and controlled by a thyristor bridge.
A withdrawable type SF6 or vacuum circuit breaker metal clad switch gear shall
be provided between the excitation transformer and the thyristor cubicle...
The design of the withdrawable type circuit breaker metal clad switch gear shall
be such that the status of the contacts can be seen to confirm electrical isolation.
The excitation system shall be of a static converter directly supplying the
generator rotor field. Its power source is derived from an excitation transformer
which is connected to the generator side of the generator circuit breaker (GCB)
via a Isolated Phase Busbar (IPB).
The excitation system is self-exciting, using DC “flashing” either from the 220V
dc Station battery or from the 400V Station supply to build up the initial field.
The excitation system shall comply with the requirements of Circular No.
25/2016/TT-BCT of Ministry of Industry and Trade dated 30 November 2016
Regulations on Electricity Transmission system
Performance
When Generator terminal voltage operation in the range of range from 80 to
120% of rate voltage and frequency in the range of 47.5 Hz to 52Hz:
(1) The ceiling level of field voltage shall be at least 2 times the maximum
continuous rating of field voltage, for stator voltages between 0.6 and 1.0 per
unit of rated value.
(2) The excitation system offered shall be of the high initial response type, with a
response ratio such that excitation increases from rated load excitation voltage
1.0 pu to a voltage greater than 2 pu in 0.1 sec in response to a step change in
generator terminal voltage of 2.5%.
The excitation system will be designed to be capable of enduring 110% of rated
value (when the generator is full load).The forced exciting voltage is not small
then 2-time the rated exciting voltage value to ensure maintaining stability in
the event of large voltage falling because of short – circuit at generator poles or
at high – voltage network, to ensure the precision cutting of the generator
protection system and the high voltage networking protection system.
(3) The excitation system shall be capable of providing the peak power required for
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 29 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
operation at ceiling voltage level.
(4) This requirement is based on an operating duty cycle of: rated output for a
sustained period, then ceiling voltage for 10 seconds, then return to rated output
for a sustained period.
(5) When the generator terminal voltage ranges from 80 to 120% of rated voltage
and system frequency ranges from 47.5 to 52Hz, the field excitation system of
the generator should be able to increase excitation voltage and current to 2.0 PU
of the rated value in a maximum of 0.1 sec.
(6) Changing speed of field excitation voltage should not be less than 2.0 times
compared to rated voltage/second when the generator is running at rated
capacity.
The Bidder shall provide, during the Contract, performance details and
preferably test curves for the design of excitation system offered.Static
Thyristors Excitation System
(1) Thyristors
(a) The Thyristor Bridge shall comply with the requirements of IEC 60146.
(b) A three-phase fully-controlled thyristor bridge shall be provided with sufficient
redundancy to permit operation of the generator at full excitation power with
20% of the thyristors failed in any set of parallel paths i.e. arm of the bridge. It
shall be possible to either replace faulty thyristors with the generator in service,
or the extent of thyristor redundancy shall be sufficient, having regard to their
reliability, to permit full excitation power without replacing thyristors more
often than once every 8000 hours.
Sufficient redundancy shall be included in the thyristor cooling system to ensure
that a single failure will not prevent the achievement of continuous 100%
generator rated output.
(c) The Bidder shall provide, during the Contract, a description of what measures
are taken to prevent damage to the Thyristor Bridge in the following situations
(and any others as applicable) and what tests are performed to confirm the
effectiveness of these measures.
A short-circuit at the generator slip rings at excitation ceiling voltage
The overload occurring with a sudden short-circuit at the generator
terminals
High voltage across the bridge due to reverse excitation current
Non-uniform current distribution between thyristors
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 30 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The design of excitation transformer shall consider the additional stray and eddy
current losses generated by the harmonics supplied to the load. The Bidder shall
calculate the extra losses due to harmonics by reference to ANSI/IEEE C57.110
The Bidder shall nominate the expected demand for excitation power (MVA) at
rated generator output.
(b) Not withstanding the protection schemes specified in this Specification, the
Contractor shall state any further protection which he feels is necessary for the
safe operation of the transformer. The protection shall not mal-operate under
any operating condition.
Technical characteristic:
Type: 3 phase, 50Hz, dry-type, step down transformer.
Wiring connection type: As per Manufacturer’s standards
Power: follows the demand of the excitation system.
Rate voltage: Ugen/Uet
Lightning impulse voltage: 125kV.
Power frequency voltage testing: 3kV
Tap changer: +2x2,5% (no-load tap changer-manually)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 31 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(4) Field Suppression
A main field circuit breaker complying with IEC60947 Parts 1 and 2, and a non-
inductive resistor shall be provided for generator de-excitation. The circuit
breaker can break the field current under the most onerous operating conditions.
On opening the breaker, the field winding shall be short-circuited through the
resistor which shall ensure that the rotor winding voltage remains adequately
below its test voltage. The field circuit breaker shall have two trip coils which
are electrically and mechanically independent.
Supervision
Equipment shall be provided for detection of a generator rotor earth fault and
measurement of generator rotor field voltage and current. The field voltage and
current measurements will be computer monitored and used to compute field
winding temperature. The Bidder shall provide during the contract details of the
fault detection and voltage and current measuring equipment.
Construction and Reliability
The excitation control system shall provide completely reliable and stable
automatic regulation of the generator excitation. The excitation control
equipment must consist of an Automatic Voltage Regulator (AVR) (with power
factor controller) and Power System Stabilizer (PSS).
(1) Technology
The regulator shall be microprocessor based.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 32 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
on the duty/standby principle, although alternative principles such as
master/slave will be considered provided they achieve the same aim.
The normal condition of operation when the generator is connected to the
system will be for excitation to be under automatic voltage control of the
selected Duty Channel, with the Standby Channel being also selected to
automatic mode. If the Duty Channel in automatic mode fails, control will be
transferred "bump less" to the Standby Channel (automatic mode). If the
Standby Channel automatic control subsequently fails, control shall be
transferred to the Standby Channel manual controller if available, otherwise
excitation shall trip.
If the Standby Channel (in either automatic or manual mode) is unavailable
when the Duty Channel automatic control fails, control shall be transferred to
the Duty Channel manual controller if available, otherwise excitation shall trip.
The Bidder shall provide a description of what abnormal conditions will cause
excitation to trip.
The equipment shall be designed and constructed to facilitate maintenance of
one Channel while the other remains in service.
If operating on the duty/standby principle, the standby circuit shall be
continuously monitored so that any abnormality is alarmed and causes lockout
of transfer to that circuit.
The status of each Channel and whether it is controlling excitation shall be
indicated in the CCR. Selection of which Channel is controlling excitation and
its mode (automatic or manual) of operation shall also be available from the
CCR.
Characteristics
The excitation control system shall have the following characteristics:
(1) Sensitivity
The excitation system shall give its maximum or minimum output with
variations in generator terminal voltage of not greater than ±2.5% from set point.
(2) Regulation
The regulator shall maintain the generator terminal voltage within limits of
±0.5% of required value between no load and full load over a range of
frequencies of 47.5 to 52 Hz.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 33 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(4) Stability and Damping
It is intended that the excitation control system will be adjusted so that, with the
generator operating on open circuit at rated voltage a step change in the AVR
input equivalent to a step change of either +2.5% or -2.5% terminal voltage,
shall result in an oscillation in field voltage with a settling time of less than 1.5
seconds.
(The settling time of a quantity is defined here as the time interval from the
instant of the step change until the resulting oscillation settles to less than ±10%
of the maximum induced change.)
It is also intended that the excitation control system will be adjusted to maintain
stable operation of the generator for a ±0.5% step change in terminal voltage
with the machine operating at all loads and power factors within its capability
limits.
The under excited capability limit shown on this drawing is based on a
theoretical model with the generator connected to an infinite bus bar through a
reactance of 0.5 pu (on rated MVA of the generator) and with rated voltage
maintained at the generator terminals (achieved by adjustment of the infinite
bus bar). The criterion of stability is a settling time of less than 5 seconds in
generator terminal voltage and rotor angle oscillations.
To achieve these requirements, the Contractor will carry out necessary
calculations before Site commissioning, of the required setting values within the
range of adjustment provided. The Contractor will co-operate in implementing
these settings and in carrying out tests to verify that the required performance is
attained.
(1) The output of the excitation regulator shall be varied in accordance with the
requirements of at least the following supplementary control circuits.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 34 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
selectable by the operator either to the ICMS or to individual unit set point
reference.
If the control system fails, control shall revert to individual control of each
generator set point, the outputs retaining the values they had at the time of
failure.
Provision shall be made for the following inputs and outputs from each unit:
Inputs: stator voltage, power output, reactive power output, 500kV bus
bar voltage, generator step up transformer tap setting
Outputs: voltage set point, provision for generator transformer tap setting.
(b) Reactance drop compensation shall be included in the AVR circuits as a
secondary means of minimizing changes in Quang Trach 500 kV busbar voltage
level during changes in station reactive power demand.
The compensation shall be proportional to the reactive power output (or
alternatively, quadrature component of stator current) of the generator and
adjusted to a setting to be advised by Owner.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 35 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
adjustments of the stabilizing signals:
Gain range 0-6,000 pu open circuit excitation volts per pu speed or frequency
or range 0-100 pu open circuit excitation volts per 100 MW.
Washout filter (high pass; at least three per stabilizing signal):
0 to 10 seconds adjustable
Lead/lag compensation (at least three per stabilising signal):
0 to 1 second lead and lag, independently adjustable
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 36 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
inadvertently during system disturbances, particularly during the recovery of
system frequency after loss of generation elsewhere in the system.
PSS Requirements:
PSS shall be capacity to provide the phase compensation corresponding to
0.2-2Hz, the phase angle of transfer function of excitation system shall be
within ±30 degree
The PSS output limit shall be set at lead ±5% of Generator voltage
Gain factor of PSS shall be set to the Gain Margin of PSS in the range of 6dB
~10dB
(10) Other functions (such as P/Q limitter, Stator current limiter, V/Hz,…) shall be
supplied.
P/Q limiter is used to prevent the generator from entering the unsteady operation
area. The limit curve may be set such that five reactive power values are
corresponding to five active power levels respectively (i.e. P=0%, P=25%,
P=50%, P=75%, P=100%).
Supplementary Protection
The following supplementary protections are to be provided and their operation
alarmed.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 37 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
This function is used to prevent oversaturation of the magnetic flux density
of synchronous generator. Compared with the reference voltage, the reference
voltage depends on the generator frequency at actual voltage value of
generator. If the actual voltage exceeds the reference value, a timer will be
triggered. After adjustable time delay is completed, if the voltage still fails to
reach the allowable value, the trip signal will be triggered
(1) Follow-up
Equipment shall be provided to cause the manual excitation control to match
the excitation level determined by the in-service automatic control. This is to
ensure that a changeover from automatic to manual control, under steady state
conditions, will generally take place without perceptible transients while
operating in the generator capability range where manual control is stable.
Similarly, while under manual control, a facility shall be provided to match the
automatic level of excitation with the manual level, so that a transfer to
automatic control will take place without perceptible transients.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 38 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Test Facilities
(1) To facilitate performance testing of the AVR and for future investigations,
quantities shall be made available for measurement at the excitation cubicle.
The quantities shall include the following and may taken the form of analogue
signals or outputs from the digital software:
e) Generator stator voltage and current
f) Generator three-phase real and reactive generator power output
g) Generator rotor voltage and current
h) Instantaneous speed of the rotor (if speed is used as a power system
stabilizer input)
i) Any other signal used by the Contractor as a feedback in the AVR
j) Intermediate signals at key points in the AVR block diagram
(2) Analogue transducers (if any) required for processing primary signals shall be
mounted in the excitation cubicle and have a time constant (lag) of less than 20
milliseconds.
Sources for Generator Voltage Signals
The generator voltage signal for each AVR Channel shall be derived from two
physically separate V.T.s. Each V.T. shall be separately connected to the phase
isolated busbars and secondary wiring shall run in separate cables to the
respective channels to minimize the possibility of a single event crippling both
automatic regulators.
Performance Data
(1) The Contractor shall provide a block diagram so that it shows the gains, time
constants, delays, limits and saturation of the excitation system as designed.
Where these can be varied, ranges and recommended values are to be shown.
Frequency response curves (Bode or Nygquist) of each block with the
recommended settings are also required. The Contractor shall at appropriate
times resubmit the block diagram amended to show the parameters and limits
obtained during testing and again to show those which apply to the excitation
system after it has been commissioned.
(2) Sample chart records of step response measurements made on machines having
similar AVR control shall be provided during the contract.
(3) A curve shall be submitted during the contract showing the estimated
time/voltage characteristic of the generator under AVR control immediately
after full load has been rejected, by opening of the generator circuit breaker.
Electrical Synchronizing Facilities
One set of automatic and manual synchronizing equipment will be provided for
the generating unit and the generators can be synchronized with electric network
by both circuit breaker located on the 500kV side of the generator transformer
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 39 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
and the generator circuit breaker.
(2) Redundancy
Redundancy in automatic synchronizing circuits will be provided by a correct
selection of auto-synchronizing equipment as follows:
Either Two automatic synchronizer functions or two check synchronizing
functions are contained in the one relay case. Each automatic synchronizer
will be checked by a check synchronizing function and operation of either
synchronizer will close the circuit breaker.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 40 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Two separate relays and each relay shall have automatic synchronizing
function and a check synchronizing function. The operation of either
synchronizer will close the breaker
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 41 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
be only permitted to synchronize from Quang Trach I TPP side after accepted
from 500kV Switchyard operator.
The Contractor shall be responsible to coordinate with NPT to design, provide
and complete the connection interface between Quang Trach I and 500kV
Switchyard for synchronization, house load, interlocking, status of (500kV CB,
500kV DS, 500kV ES, 500kV CVT ).
Generator Cooling
Cooling System
Core and Rotor: direct hydrogen
Stator Conductor: water
Totally Enclosed Water Air Cooled can be offered as an option.
Generator cooling systems shall be provided to maintain the temperature of the
various parts of the generator within the limits required by IEC60034 at
continuous rated output.
The complete equipment requirements for the following shall be provided:
Hydrogen cooling system,
Hydrogen seals and seal oil system,
Stator cooling system,
Brush gear ventilation system,
Generator casing purging
The equipment shall include all necessary pumps, valves, piping, reservoirs,
make-up tanks, filters, heat exchangers, instrumentation and ancillary
equipment.
Hydrogen Cooling System
(1) A hydrogen cooling surface system shall be required at both end of generator
shell to maintain the hydrogen temperatures within IEC60034 specified limits.
The hydrogen gas is forcedly circulated through coolers by cooling fans
coaxially fitted with shaft of generator. Water for coolers is supplied from cooler
inlet water system via automatic controlled valve.
(3) The hydrogen coolers used closed cooling water (demineralized water)
(4) Provision shall be made for any hydrogen leakage into the cooling water system
in service to be detected, alarmed and the rate of leakage measured. The
hydrogen leakage detector shall be provided and installed in suitable
location.The signal will be transferred to DCS for monitoring.
(5) The hydrogen leakage detector shall be provided and installed at generator
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 42 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
outlet terminal.The signal will be transferred to DCS for monitoring
(7) A covered water head tank shall be provided complete with inlet float valve and
discharge piping and valves.
(8) Any apparatus necessary for the withdrawal of the hydrogen coolers from the
generator casing shall be provided by the Contractor and itemized in the
Essential Tools and Appliances of the Proposal Documents.
(9) Drying equipment shall be provided for removal of moisture from the hydrogen
in the generator. If the equipment uses desiccant, facilities shall be provided for
its regeneration within the equipment without incurring the risk of hydrogen
explosion. Equipment shall be provided for measurement of generator hydrogen
dew point temperature and a signal provided for computer monitoring. In
addition, facilities shall be provided for filling the generator with dry air and for
passing dry air continuously when the generator is open for maintenance.
(10) An indicating and integrating flow meter shall be provided for measurement of
the hydrogen consumption rate of the generator. The range of the meter shall
cover the flow rate for a "tight" generator up to the flow rate at which the unit
must be taken out of service. The Proposal Documents shall state the maximum
rate of hydrogen leakage from the generator as a whole when the generator is at
rated conditions.
The flow meter shall incorporate a transmitter for computer monitoring of gas
consumption rate. Equipment shall also be provided for measurement of the gas
mixture purity of hydrogen in air, hydrogen in carbon dioxide and air in carbon
dioxide and signals provided for computer monitoring.
(11) Details of the source of hydrogen, its source pressure and its source dew point
will be provided by the Contractor.
(12) All necessary hydrogen vent lines shall be provided and shall discharge at least
2000mm above the turbine house roof. All hydrogen piping routes shall avoid
areas subject to a hazard from mechanical or fire damage.
Generator Cooling Board
(1) A generator cooling board shall be provided to accommodate all the equipment
associated with the control and monitoring of the generator cooling and seal oil
systems, but excluding the generator purging system. This shall include control
equipment, purity measurement equipment and instruments as recommended by
the Contractor. The board shall be located on the basement level of the turbine
house.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 43 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
atmosphere could occur due to hydrogen leakage.
Hydrogen Seals and Seal Oil System
A seal oil unit shall be provided to contain safely the hydrogen gas within the
generator housing.
Function: the system is provided to prevent hydrogen from leaking out of
generator casing to atmosphere
Normally, the seal oil source is taken from the main lube oil pump upstream of
lube oil control valve. The seal oil pressure in the system is automatically
maintained at a preset point by a seal oil regulator. The seal oil discharged from
sealing packing is routed back to the main oil tank through a set of stabilizing
and degasifying equipment.
(1) In addition to the automatic seal oil regulator, the system shall be equipped with
a manual standby feeding set ensuring the uncorrupted seal oil flow to the
generator hydrogen packing even for a prolonged outage of the unit.
(2) The system shall also be provided with adequate monitoring and protecting
equipment including liquid detectors etc.
(3) Shaft oil seals of a proven reliable design shall be provided. Details of the seals
shall be provided by the Contractor. The seal oil to hydrogen differential
pressure shall be maintained automatically at all pressures up to the maximum
hydrogen pressure, irrespective of the source of seal oil. The system shall be
capable of sealing rated gas pressure in the generator with the turbo-generator
stationary.
(4) 3x100% seal oil pumps (one AC seal oil pump, one AC emergency seal oil
pump and one DC seal oil pump).
(5) Two (2) seal oil coolers shall be provided. These shall be cooled from the
auxiliary cooling water system and shall be parallel on the water side. Adequate
seal oil cooling shall be provided by one (1) cooler in service in case of a cooler
inlet water temperature is low. The two (2) coolers may be paralleled to enable
generator MCR to be achieved in case of temperature is high.
(6) Equipment shall be provided for the treatment of seal oil to removed dissolved
gas to minimize the contamination of hydrogen in the generator.
Generator Casing Purging System
(1) The system shall permit purging the generator of hydrogen using carbon dioxide,
or of carbon dioxide using compressed air, in less than 90 minutes with the
generator stationary.
(2) The characteristics of the carbon dioxide supply shall be provided by the
Contractor.
(3) A panel shall be provided from which all operations necessary for purging the
generator can be carried out. The panel shall accommodate all monitoring
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 44 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
equipment associated with the purging system. The panel shall be located on the
basement level of the turbine house remote from the turbo-generator foundation
block, so that it can be reached safely in the event of a generator fire.
(4) The Contractor shall provide all necessary heating equipment should the carbon
dioxide require warming prior to injection into the generator.
(5) Provision shall be made for a 'visible-break' between the generator and the
sources of hydrogen, carbon dioxide and air to provide proof of isolation before
access is made available for maintenance of the system. The visible breaks may
consist, for instance, of flexible hoses with quick disconnect couplings, or
removable sections of pipe work.
Temperature Measurement
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 45 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
On-line water temperature monitoring system for stator winding bars: The
processor shall be complete with all software & hardware required to detect
any abnormalities in the temperature at any given generator operating point
and shall be sensitive to generator loads, header water flows, pressure etc.
and shall be possible to exchange information with DCS through suitable
protocol.
Instrumentation for vibration monitoring system: At least 6 nos. of pickups
at each end of over-hang portion of the winding to be provided,
symmetrically located around the periphery with connection to “Turbine
Supervisory” system. Provision shall be made to connect the same to DCS.
Instrumentation for liquid leakage detector shall be provided at all the low
level points inside the generator casing including end shields along with
provision for indication and alarm during leakage of liquid in generator.
Generator Current and voltage Transformers
(1) All current transformers shall be of the toroidal type suitable for installation at
the following locations:
a) In the ductwork between the generator and generator circuit breaker (GCB),
as close as possible to the GCB
b) On the generator neutral busbar terminals.
c) In the unit transformer busbars.
The secondary windings of all current transformers shall be brought out to
suitable terminals via isolating links for testing.
(2) Adequate supports shall be provided for all current transformers and such
supports shall not use in any way the main busbar, generator terminals nor the
terminals of the earthing transformers. The Contractor shall include in their
drawings detailing the proposed method of mounting current transformers.
(3) All protection and metering current transformers shall be insulated for the
system highest voltage. This system is none effectively earthed.
(4) Interposing CT's shall be mounted adjacent to the main CT's and the leads
between them shall be jointed by brazing. Each interposing CT cubicle shall
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 46 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
contain an anti-condensation heater.
(6) Test links shall be connected into the CT secondary circuits so that only the
external burden is subject to isolation by these links.
Voltage Transformers
(1) The high voltage neutral of the generator voltage transformers shall be isolated
from ground.
(2) The high voltage neutral of the generator transformer voltage transformers shall
be brought out from the tanks and connected by means of an approved cable to
the star point of the generator.
(3) The transformers shall be of the oil immersed, sealed non-breathing type
mounted in sheet steel tanks.
(4) The transformers shall consist of single-phase, fully isolated metal clad units,
comprising single-phase transformers for each phase, connected up as to form
three-phase, star-connected banks and shall be mounted in voltage transformer
cubicles.
(5) Bidders may offer arrangements consisting of either three single-phase metal
clad units (i.e. one per phase) or three units combined into a single
compartmented tank: the star point connections in this case being made via
bushings through the compartment walls, the star point being under oil. The
compartment walls shall be of metal and each compartment shall be entirely
scaled off from the adjacent compartments.
(6) Voltage transformer cubicles shall be provided with two phase isolated
compartments for each phase.
(7) One compartment shall house the VT truck for that phase and the second
compartment may be shared at a later stage by a surge diverter capacitor.
Facility shall be provided for taking oil samples. For this purpose a drain valve
shall be installed.
(9) Fire resistant shutters shall be provided which automatically close over the
apertures in the busbar chambers and over all primary conductors when the
voltage transformer is racked out from the busbar. The shutters shall be provided
with padlocking facility in the closed position. Padlocking shall be easily
accessible with the transformers in the racked-out position.
(10) The transformers shall be of the horizontal withdrawable truck type. The
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 47 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
arrangement shall be such as to enable the operation of racking-out and
replacing a transformer to be done with ease by one operator.
(11) Floor rails shall be provided to prevent damage to the floors of the cubicle while
the trucks are being withdrawn or replaced. The rails shall be zinc plating to a
minimum thickness of 25 microns.
(12) A mechanical locking device shall be provided on each VT truck to secure VT's
against accidental movement in both racked-in and out positions. It shall be
possible to close cubicle doors when VT truck is racked-out and shutters closed.
(13) It is preferred that the high voltage connections to the voltage transformers be
of the spring loaded male and female "spout" type. This insulation shall attain
the specified lightning impulse withstand level (LIWL) without the use of any
ancillary means (e.g. rubber glove). Tenderers shall comment on the method
used to maintain contact with the fixed conductors. Alternatives may be
proposed but in such case full details shall be included in the Bid. Bidders shall
submit test certificates with their offer proving their design obtains the required
LIWL with the VT in the in-service position.
Each compartment or individual tank shall be provided with an approved gas
impulse relay having two normally open contacts, one for tripping and one for
computer input. Each gas impulse relay shall be accessible for inspection and
gas sampling without withdrawing the truck. The secondary fuses shall be
accessible, in safety, with the transformer racked-in and in service. It is
preferred that connection of the secondary wiring to the fixed part of the cubicle
be by withdrawable plug connections. The use of sliding contacts when the VT
is racked into position is unacceptable. All secondary wiring shall be brought
back to the "CT/VT marshalling cubicle"
CT/VT Marshalling Cubicles
(1) A marshalling cubicle for each generator shall house all the secondary wiring
terminals required for the whole installation, together with the current
transformers, current test links, voltage test terminals and all auxiliary apparatus.
(2) Terminals of the same function and voltage shall be grouped together.
Generator Neutral Earthing Transformers
General
(1) Earthing transformers shall be of the single phase distribution type and shall
comply with the requirements of IEC60076 and IEC60726. One transformer for
each generator shall be supplied.
(3) The transformers will normally operate without any appreciable voltage on the
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 48 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
primary circuit.
Frequency 50 Hz
(5) The secondary terminals of the transformer shall be wired back to the
marshalling cubicle.
(6) The transformers shall be mounted within the generator foundation blocks.
Wheels are not required on the transformers.
Earthing Resistors
(1) The resistors shall be of the continuous strip type, shall be mechanically
robust, fireproof and mounted in wall or floor mounting weatherproof
enclosures.
(2) The resistors shall comply with the following requirements:
Cooling AN
Frequency 50 Hz
Resistance 2 ohms
Resistance tolerance +5%
Tappings 0.5 ohms to 2 ohms in 0.1 ohm steps
Power factor 0.95 minimum
Insulation test voltage 17 kV rms
(1 min. at 50 Hz)
30 minute current rating on each tap:
0.5 ohm - 551 A 1.3 ohm - 212A
0.6 ohm - 460 A 1.4 ohm - 197A
0.7 ohm - 394 A l.5 ohm - 184A
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 49 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Fire protection for the generator and related plant apply following clauses:
(1) The carbon dioxide purging system for the generator will be regarded as
providing adequate fire protection for the interior of the generator.
(3) A system shall be provided for the detection of hydrogen leakage to atmosphere
from the generator. In particular, detectors shall be located to detect leakage in
the region of the rotating hydrogen seals and from the pipe connections below
the generator. The detection of hydrogen leakage shall be alarmed in the fire
detection.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 50 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
harmonics and the effects of electrical interference between power and
control/instrumentation circuits, and comply with international requirements on
electromagnetic compatibility.
(5) The Bidder must provide a complete and comprehensive protection system for
the generators/generator transformers/unit auxiliary transformers, transmission
lines and the station electrical distribution systems during the detailed
engineering stage.
The Bidder must undertake the installation of the protection relay panels within
the control room, wiring between panels, and commissioning test of protection
schemes. Protection must be coordinated with Vietnamese Grid Company (i.e
Vietnam National Power Transmission Corporation) in accordance with the grid
codes.
7.3 500KV EHV OVERHEAD LINE
General Information
Scope of work
This specification covers the design, manufacture, testing at manufacturer's
works, supply and delivery, laying and installation at site, testing and
commissioning of the 500kV equipment (Current Transformer (CT), Voltage
Transformer (VT), Surge Arrester (SA), Insulator ), 500kV Overhead Line
conductor, Optical Ground Wire (OPGW+NMOC/24SM, Fiber Optic Media
Converter, Junction Box…) along with its accessories for the transmissions link
between 500kV Switchyard to Generator Transformers of the Project.
The Contractor shall be responsible for the design, manufacture, testing at
manufacturer's works, supply and delivery, laying and installation at site of the
500kV Tower and accessories from Quang Trach I to 500kV Switchyard.
The line conductor and its accessories shall be complete with all fittings and
components necessary for its effective working and efficient performance and
satisfactory maintenance under the various operating conditions specified. All
such parts shall be deemed to be included within the scope of supply whether
specifically included or not in these specifications. The successful Bidder shall
not be eligible for extra charges for such accessories.
The specifications covers steel structure components and electrical material
only at power plant's end required for linking 500kV line conductor to 500kV
Switchyard.
The specification also covers the jointing, end termination, testing and
commissioning of the line conductor and accessories at site. Exclusion(s) if any,
shall be brought out clearly and explicitly.
General
The conductor line and accessories furnished under this specification shall
conform to the standards specified under this specification.
The Contractor shall furnish the required instruction manuals as also the detailed
drawings for the cross linked polyethylene cable asked for in this specification..
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 51 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The Owner would like to conduct the type tests for the present order. The
charges for various type tests shall be quoted separately and these charges shall
be taken for evaluation. The Owner reserve the right to conduct all the type test
or any of the type test as considered necessary.
Unless brought out clearly, the Bidder shall be deemed to conform to this
specification scrupulously. All deviations from this specification shall be
brought out in the schedule of deviations. Any deviation between the
specifications and catalogues or the bid offered if not clearly brought out in the
schedule of deviations will not be considered as valid deviation.
The Bidder shall furnish the following information:
(2) Standing of firm as manufacturer of 500kV line conductor and accessories from
power plant to 500kV switchyard's gantry;
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 52 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The line conductors shall consist of aluminum conductor steel reinforced
(ACSR) of the cross section and having the characteristics as stated in the
ASTM standard B232
The earthwire shall consist of aluminum-clad steel conductor (ACS) of the cross
section and having the characteristics as stated in the ASTM standard B416-93
The conductors shall comply in all respects in accordance with the above
mentioned standards and/or other approved standards.
The steel wires, aluminum-clad steel wires and aluminum wires shall be
preformed so they remain inert when the conductor/earthwire is cut.
The steel cores of conductors shall be covered with an approved grease of
applied mass per unit length, in accordance to IEC 61089, Annex C, figure C2
Line conductor
Surface Conditions
All wires making up the conductor shall be uniform and smooth and shall have
no defects such as points, sharp edges, abrasions or other imperfections that
would tend to increase radio interference and corona losses. The conductors
shall also be free of metal particles and dirt. The make-up and the laying of the
conductor strands shall be such as to produce a conductor free of a tendency to
untwist or spring apart when cut.
The aluminum wire shall of the highest purity commercially obtainable and not
less than 99.5 percent. The contractor shall submit certificates of analyses giving
the percentage and nature of any impurities in the metal of which the wires are
made. Precautions shall be taken during manufacture, storage and erection of
ACSR conductors to prevent the possibility of contamination by copper or other
materials which may adversely affect the aluminum. The individual wires shall
be covered with aluminum. The covering must be smooth of uniform thickness
and free from surface imperfections.
Conductors to be applied in bundles shall be stranded preferably on the same
stranding machine to minimize settling differences. The Supplier shall prove
that the conductors applied at a bundle are manufactured with the same tension-
torque behavior. As there are at present no international standards known, the
Supplier shall propose a test method to be applied, to obtain characteristic values
of the conductor. After approval of the method, the tension-torque characteristic
value of the conductor from each reel/drum shall be recorded and shall be
marked at each reel. During acceptance tests, these values shall be remeasured
for all drums from which samples are taken.
Testing and Inspection
The inspection and testing shall be carried out on individual wires and stranded
conductors in conformity with IEC 61089
The test specimens shall be taken from 2% of the reels for conductors and from
least two reels. The test specimens of component wire before stranding shall be
taken from 10% length so that the following tests can be carried out:
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 53 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(1) Aluminum wire
Appearance test
Diameter Tensile test
Wrapping test Electric Conductivity
Surface Conditions
All wires making up the earthwire conductor shall be free of points, sharp edges,
abrasions or other imperfections. The conductor shall also be free of metal
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 54 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
particles and dirt. The make-up and laying of the conductor strands shall be such
as to produce a conductor free of tendency to untwist or spring apart when cut.
The wire strands shall be in close contact. The outermost layer shall be stranded
in the right hand way.
Testing and Inspection
The inspection and testing shall be carried out on individual wires and stranded
conductors in conformity with IEC 61089
The test specimens shall be taken from 2% of the reels for conductors and from
at least two reels. The test specimens of component wire before stranding shall
be taken from 10% length so that the following tests can be carried out:
Hard Drawn Aluminum-Clad Steel wire
Appearance test
Diameter
Tensile test
Torsion test
Elongation test
Concentric Lay Stranded Aluminum-Clad Steel Conductor
Appearance test
Construction test
Weight
Tensile strength
For each test the contractor shall bear the travel expenses for the EMPLOYER
or his Representative. Related costs shall be contained in material prices.
For the earthwire, the Bidder shall provide certified test reports with the Bid for:
A stress-strain test
A breaking strength test
Test to demonstrate that jointing of individual steel wires meets the
requirements of IEC 61089
Acceptance of Already Existing Test Reports
In case of existing proven and applicated design of the above testing, certified
results of a previous test may be acceptable, provided that the test results were
adequately documented and test parameters met the test requirements specified
herein and that the conductors and earthwire tested were of the types tendered
and specified for testing.
Factory Acceptance Tests
All materials are subject to inspection by the Purchaser and it is the Contractor's
responsibility to advise the Purchaser when equipment and materials are
available for inspection.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 55 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The Contractor shall carry out the tests specified in accordance with the latest
applicable Standards or Recommendations and such additional tests as in the
opinion of the Purchaser are necessary to determine that the Works comply with
this Specification either under test conditions (in the Manufacturer's Works or
at the destination port) or in ordinary working. Type tests may be omitted at the
discretion of the Purchaser if satisfactory evidence is given of such tests already
been performed on identical equipment.
All materials used shall also be subjected to and shall withstand satisfactorily
such routine tests as are customary in the manufacture of the types of plant or
material included in the Works.
All tests shall be carried out to the satisfaction of the Purchaser and in his
presence, at such reasonable times as he may require, unless agreed otherwise.
As many tests as in the opinion of the Purchaser are possible shall be arranged
together.
The original and 5 copies of test records whether they have been witnessed by
the Purchaser shall be supplied to the Purchaser
Measuring apparatus shall be approved by the Purchaser and if required shall
be calibrated at the expense of the Contractor at an approved laboratory.
The Contractor shall be responsible for the proper testing of materials supplied
by a sub-Contractor to the same extent as if the work, plant or materials were
completed or supplied by the Contractor himself.
The Contractor shall supply suitable test pieces of all materials as required by
the Purchaser. If required by the Purchaser test specimens shall be prepared for
check testing and forwarded at the expense of the Contractor to an independent
testing authority selected by the Purchaser.
No inspection or passing by the Purchaser of work, plant or materials whether
carried out by the Contractor or sub-Contractor, shall relieve the Contractor
from his liability to complete the Contract works in accordance with the
Contract or exonerate him from any of his guarantees.
Requirements for Materials
(1) Aluminum:
Aluminum bar or Aluminum thread 9.5mm standard.
Country of Origin of Aluminum (name and adress of the Manufacturer).
Before manufacture, the Bidder must submit documents which prove country
of origin of material.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 56 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(2) Steel:
Country of Origin (name of Manufacturer and adress of importer steel
thread/core)
Before manufacture, the Bidder must submit documents which prove country
of origin of material.
Requirements of quality of aluminum
Aluminum bar/ingot: Aluminum content 99.7% (minimum)
Steel content 0.2% (maximum)
Silic content 0.1% (maximum)
Aluminum thread: Conductivity 61.3% (minimum)
Breaking strength 70-170N/mm2
Elongation 4-18%
System Description, Characteristics and Operating Conditions
General
The connection between the Generator Transformer and Switchyard shall be
made by 500kV transmission lines.
The Bidder shall design, supply and installation the gantry steel structure and
towers at power plant's side and other materials to furnish all composition of
these systems.
Conductor Parameters
A brief description of the 500kV system parameters are given hereafter: 500kV
General
Current transformers shall be of the single-phase, oil immersed, outdoor post
type complying with IEC 61869.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 57 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The primary winding of the transformers shall be designed for the rated current
and shall withstand the specified through fault current without damage.
Secondary windings and connected equipment shall be protected against
damage by electrical contact with windings at system voltage as the result of
breakdown of insulation, by the provision of an earthed shield between primary
and secondary windings. This shield shall be earthed at the end closest to the
"P2" primary terminal. The current transformer shall mark clearly the P1, P2
terminal.
Ratings of 500kV Current Transformers as following:
Highest system voltage: 550 kV
Rated frequency: 50 Hz
Accuracy class and accuracy limit factor for measuring is 0.5 and protection
is 5P20:
The cores of current transformer for revenue metering shall have accuracy
class of 0.2 and shall be separated from other cores complying with
Vietnamese regulation.
Continuous Overcurrent: 1.5 times of rated primary current
Insulation level:
Rated power frequency withstand voltage: 710 kV
Rated lightning impulse withstand voltage: 1800 kV
Temperature rise : 65K.
General Arrangement
Current transformers shall be suitable for mounting directly on concrete pads
and shall include all necessary supporting steel structures. Anchor bolts shall be
provided and shall be of a type enabling the current transformers to be
positioned without the necessity of jacking over the anchor bolts.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 58 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
An earthing terminal shall be provided for each piece of equipment to enable
the equipment to be connected to the main earthing system.
500kV Voltage Transformer
General
Voltage transformers shall be of the single-phase, oil immersed, hermetically
sealed, outdoor, capacitor type complying with IEC 60358, IEC 61869.
Ratings of 500kV Capacitive Voltage Transformers:
Highest system voltage: 550 kV
Rated frequency: 50 Hz
Rated voltage factor and rated time : 1.2 (Continuous) / 1.5 (30 seconds)
Accuracy class (for measuring / for protection): class 0.5 / class 3P
The cores of voltage transformer for revenue metering shall have accuracy
class of 0.2 and shall be separated from other cores complying with
Vietnamese regulation.
Accuracy class of voltage transformer core for synchronization system shall
be of 0.2
Insulation level
Rated power frequency withstand voltage : 710kV (r.m.s)
Rated lighting impulse withstand voltage : 1800kV (p)
General Arrangement
Voltage transformers shall be suitable for mounting directly on concrete pads
and shall include all necessary supporting steel structures. Anchor bolts shall be
provided and shall be of a type enabling the voltage transformers to be
positioned without the necessity of jacking over the anchor bolts.
An earthing terminal shall be provided for each piece of equipment to enable
the equipment to be connected to the main earthing system
500kV Surge Arresters
General
The surge arresters shall be of the metal-oxide type without gaps, connected
between phase and earth suitable for outdoor installation, complying with the
requirements of IEC 60099-4.
Ratings of 420 kV Surge Arrests:
Type: outdoor, ZnO
Nominal for system voltage: 500 kV
Maximum system voltage: 550 kV
Neutral earthing: Directly earthed
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 59 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Max continuous operating voltage: 360 kV
Rated voltage: 420 kV
Rated frequency: 50 Hz
Nominal discharge current (8/20μs): 20 kA
Rated insulation level:
Rated frequency withstand voltage : 710 kV (r.m.s)
Rated lightning impulse withstand voltage: 1800 kV (peak)
Creepage distance : 31 mm/kV
General Arrangement
For transformer protection, each set of three surge arresters is to be mounted as
close as possible to the transformer line terminals while at the same time
allowing unimpeded access for the installation and possible subsequent removal
of the transformer.
The arresters shall be complete with supporting structures and a surge counter
for each phase.
The connection from the surge arrester via the surge counter to the substation
earth grid shall be without joints. The earth connection shall be insulated or
screened to protect personnel against transient voltages under surge conditions
500kV Insulator Unit
(1) Standards
Dry type transformers shall comply with IEC 60726, IEC 60076-11 as well as
the requirements of this specification as appropriate. Its windings with core are
kept within a sealed tank that is pressurized with air.
(2) Windings
(a) Short Circuit Capability
Transformers shall withstand for three seconds without significant mechanical
distortion or electrical failure the maximum fault conditions at any terminal or
any tapping.
(b) Winding Design and Construction
Asbestos shall not be used, in any form in transformers.
The windings shall be of the best modern design.
The windings shall be supported and clamped to withstand the stresses imposed
during normal service, short circuits and transport.
The insulation of the windings and tapping leads shall be suitably reinforced to
withstand voltage surges. Tappings and coils shall be arranged to preserve the
magnetic symmetry of the windings.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 61 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The flux density and ampere turns (B/H) curve is to be supplied for the core
steel to be used. The curve shall cover the range for the voltages specified.
(9) Foundations
The Bidder/Contractor shall provide all foundations.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 62 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
General Requirement of Oil Filled Transformer
(1) Standards
Mineral oil filled transformers shall comply with IEC 60076 as well as the
requirements of this specification as appropriate.
(2) Windings
(a) Short Circuit Capability
Transformers shall withstand for three seconds without significant mechanical
distortion or electrical failure the maximum fault conditions at any terminal or
any tapping.
(b) Winding Design and Construction
Asbestos shall not be used, in any form in transformers.
The windings shall be of the best modern design.
The windings shall be supported and clamped to withstand the stresses imposed
during normal service, short circuits and transport.
The insulation of the windings and tapping leads shall be suitably reinforced to
withstand voltage surges. Tappings and coils shall be arranged to preserve the
magnetic symmetry of the windings.
The conductors shall be free from scale, burrs and splinters and shall have
suitable rounded corners to reduce electrostatic stress concentration. A sample
of the conductor from each reel used for each H.V. winding shall be obtained
for testing. The testing shall be dimensional checks and metallurgical
examination for oxide inclusions and each sample shall satisfy the tolerance set
by the Bidder/Contractor. The Owner reserves the right to be provided with
samples for testing.
All joints between conductors shall be welded or brazed.
The insulation shall be applied to the conductors in a manner that will minimise
the occlusion of air.
No spaces, blocks, strips, washers or barriers shall be affixed to the insulation
on the conductors or turns by any adhesive material, composition or compound.
A detailed description of the concentration of the windings shall be included in
the Bid. Details on the following items are required.
The method of reinforcing the insulation to withstand voltage surges;
The manner in which the arrangement of tappings and coils preserves the
magnetic symmetry of the windings.
The method adopted for the even distribution of impulse voltage stresses.
This description shall indicate the location and function of any device
employed and its effect on the fault detection methods used in the impulse
withstand tests.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 63 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The techniques used to eliminate corona discharge within the transformer
under normal and test voltages.
The Bidder/Contractor shall provide design calculations of forces and stresses
on windings under short circuit conditions.
These shall comprise the following on all windings:
Forces and stresses.
Description of the sizing process and winding clamping pressures.
Basic core dimensions, winding sizes and location and all conductor details.
Details of winding insulation support structure.
The oil flow through the transformer oil cooled shall be such as not to cause
damage due to streaming electrification. The Bidder/Contractor shall provide
details of design changes limiting the oil speed within the requirements of
transformer under all operation conditions.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 64 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(4) Flux Density
The flux density and general design of the transformer shall be such that at 5%
and 10% over-voltage the RMS no-load current shall not exceed 2.3 times and
5.5 time respectively the value at rated voltage.
Attention shall be paid to the suppression of harmonic voltages, (particularly
the fifth and seventh harmonics) to minimise wave form distortion and to
minimise the possibility of high frequency disturbances, induction effects, or of
circulating currents between the neutral points of different transformers
reaching a magnitude such as to cause interference with communication circuits.
The Bidder/Contractor shall state in the technical schedules the magnitude of
third, fifth, seventh and ninth harmonics that will be present in the exciting
current at rated voltage, 5%, 10% and 35% over-voltage.
Under conditions of load rejection the generator transformer may be subjected
for one minute to a voltage of 135% rated voltage at the low voltage terminals.
The flux density and ampere turn (B/H) curve is to be supplied for the core steel
to be used. The curve shall cover the range for the voltages specified.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 67 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
conservator will come out. Again at low oil temperature; the volume of the oil
is decreased, which causes the volume of the oil to be decreased which again
causes air to enter into conservator tank.
The natural air always consists of more or less moisture in it and this moisture
can be mixed up with oil if it is allowed to enter into the transformer. The air
moisture should be resisted during entering of the air into the transformer,
because moisture is very harmful for transformer insulation. A silica gel
breather is the most commonly used way of filtering air from moisture.
Silica gel breather for transformer relates to conservator tank by means of
breathing pipe
The silica gel breather of transformer is very simple in the aspect of design. It
is nothing but a pot of silica gel through which, air passes during breathing of
transformer. The silica gel is a very good absorber of moisture. Freshly
regenerated gel is very efficient, it may dry down air to a dew point of below -
40oC. A well maintained silica gel breather will generally operate with a dew
point of -35oC if a large enough quantity of gel has been used. The picture
shows a silica gel breather of transformer.
Silica gel crystal has tremendous capacity of absorbing moisture. When air
passes through these crystals in the breather; the moisture of the air is absorbed
by them. Therefore, the air reaches to the conservator is quite dry, the dust
particles in the air get trapped by the oil in the oil seal cup. The oil in the oil
sealing cup acts as barrier between silica gel crystal and air when there is no
flow of air through silica gel breather. The color of silica gel crystal is dark blue
but, when it absorbs moisture; it becomes pink and they shall be replace. When
there is sufficient difference between the air inside the conservator and the
outside air, the oil level in two components of the oil seal changes until the lower
oil level just reaches the rim of the inverted cup, the air then moves from high
pressure compartment to the low pressure compartment of the oil seal. Both
happen when the oil acts as core filter and removes the dust from the outside air.
(f) Pressure Relief Vent
A vent shall be provided for relieving the tank of excessive pressure in the event
of a fault. The vent shall be as described below or a device like a “Qualitrol”
Pressure relief device. If such device is provided the discharge side shall be
covered so that oil cannot be sprayed beyond the bund area. The
Bidder/Contractor shall indicate release and reset pressures of the pressure relief
device.
The free end of the vent shall be closed from atmosphere by a diaphragm and
the air space between the oil and the diaphragm shall be connected to the
conservator. The bursting pressure of the diaphragm shall be stated on a label
adjacent to the diaphragm.
The lowest point of the diagram shall be above the highest level of oil in the
conservator. The vent shall direct the oil vertically downwards to discharge
within the below the bund wall enclosure provided should the diaphragm burst.
The inlet of the vent pipe shall be in a position where it does not collect gas.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 68 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(g) Valves
Valves required for installation, condition monitoring and maintenance shall be
provided.
Oil line connections to the coolers shall be made using valves for isolation of
the coolers.
A sampling valve shall be provided at the bottom of each oil cooler.
All valves used for the fitting of external hoses or for draining purposes shall be
fitted with blank flange plates with gaskets.
All flanges shall be drilled to ISO 7005.
All oil valves having a bore of 25 mm and above shall be of the gate outside
screw type.
(h) Thermometer Pockets
At least two thermometer pockets shall be provided in each transformer lid for
testing purposes. One pocket shall be placed near the edge and one close to the
middle of the lid.
(i) Oil Sampling Points
Oil sampling points shall be provided to sample oil from important locations for
condition monitoring purposes. Each sampling point and valve shall be brought
to a point not greater than one metre above ground level. The oil sampling points
shall be labeled to indicate the source from which the oil is taken. Screwed caps
with captive chains shall be provided on sampling valves
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 70 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Variation in oil pumping rate or pumping starting stopping shall not cause the
Buchholz relay to operate.
Drain and gas sampling valves shall be fitted with screwed caps to prevent
leakage. The caps shall be attached with brass or other approved corrosion-proof
chain to approved lugs on the transformer tank.
In addition to the screwed caps specified above, the gas sampling device shall
be supplied with a machined gunmetal nozzle which shall be attached to the
body of the device by means of a brass chain. The nozzle shall have a bore of 3
mm, and over a length of 50 mm shall be tapered from 10mm diameter at the
threaded end to 6mm diameter. The nozzle shall have a tapered thread of such
size that it may be substituted for the screwed cap when required for use.
The nozzle will be used to connect the hose of a Buchholz relay test set.
All parts shall be located for easy maintenance, operation and testing.
All the equipment shall operate satisfactorily, without the necessity for any re-
adjustment, within ambient air temperature limits of 0o and 40o and a maximum
transformer oil temperature of 90oC.
The Buchholz relay shall be inserted in a section of pipe between the conservator
and the transformer tank, which pipework shall be sufficiently braced to prevent
the mal-operation of the relay due to mechanical amplification of ground
vibrations during seismic activity. The Buchholz relay shall be positioned so
that the reservoir’s graduated window is as close to the perimeter of the
transformer’s lid on the L.V. side and at the tap changer end as practical. The oil
level in the reservoir is required to be observed from ground level and for any
maintenance to the relay. The position shall give the maximum section clearance
between the H.V. line conductors and the relay but will not prevent the relay
from operating satisfactorily. Non-ferrous or stainless steel nuts and bolts shall
be used to secure the relay to the piping.
An isolating valve shall be fitted in the pipework both sides of the Buchholz
relay to facilitate removal and testing of the relay.
The gas accumulation switch shall be self-resetting upon the release of gas or
air from the relay chamber.
Electrical connections to terminal studs within the relay shall be designed in
such a manner as to prevent terminal looseness and bad contacts developing as
a result of possible distortion or shrinkage of the insulating material used to
support the terminal studs.
The connections between the terminals and the switches shall be carried out in
flexible wires suitable insulated with material which will not be adversely
affected by the insulating oil used in the transformers or by the gases liberated
from this oil due to internal transformer faults.
Electrically separated pairs of terminals shall be provided for each switch circuit
and all such terminals shall be enclosed in a weatherproof housing with facilities
for conduit termination. The terminals for the gas and surge switches shall be
so spaced that the use of a tube spanner on one terminal shall not cause bridging
to an adjacent terminal
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 71 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(8) Winding Temperature Indicators, Heaters and Fibre Optics.
(a) Each transformer shall be fitted with winding temperature indicators of the type
which operates in conjunction with an associated heater and current transformer.
A removable earth connection shall be provided at one terminal of each current
transformer.
The winding temperature indicator heater systems shall be provided with means
to adjust the heat output of the heater without lowering the oil level in the
transformer. The heater shall be so adjusted that the temperature indicated shall
be the hot spot temperature of the winding.
Each winding temperature indicator assembly shall also be fitted with facilities
for showing the maximum temperature attained and the indicator shall be
arranged for resetting by hand.
Winding temperature indicators shall be fitted with switches with normally open
contacts. The switches shall be adjustable for closing temperatures. Two
contacts shall be cabled back to the ICMS (integrated control and monitoring
system).
(b) Resistance Temperature Detectors (R.T.D.’s)
Each transformer shall be fitted with not less than two platinum resistance
thermometers for remote indication to top oil temperature and for the remote
indication of “hot-spot” winding temperature.
All resistance temperature detectors shall be supplied with integral junction
boxes (heads).
The detector wiring shall be non-magnetic screened.
All resistance temperature detectors shall be of the three-wire type to permit the
power supply voltage to be brought out to the resistance temperature detector
head, thus minimising errors due to lead resistance variations with ambient
temperature changes. Cabling to resistance temperature detectors in pockets
shall be arranged to permit withdrawal of the resistance elements without
disconnecting the leads at the resistance element heads.
All resistance temperature detectors shall meet ± 0.25% accuracy from 0oC to
150oC.
The outputs shall be cabled to the ICMS for trend analysis.
(c) Fibre Optics
Sensors connected by optical fibres shall measure the top oil temperatures and
the hot-spot winding temperatures. Three different measuring points of the top
oil temperature shall be selected and three different measuring points in each
winding shall be monitored, total of 12 points. The Bidder/Contractor shall
indicate on transformer drawing(s) the proposed position where each sensing
point is to be located.
All equipment necessary to convert the reading to a display of the temperature
shall be supplied. The temperature reading display shall be positioned so that it
is near the winding temperature indicators. The provision of selecting the
temperature being measured shall be adjacent to the temperature display.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 72 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Provision shall be made to monitor 6 points in the ICMS control system.
(d) Indicating Thermometer
An indicating thermometer of an approved capillary tube type fitted with an
adjustable pointer and alarm contacts suitable for 220V DC. shall be provided
in a thermometer pocket on each transformer to indicate top oil temperature.
The sensing element shall be mounted so that it can be removed from the tank
without lowering the oil level.
Indicating devices on the transformer shall be mounted in such positions that
they are visible to an observer approaching the transformer along the
transformer yard runway or from the front of the auxiliary control cubicle
whichever is applicable. Temperature indicators may be mounted in a
weatherproof cabinet supported by resilient mountings on the transformer tank.
Two contacts of this device shall be cabled back to the ICMS (Refer to B-6).
The measurement systems referred to in paragraphs ii and iii above shall be
connected through 4-20 mA transducers for the purpose for ICMS monitoring.
(e) Temperature Indicator of Transformer
These are generally precision instruments. A temperature indicator of power
transformer is specially designed for protection of transformer in addition to its
temperature indication and cooling control features. That means, this device
performs three functions.
These instruments indicate instantaneous temperature of oil and windings of
transformer.
These also record maximum temperature rise of oil and windings.
These instruments operate high temperature alarm at a predetermined value
of allowable temperature limit.
Temperature indicators of transformer can also trip the circuit breakers
associated with the power transformer when the temperature of oil or winding
reaches a predetermined limit.
These devices also control the cooling system of transformer. Switch on the
cooling equipment when the winding attains a preset high temperature and
switch it off when the temperature drops by an established differential.
(f) Types of Temperature Indicator of Transformer
There are mainly two types of temperature indicators used in transformer.
Principally both instruments are the same but, one is used for oil temperature
and the other is used for winding temperature. There is another type of
temperature indicator often used in power transformer, which is little bit
different principally and this is remote temperature indicator. The
types of temperature indicator of transformer are:
Oil temperature indicator (OTI)
Winding temperature indicator (WTI)
Remote temperature indicator (RTI)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 73 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(9) Bushings and Terminal Arrangements
Bushings shall comply with IEC 60137.
Transformer bushings of GSUT HV side shall be oil filled and shall have an oil
level gauge and be provided with means for sampling and draining the oil.
Transformer bushings of GSUT LV side and both sides of UAT shall be
porcelain type.
The earth shield of condenser type bushings shall be brought to an external
insulated terminal for dielectric loss angle test purposes. A link shall be
provided by means of which this terminal will be connected to earth during
normal operation.
Bushings shall be permanently sealed to prevent breathing to the atmosphere.
The pollution level of outdoor bushings shall be ‘heavy’ to IEC 60815.
Porcelain insulators shall be sound, free from defects and thoroughly vitrified
so that the glazing is not relied upon for insulating purposes. The glazing shall
be smooth and hard. Porcelain insulators shall be secured in an approved manner
preferably by means of metal clamping plates with suitable packing material
interposed. Porcelain surfaces intended for mating shall be ground accurately
and free from glazing.
The bushings shall be capable of withstanding the same tests as the transformer.
The bushings shall not cause the production of anomalous oscillograms under
impulse tests.
Up to the time of tests on completion and as may be directed thereafter all
bushings exposed at Site shall be protected against contamination or mechanical
damage using robust coverings which shall envelope each bushing. Coverings
shall be renewed from time to time as may be required to ensure protection of
the bushings.
A bushing like those offered shall have been successfully type tested by a
recognised testing station. Certified copies of the test results shall be supplied.
Those which are available at the time of Request for Proposal shall be included
with the Bid.
A detailed description of the bushings, shall be included with the Bid.
The 500kV bushings shall be provided with adjustable arcing gaps. Dimensions
shall be subject to the approval of Owner.
The phase identity of the bushings shall be clearly identified in a satisfactory
manner using appropriately coloured enamel-filled, machined-engraved
stainless steel labels.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 75 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The diverter switch, and the selector switches shall be readily accessible for
inspection and maintenance.
It shall be possible to drain the diverter switch compartment and any separate
selector switch compartment without lowering the oil in the main tank below
the windings.
Where a tap changer is connected at the neutral end and is arranged for “buck-
boost” operation, the Bidder/Contractor shall state the means used to prevent
transient voltages appearing between the neutral terminal and the station earth
grid during tap changes when the reversing switch is changing from one mode
to the other.
(1) Essential Control Requirements
The tap changer shall be selectable for control from either
CCR or Remote Tap Control Cubicle
Local to the transformer.
Normal control will be exercised from the CCR by ICMS. CCR indication shall
be fed through 4-20 mA transducers.
A four-position selector switch located on the auxiliary control cubicle shall be
provided for the control of the tap changer as described below:
OFF - 12 o’clock
Tap changer control circuits disconnected. Tap changing by use of handle at tap
changer is possible.
LOCAL - 3 o’clock
Tap changer operable under pushbutton initiation from the auxiliary control
cubicle.
CCR - 6 o’clock
Tap changer operable under pushbutton initiation in the CCR. Separate “Raise
Tap change in Progress” and “Lower Tap change in Progress” lights and tap
position indicator shall be mounted in the CCR.
PORTABLE PUSHBUTTON STATION - 9 o’clock
Tap changer operable by means of pushbuttons connected to a flexible lead.
The tap changer control shall be arranged for step by step operation.
All tap changer control equipment shall be suitable for operation on a two-wire,
220V DC. supply.
All tap changer motors shall be suitable for operation on a 400V, three-phase,
50 cycle supply.
The Bidder/Contractor shall describe fully the effect on the tap changer offered
should the 400V a.c. and/or 220V DC. supplies be interrupted after the initiation
of a tap change.
(2) Control Equipment
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 76 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
All equipment necessary for the correct operation of the tap changer shall be
provided and shall include but shall not be limited to the following equipment
which shall be enclosed in the tap changer cubicle:
Operating mechanism including manual operating gear and handle.
Operating motor or motors.
Manually reset “range indicator” to indicate the range over which the tap changer
has operated.
Tap position indicator which shall be readable from outside the cubicle without
opening the cubicle door.
An operation counter.
“Tap change in progress” indicating light. This light shall remain illuminated
until the tap change has been completed.
Limit switches shall be included in both the power and control circuits to prevent
overtravel of the equipment on the extreme “raise” and “lower” limits.
A safety cut-off switch to isolate the motor controls before the manual operating
handle can be inserted or alternatively a device to prevent the manual operating
handle engaging when the control selector switch is at any position other than
“off”.
Out-of-step detection relays.
Terminals
Cable glands or gland plates
Wiring
Anti-condensation heaters
The following equipment associated with the transformer shall be enclosed in
the auxiliary control cubicle:
Power supply circuit breaker
Control supply circuit breaker and relate links
Motor contactors
Thermal overload relay
Pushbuttons for local control
Control selector switch
Indicating lights and alarm contacts for functions:
“Tap change in Progress”
“Tap change Incomplete”
“Tap changers Out-of-step”
Control relays
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 77 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Supply supervision relays
Anti-condensation heater/s
Portable pushbutton station (one for each cubicle)
(b) Automatic Voltage Control/Automatic Voltage Regulator (AVR)
Automatic Voltage Control shall be provided on the Generator Step Up
Transformers and the Unit Auxiliary Transformers (machine voltage to 11kV)
to maintain the 11kV voltage at the desired level. The tap changer controls shall
be arranged to provide this feature in auto both in the CCR. and local. Selection
switches shall be provided at both locations to permit manual or AVR control
of the tap changers
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 78 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(12) Bushing Current Transformers
The Bidder/Contractor shall provide current transformers within the
transformers. Details of current transformers are nominated in this Request for
Proposal Document.
General
The impedance of the generator transformer indicated in this Specification is
only the indicative value for system design purposes. The Bidder/ Contractor
shall determine the appropriate impedance value such that voltage distribution,
regulation and fault withstand capability of its connected equipment.
Rating and specification
Standard: IEC 60076
Phases: 3 phase
Type: Three phase, 2 windings transformer, oil immersed
outdoor
Frequency 50Hz
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 79 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The system shall include at least the following equipment and comply with the
following requirements:
The system shall be able to monitor the Oil & Internal temperature
conditioning and Oil circulation pump.
The local analyzer shall be mounted in a NEMA 4 enclosure.
The Oil Analyzing Systems shall have One (01) computer with LCD monitor
(24 inch) and one (01) data logging printer shall be provided to indicate the
abnormal status and the fault alarm.
All analyzers shall be connected to the computer for local monitoring and
shall also be connecting to the Distributed Control System (DCS)/ Integrated
Control & Monitoring System (ICMS) for the remote monitoring.
Communication interface shall be Modbus RTU or Modbus TCP allowing
networking with other devices via TCP/IP protocol
The special software required shall be provided together with the system. The
software required for modifying by operator shall also be provided. Help and
training software for using the equipment shall also be provided.
All data shall be recorded in the local analyzer and shall be available to be
downloaded to the computer, and the data shall be suitable for examination
and historical analysis.
The proposed design and the proposed equipment shall comply with this
Request for Proposal and shall also be subject to approval by the Owner.
The analyzers shall be connected to a local computer with LCD monitor (24
inches) for local monitoring and shall also be connected to the ICMS for the
remote monitoring.
The special software required for Generator Step-Up Transformer (GSUT)
On-line Oil Analyzing System shall be provided together with the system.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 81 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 82 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Unit Auxiliary Transformer (UAT)
General
The 22/11kV Unit Auxiliary Transformers shall be three-phase, mineral oil
immersed transformers.
The rating and impedance of the 22/11kV transformer indicated in this
Specification are only the indicative values for system design purposes. The
Contractor shall determine the appropriate values of transformer rating and
impedance such that voltage distribution, regulation and fault withstand
capability of its connected equipment.
The transformer oil shall be mineral type, without oxidation inhibitor and PCB
and can be mixed perfectly with Shell Diala, Nynax Nitro 10XT.
Contractor shall submit the type, origin of oil for Transformer, CT, VT to Owner
for information
Rating and specification
Standard IEC60076mineral oil filled
Type Three phase, 2 windings transformer, oil immersed , outdoor
Phases 3 phases
Frequency 50Hz
Rating 60 MVA (or depend on unit’s capacity which is chosen by
Contractor)
Vector Relationship Dyn1
Voltages:
HV 22kV (or generator voltage)
LV 11kV
Cooling: ONAN/ONAF (100% duty with one cooler unit out of service)
Impedance: Shall be calculated and confirmed by the Bidder/Contractor
Tap changer: On-load - IEC 60214
Tapping Range: ±8x1.25%
Terminals:
HV - Bushings with IPB heavy pollution class to IEC 60815 and to IEC
60137
LV - NSPB
LV neutral - outdoor bushing - heavy pollution class to IEC60815 and to
IEC 60137.
Insulation Levels:
HV Lightning Impulse 125 kV
Power Frequency 50 kV
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 83 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
LV Lightning Impulse 75 kV
Power Frequency 28 kV
Sound Level: IEC 60551 standard
Earthed: neutral point of the LV side (11kV) connects to earth
through resistor
Fault levels: Shall be verified by the Bidder
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 84 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Sound Level: IEC 60551 Standard
General
The Generator Circuit Breaker (GCB) shall be provided for each unit and shall
comply with all related standards including, but not limited, to the following
standards:
(1) IEEE Standard C37.013 Standard for AC High Voltage Generator Circuit
Breakers Rated on a Symmetrical Current
(2) IEC 60056 & IEC 62271-100 High Voltage Alternating Current Breaker
(3) IEC 60298, IEC62271-200 AC Metal Enclosed Switchgear and Control
gear for Rated Voltage Above l kV up to and including 25kV.
(4) IEC 60694, Common Clauses for High-Voltage Switchgear and Control
gear Standards.
(5) IEC 60529, Degrees of protection provided by enclosures (IP Code).
(7) IEC 60233 Checking the insulation distance used for electric device.
(8) Any other relevant standards
The Contractor shall be responsible to design, manufacture, inspect, supply,
delivery, unload at Site, install, test, commission and guarantee the GCB and
auxiliaries for each Unit to ensure the safe, efficient and reliable operation of
the Plant
The circuit-breakers shall be of the three phases, Sulphur hexafluoride (SF6)
gas insulation type. The circuit-breakers shall be of the non-withdrawable type,
totally enclosed inside phase isolated, metal enclosures. The metal enclosures
shall include removable covers for maintenance purposes.
The GCB's shall be complete in every respect and shall include a series circuit
breaker, disconnector switch, generator side earthing switch, transformer side
earthing switch, surge arrester, CT's, VT's and Local Control Kiosk complete
with mimic diagram and all necessary control, monitoring, indication and alarm
annunciation facilities.
The design shall ensure that the rated current of the GCB's and their associated
equipment exceeds the gross output of their respective turbine generator units
at minimum generator voltage, 0.85 power-factor lagging across the operating
ambient temperature range on Site with a design margin of not be less than ten
(10) percent. Characteristic curves of gross turbine generator output and GCB
rated current versus ambient temperature shall be submitted accordingly and
shall be subject to approval by the Owner.
Static and moving gas seals shall be designed to prevent the leakage of gas or
ingress of moisture throughout the service life of the interrupting module.
Where the design is such that leakage could cause gas pressure to fall below that
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 85 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
at which the specified insulating and interrupting capacities can be maintained,
gas pressure monitoring devices shall be incorporated to provide an alarm and
block operation.
Adequate external clearances and surface creepage distances shall be provided
to ensure satisfactory performance under service conditions
Generator Circuit Breaker parameter requirements
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 86 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(1) The breaker shall be comply with IEEE Std C37.013 Standard for AC High
Voltage Generator Circuit Breaker rated on a Symmetrical Current and
IEC60056 High Voltage Alternating Current Circuit Breaker.
(2) The circuit breaker and isolating switch shall be designed for horizontal
mounting in the phase isolated busbar system.
(3) Each single phase circuit breaker complete with isolating switch and grounding
switches shall be furnished with a separate enclosure to maintain the integrity
of the isolated phase bus ducting. The enclosure shall be a rigid self supporting
structure fabricated from aluminum and suitable for indoor installation. All
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 87 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
contact surfaces shall be silver plated.
(4) The circuit breaker shall be capable of clearing the following faults as well as
normal switching duty associated with large steam driven turbine generator
plant.
a) Fault in Turbine, Generator or between Generator and Generator Circuit
Breaker. Breaker shall isolate generator to ensure continuous power supply
from the 500kV switchyard for the auxiliary system via the GSUT.
b) Fault in GSUT or between GSUT and GCB, between GSUT and 500kV
switchyard.
c) Fault in 500kV switchyard ( in case the 500kV circuit breaker is not tripped
successfully)
d) Fault in UAT and Excitation transformer or between UAT, excitation
transformer and GCB.
e) It shall be possible to obtain full isolation including provision of a visible
break by the inclusion of a built in isolating switch associated with the
circuit breaker.
(5) The isolating switch and circuit breaker shall both be provided with their own
separate grounding switches. Each grounding switch shall be rated for full fault
current closure.
(8) Removable panels shall be provided on all equipment to permit access to all
working parts for maintenance.
(9) A mechanical locking device shall be provided to permit padlocking the breaker
in the open position.
(10) Single phase operation or three phase operation of the three pole assembly will be
applied.
(11) An integral sheet metal control cabinet shall be supplied with instruments and
equipment for controlling, monitoring and indicating the switching operations
of the circuit-breaker, and its associated auxiliaries. The following control and
indicating facilities shall be provided as a minimum:
(a) Local - Off - Remote key operated selector switch.
(b) Local electrical opening and closing facilities.
(c) Remote electrical opening and closing facilities via interposing relays.
(d) Mechanical open and closed indication facilities.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 88 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(e) D.C. close and trip coils and an additional D.C. trip coil per pole.
(f) Gas pressure meter for each SF6 filled compartment
(g) Operations counter.
(h) Status of circuit breakers, earthing switches, disconnector switch
(i) Mimic diagram.
Alarm tableau with first up facility.
Lamp test push-button.
Circuit Breaker Operating Mechanism
(1) The circuit-breaker operating mechanism shall be of the stored energy type, and
shall have a capacity which is sufficient to perform an open-close-open (O-C-
O) duty without replenishment from any external source. No closing operation
shall be possible without sufficient stored energy in the mechanism to open the
circuit-breaker again.
(2) The operating mechanisms shall be designed such that the circuit-breaker is free
to open immediately the tripping circuit is energised and without the use of any
additional external power. Mechanisms shall be “trip-free” as defined in IEEE
Std C37.013 and shall have an anti-pumping feature. It is recognised that it may
be necessary for contacts to close momentarily prior to opening to ensure
satisfactory current interruption
(3) A direct acting mechanical trip via an emergency push button shall be provided
on each circuit-breaker.
(5) Means shall be provided for manual operation and slow closing of the circuit-
breaker for maintenance purposes when the equipment is disconnected and
earthed.
(6) Means shall be provided to prevent the local and remote control apparatus from
being in operation simultaneously.
(7) It shall not be possible without the use of tools to gain access to the tripping
toggle or any part of the mechanism which would permit defeat of the
mechanical tripping feature.
(8) It shall not be possible to render the electrical tripping feature inoperative by
any mechanical locking device.
(9) It shall be possible to complete the closing, tripping and interlock circuits when
the circuit-breaker is isolated to permit operation for test purposes
(10) Single phase operation or three phase operation will be applied to the circuit breaker
operation mechanism.
circuit breaker by means of a single (common) operating rod.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 89 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(11) The three phase circuit breaker assembly shall be controlled by one of the
following methods:
(a) Hydraulic operating mechanism,
(b) Stored energy spring charged operating mechanism,
(c) A combination of stored energy spring charged/hydraulic operating mechanism.
(1) There shall be two (2) circuit-breaker trip coils, preferably supplied from two
(2) different DC sources. Furthermore a fault in the D.C. closing circuit shall
not prevent the tripping of the circuit-breaker. Two electrically and magnetically
separate tripping mechanisms, each operated by a separate trip coil shall be
provided for each circuit breaker. If one tripping mechanism fails or fails to
operate correctly it will not prevent the other mechanism from operating
correctly.
(2) Trip coils shall be suitable for nominal 220V DC. Operation and be capable of
operating within the voltage range of 154V(70%) to 242V DC(110%)
(3) Trip circuit supervision with the circuit-breaker in the open and in the closed
position shall be provided together with local and remote alarm annunciation
facilities
Closing Coil
The closing coil shall be suitable for nominal 220V DC. Operation and be
capable of operating within the voltage range of 187V(85%) to 242V
DC(110%).
Disconnector Switch Operating Mechanism
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 90 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
earthing switch operating mechanisms and in addition to the normal local
electrical open/close control facilities the mechanism shall also be provided
with manual operation facilities for emergency and maintenance purposes.
Mechanical open/closed status indications shall also be provided.
(3) The disconnector shall be interlocked such that it cannot be opened or closed
unless the circuit-breaker is open and viewing windows shall be provided in the
equipment enclosures to facilitate direct observation of the disconnector
position and confirmation of the isolating distance
(4) Single phase operation or three phase operation will be applied to the
Disconnector switch operation mechanism.
(5) The disconnectors shall be operated by a 400V LV, 3 phase motor driven
operating mechanism and the three (3) poles shall be mechanically and
electrically interlocked to ensure that all three (3) poles open and close
simultaneously.
(7) The three-phase Disconnector switch assembly shall be equipped for emergency
manual operation by means of a hand crank
(1) Earthing switches shall be fitted on both sides of the circuit-breaker to permit
maintenance of both the generator circuit and/or the generator step-up
transformer and unit auxiliary transformer circuit.
(2) The earthing switches shall be operated by a 400V LV, 3 phase motor driven
operating mechanism and the three (3) poles shall be mechanically and
electrically interlocked to ensure that all three (3) poles open and close
simultaneously
(4) The earthing switches shall be interlocked such that they cannot be opened or
closed unless the circuit-breaker and its disconnector are open and viewing
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 91 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
windows shall be provided in the equipment enclosures to facilitate direct
observation of the earth switch position. Interlocking shall also be provided to
prevent the operation of the earthing switches unless the relevant remote
switching devices are open (disconnectors) or withdrawn into the test position
(circuit-breakers).
(5) The three-phase earthing switch assembly shall be controlled by a 220V DC.
(6) The three-phase earthing switch assembly shall be equipped for emergency
manual operation by means of a hand crank.
(1) It is required that the construction details and the design of the equipment should
be such that it will continue in reliable service with a minimum of maintenance.
Furthermore, this maintenance should not require that personnel be especially
trained and skilled in the details of this equipment because unusual or sensitive
component designs have been incorporated.
(2) In assessing the generator switchgear offered, close attention will be paid to the
way the following principles of design have been observed.
a) All similar mechanical parts are to be strictly interchangeable without
special adjustment or individual fitting.
b) The assembly of parts shall be easy and simple without requiring special
skill in adjustment of alignment. This requirement is to be provided by
dowels, spigots, counter bores, etc.
c) The design should be such as to avoid as much as possible the necessity of
close tolerances and fits to ensure that the presence of foreign bodies, dust
and moisture or the occurrence of high or low temperatures cannot cause
any maloperation.
d) The performance of the design, particularly that of individual components,
shall be checked not only many times at normal operating conditions, but at
conditions above and below normal to establish the limits at which
equipment fails to operate correctly, thus establishing the safety margin to
allow for variations in manufacture and in service conditions and
maintenance.
e) All mechanical parts and linkages shall be robust, requiring a minimum of
maintenance.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 92 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
f) Operating forces available from electrical and mechanical sources should be
a suitable multiple of and where possible may times the forces required for
functioning under designed conditions to ensure beyond any doubt that all
elements will operate correctly and reliably for an indefinite period under
minimal maintenance attention, most normal service conditions, and
considering the variations in manufactured materials, workmanship and
tolerances.
g) When components of well-tried designs but with lower operating forces are
to be used at higher operating forces and speeds, the operation should be
thoroughly examined to ensure that the operating margins are still intact
h) Where Bidders offer a design which is generally well-proved in service they
must draw attention to any components which may have had to be modified
recently or which may in fact be newly designed, even though they regard
these as minor components. Changes will not be accepted which in any way
invalidate the type test certification of the whole device in any respect.
i) It is required that the circuit breakers, disconnector switches, earthing
switches and operating mechanism should be of the highest reliability.
j) All rubber components of the circuit breakers should be completely suitable
for their duty and should maintain their effectiveness indefinitely in the case
of joints, gaskets and other such non-working parts. In the case of rubber
parts subject to dynamic stresses, e.g. valve faces, they should also maintain
their effectiveness indefinitely.
However, where they can readily be replaced without replacing the
components in which they are mounted then they should be effective for a
period of at least ten years under service conditions without replacement
and without detriment to circuit breaker operation.
(3) Bidders shall state in their technical description of the generator switchgear
offered such details as are necessary to assess their offer in the light of the above
design, construction and maintenance principles.
(4) A lightning arrester and a surge capacitor at each phase should be provided at
(22kV) line side
Control and Interlocking Philosophy
The control power for circuit breaker, disconnector switch and earthing switch
shall be controlled by 220V DC.
(4) The scheme of mechanical and electrical interlocks shall be provided. All
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 93 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
mechanical and electrical interlocks shall be of the preventative type and shall
be arranged to prevent mal-operation of the equipment if the interlock is
defeated.
(5) Electrical interlocks shall be hard wired fail safe design and shall function to
interrupt the operating supply and shall also include for emergency hand
operation. Failure of the electrical supply or its restoration shall not produce or
permit faulty operation.
(7) Under normal operating conditions and when selected for remote operation the
circuit-breakers shall be closed by their respective synchronising systems and
electrical interlocks shall be provided to prevent the closing of circuit-breakers
on to live connections unless the incoming and running voltages are equal and
in synchronism.
(8) Interlocking shall also be provided such that except under maintenance
conditions, it shall not be possible to close the circuit-breaker unless the
respective series disconnector and HV circuit-breaker are closed.
(9) Simultaneous operation from local and remote shall be prevented by the
provision of a Local/Off/Remote Selector Switch key operated with the key
withdrawable in the remote position only. Except for the circuit-breaker all other
equipment shall be operated locally.
(10) A system of hard wired safety interlocks shall be provided by means of auxiliary
contacts on all necessary remote equipment to prevent (i) the closing of
disconnectors unless all relevent earthing switches are open and (ii) the closing
of earthing switches unless all relevent disconnectors are open and all relevent
MV and LV circuit-breakers withdrawn into the test position. Back reporting
contacts for the status of the circuit-breaker, disconnectors and earthing
switches shall be provided to enable the interlocking of the remote equipments.
In other words the interlocking philosophy implemented shall be a visible break
fail safe interlocking philosophy throughout.
Current transformers (CT)
The CTs are supplied for measurement and protection relay. The CTs are
installed in separate cubicles.
The CTs are accordant with IEC 61869 standard. They shall have high
precision level.
Voltage transformers (VT)
The VTs are supplied for measurement and protection relay. The VTs are put
at fixed position in casing of generator circuit breakers.
The VTs are accordant with IEC 61869 standard. They shall have high
precision level.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 94 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Circuit Breaker Control Cubicle
A control cubicle shall be provided for the generator circuit breakers, isolators
and grounding switches.
Maintenance Equipment and Special Tools
(1) One complete set of all SPECIAL spanners, tools and applicances including
special slings and lifting equipment necessary for maintaining the whole of the
plant including that plant supplied by Subcontractors, shall be provided. The
spanners and tools supplied under this Clause shall be new and shall not be used
during the erection of the plant. A list of such spanners, tools and appliances
shall be given in the appropriate Schedule of the Specification.
(2) The spanners shall include two spanners to fit the nuts of all bolts 25 mm
diameter and over. Grease guns, spanners and tools which are of a size and type
which could be reasonably expected to be readily available to tradesmen are not
required to be provided under this Clause.
Spare Parts
(1) The Bidder shall list in the pricing schedule of the Specification the individual
prices of the spare parts (if any) included in the Bid together with the prices of
all other spare parts that the manufacturer recommends should be held. Unit
prices should be stated and the price given shall be valid for any reasonable
quantity required under the Contract.
(2) The Owner may order all or any number of the parts at its discretion. The
Contractor shall supply the parts selected at the individual prices stated in the
Schedule.
(3) All parts ordered shall be interchangeable and suitable for use in place of
corresponding parts supplied with the plant. They shall comply with the
Specification and shall be suitably marked pr numbered for identification and
prepared for storage in an approved manner to prevent deterioration. Packing
and identification of spare parts shall be in accordance with the requirements of
this Specification.
Consumable spares which will require replacement at intervals of less than 12
months, shall be provided as part of the Contract and the price included in the
Bid. The consumable spares shall be sufficient for one year's normal usage,
where an item is not listed in the appropriate schedule and requires replacement
in less than 12 months from the date of Practical Completion
7.6 ISOLATED PHASE BUSBAR (IPB)
General
The IPB shall be complied with all related standards including, but not limited,
to the following standards:
IEEE C37.23 - Standard for Metal-Enclosed Bus
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 95 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
IEC60071 Part 1 - Insulation Co-Ordination - Definitions, Principles and Rules
IEC60071 Part 2 - Insulation Co-Ordination - Application Guide
BS 159 - Specification for High Voltage Busbars and Busbar Connections
BS 1977 - Specification for High Conductivity Copper Tubes for Electrical
Purposes
BS 2898 - Specification for Wrought Aluminum and Aluminum Alloys for
Electrical Purposes - Bars, Extruded Round and Sections
IEC600168 - Tests on Indoor and Outdoor Post Insulators of Ceramic Materials
or Glass for Systems with Nominal Voltages Greater than
IEC60137 - Bushings for Alternating Voltages above 1000V
IEC60060 Part 1 - High Voltage Test Techniques - General Definitions and Test
Requirements and Test Requirements
IEC60060 Part 2 - High Voltage Test Techniques - Measuring Systems
ISO 9606-2 - Approval Testing of Welds - Fusion Welding -Aluminum and
Aluminum Alloys
ISO 3777 - Radiograph Inspection of Resistance Spot Welds for Aluminum
and its Alloys - Recommended Practice
ISO 2437 - Recommended Practice for the X-ray Inspection of Fusion Welded
Butt Joints for Aluminum and its Alloys and Magnesium and its
Alloys 5 to 50 mm thick.
Scope of supply
The Contractor shall responsible to design, manufacture, factory test, inspect,
supply, delivery, unload at Site, install, test, commission and guarantee the
Isolated Phase Busbar (IPB) and auxiliaries for each Unit to ensure the safe,
efficient and reliable operation of the Quang Trach I Thermal Power Plant
Two complete three phase sets of IPB with all supporting insulators and
enclosing ductwork. Also two complete sets of supports, frameworks and
brackets. The set of busbars shall consist of the following sections (for 1 set):
(1) The main busbars between the Generator and its Generator Step Up Transformer
including the flexible connections to the generator terminal stalks and to the
terminals of the GSUT.
(2) The generator star point busbar including the flexible connections to the
generator neutral terminal stalks.
(3) Unit Auxiliary Transformer tee off, including the flexible between the busbars
and the high voltage transformer terminals.
(4) The excitation transformer tee off, including the flexibles between the busbars
and the transformer terminals.
(5) The voltage transformer connections from the main busbars to the voltage
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 96 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
transformer cubicles.
(1) The busbars shall be of the air insulated, self-supporting, isolated phase busbar
type enclosed in weatherproof metal ductwork and shall be naturally cooled.
This shall be achieved with an air delivery and drying system with a delivery
rate matched to a controlled overall bus system air leakage rate. The delivery
capacity shall be sufficient to maintain positive pressure at all times. Sight-glass
ground level water collection points will be provided as a means of monitoring
dryness.
(2) The busbars and ductwork from the foundation block, across the floor of the
turbine house, through the turbine house wall to the transformer terminals, etc.,
shall be supported by means of structures, frameworks and brackets to form a
rigid structure. The busbars shall be of the air insulated, self supporting, phase
isolated
(3) The busbars and ductwork from the foundation block, across the floor of the
turbine house, through the turbine house wall to the transformer terminals, etc.,
shall be supported by means of structures, frameworks and brackets to form a
rigid structure.
(4) The Contractor shall provide weather proof sealing plates where the ductwork
passes through the turbine house wall.
(5) The Contractor shall prevent the transmission of building vibration to the
ductwork as well as allowing for electrical isolation of the ducting.
Electrical Characteristics
(1) The whole of the busbars and connections shall have a current rating of not less
than 110% of rated current of generator. These and all following fault levels are
based on a generator line voltage of 22kV. For any higher generator line voltage
all fault currents will have to be adjusted by the Contractor.
(2) The branch isolated phase busbars between the main isolated phase busbars and
the Unit Auxiliary Transformer 22(Ugen)/11kV are required to have a current
rating of not less than 110% of rated current of these equipment. For any
different generator line voltage all fault currents will have to be adjusted by the
Contractor.
(3) The branch isolated phase busbar between the main isolated phase busbars and
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 97 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
the excitation transformer is required to have a current rating of not less than
110% of rated current of these equipment. For any different generator line
voltage all fault currents will have to be adjusted by the Contractor.
(4) All conductors and conductor details, including the neutral conductor shall be
insulated for a lightning impulse withstand voltage as per IEC60071 Parts 1 and
2.
(5) The IPB must carry the rated current continuously without exceeding the
following temperature limits considering an ambient temperature of 40°C
and duly considering the effect of solar radiation:
Main conductor: 105°C
Bus connections: 105°C
Busduct enclosures and support structures: 80°C
(6) Rated voltage: 1.1 times of generator rated Voltage (Ugen plus 10%);
(11) The Bidder shall provide all the details as set out in the Technical Schedules.
Construction
(1) Busbars shall be of copper, aluminum or aluminum alloy and shall comply with
the requirements of BS 159 and BS 1977 or BS 2898 as required.
(2) Allowance shall be made for expansion and contraction of the conductor and
housing due to normal or short circuit temperature rises. The use of sliding joints
in conductors will not be considered. Conductors may be joined together leaving
a suitable expansion clearance and the electrical connection made by means of
bolted flexible conductors.
(3) The connection point to the generator, unit and excitation transformer busbar
Interconnections shall be of the flexible type and these flexible shall be
removable for isolation purposes.
(4) The generator neutral current transformer (GNE), the primary terminals of the
neutral earthing transformer, the neutral cable and bushing and all high voltage
connections between these parts shall be situated in a weatherproof aluminum
casing, the side panels being removable to allow access to the inside of the
casing.
(5) Busbar adaptor plates shall be provided at the terminal points to take up possible
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 98 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
minor misplacement during erection. The adaptor plates shall be drilled on site.
(6) The joining of busbar sections shall be carried out by either bolting or welding.
If bolted, the bolting details shall not be subject to electrolytic action.
(7) All bolts and nuts shall be locked after erection. For electrical conducting
connections all bolts, nuts and washers shall be of non magnetic stainless steel
grade 8.8. Belleville type washers shall be used at joints on the main connections.
(8) All jointing surfaces to copper busbars, intermediate or adaptor plates and
flexible conductors shall be silver plated.
(9) All jointing surfaces on aluminum busbars, intermediate or adaptor plates shall
be greased with Penetrox or other approved contact compound and wire brushed
before bolting up. Different method may be used only if approved by The Owner.
Ductwork
(3) Provision shall be made to ensure that water leaks from any source will not
accumulate in the ductwork. Drains shall be provided at all low points of the
ductwork system i.e. voltage transformer cubicles, excitation transformer, unit
auxiliary transformer and generator transformer. Drains shall be of the sealed
type and description shall be given of the provisions made to maintain pressure
within acceptable limits. Each drainage location the drains from each phase shall
drain into a single drainage container located at ground level. The drainage
container shall be made from glass or UV protected plastic and be fitted with a
drain valve.
(5) The enclosure around the generator terminals shall be so arranged that the
current carrying flexible connections and the bushing connections are easily
accessible for inspection and maintenance.
Aluminum Welding
(1) Aluminum welding shall comply with all clauses of ISO 9956-4, ISO 10043 and
ISOTR 11 069.
(2) All butt welds shall be complete penetration butt welds. Backing bars shall be
close fitting, centred at the joint and of sufficient thickness to avoid burn
through. Typical joint details shall be submitted by the Contractor to OWNER
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 99 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
to designate joints for non destructive testing.
Support Structures, Framework and Brackets
(2) They shall be designed to withstand, with ample margin, the thermal stress
arising from the normal full load current and the mechanical and thermal
stresses arising from the maximum fault currents.
(3) It is preferred that no support be taken from the generator block. However, if
the design of the ducting is such that this is necessary, special provision shall be
made for preventing the transmission of vibration from the generator block to
the ducting. The design of anti-vibration mountings shall be submitted to the
Owner for approval.
(4) The temperature of any portion of the supports, etc., (excluding the ductwork)
shall be raised by not more than 40oC measured by thermometer when the bus
is carrying full rated current. If necessary, the Bidder shall provide suitable
magnetic screens to ensure that this temperature rise is not exceeded.
Busbar Support Insulators
(2) The Bidder may offer either porcelain or epoxy resin type insulators.
(3) As part of the Bid Proposal, the Bidder shall provide detailed evidence in
relation to the nominated insulator manufacturer for each of the following items:
(a) Previous experience in manufacturing these insulators (detailing respective
clients).
(b) Facilities available for testing to prescribed standards (i.e. type test etc.). If the
manufacturer is unable to conduct certain tests, the tenderer shall nominate the
venue for such testing.
Dished Spring ("Belleville") Washers
(1) All Belleville washers shall be manufactured from suitable spring steel so that
the finished product will have the mechanical properties and as indicated below.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 100 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(2) To avoid stress concentration, the internal and external edges shall be rounded
by shot-peening or by other approved method. The washers shall be suitably
heat-treated to avoid hydrogen embrittlement. After the fabrication and heat
treatment, all washers shall be subjected to a suitable cleaning process to
completely remove any grease, rust, scale, dirts, etc.
General
Two diesel generator sets shall be provided for each Unit. Each diesel generator
set shall be a stationary industrial type installed inside container located outside. The
fuel oil tank, cooling tower and exhaust silencer shall be suitable for outdoor
installation. Both diesel engine and generator with its exciter shall be close
coupled with outboard bearing and mounted on a substantial bedplate.
Design and Selection
(1) Each set and its auxiliaries shall be physically, mechanically and electrically
separate to ensure that no single event can cripple both sets. Similarly, each
diesel generator and its auxiliaries shall be able to operate independently of the
availability of other power station plant.
(3) The diesel generator shall be of established manufacture and the model offered
shall be well proven in service with minimum 5 years operating experience.
(4) The design shall be such that overall functional reliability, ease of maintenance
and simplified controls are given due consideration.
(6) All parts shall be easily accessible for operation and maintenance. Where
necessary, the Contractor shall provide all necessary platforms and steps.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 101 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
available.
(8) The Bidder shall describe the type and nature of after sales facilities available
in Vietnam. Consideration will be given to after sales service facilities in the
assessment of bids.
Rating
The Contractor shall determine the rating of the diesel generator based on the
philosophy and parameters described hereafter
Capacity Power : 1000kW (to be specified by constructor),
Quantity : 2 sets
Rated voltage : 400V
Phase : 3 phase
Frequency : 50Hz
Power factor : 0.85
Rated speed : 1500 rpm
The daily tank shall have sufficient capacity for at least 12 hours of continuous
engine operation at full load. An alarm shall be provided which warns that the
volume of fuel in the day tank is less than this amount.
(1) Each diesel generator set with its auxiliaries shall be capable on its own of
providing electrical power to maintain both of the boiler-turbine units and
associated auxiliary plants together at the power station in a safe condition
following a shut-down under emergency conditions with a margin of at least
10%. A typical case is the loss of all external power supply to the station. The
loads to be supplied by the diesel generators in an island condition shall as a
minimum include the following:
The loads to be supplied by the diesel generators in an island condition shall as
a minimum include the following:
A.C. turbine turning gear
A.C. turning gear oil pump ,if the case
A.C. hydrogen seal oil pump, if the case
A.C. turbine oil tank vapour extractor
A.C. main oil pump
A.C. steam feed pump turning gear
A.C. steam feed pump oil pump
A.C. flame scanner fan
Boiler fans oil pumps
Gas air heater lube oil pump
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 102 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Diesel oil forwarding pump
Gas air heater main drive
any other A.C. drives required for a safe shutdown
battery chargers
diesel generator auxiliaries
CCR and control room lighting (via battery chargers/UPS)
Switchyard control room lighting (via battery chargers/UPS)
Stack obstruction lighting (via battery chargers/UPS)
Remote plants emergency lighting (via battery chargers/UPS)
Fire-fighting system
HVAC
Lifts
Coal and ash plant
And other loads/system subject to approval by Owner.
Bidder/Contractor will be required to make their own assessment of diesel
generator loads for generator capacity.
(2) For any motor being supplied from the islanded diesel generator, the voltage
drop at the motor terminals during starting shall be no greater than 15% from
the pre-start voltage level.
(3) The frequency drop during the connection of any block of load to the islanded
diesel generator shall not exceed 2.5 Hz of rated.
(4) The Bidder shall describe the loads to be connected to the diesel generators and
submit to the Owner calculation sheets to justify the rating selected.
(5) The Bidder shall guarantee the performance of the diesel generator by
acceptance tests in accordance with ISO 3046/2 and IEC 60034.1.
Operating Philosophy
The diesel generators shall form part of the emergency power supply system
whose purpose is to protect the boiler/turbine-generator plant and to maintain
systems necessary for the safety of personnel in the event of loss of normal a.c.
supplies. In the immediate aftermath of loss of a.c. supplies, plant safety shall
be maintained by d.c. auxiliaries supplied from the 220 V d.c. system. The
batteries will be sized to be capable of maintaining the safety of plant of both
units together without restoration of the battery chargers for 1 hour with one
station batteries available
The diesel generator shall start automatically and excite to rated generator
voltage as soon as possible after loss of normal A.C. supply, then restoring
power supplies to the 400V Emergency bus. The ICMS will initiate
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 103 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
automatically the loading sequence to the A.C. safe shutdown supplies and the
220V battery chargers. Once emergency shutdown supplies are established, the
diesel generator shall maintain voltage and frequency of the island system
within specified ranges while the critical A.C. auxiliaries are re-started to
replace the D.C. shutdown auxiliaries until normal A.C. supplies are restored.
Shutdown of the diesel generator shall not occur automatically on restoration of
normal A.C. supplies, but only by manual operator action.
In-Service Testing
Provision shall be made for testing the diesel generator from the CCR via a
single control command. The aim of the tests is as follows:
Prove reliable starting. The point in the control system at which the test is
initiated should ensure that as much as possible of the automatic start logic
as possible is included in the test.
Prove the ability of the diesel generator to successfully respond to step load
changes up to the largest single load both in load addition and load rejection.
Prove the ability of the diesel generator to continuously supply its maximum
isolated load and its rated output when connected in parallel with the normal
400 V source of supply.
The diesel generator shall have its own controller to enable periodic testing of
the diesel generator following a command to start from the CCR. Shutdown of
the diesel generator shall not occur automatically after the load tests, but only
by manual operator command.
D.C. Auxiliaries for the Diesel Generators
If the Bidder requires d.c. supply to the diesel generator for control purposes,
for the supervisory system, or for the running of its stand-by pumps etc., prior
to establishment of diesel alternator voltage, he shall include in his bid for the
provision of the appropriate battery systems complete with trickle/boost
charging equipment local to the diesel generator.
Extent of Supply
This clause shall be used solely as a guide to the works involved. It no way alters
the responsibility of the Contractor as detailed elsewhere in this Specification.
Each of the diesel generator shall be complete with all necessary associated
ancillary plant, controls and services as follows:
A starting system capable of starting the diesel engine in any position without
the need to use the barring gear.
A lubricating oil system with pumps, filters, oil cooler, piping and controls.
An engine cooling system which does not depend on the operation of cooling
systems elsewhere in the power station and has sufficient capacity to
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 104 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
maintain safe operating temperatures within the specified ambient
temperature range.
Local and remote control facilities including a diesel generator control
cubicle and diesel generator auxiliary switchboard, both located in the diesel
generator room, together with instrumentation protection and alarms and all
necessary provisions for starting, loading, control and shut down.
A complete engine air intake system.
A lagged exhaust system with silencers mounted on separate structure
outside the building and unlagged discharge above the level of the engine
room roof.
All water, and fuel services.
A fuel oil day storage tank and complete reticulation for start-up and running
purposes.
Provision of all appropriate control, protection and alarm signals to the CCR.
Provision of all necessary or desirable peripheral instrumentation on diesel
generator and auxiliaries, and associated cabling.
All local power and control cabling.
Batteries, chargers and d.c. distribution system if applicable.
Removable guards for any exposed moveable part of the diesel generator or
an auxiliary, for personnel protection.
Provision for connecting / disconnecting generator neutral point to the station
earth grid.
Particulars of Plant
Diesel Engine
(1) General
The diesel engines offered shall operate on either the 2 or 4 stroke cycle and be
suitable for operating with the same fuel oil used by power station mobile plant.
They shall be of proven design, with a record of successful and low maintenance
performance in the size and configuration offered and with a proven record of
start reliability. The maximum speed of the diesel plant offered shall not be more
than 1,500 rpm. Units are required to be capable of rapid loading.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 105 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
maintenance.
Bidders are required to set out particulars of the design offered and, where
practicable, substantiate the claims with records of actual engine performance.
It is preferred that the following design features be incorporated:
Cylinder liners manufactured wholly from a single high quality material with
inherent anti-galling and oil retaining properties with the working surfaces
finished in a manner to enhance these properties. Chrome-plated liners will
not be accepted.
Piston and ring materials to be fully compatible with the abovementioned
liner properties.
Inlet and exhaust valves in separate removable cages with renewable guides
fitted to all valve stems.
Valve, valve seats and valve cage materials selected for operation over a
whole range of engine loading. Valve seats deposited by welding on base
metal will not be accepted.
A separate fuel pump to each injector is preferred but fuel pumps and
injectors shall be of an approved well proven type and full details shall be
submitted with the Tender.
Covers over the valve gear shall be of robust construction with strong locking
facilities.
The engine crank case shall be provided with suitable safety devices to
minimise the possibility of a rapid increase in pressure in the crank case
above the permissible level.
The engine shall be tested in the maker's works in accordance with ISO 3046-
1 and ISO 3046-2.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 106 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The exhaust duct and silencer shall be either hot-dipped galvanized or
alternatively, constructed in stainless steel of adequate thickness to withstand
all structural, thermal and wind loads. Expansion bellows shall be in stainless
steel. Unlagged portions of the exhaust system, if not in stainless steel, shall
be painted externally with approved paint.
Silencers shall be mounted on independent structures outside the building
and the exhaust piping shall be arranged to discharge above the level of the
building roof.
The exhaust piping up to and including the silencer shall be lagged and the
section outside the building shall be sheet metal cladded.
(1) General
The engine shall be provided with a forced lubrication system incorporating
oil pump, oil coolers, filters, oil reservoir, pipework, valves, and instruments.
If the main oil pump is driven from the engine then facilities shall be provided
for priming the system by a 100% duty electric motor driven pump which
will be arranged to pump for 10 minutes in every hour whilst the diesel is
shut down or at an interval considered sufficient to ensure that the diesel
engine bearings are ready for an instant start. The electric stand-by pump
shall be arranged to start automatically on loss of lubricating oil pressure. A
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 107 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
hand operated priming pump shall also be supplied and fitted for hand
priming purposes.
The capacity of the lubricating system shall be adequate for the combined
requirements of the diesel engine and generator.
Where an engine-driven pump is fitted, it is preferred that the pump can be
readily isolated from the engine (without affecting its reliability) so that the
engine may be placed in service on the stand by pump in the event of a failure
of the engine-driven pump only.
Means shall be provided to collect any lubricating oil likely to leak or drip
from the unit and return it by suitable drains to a collecting point for disposal.
Bidders shall indicate in the Schedules the guaranteed lubricating oil
consumption in litres per engine hour and the period of running necessary to
achieve stable oil consumption conditions.
Facilities for draining the lubricating oil from the sump shall be provided.
The Contractor in his offer shall include a description of how the draining
and replenishment is done.
(2) Filters
At least two lubricating oil filters shall be provided. They shall be suitable
for the nominated grade of oil and be of the total flow type.
The filters shall preferably be capable of being cleaned by one man without
the use of tools.
Each filter shall be fitted with a differential gauge and alarm and shall have
interchange valves interlocked to prevent total isolation of the oil filtration
system.
(3) Coolers
Oil coolers shall preferably be of the tube in shell type and the tube bundle
shall be removable.
Facilities shall be provided to enable oil from engine sump to be discharged
into drum containers for disposal.
(3) Reticulation
The Contractor shall supply all piping, isolating valves, non return valves,
drains, overflows, air release valves, vents, supports, recirculating valves,
piping, safety devices, alarms and initiating devices necessary for the safe
and convenient operation of the plant.
The filtering system shall include at least two (2) stages of filters capable of
retaining all particles above five microns in size, and a water separator.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 109 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Engine Governor
(1) Receivers
Each receiver shall be complete with pressure gauge, alarm contacts, relief
valve, automatic moisture trap and by-pass, isolating and drain valves.
Adequate provision shall be made for internal inspection.
Each air receiver shall have a storage capacity sufficient to provide the air
required for at least five engine starts without recharging the receiver.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 110 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(2) Compressors
2x100% electric driven compressors should be provided, alternatively one
electric driven compressor and one combustion engine driven mobile
compressor of same rating.
Each receiver shall be provided with one 400 V a.c. electric motor-driven air
compressor of sufficient capacity to charge the receiver in a period not greater
than 30 minutes. The compressor shall be arranged to automatically maintain
the required air pressure in the receiver.
All necessary interconnecting pipework in butt welded steel and automatic
drain traps shall be provided.
Cooling System
Cooling of the engine shall be provided by a closed pressurised water system(s)
with pump(s) circulating the water between the engine and a fan cooled radiator.
The water shall be suitably dosed with inhibitor and if appropriate for the range
in ambient temperature, with anti-freeze.
The fan(s) shall be enclosed in a substantial shroud for physical protection of
personnel and for increased efficiency. If the radiator is located within the room,
flexible ducting shall be provided between the radiator and the wall of the
building to ensure that all heated air is directed out of the engine room.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 111 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
All necessary integral pipework and valves shall be provided and all
necessary precautions shall be taken to ensure that the piping will be free
from vibration problems. Compression fittings will not be acceptable.
Pipework shall be installed such that it does not prevent free and easy access
around the diesel generator unit and auxiliaries.
Lagging and trace heating shall be provided wherever there is a danger of
freezing.
Instrumentation
The plant shall be supplied with all necessary instrumentation for control and
monitoring purposes
(2) In addition to local indication, all vital instrumentation and controls shall be
transmitted to and mounted on the Diesel Generator Control Cubicle
(1) General
The generator shall be of the horizontal shaft, brushless, rotating field, solidly
coupled to the diesel engine flywheel, and shall meet the requirements of IEC6
0034 and this Specification.
(2) Rating
The continuous maximum rating of each generator shall match the ISO 3046/1
rating of the engine. The generators shall be designed for the following
conditions:
Rated voltage 400 V
Rated frequency 50 Hz
(3) Enclosures
Generators shall be totally enclosed air circuit air cooled type to IEC
60034-6 with degree of protection to IEC 60034-5 of IP56.
Exciters shall be totally enclosed fan cooled type to IEC 60034-6 with
degree of protection to and IEC 60034-5 of IP56.
(4) Insulation
Insulation of generators and exciters shall be rated at Class F to IEC 60034,
but the limit of temperature rise shall be that nominated for Class B
insulation.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 112 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(5) Stator
The stator casings shall be of fabricated steel construction, and the stator
core shall be made of high permeability low-loss stampings tightly
clamped to reduce noise and vibration to a minimum.
The stator windings shall be of copper, star-connected, with all six
terminals brought out. The windings shall be effectively braced and
blocked to withstand, without damage or permanent deformation, the
forces resulting from single or three-phase sudden short circuits at the
terminals. The stator windings shall have full insulation; graded
insulation is not acceptable.
(6) Rotor
The rotor shall be of the outboard pedestal bearing arrangement with
over-hung exciter. Bearings shall be of the sleeve type with flood or
pressure lubrication from the engine lubricating oil system, fitted with
embedded thermostats for alarm purposes, and sight flow provision in
the oil drain. They shall be insulated.
Pole and damper windings shall be suitably braced to prevent damage in
service, and damper windings shall be adequately rated for currents due
to transient and/or cyclic irregularity conditions.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 110 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Excitation Controller
Each generator shall be provided with a solid-state excitation controller which,
by controlling the field current of the brushless exciter, will provide automatic
regulation of generator terminal voltage with changing load. Manual control of
excitation current shall also be provided as backup to the voltage regulator and
for maintenance purposes.
The excitation controller shall provide for automatic build-up to rated generator
voltage as part of the starting sequence of the diesel generator set. The sequence
shall end with the automatic voltage regulator being in control, in preparation
for synchronizing.
(1) General
Each set shall be provided with a diesel generator control cubicle to be mounted
in the diesel generator room adjacent to the set. The cubicle rating shall be that
applicable to a switchboard in the same location. The diesel generator control
cubicles shall contain all the controls, alarms and indication for the whole of
each set, with certain functions repeated in the CCR.
Anti-condensation heaters shall be provided.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 111 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
excite generator: establish generator rated voltage ready for manual
synchronising
normal stop
emergency stop, which shall also trip the diesel generator circuit breaker and
excitation
A.V.R. voltage raise/lower
Governor speed raise/lower
A.V.R. auto/manual selector switch
Excitation manual raise/lower
Generator circuit breaker open/close
Synchroscope on/off (also provides an interlock to enable closure of
generator circuit breaker)
Anti-condensation heaters on/off
Jacket water heaters on/off
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 112 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
lube oil temperature
jacket water temperature
engine exhaust temperature
intake air cooler temperature
air receiver pressure
battery charge current (A)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 113 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(6) CCR (CCR)
The Contractor shall provide in the CCR all the remote control and
instrumentation meters, indicating lights and pushbuttons required to operate
the diesel generator from that location.
The following list is included as a guide. The Contractor shall state in his offer
what facilities he recommends providing for safe, reliable, automatic and
manual starting and operation.
Control
Control level: diesel generator shall be capable of starting/stopping from
equipment/local control panel/DCS.
Automatic/Manual start selection: automatic start on loss of supply to the Station
400 V Switchboard bus section to which the diesel generator is connected ready
for synchronising and closing onto the 400 V Station Switchboard; manual start
as described below.
Manual start diesel generator: initiation of automatic start and run-up sequence
ready for synchronising and closing onto the 400 V Station Switchboard by the
operator
Stop diesel generator
Governor speed raise/lower
A.V.R. voltage raise/lower
Manual excitation voltage raise/lower
A.V.R./manual excitation selection
Open/close generator circuit breaker
Synchronising plug: to connect synchroscope and enable circuit breaker closing
circuit
Indication
Generator power output (kW)
Generator reactive power output (kVAR, centre zero)
Generator frequency (Hz)
Generator voltage (V)
Station 400 V Switchboard busbar voltage (v)
Synchroscope
Generator current (A)
Diesel engine speed (rpm)
Lubricating oil pressure (kPa)
Jacket water temperature (C)
Battery voltages
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 114 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Status
Diesel ready to load
Limit of excitation adjustment reached
Limit of governor speed adjustment reached
Diesel generator unavailable (conditions monitored to be listed)
Generator reactive power limiter operating
Excitation high
Alarms
Diesel generator general alarm
Lubricating oil pressure low
Lubricating oil temperature high
Jacket water temperature high
Diesel failed to start/shut-down
Diesel generator overload
Battery failed.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 115 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The Bidder shall describe the proposed generator protections.
Test links shall be provided in current and voltage input circuits to electrical
protection relays. Trip isolation links or other means of providing isolation of
in-service protection relays for test shall be provided.
Batteries
(1) If batteries are required, they shall be of the valve regulated lead acid (VRLA)
batteries complying with IEC 60896 and shall be provided with 100% rated duty
float/boost chargers. The batteries shall be sized to supply at least five black
starts and in addition one black shut-down without the need for recharging.
Under normal operation the chargers shall supply the required d.c. load and at
the same time automatically float charge the battery to keep it fully charged
within the correct voltage limits.
(2) Selection of boost charge shall be manual, and controlled by a preset timing
switch. The boost charge shall be such that the time for recharging the battery
from the discharged condition to 90% of the fully charged condition, and at the
same time supplying the d.c. load requirements, does not exceed eight hours.
Piping
Piping shall generally comply with the Specification and shall be of butt welded
construction. Flanged joints shall be used only for connection to equipment,
valves and fittings. Screwed joints and compression type joints shall not be used
for fuel, lubricating oil and compressed air supply. Copper piping shall not be
used for fuel or lubricating oil services.
Piping shall be neatly arranged and adequately supported. The Contractor shall
submit detailed arrangement drawings of all pipework for approval by the
Owner before erection at Site.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 116 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Valves
Valves shall conform to the Specification.
Valves shall have flanged end connection. Screwed valves shall not be used
unless specifically approved. Valves for air, water, fuel and lubricating oil
services shall be globe or gate type.
All valves shall be provided with a valve number and nameplate inscription
approved by the Owner.
General
Control and relay protection system of electrical equipment of the project shall
be designed to meet the Viet Nam standards, EVN regulation as well as
specified International Standards. Control and relay protection system shall be
designed according to follow:
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 117 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
IEC 60947 (all parts) Low Voltage Switchgear and Control Gear
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 118 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Contractor shall be responsible to combine and submit the calculation and
setting sheet of total plant (HV, MV, LV) into one document before Reliability
Run of last Unit.
The protection tripping matrix shall be submitted to Owner.
The fault monitoring system (FMS) shall be provided to monitor the event of
fault. The communication output ports of the numerical generator protection
systems (No.1 and No.2 schemes), excitation transformer, generator step up
transformer & unit auxiliary transformer protection systems, 500V overhead
line protection and of the protection relays used in MV (11kV) power system
shall be connected to the central monitoring, relay setting and recording station
which will be located in Electronic equipment room of the Central Control
Building (CCB)
This section established the criteria and minimum requirements for the
protection of the power station electrical system comprising the generator,
generator step up transformer, generator excitation transformer, unit auxiliary
transformer, 500kV OHL, 11 kV and 400 V A.C. auxiliary power systems. The
11 kV and 400 V auxiliary power systems comprise the main switchboards in
the CCB and other Control Buildings together with associated outgoing circuits.
The Bidder shall also provide a dual, fully duplicated unit synchronizing system.
It shall include duplicated automatic synchronisers, manual check synchroniser
and other indicating instrument to allow automatic and manual synchronizing
of the generator circuit breaker.
The Bidder shall also provide a station synchronizing system which includes a
manual check synchronizing relay for the 11 kV station incomers and unit-
station interconnector circuit breakers.
The electrical protection schemes shall be designed to promptly, precisely and
reliably isolate from service any element of the power system when that element
is subjected to an abnormal condition detrimental to its effective operation,
while leaving other unaffected elements in service. The protection schemes shall
also be designed so that they do not operate under load conditions or faults
external to the relevant zone.
The protection systems shall be based on digital, microprocessor based device
with monitoring, measurement and communication capability.
The communication output ports of the numerical generator protection systems
(No.1 and No.2 schemes), excitation transformer, generator step up transformer
& unit auxiliary transformer protection systems, 500V overhead line protection
and of the protection relays used in MV (11kV) power system shall be connected
to the central monitoring, relay setting and recording station which will be
located as close as possible to the CCR.
Suitable menu-guided software to communicate with these protective relays via
a personal computer shall be provided, installed and tested to a satisfactory
performance. This central monitoring and control station shall be connected to
the Station ICMS via a “Miscellaneous Station System” drop.
The protection relays and systems shall meet all requirements of IEC 60255 and
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 119 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
other IEC publications.
(a) Design philosophy
In general, the 11kV power system shall be non-effectively earthed via resistors
connected to the neutral points of 11kV windings of power transformers. These
resistors are to limit earth fault current to 400 amps and shall meet maximum
time duration of 30 seconds.
Neutral earthing transformers shall be provided for non-effective earthing of the
neutral points of the generators and the neutral displacement relays shall be
connected to the secondary side of these transformers.
Technical specification of relay:
Frequency: 50Hz
Input Current: 1A
Input voltage: 110V
Type: Numerical protection relay, microprocessor, event
recording/data display
The protection systems shall include at least the following:
Generator: - Overspeed (12)
The generator protection - Phase distance (21G)
system will have duplicate
systems (redundancy) for - Generator overfluxing (24G)
each unit, each system - Synchronizing checking (25)
shall have at least - Under voltage (27)
following protection:
- Reverse power (32)
- Loss of excitation (40)
- Negative phase sequence (46)
- Overload (49)
- Overcurrent/undervoltage (50/27)
- Breaker failure (50BF)
- Stator earth fault 95% (59GN)
- Stator earth fault 100% (64GN)
- Voltage balance (60)
- Generator rotor earth fault (64R or 64F)
- Different phase angle or Out of step
protection (78)
- Over/under frequency protection
(81O/81U)
- Differential (87G)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 120 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
- Inter turn stator winding fault
- Subsynchronous resonance protection
- Lock out device (86)
- Trip circuit supervision (74)
Excitation transformer
The excitation transformer - Overload (49)
protection system will - Instantaneous overcurrent (50)
have duplicate systems
(redundancy) for each - Inverse time overcurrent (51)
unit, each system shall - Differential (87ET)
have at least following
protection: - Lock out device (86)
- Trip circuit supervision (74)
Generator Step Up Transformer: - Overfluxing (24)
The Generator Step up - Overload (49)
Transformer protection
system will have duplicate - Instantaneous overcurrent and earth
systems (redundancy) for fault overcurrent. (50/50N)
each unit, each system - Inverse time overcurrent and earth fault
shall have at least overcurrent. (51/51N)
following protection: - Restricted Earth Fault (87REF)
- Differential (87T)
- Lock out device (86)
- Trip circuit supervision (74)
Unit Auxiliary Transformers: - Overfluxing (24)
The Unit Auxiliary - Overload (49)
Transformer protection
system will have duplicate - Instantaneous overcurrent and earth
systems (redundancy) for fault overcurrent. (50/50N)
each unit, each system - Inverse time overcurrent and earth fault
shall have at least overcurrent. (51/51N)
following protection: - Restricted Earth Fault (87REF)
- Differential (87UT)
- Lock out device (86)
- Trip circuit supervision (74)
Non-electric protection for - Oil temperature (26O)
GSUT&UAT:
- Winding temperature (26W)
Non-electric protection for
GSUT&UAT of each unit shall - Pressure relief device Trip (63)
have at least following protection: - Sudden Pressure (63 OLTC)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 121 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
- Oil level (71)
- Oil level OLTC (71 OLTC)
- Oil flow OLTC (80 OLTC)
- Cooler fault (95)
- Buchholz relay (96)
500kV EHV Over Head Line - Distance (21/21N)
Protection (Incoming)
- Under/Over voltage (27/59)
500kV EHV overhead line
protection system will - Breaker failure (50BF)
have duplicate systems - Instantaneous overcurrent and earth
(redundancy) for each fault overcurrent. (50/50N)
circuit, each system shall - Inverse time overcurrent and earth fault
have at least following overcurrent. (51/51N)
protection:
- Directional overcurrent (67/67N)
- Lock out device (86)
- Trip circuit supervision (74)
- Auto-recloser (79/25)
- Carrier or pilot-wire receiver/signal
(85)
- Differential (87L)
- Fault recorder/ Fault location (FR/FL)
11kV Switchgears: - Under voltage (27)
- Over voltage (59)
- Instantaneous earth fault overcurrent.
(50N)
- Inverse time overcurrent earth fault
overcurrent. (51N)
- Breaker failure (50BF)
- Busbar protection (87B)
- Synchonization check (25)
- Local back up
- Lock out device (86)
- Trip circuit supervision (74)
11 kV Motors (More than 1MW): - Over speed motor protection (12)
- Under speed motor protection (14)
- Under voltage (27)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 122 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
- Over voltage (59)
- Thermal overload (49)
- Instantaneous overcurrent and earth
fault overcurrent. (50/50N)
- Inverse time overcurrent and earth
fault overcurrent. (51/51N)
- Number of Starts per hour (66)
- Differential (87M)
- Vibration Monitoring
- Switching Surge Protection
- Breaker failure (50BF)
- Lock out device (86)
- Trip circuit supervision (74)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 123 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Other 11 kV motors: - Under speed motor protection (14).
- Under voltage (27)
- Over voltage (59)
- Single phasing and unbalance (47)
- Thermal overload. (49)
- Instantaneous overcurrent and earth
fault overcurrent. (50/50N)
- Inverse time overcurrent and earth fault
overcurrent. (51/51N)
- Number of Starts per hour (66)
- Start/stall protection (51LR)
- Switching Surge Protection
- Breaker failure (50BF)
- Lock out device (86)
- Trip circuit supervision (74)
11kV-Non Motor feeder - Instantaneous overcurrent and earth
fault overcurrent. (50/50N)
- Inverse time overcurrent and earth fault
overcurrent. (51/51N)
- Breaker failure (50BF)
11kV VT bus panel - Under voltage (27)
- Over voltage (59)
400 V Motors (above 110kW): - Under speed motor protection (14).
- Under voltage (27)
- Over voltage (59)
- Single phasing and unbalance (47)
- Thermal overload. (49)
- Instantaneous overcurrent and earth
fault overcurrent. (50/50N)
- Inverse time earth fault overcurrent.
(51N)
- Start/stall protection (51LR)
- Number of Starts per hour (66)
400 V Motors (below 110kW): - Under voltage (27)
- Over voltage (59)
- Thermal overload. (49)
- Inverse time overcurrent and earth fault
overcurrent. (51/51N)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 124 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
- ACB/MCCB/MCB
400 V Switchboards: - Under voltage (27)
- Over voltage (59)
- Instantaneous overcurrent and earth
fault overcurrent. (50/50N)
- Inverse time overcurrent and earth fault
overcurrent. (51/51N)
Emergency Diesel Generator - Under voltage (27)
- Over Voltage (59)
- Reverse power(32)
- Overcurrent (51)
- Earth fault (51G)
- Loss of Excitation.(40)
- Negative sequence protection (46)
- Thermal overload (49)
- Over/Under Frequency (81O/81U)
- Lock out device (86)
- Differential (87DG)
Unit Overall Differential Overall Differential protection (87O)
protection
Two (2) 500kV EHV overhead line connections between the Generator Step-
Up Transformers gantries and the 500kV EHV Switchyard gantries shall be
provided with two (2) main protection (Main Line Differential Protection) fed
from separate current transformers. The scheme using the Generator step-up
transformer overall differential protections as main protections may also be
considered.
The differential protections shall be equipped fibre optic communication
channels, fibre optic cable and auxiliaries for connection.
The configuration, type and specification of protection relay and auxiliaries at
both side of 500kV Overhead Line shall be same, compatible and complied with
the Viet Nam standards, EVN regulation on the protection relay for 500kV OHL
with transmitted signal by Optical cable.
The auxiliary protection relays shall also be provided in accordance with the
related drawing and standards.
Both ends of the circuit shall be tripped by the Main protections.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 125 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Sufficient output contacts shall be included to operate separately, duplicate trip
coils on each circuit-breaker pole.
A feature shall be included to allow a direct inter-trip signal to be superimposed
on the protection scheme.
Evidence of through fault stability shall be provided and shall be subject to
approval by the Owner including current transformer knee point voltage
calculations related to maximum system fault levels and X/R ratios together
with relay type test reports to justify any formulae used.
The overall operating time of the differential protection or direct inter-trip
feature shall not exceed 30ms.
The protection shall be, as far as possible, self-monitoring and shall include end
to end supervision of the data channel with blocking of the protection if a defect
is detected.
Facilities shall be provided for routine testing of the equipment while in service.
Preference shall be given to relays with internal memory of data relating to
monitoring quantities and of fault data for three (3) or more fault operations.
The interface arrangement with the signal multiplexer shall be completely
compatible with other signaling requirements which may be required and all
interface cabling, fibre optic or otherwise and interface units shall be included.
A back-up time delayed overcurrent protection shall be included within the
digital differential relay or shall be provided by separate relays sharing the Main
1 protection current transformers
Generator Protection
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 126 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Stage 1 time delay settings should cover the range 1-10 seconds and Stage 2
time delay settings should cover the range 5-60 seconds.
The voltage/frequency ratio setting range should be continuously adjustable
between 1.0 and 1.25 times.
The relay should reset when the ratio of voltage/frequency drops to no less than
95% of the pick-up value.
The relay should provide alarms in the CCR for both Stage 1 and Stage 2.
Generator Reverse Power Protection (32-1 / 32-2)
Two (2) stage generator reverse power protection shall be adequately sensitive
to detect a motoring condition on complete loss of input to the turbine. In
addition the protection shall be as sensitive as practical to detect governor failure.
A time delayed trip output shall be provided such that there shall be no risk of
incorrect operation caused for example by rotor swings accompanying a system
electrical fault.
Generator Loss of Excitation Protection (40)
The loss of excitation protection shall be additional to any loss of excitation
devices included in the excitation system or automatic voltage regulator.
The protection shall monitor the generator terminal impedance vector and shall
have a negative reactance offset mho (circular) characteristic with adjustable
offset and adjustable diameter.
The relay shall be operative down to 5% voltage.
An adjustable time delay shall be provided.
Generator Negative Phase Sequence Protection (46)
The generator negative phase sequence protection shall comprise a two (2) stage
device.
Stage 1 (alarm) shall have an adjustable setting to match the generator
continuous negative phase sequence capability and shall include an adjustable
definite time delay or a fixed time delay of not less than 3 seconds.
Stage 2 (trip) shall have an adjustable thermal characteristic capable of being
set to match the generator short time negative phase sequence capability, based
on I22t = a constant.
It shall be possible to set Stage 2 to pick-up at a negative phase sequence current
equal to the generator continuous capability while still closely matching the
generator I22t capability.
Generator Under-Voltage Started Overcurrent Protection (51V)
The above relays shall be of the 3 phase microprocessor, multi-characteristic
inverse/definite minimum time current type in accordance with BS 142, 3
second curve, and shall be provided with adjustable current settings as specified
and time multiplier adjustments at intervals of 0.025.
The starting relay shall be of the 3 phase instantaneous under-voltage type with
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 127 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
a setting range of 50-80% voltage and a high drop-off/pick-up ratio of not less
than 90%. The relay shall be self reset with no flag indicator.
Generator Overvoltage Protection (59)
The generator overvoltage protection shall be supplied to detect overvoltages at
the generator terminals. Essentially the protection is a back-up device, operable
if the generator automatic voltage regulator is faulty.
The overvoltage relay shall have an adjustable setting range up to 1.4 per unit
rated voltage and shall have an adjustable time delay of 0.5-5 sec.
Busbar Earth Fault Protection (59NB)
These relays shall be connected to an open delta secondary winding of a voltage
transformer.
The relay shall have a minimum voltage setting of not greater than 10% of the
maximum residual voltage of the voltage transformer secondary windings
which energise the relay.
The relay shall have either a definite time delay or inverse definite minimum
time delay so that the minimum operating time may be set to not less than 3
seconds. The relay shall be insensitive to harmonic voltages.
Generator Stator Earth Fault Protection (59GN/64GN)
The stator earth fault protection shall detect earth faults on 95% of the generator
winding. The relay shall be insensitive to frequencies other than 50Hz. The relay
shall be instantaneous in operation and shall be rated for 5 minutes operation
with a full voltage earth fault on the system.
100% Stator Earth Fault Protection shall be achieved by the continuous injection
of a voltage on to the stator circuit at a suitable frequency other than system
frequency (or by other approved means).
The protection shall be functional with the machine on load, shut down or while
running up or down with or without excitation applied. The injected supply and
all input supplies shall be continuously monitored. The equipment shall include
any necessary injection transformers.
Rotor Earth Fault Equipment (64F/64R)
Equipment of an approved type shall be provided to indicate an earth fault on
the generator rotor winding whilst the machine is running.
An alarm shall be initiated in the CCR (CCR)if a single rotor earth fault, whether
transient or otherwise, occurs.
The equipment shall detect earth faults under any conditions of speed, load or
rotor temperature.
A double earth fault on the rotor winding shall cause instantaneous tripping of
the generator.
Full details of the equipment and the method of detection offered that is
potentiometer, A.C. or D.C. injection method shall be submitted with the Bid.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 128 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Out of step (78)
Pole slipping protection shall operate by monitoring the generator and system
impedance as viewed at the generator terminals. Adjustable ohmic settings shall
be available to accommodate the possible range of system condition.
A trip output shall be given if the generator slips one (1) or more complete poles
only if the impedance locus remains in the operate region for a minimum time
of 50ms.
Over and Under Frequency Relays (81)
These relays shall be of the microprocessor type and shall be provided with two
(2) adjustable over and under frequency settings and two (2) adjustable time
settings for each frequency setting. The relay shall be energised from an external
D.C. power supply and shall be capable of full operation over a measurement
voltage range of 60-120 percent of nominal voltage.
Generator Differential Circulating Current Protection (87G)
The differential circulating current protection shall be of the 3-pole high
impedance relay type using Class X current transformers.
Before approval of the scheme the Bidder/Contractor shall submit full details of
calculated performance including current transformer design data and full
details of any non-linear resistors and setting resistors proposed.
Low Forward Power Interlock Relays (37G)
Two (2) low forward power interlock relays shall be supplied for the steam
turbine generator to act as a permissive interlock in the generator tripping
circuits to reduce the risk of overspeed by delaying opening of the generator
circuit-breaker for certain non-urgent fault conditions. The relay shall be
designed to close its contacts when the level of real power output falls below a
preset level, and open on increase of real power output.
The relay shall be a three phase A.C. power measuring device, capable of
measuring both balanced and unbalanced power, capable of carrying 3 times
full load continuously, at rated voltage.
The relay setting shall be preset and have an operating value of plus 0.5% of
rated forward three phase power and the minimum pick up value shall be no less
than plus 0.2% three phase power and the maximum pick up value no greater
than plus 0.7% rated three phase power. These settings shall be the limiting
values and shall be effective over the range of phase angles 89” lag to 89” lead.
The combined phase angle error of CT’s and VT’s must not exceed 20 minutes
over the ranges 80% - 120% voltage and 5% - 120% current at any burden from
25% - 100% of rating.
To enable current and voltage transformer errors to be compensated, the relay
shall be fitted with a device to allow easy setting on Site to cover the whole
range of errors permitted for the current transformers and voltage transformers.
The power relay shall include a time delay on pick up capable of fine adjustment
between 1 and 10 secs.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 129 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
At least two (2) output contacts shall be provided, which shall close when the
level of output power falls below the set value, and shall be suitable for initiating
a trip relay operating coil.
An operation indicator is not required.
The following protection relays shall initiate tripping of the machine via the low
forward power interlock relay:
Generator transformer and unit auxiliary transformer winding temperature trip,
field failure, stator earth fault 1 and 2, over fluxing stage 2, overvoltage and unit
auxiliary transformer MV earth fault.
Voltage Transformer Supervision Relays (60)
The main purpose of the voltage transformer supervision function is to indicate
the VT failure.
When a VT failure occurs on one or two phases, the voltage levels seen by the
protection become unbalanced.
The relays shall compare the secondary voltages of a pair of voltage
transformers and shall be arranged to block the protection tripping before it has
time to operate on loss of voltage.
Trip circuit supervision Relay (74)
Trip circuit supervision Relay are connected through resistors, are installed to
monitor all the trip circuits when CBs hay other automatic devices are at close
or trip position. This relay has the lag time to avoid inaccurate alarming cases.
Relay just only alarm if the voltage supplied for trip circuit or auxiliary source
are faulted
Sub-Synchronous Resonance protection
Contractor shall to provide the solution of protection relay, supplementary
excitation damping control, Blocking Filter…) for Sub-synchronous Resonance
(SSR) to ensure the safety and stability operation of Quang Trach I TPP as well
as Power Grid. Contractor shall submit all detailed calculation sheet, setting
sheet, solution, test to prevent the SSR phenomenon.
Other relays
Other relays shall be provided in accordance with the drawing of this Request
for Proposal Document and the related standards
Unit Overall differential Protection (87O)
Unit overall differential protection relays shall provide to protect the full range
of the Generator-Generator step up transformers-Unit auxiliary transformer
block to ensure the safety operation of Power Plant.
Generator Step-Up Transformer Protection
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 130 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
transformer. Interposing current transformer ratios shall be chosen to achieve
exact overall balance with the transformer at the mid-point of the tapping range.
Second harmonic bias (or other approved means) shall be included to overcome
the un-stabilising effect of transformer magnetising in rush current. Delayed
operation is not an approved means and induction disc relays shall not be used.
Restricted Earth Fault Protection (87NT)
The restricted earth fault protection shall be of the high impedance relay type
using Class X current transformers shared with transformer biased differential
protection.
Before approval of the schemes the Bidder/Contractor shall submit full details
of the calculated performance including the effects of the biased differential
relays and interposing current transformers and including full details of all
setting resistors, non-linear resistors proposed and current transformer design
data.
The fault setting shall be within the limits 10-60% of the rated current of
transformer windings with solidly earthed neutral.
For transformer windings connected to impedance earthed systems the fault
setting shall be within the limits 10-25% of the minimum current available for
an earth fault at the transformer line terminals.
Overcurrent and Earth Fault Protection (50-51/50N-51N)
These relays shall be of the microprocessor, multi-characteristic inverse definite
minimum time/current type in accordance with BS 142 and shall be provided
with adjustable current settings as specified and time multiplier adjustments at
intervals of 0.025.
High set instantaneous elements shall be of the transient free type (i.e.: they
shall be insensitive to the direct component of fault current). All high set
elements shall be provided with a means of achieving an infinite setting.
Buchholz Relays (96B)
Transformers with the conservator type of oil preservation system shall be fitted
with gas and oil actuated relays (Buchholz type). These relays shall be of the
two (2) element type having alarm contacts for when gassing occurs and trip
contacts for when oil surging occurs. The relay shall include a lock-out device
(located inside the case) to lock out the Buchholz trip circuit.
Transformers with the sealed tank or positive nitrogen pressure oil preservation
systems shall be fitted with sudden pressure relays. These relays shall provide
trip contacts for abnormal rate-of-rise of pressure within the transformer tank.
Additionally each generator transformer and inter bus transformer with positive
nitrogen pressure oil preservation system shall be provided with gas analyser
relays.
These relays shall automatically test the combustibility of the nitrogen at regular
intervals and shall initiate an alarm circuit if the combustible content of the gas
over the surface of the oil exceeds a predetermined level.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 131 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
All necessary flag indication tripping relays and alarm relays associated with
this protection shall be provided.
Pressure Relief Device (63)
A pressure relief device on the main tank and on the diverter switch oil
compartment set to open on excess pressure and to re-seal automatically
complete with trip contacts.
The oil flow shall be directed away from equipment, towards the ground and
the oil shall be contained within the transformer bund.
Winding Temperature (26W)
An eye level mounted dial thermometer to read HV and LV winding
temperatures fitted with a red maximum indicating pointer and with adjustable
trip and alarm contacts, adjustable from 70-100oC.
Oil Temperature (26O)
An eye level mounted dial thermometer to read top oil temperature fitted with a
red maximum indicating pointer and with adjustable trip and alarm contacts
adjustable from 70-100oC.
Two (2) additional temperature devices, either thermometers or thermostats,
with the same temperature adjustable range shall be provided as back-up.
Transformer Auxiliary Relays (overflux, overload,..)
Transformer auxiliary relays shall be provided for repeat of the Buchholz, oil
flow, oil level, pressure relief, winding and oil temperature alarms and trips.
Over fluxing (24);
Overload protection (49);
Etc.
Other relays
Other relays shall be provided in accordance with the drawing of this Request
for Proposal Document and the related standards.
Unit Auxiliary Transformer Protection
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 132 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
protection.
Before approval of the schemes the Bidder/Contractor shall submit full details
of the calculated performance including the effects of the biased differential
relays and interposing current transformers and including full details of all
setting resistors, non-linear resistors proposed and current transformer design
data.
Overcurrent and Earth Fault Protection (50/51; 50N-51N)
These relays shall be of the microprocessor, multi-characteristic inverse definite
minimum time/current type in accordance with BS 142 and shall be provided
with adjustable current settings as specified and time multiplier adjustments at
intervals of 0.025.
High set instantaneous elements shall be of the transient free type (i.e.: they
shall be insensitive to the direct component of fault current). All high set
elements shall be provided with a means of achieving an infinite setting.
Buchholz relay (96)
Transformers with the conservator type of oil preservation system shall be fitted
with gas and oil actuated relays (Buchholz type). These relays shall be of the
two (2) element type having alarm contacts for when gassing occurs and trip
contacts for when oil surging occurs. The relay shall include a lock-out device
(located inside the case) to lock out the Buchholz trip circuit.
Transformers with the sealed tank or positive nitrogen pressure oil preservation
systems shall be fitted with sudden pressure relays. These relays shall provide
trip contacts for abnormal rate-of-rise of pressure within the transformer tank.
Additionally each generator transformer and inter bus transformer with positive
nitrogen pressure oil preservation system shall be provided with gas analyser
relays.
These relays shall automatically test the combustibility of the nitrogen at regular
intervals and shall initiate an alarm circuit if the combustible content of the gas
over the surface of the oil exceeds a predetermined level.
All necessary flag indication tripping relays and alarm relays associated with
this protection shall be provided.
Pressure Relief Device (63)
A pressure relief device on the main tank and on the diverter switch oil
compartment set to open on excess pressure and to re-seal automatically
complete with trip contacts.
The oil flow shall be directed away from equipment, towards the ground and
the oil shall be contained within the transformer bund.
Winding Temperature (26W)
An eye level mounted dial thermometer to read HV and LV winding
temperatures fitted with a red maximum indicating pointer and with adjustable
trip and alarm contacts, adjustable from 70-100°C.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 133 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Oil Temperature (26O)
An eye level mounted dial thermometer to read top oil temperature fitted with a
red maximum indicating pointer and with adjustable trip and alarm contacts
adjustable from 70-100°C.
Two (2) additional temperature devices, either thermometers or thermostats,
with the same temperature adjustable range shall be provided as back-up.
Transformer Auxiliary Relays
Transformer auxiliary relays shall be provided for repeat of the buchholz, oil
flow, oil level, pressure relief, winding and oil temperature alarms and trips.
Over fluxing (24);
Overload protection (49);
Etc.
Other relays
Other relays shall be in accordance with the drawing of this Request for
Proposal
Auxiliary Power Transformers protection
(1) Three-phase differential protection: the zone of protection shall include the HV
terminals of the transformer; the transformers and its LV connections up to LV
switchgear. (for rating of 2.5 MVA and above)
(4) Neutral earth fault protection in the neutral of the LV winding. This protection
shall co-ordinate with the earth fault protection provided at the LV main
incoming circuit breaker at LV switchboard.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 134 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Hot oil temperature.
Tapchanger overpressure.
(7) The power transformer protection shall provide trip signals to the following
sources:
MV feeder circuit breaker at MV switchgear.
LV incoming circuit breaker at LV switchboard
Emergency Diesel Generator Protection
(1) The incoming supplies from the Station and Unit Auxiliary transformers to their
corresponding 11kV switchboards shall be provided with three-phase
overcurrent protection (IDMT characteristics) and earth fault protection.
The three-phase overcurrent protection settings shall be coordinated with the
three-phase overcurrent protection provided on the HV side of Unit Auxiliary
transformers to ensure discriminative tripping and back-up protection. Similarly,
the earth fault protection settings shall be coordinated with the neutral
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 135 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
earth fault protection on the LV side of the respective transformers.
In addition, both three-phase overcurrent and earth fault protection shall be
coordinated with outgoing circuit protection.
(3) Feeder circuits to load centres, and to step-down transformers associated with
the variable speed drives (if there are any variable speed drives) shall be
provided with three-phase overcurrent protection (instantaneous and IDMT
characteristics) and earth fault protection (instantaneous and IDMT
characteristics). The settings on these types of protection shall ensure co-
ordination and discrimination with the protection provided in the load centres
and also with the thermal capability of the protected transformers.
(4) Each 11kV Unit Auxiliary switchboards shall be provided with busbar
protection.
The busbar protection shall also provide trip signals to associated interconnector
circuits and all circuits connected to the 11kV Unit switchboard.
(5) Each 11kV Unit Auxiliary switchboard supplying one or more motors shall be
provided with under voltage protection. This under voltage protection shall
initiate load shedding to prevent connection of all the motor loads
simultaneously on the return of A.C. power source to the 11kV bus.
(6) If there are any variable speed drives connected to the 11kV switchboards (Unit
Auxiliary or Station), the need for protection from harmonics that will be
generated from the static power unit forming part of the variable speed drive
units will need to be evaluated. Consideration for 11kV harmonic filters and
their effect on the performance of the Unit Auxiliary transformers shall be
evaluated and provided if required
(7) Each section of the 11kV Station switchboard shall be provided with busbar
protection.
The busbar protection shall also provide trip signals to associated interconnector
circuits, incoming Station transformer and all outgoing circuits.
(8) If there are motors connected to any section of 11kV Station switchboard, that
section of 11kV station switchboard shall be provided with under voltage
protection. This under voltage protection shall initiate load shedding to prevent
connection of all the motor loads simultaneously on the return of A.C. power
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 136 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
source to the 11kV bus
(1) The 11kV/400V Unit Auxiliary transformers, the 11kV/400V Station Auxiliary,
Station Emergency transformers shall be provided with winding temperature
detector for alarm. The neutral of the 400V windings shall be provided with the
inverse time neutral earth fault protection.
The incoming supplies from the 11kV/400V Station Auxiliary & Station
Emergency and Unit Auxiliary transformers to their corresponding 400V
switchboards shall be provided with three-phase overcurrent protection (IDMT
characteristics) and earth fault protection.
The three phase overcurrent protection settings shall be coordinated with the
three phase overcurrent protection provided on the 11kV side of the Station
Auxiliary, Emergency Station and Unit Auxiliary transformers to ensure
discriminative tripping and back up protection. Similarly, the earth fault
protection settings shall be coordinated with the neutral earth fault protection on
the 400V side of the respective transformer.
In addition, both three phase overcurrent and earth fault protection shall be
coordinated with the protection provided on outgoing circuits.
(3) The load centre MCC feeder circuits shall be provided with three phase
overcurrent protection (instantaneous and IDMT characteristics) and earth fault
protection (instantaneous and IDMT characteristics). The settings on these types
of protection shall ensure co ordination and discrimination with the protection
provided on outgoing circuits in the load canters.
(4) The essential section of the 400V Unit Auxiliary switchboard shall be provided
with under voltage protection. On detection of under voltage, it shall trip the
normal power source breaker and automatically transfer to an alternative power
source (from 11kV/400V emergency transformer) to ensure an uninterruptable
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 137 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
power supply source.
(5) The non essential section of each 400V Unit Auxiliary switchboard shall also
be provided with under voltage protection. This under voltage protection shall
initiate load shedding to prevent connection of all the motor loads
simultaneously on the return of A.C. power source to the 400V switchboard.
(6) If there are any variable speeds drives connected to the 400V switchboard, the
need for protection from harmonics that will be generated from the static power
unit forming part of the variable speed drive units will be evaluated.
Consideration for 400V harmonic filters and their effect on the performance of
the Unit Auxiliary, Station Auxiliary and Station Emergency transformers shall
need to be evaluated and provided if required.
400 V Motor Control Centre (Unit Auxiliary and Station Services)
(1) The incoming feeder circuits shall be provided with three-phase overcurrent
protection (instantaneous and IDMT characteristics).
(2) Outgoing circuits shall be protected thermally and against short-circuit faults by
the following devices:
Combination starters consisting of adjustable magnetic trip-only breakers and
thermal overload elements in each phase of the starter.
MCCB/ MCB
Motor Protection
General
Motors shall be protected against short-circuit faults, overload, stall and surge
taking into account the following:
Motor characteristics such as type, speed, voltage, kW rating, service factor,
thermal capabilities during starting, running and stall conditions.
Motor starting magnitude and duration of inrush current.
Inertia characteristics of the load (valve and high inertia loads).
Switching surges and pre strike, re strike voltage magnitudes due to switching
by vacuum switchgear, exposure to harmonics when motors are powered
from variable speed drives.
Motor service criticality of the motors for reliability and availability of the
overall plant.
The pickup settings and trip settings for each protection relay shall be calculated
in accordance with requirements of the respective manufacturer's instruction
manuals, maximum fault currents, load currents and proper co ordination with
the protection provided with the incoming supply feeders.
Motor Electrical Protection Functions
As a minimum, the plant drive motor protection shall comprise the following
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 138 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
protection functions:
General
The contractor shall be responsible for design, installation, test and
commissioning the tariff metering system in accordance with:
Agreement document of tariff metering system with Electric Power Trading
Company (EPTC);
Circular 42/2015/TT-BCT dated 1st of December, 2015 of MOIT –
Regulations on tariff metering in power system;
Circular 30/2014/TT-BCT dated 2nd of October, 2014 of MOIT – Providing
for operation of competitive electricity generation market;
Decision No. 1232/QĐ-EVN dated on 21 December, 2011" Regulation of
Metering Management at Terminal Point for tariff metering points.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 139 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Decision No. 887/QĐ-EVN dated on 14 October, 2014" Technical
requirement for tariff metering using in Vietnam Electricity.
Decision No. 103/QĐ-EVN dated on 21 June, 2017" Technical requirement
Tariff metering and data transfer equipment for metering using in Vietnam
Electricity
Circular No. 23/2013/TT-BKHCN dated 26th September, 2013 Regulation
Calibration, verification and testing for group 2 measuring instruments
Relevant National Technical Codes and Regulations;
IEC 61869 Instrument Transformer
IEC 62053 Electricity metering equipment
International standards and codes in relation to tariff metering system.
The tariff metering shall include main tariff metering system and backup tariff
metering system.
Main tariff metering system and backup 1 tariff metering system are located
at Quang Trach 500kV Switchyard (out of EPC’s scope)
Location: 500kV Switchyard side
Accuracy class of CT, VT: 0.2 for main and 0.5 for backup
Accuracy class of metering (real energy): (0.2 for main and 0.5 for back-up) for
real energy and 2.0 for reactive energy
Backup 2A tariff metering systems are located at high voltage side of
generator step up transformers
Location: Quang Trach I side
Accuracy class of CT, VT: 0.5
Accuracy class of metering: 0.5 for real energy and 2.0 for reactive
energy
Backup 2B tariff metering systems (for Vietnam Competitive Generation
Market) are located at high voltage side of unit auxiliary transformers and
generator circuit breaker side.
Location: Quang Trach I side
Accuracy class of CT, VT: 0.5
Accuracy class metering: 0.5 for real energy and 2.0 for reactive energy
All three (3) sets of meters shall have solid state recorders (or latest technology
type recorders with high accuracy) and communication interface. For accurate
measurement of energy exported (kWh, kVArh),
Each identical set of tariff metering shall consist of one (1) import and export
MWh meter, one (1) import and export MVARh meter, accessories plus demand
meters, .
The data storage in MW and MVAR shall be auto-recorded each hour and shall
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 140 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
also be flexible enough to accommodate all without limits.
The meters shall combine voltage and current sensor technology with state of
the art A/D converters, filters and signal processors that accurately reproduce
voltage and current in a wide linear range per phase, to the 15th harmonic.
The meters shall have an accurate four-quadrant measurement technique with a
user defined kVA calculation. The data storage matrix shall be flexible enough
to accommodate all known tariff structures without yet testing the matrix limits.
The meters shall preferably use a typical Windows structure and method of use
with the communicating package and data handling packages merged into one
(1) user friendly installation.
The Power measuring data managing and collecting system:
Power measuring data managing and collecting system shall complied with
the Decision No. 56/QĐ-ĐTĐL dated on 20th May 2011 Regulation on
technical standard for Metering Data Transmission system
Metering data shall be monitored at power measuring data acquisition and
transmission computer at CCR of Quang Trach I TPP and Power metering
data management center of EVN (refer drawing No. QTI-RFP-CO-009).
The Technical specification and software for Power measuring data
managing and collecting system shall be complied with the requirement in
Tariff Metering Agreement No. 1012/EPTC-KT&CNTT-KDBĐ on March
26th, 2018 signed between Electricity Power Trading Company (EVNEPTC)
and TPMB2 (Current name is EVNPMB2).
Contractor shall be responsible to supply all related equipment and
accessories for installation, configuration, test and commissioning the Power
measuring data managing and collecting system.
Contractor shall be responsible to provide all necessary equipment such as
Router, Converter, Switch, Card,…for connecting to Existing equipment
Power metering data management center of EVN.
The proposed design and the proposed equipment shall be subject to approval
by the Owner.
Meters shall comply with IEC 60687 standard with minimum acceptable
accuracies of (0.2 for main and 0.5 for back-up) for real energy meters and 2.0
for reactive energy meters. Transducers (kWh and kVArh) shall be provided.
The transducers shall have an output range of 4-20 mA. The outputs of the
transducers will be connected to the ICMS.
Various meters required are:
MWh meter
MVArh meter
MW meter with demand indicator
Voltmeter, Ammeter, Power factor and Frequency meters (for statistical
purpose).
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 141 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The CTs, VTs and meter for tariff metering system shall be sampled, verified
and calibrated in accordance with the appropriate test Codes and Standards by
an approved independent testing authority in the local country (Circular No.
23/2013/TT-BKHCN dated September 26th 2013 issued by Ministry of Science
and Technology and current relevant regulation)
All acceptance stage of Tariff metering system shall be complied with EVN
regulation.
Metering Panels
Metering Panels will be installed in the Control Equipment Room of CCB. As
the meters require periodic access for reading purposes they shall be located in
positions where reasonable access is available
Measurement system
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 142 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Motor data sheet and specification
Outline drawing
Characteristic curves
Wiring connection drawing
CT, VT, Metering certificates
Other related documents
7.9 AC SYSTEM
General
This section establishes the criteria for the switchgear to be incorporated in the
medium (11kV) and Low voltage (400/230V) power distribution systems.
The Contractor shall responsible to design, manufacture, factory test, inspect,
supply, delivery, unload at Site, install, test, commission and guarantee the
11kV Switchgear, 400/230V switchboards and auxiliaries for each Unit load
and common load to ensure the safe, efficient and reliable operation of the
Quang Trach I Thermal Power Plant
Switchboard control switches shall be of three position spring return to neutral
type having all the necessary contacts. They shall have contacts of the wiping
type and shall have a mechanical endurance of at least 100,000 operations.
Control selector switches shall be of the four position rotary snap action type
having wiping contacts with a mechanical endurance of at least 100,000
operations. It shall be possible to rotate the switch in a clockwise direction only
and provision shall be included for locking the selector in any position using a
padlock.
The switchboards shall have the following degrees of protection (IP ratings to
IEC 60529) depending on the location of the boards:
IP 4X (for Indoor, air-conditioning rooms);
IP 54 ( for Indoor, without air-conditioning rooms);
IP 56W (for Outdoor).
IP 55 ( for Indoor Connection/Junction Box )
IP 65W ( for Outdoor Connection/Junction Box )
IP 65 ( Dust laden atmosphere)
The remote indication shall be provided to ICMS as below
MV incoming : Voltage, Current, Power, Power Factor
MV Bus : Voltage
MV Tie : Current
MV Motor Feeder : Current, Power, Power Factor
MV Static Feeder : N/A
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 143 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Transformer Feeder : Power(kWh)
LV Incoming : Voltage, Current
LV Bus : Voltage
LV Tie : Current
LV ACB Motor Feeder : Current
The above indication signals shall be enable at both locations (local/remote).
Inner lighting shall be equipped for control panels, power panels and panels
where is required to be lighting level for checking.
Each cubicle shall be provided with hygrostat controlled space heaters. Space
heaters shall be located near the floor so as not to pose any hazard to service
personnel.
Nameplates shall be furnished at each cubicle and at each instrument and device
mounted on or inside the cubicle. The material shall be stainless steel. Caution
notice on suitable metal plate shall be affixed both in front and at the back of
each vertical panel. All labelling, label sizes and colors shall be submitted to
Owner for approval.
This section establishes the criteria for the switchgear to be incorporated in the
high and main low voltage power distribution systems within the CCB of the
power station.
A 20% spare compartment shall be provided for motor control center,
distribution boards for each current rating with all equipment and hardware
provided to receive starter modules.
The Bidder/Contractor shall also provide the necessary 400V switchgear spares
to supply the 400VAC for Quang Trach II Power Plant Project in future for
maintenance.
The Bidder/Contractor shall also provide the necessary 400V switchgear spares
to supply the 400VAC at TT5 for interface with Quang Trach II to transfer coal
from Quang Trach I to Quang Trach II Power Plant and reverse way in the future.
The Bidder/Contractor shall provide the necessary cable and accessories for
connection to 11kV incoming switchgear at electrical room of jetty
Manufacturer’s nameplate shall be provided. Nameplate shall show the
technical specification of switchgear (Manufacturer, Rated Voltage, rated
current, phase,…)
Medium Voltage Switchboards (11kV)
Standard
The switchgear shall be designed and tested to the following standards:
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 144 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
IEC 60420 HV Alternating Current Fuse Switch Combinations and Fuse Circuit
Breaker Combinations
IEC 60298 AC Metal enclosed Switchgear and Control gear >1kV to 52kV
(1) A spare circuit breaker/switching device shall be provided for each current
rating.
(2) The circuit breakers and switching devices shall be capable of meeting their
rated performance when the voltage at the closing device or at the shunt trip
coils is any value from 176V to 264V.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 145 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 146 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
supply
As part of the integrated control and monitoring system (ICMS) interface, the
Contractor shall provide a power (watts) and/or current transducer on each
circuit. These transducers shall have an output with a range of 4-20 mA. Supply
power for the transducer shall be obtained from the relevant switchboard control
circuit. Power transducers are required on all 11kV circuits and 400V incoming
circuits. The remaining circuits shall have current transducers.
Switchboard circuits shall be provided in accordance with the switchboard
single line diagrams and circuit schematic diagrams.
A 20% spare compartment shall be provided for each current rating with all
equipment and hardware provided to receive starter modules
Switchboard busbars shall consist of hard drawn high conductivity copper bar
of uniform cross-section throughout the length of the switchboard.
Interlocks shall be provided to prevent switchboard control of the switchgear
unless the switchgear is in the service and test (switchboard) positions.
Trip interlocks shall be provided to prevent racking-in or racking-out whilst the
switch is closed. Mechanical and electrical interlocks shall be provided to
prevent operation of the switchgear unless it is fully racked-in or racked-out.
The main busbars and all connections thereto and busbar supporting insulators
shall be capable of withstanding for one second the mechanical and thermal
stresses arising from the maximum possible fault currents.
All jointing surface on busbars and connections thereto shall be either electro-
tinned, solder-tinned or silver plated and shall be firmly bolted together with
suitably spaced bolt assemblies. The components of each bolt assembly shall be
fully machined and shall be stainless steel, phosphor or manganese bronze.
The busbar and busbar enclosure shall be arranged to facilitate extension of the
busbars for the connection of additional switchgear units.
The sheet metal switchboards shall be constructed of folded and welded sheets
of 2.0mm minimum thickness and where equipment is to be mounted on a panel
the thickness of the sheet metal shall be sufficient to prevent vibration affecting
the correct operation of the equipment.
If switchboards are located in areas where the floor may become wet it shall be
placed on 10 cm high concrete supports with an apron and ramp to facilitate the
rolling of circuit breakers up to, into and out of the compartments. In all cases
the switchboards shall be mounted on steel leveling channels.
The minimum size of the switchboard earth bus shall be designed to handle the
maximum expected fault level for a time determined by the maximum back-up
protection clearance time.
The switchboard cable entry facilities shall be designed to suit the proposed
cabling system (bottom entry preferred).
All switchboards shall be vermin, insect, animal and dust proof. Switchboards
requiring ventilation shall be constructed as dustproof except for the ventilation
louvers, which shall be backed with fine non-corrodible gauze filters. Filters
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 147 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
shall be able to be removed for cleaning.
Each outgoing circuit operating at 1,000V or above shall be provided with an
earthing switch. Earthing switches shall be mechanically interlocked with the
adjacent insolating switch and key interlocked with any remote isolating switch.
Each bus shall be provided with one earthing switch
The minimum size of the switchboard earth bus shall be designed to handle the
maximum expected fault level for a time determined by the maximum back-up
protection clearance time or 300 mm2 conductor whichever is the greater.
The switchboards shall have been tested for arcing fault containment to IEC
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 148 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
One LOCAL / REMOTE selector switch maintained type with pistol
grip handle and key interlock.
One TRIP / CLOSE selector switch.
As part of the integrated control and monitoring system (ICMS) interface, the
Contractor shall provide a power (watts) and/or current transducer on each
circuit. These transducers shall have an output with a range of 4-20 mA. Supply
power for the transducer shall be obtained from the relevant switchboard control
circuit. The remaining circuits shall have current transducers.
The remote indication shall be provided as below:
MV incoming : Voltage, Current, power factor
MV Bus : Voltage
MV Tie : Current
MV Motor Feeder : power, current, power factor
MV Protection Relay function
Transformer Feeder : Power, current, power factor
Status of circuit breaker : On/OFF
(The above indication signals shall be enable at both locations (local/remote).
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 149 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
length of the switchgear.
Each stationary unit shall be connected directly to the ground bus. The frame of
each circuit breaker and draw-out VT unit shall always be grounded through
heavy multiple contacts, except when the primary disconnecting devices are
separated by a safe distance. CT and VT secondary neutrals shall be earthed
through removable links so that earth of one circuit may be removed without
disturbing the other
Low Voltage Switchboards, Motor control center (400/230 V)
Standards
The switchgear shall be designed and tested to the following standards:
IEC 60947 Low Voltage Switchgear and Controlgear.
IEC 61439.1 Low Voltage Switchgear and Controlgear Assemblies
IEC 60408 Low Voltage Air Break Switches, Air Break Disconnectors, Air
Break Switch Disconnectors and Fuse Combination Units.
IEC 60269.1 Low Voltage fuses - General Requirements
IEC 60529 Degrees of Protection Provided by Enclosures
Switchgear Types, Ratings and Requirements
The 400V power distribution shall be by means of Switchgears/Switchboards
and MCCs. 230V distribution shall be through 230V DBs. The Switchboards
shall be used to supply auxiliary power for normal and startup operation of
generation units. The MCCs / DBs shall be used to provide power, control,
and protection for AC and DC auxiliary services (motors and feeders) of
generating units. The ambient temperature to be considered for electrical
design shall be 40 deg C
The 400 V circuit breakers shall be capable of meeting their rated
performance when the voltage at the closing device is any value from 176 V
to 264 V and the voltage at the shunt trip coils is any value from 110 V to
264 V d.c.
Contactors shall be co-ordinated with the operating characteristics of
associated short circuit protection such that short circuits do not cause
welding of the contacts.
Circuit Breaker
Voltage: 400/230 V
Phases: 3 phase, 4 wire including neutral
Frequency: 50 Hz
Current Rating: To be determined by load requirements
Breaking and Short- Time Breaking current capacity (rms symmetrical)
Current Capacity: shall be verified at the detail design stage
according to the results of System Study.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 150 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Short time current capacity shall be one (1)
second.
Circuit Breaker Type: Air-Break
Control Voltage: 220 V DC or 230VAC
Power frequency Withstand 2.8kV
Voltage:
Impulse Withstand Voltage: In accordance with IEC 61439
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 151 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The fixed live parts of the switches shall be fully and individually shrouded
to prevent, as far as possible, a fault developing between phases or to earthed
metal.
Auxiliary contacts of the contactors shall be provided in accordance with the
appropriate schematic diagrams.
All 400 V contactors shall be of the enclosed, electro-magnetically operated
air break type. The main contacts shall be silver inlaid or silver faces. The
utilisation category shall be AC4 for a.c. motors.
With 70% voltage at the coil terminals, the contactors shall not chatter or part
when motor starting current is flowing.
LV switchgears/MCCs/DBs shall be installed indoor and air insulated. LV
switchgears/MCCs shall be constructed Form 3b and DBs shall be Form 1
according to IEC 61439. LV switchgears/MCCs shall be draw-out type, and
DBs shall be fixed type. Generally, LV switchgears with ACB panels shall
be of single-front construction, and MCCs with MCCB panels shall be
single-front or double-front construction.
Load rated above 100kW, Incoming feeder and bus-tie shall be fed from
400V ACB. Load rated below 100kW shall be fed from 400/230V
MCCB/MCB.
Switchboards
The switchboard cable entry facilities shall be designed to suit the proposed
cabling system (bottom entry preferred).
If switchboards are to be located in an area where the floor may become wet
they shall be placed on 10cm high concrete supports. Switchboards shall be
mounted on steel leveling channels.
The sheet metal switchboards shall be constructed of folded and welded sheets
of 2.0mm minimum thickness and where equipment is to be mounted on a panel
the thickness of the sheet metal shall be sufficient to prevent vibration affecting
the correct operation of the equipment
All switchboards shall be vermin, insect, animal and dustproof. Switchboards
requiring ventilation shall be constructed as dustproof except for the ventilation
louvres, which shall be backed with fine non-corrodible gauze filters. Filters
shall be able to be removed for cleaning.
Enclosures shall be arranged so that equipment requiring manual operation (e.g.
control switches) is at a height between 750 mm and 1600mm above floor level
for easy control and operation.
It shall be possible to install cables without dismantling any part of the enclosure.
All labeling, label sizes and colors shall be submitted to Owner for approval.
Interlocks shall be provided to prevent switchboard control of the switchgear
unless the switchgear is in the test (switchboard) position.
Trip interlocks shall be provided on the 400V circuit breakers to prevent
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 152 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
racking-in or racking-out whilst the switchgear is closed. Mechanical or
electrical interlocks shall be provided to prevent operation of the switchgear
unless it is fully racked-in or racked-out.
For breaker panels, all switches, lamps, and indicating instruments shall be flush
mounted on the respective compartment door whereas relays and other auxiliary
devices shall be mounted in a separate compartment. For MCC/ DB modules,
all push buttons, lamps, and indicating instruments shall be flush/ semi flush
mounted on respective module compartment. For double-front assemblies, two
full height vertical cable alleys with cable supports shall be provided in each
section, one on either front, to facilitate unit wiring. These chambers shall be
liberally sized to accommodate all cables and shall have a removable front cover
for access
Each main 400/230V switchboard in the Main Control Building shall be
provided with 20% spare compartments for each current rating with all
equipment and hardware provided to receive starter modules.
Each vertical section shall be provided with hygrostat controlled space heater.
In addition, motor starters rated 30kW and above shall be configured for feeding
the motor space heater through suitably rated breaker auxiliary NC contact
and/or contactor. Cubicle heater and motor heater circuits shall have individual
MCCB/MCB.
Each main 400V switchboard in the Main Control Building shall be provided
with spare compartments with all hardware provided to receive starter modules
as follows:
ACB Feeder : One (1) motor type and One (1) non-motor type at each bus
MCCB Feeder : 15% of total feeders regardless of feeder type
The main 400 V switchboards shall be directly connected by busbar and
enclosure to their respective 11kV/400 V dry type transformers.
The switchboards shall have been tested for arcing fault containment to IEC
61439 and shall have separate compartments for the following:
Busbars
Air Circuit Breaker (ACB) or Moulded Case Circuit Breakers (MCCB)
Contactors (where applicable)
Control cable terminals, control fuses, current transformer links, protection
and auxiliary relay
Voltage transformers
Current transformers and power cable terminations
Arc fault containment shall be to IEC 61439
Compartmenting shall be such that maintenance can be carried out safely on one
circuit with the other adjacent circuits in service.
Power transducers and current transducers shall be provided for all 400V
incoming circuits. Current transducers shall be installed on all remaining 400 V
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 153 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
feeder circuits. The transducers shall have an output with a range of 420 mA.
The main busbars and all connections thereto and busbar supporting insulators
shall be capable of withstanding for 1 second the mechanical and thermal
stresses arising from the maximum possible fault currents.
Where a control power supply for switchboards is required and the main
220VDC power supply is not available (i.e. remote from Main Control Building)
switchgear, circuit breaker and transformers shall be supplied as necessary. If
d.c. is needed, the Bidder/Contractor shall also supply the rectifiers
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 154 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
necessary. This Clause covers the following:
Polyphase a.c. control transformers;
D.C control system using three-phase transformers and bridge rectifiers;
D.C control system using single-phase transformers and rectifiers.
The relevant standards associated with these power supplies are:
IEC 60076 Power Transformers
IEC 60146 Semiconductor Rectifier Equipment
Control voltage supplies shall be suitable for continuous operation at rated kVA.
Suitable tappings connected to the low or high voltage side of each transformer
shall be provided to permit adjustment over the range 95% - 105% Volts for
Low Voltage and 90% - 110% Volts on open circuit.
All external connections to the primary and secondary windings including
tappings and earthing points shall be solderless.
Single-phase control supply transformers shall have the centre point of the
secondary winding brought out to an earth terminal. For a.c. control systems,
the earth terminal shall be connected to the power station earthing system.
For direct current control systems three-phase star/star connected transformers
shall be used in combination with bridge connected rectifiers. The secondary
star points shall be connected to terminals but shall not be earthed unless
otherwise specified. Alternatively, single-phase transformer/rectifier units may
be provided together with smoothing networks sufficient to give an output wave
form at least as smooth as that of a three-phase bridge.
Transistors and diodes used in power supplies shall be adequately protected
against damage due to switching transients by resistor-capacitor networks, non-
linear resistors, selenium surge suppressors or other approved method.
Under the service conditions, maximum transient and operating stresses applied
to semi-conductor rectifiers shall not exceed 70% of the manufacturer’s P.I.V.
(Peak Inverse Voltage) operating ratings and the current transients shall not be
more than 70% of the manufacturer’s continuous or transient rating - whichever
is lower.
Duplicate power supplies, each rated to carry the full load, shall be provided. In
situations where failure of a power supply would result in a reduction of the
boiler-turbine load or would lead to a dangerous condition, the power supplies
shall be connected in parallel via an auctioneering arrangement or alternatively
automatic changeover of power supplies shall be provided sufficiently fast to
maintain the associated plant in service. Alarm initiating contacts shall be
provided to signal a failure of each power supply
Small multiple cooling fan systems shall be provided for electronic cabinet
(Relay protection, Generator Control Panels (GCP), Automatic Voltage
Regulators (AVR),…) . Each fan is individually protected by MCCB/MCB, is
provided with LED indication of fan failure.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 155 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Drawings to be provided by the Contractor during Contract
The following drawings and design documents shall be provided by the
Contractor during the contract:
(1) Detailed layout of all switch rooms.
(2) Detailed layout (inside and outside) of MV (11kV) and LV (400V)
switchboards including bill of material.
(3) Single line diagrams for all 11kV and 400V switchboards.
(4) Control schematics, termination and wiring diagrams for all 11kV and
400V switchboards.
(5) Load Flow and Fault calculation (three phase and single phase to earth
fault level) for the entire power system at all voltage levels.
(6) Operating and Maintenance Manual
(7) Training Manual
(8) Operation tools and special tools
(9) Technical specification
(10) Logic diagram
(11) Operation description
7.10 DC AND UPS SYSTEM
DC system
System Description
All necessary D.C. Systems and UPS for Unit, Station shall be provided by the
Contractor for all equipment requiring safe secure electrical supplies and the
proposed equipment shall comply with the appropriate IEC and IEEE Standards
as amended and supplemented by this Request for Proposal.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 156 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Each 100% battery should be capable of supplying the emergency loads that
apply when the normal AC power system has failed, or when the AC supply to
the battery chargers has failed.
The minimum acceptable level of reliability in the system is that it should meet
its full operational requirements with one battery out of service. Batteries shall
be rated such that one battery can meet the requirements of the generating unit
for a minimum period of 120 minutes in the event of a total loss of A.C. supplies.
This protects the security of the plant in the event of a battery failure and permits
off-line boost charging, discharge testing etc.
Each battery will be housed in a separate dedicated room incorporating
appropriate ventilation, showers, floor treatment and other safety features.
Each 100% battery charger shall be capable of supplying the continuous and
intermittent loads associated in the ‘float' mode of operation.
In addition each charger when off line shall be able to supply the necessary
current to enable boost charging of a battery.
During periods of intermittent loads, or when the battery is taking the full
emergency load (i.e. during the safe shutdown of a unit) the DC system voltage
shall not fall below a value which is injurious to any of the equipment connected
to the DC system. In any event the DC system voltage shall not fall below 198
volts, during the Duty Cycle following the complete loss of AC supply, with
one battery in service.
The power for DC system shall be supplied from Emergency bus of each Unit.
(4) The Contractor shall submit full details of proposed safe shutdown/emergency
loads for approval by Owner.
The DC system shall be designed with the following minimum requirements:
Two radial feeders to each load to allow for maintenance on a switchboard
or a feeder, without loss of availability of a supply.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 157 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Battery installation in accordance with the safety provisions of the latest
international standards.
Routine off line maintenance capacity testing of a battery, in accordance with
international standards whiles the second battery remaining in service
supplying the requirements of the generating unit.
The ripple to be maintained at less than 2%.
Battery shall be sized in accordance with IEEE Standard 485 1997 and based
on the duty cycle diagram, showing the current versus time characteristic of
the DC system, following the loss of AC supply, with one battery in service.
The duty cycle diagram shall be submitted to Owner for approval prior to
manufacturing.
The sizing of the battery shall use an end voltage of 1.75 volts/cell (battery
of Nickel-Cadmium type has the end voltage of 1.1 volts/cell and boost
charging voltage of 1.65 volts/cell typically) and a temperature of 25oC with
account being taken of the relatively high ambient of 30oC.
To minimise the voltage drop on the DC system and to DC standby motors,
series resistance starters shall be used which limit the starting current to twice
the full load current.
Voltage drop in all elements including cables shall be considered so that the
DC standby motors terminal voltage does not fall below 85% of the DC
nominal system voltage during starting.
(5) Separate D.C. Systems as required shall be provided for the following:
220VD.C Systems as required for each Unit Auxiliaries and Station Common
Auxiliaries control, operation, synchronising, metering, protection etc. and
for the safe shutdown of the Plant including motor drives and for SCADA
and Communication Systems, coal handling system, CWP.
Contractor shall equip the equipment to convert/ supply the 48V or 24V DC
in the panel/board if necessary.
Individual D.C. power supply systems as required for the Emergency Diesel
Generator, Station Communication, Fire Fighting/Detection Systems etc.
Batteries, Chargers
(1) Batteries
The batteries shall comprise cells of the valve regulated lead acid (VRLA)
batteries complying with IEC60896-1.
The batteries shall be sized in accordance with IEEE Standard 485 1997.
A performance test of the battery capacity shall be included as part of the
commissioning procedure.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 158 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
generator unit and each battery charger shall be of the constant potential type.
Each battery charger shall be sized to supply the DC requirements of the inverter,
the recharging current of the batteries as well as supplying the standing DC loads
under all system conditions.
The battery chargers shall be suitable for operating in parallel with the batteries,
and operating on a stand alone basis with the batteries disconnected and the
battery chargers supplying the standing load.
The battery chargers shall also be capable of boost charging their respective
battery from the fully discharged condition to the fully charged condition within
a period not exceeding ten (10) hours with the emergency load disconnected.
The battery chargers shall operate from a 3 phase, 400V ± 10%, 50Hz ± 5%
supply, except for units with a rated output of 5 kW or less, which may operate
from a single phase 230V ± 10%, 50Hz ± 5% supply with the same tolerances.
The battery chargers shall be designed and sized accordingly including a design
margin of not less than ten (10) percent of the total D.C. load requirement.
They shall be silicon controlled rectifier (thyristor) type devices suitable for
either manual or automatic operation and complying with IEC 60146, as
amended and supplemented by this Request for Proposal.
The battery chargers shall be located indoors in a switchgear room or other
similar environment and shall have an enclosure classification of at least IP 42.
The room shall be an air conditioned room (non hazardous location) however
in the event of the air conditioning system failing the battery chargers shall be
capable of operating with an external ambient air temperature of 40°C.
All chargers shall be naturally air cooled (AN) using the air within the room and
all internal devices shall be designed with a temperature margin allowance to
address the build-up of heat inside the equipment enclosure in which these
devices are mounted.
Each battery charger shall normally operate automatically in the "Float" charge
mode and except in the case of battery chargers being used in conjunction with
valve-regulated (recombination technology) batteries, shall also be provided
with manual "Boost" charge and manual "Equalize" charge facilities.
The float operation shall have a constant voltage current limiting characteristic
(IU Characteristic in accordance with VDE 0510) and shall be rated for
supplying the maximum standing D.C. load while at the same time maintaining
both its associated batteries in the fully charged condition.
Following a full discharge and having reached the specified end of discharge
voltage, re-charging of the battery shall be achieved at the fastest possible rate
after initiation of the boost charge facility which when manually selected shall
connect the charger in boost mode and recharge the battery from the fully
discharged condition to the fully charged condition within a period not
exceeding ten (10) hours.
The boost operation shall have a constant voltage current limiting characteristic
to suit the battery type.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 159 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
At the end of the ten (10) hour boost charge period the charger shall revert
automatically to float charge commencing from the knee point of the battery
recharge characteristic.
The charger shall also have the facility to deliver an equalising charge to the
battery. In this mode, which shall also be manually selected and supervised, the
charge shall follow a drooping (W) characteristic (VDE 0510) and the charging
current shall be limited within safe values specified by the battery manufacturer.
Boost charging and equalize charging, both of which shall be manually selected,
shall be carried out off line with the D.C. switchboard incoming supply
contactor open.
Failure of the A.C. supply during boost or equalizing charging shall
automatically restore the battery and battery charger to float operation and
reconnect them to the switchboard.
The above requirements are to be met within the limits specified for Immunity
Class B.
The voltage output of chargers for consumers shall be maintained within
nominal voltage (e.g.: 220V + 10%) and if required by the design voltage
dropping diodes shall be fitted in the charger together with any contactors or
voltage sensing relays required for their operation to protect consumers from
damage due to over voltages. The maximum continuous and short time rating
of the voltage dropping equipment shall be in accordance with the standing and
peak load requirements.
The charger rectifiers and output blocking diodes shall be current rated at least
50% greater than the charger maximum rating. The peak inverse voltage rating
shall be at least 2kV.
The chargers shall be short-circuit proof complete with adjustable voltage and
current limiting devices.
Each charger shall also be capable of sustaining without damage to itself, a
continuous permanent short-circuit across its output terminals..
Although it is not intended that chargers are operated without a battery
connected, the design of the charger shall, nevertheless, be such that without a
battery connected the chargers can supply directly all consumers continuously
without any detrimental effect to the charger itself or to the consumers and
maintain nominal system voltage as previously specified with a ripple voltage
no greater than 10% rms of the nominal output voltage.
Smoothing chokes shall be provided to decrease the ripple in the output voltage
under normal circumstances with the battery connected to a maximum of 1%.
In addition short term supply voltage dips of up to 20% nominal voltage (e.g.
due to motor starting) shall not cause the battery charger to trip. Within the
limits specified for Immunity Class B, the output voltage at any load shall be
controlled within the limits of ± 1% of the set value, and the output current shall
be limited within ± 2% of the set value, when operating under current limiting
conditions.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 160 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The output voltages and the current limits shall be set by means of adjustable
devices, which are accessible within the control panel.
Each charger shall include an A.C. contactor to automatically isolate the charger
from the A.C. supply should a fault develop within the charger.
The battery chargers shall be rated for Duty Class 1 unless otherwise specified.
Component failures within the chargers shall be indicated to the maximum
extent practicable.
Battery end-cell tapping arrangements will not be permitted.
The chargers shall incorporate the following alarm devices and indicating lamps
to identify main faults:
Charger failure
Float charge voltage high
Boost charge voltage high
Equalise charge voltage high
Voltage low
A voltage free common repeat alarm shall be provided for remote indication.
Each battery charger shall incorporate at least the following equipment:
Lockable incoming LV A.C. supply switch disconnector with Utilisation
Category AC23 complete with front door interlock ;
Short-circuit protection ;
Isolating transformer ;
Phase reversal protection for semi-conductors ;
Outgoing circuit breaker to battery D.C. distribution board ;
A.C. input off/on indicating LED's ;
Incoming A. C. voltmeter;
Incoming A. C. supply ammeter;
Float, Boost and Equalise change over selector switch;
All necessary controls and alarms;
D.C. charger output ammeter;
D.C charger output voltmeter
Voltage dropping diodes (if required)
Output blocking diodes.
Thermostatically controlled anti-condensation heater.
All instruments, lamps and switches shall be flush mounted on the front of the
cabinet and the arrangement shall be subject to approval by the Engineer.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 161 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
DC Distribution
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 162 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Positive earth fault (for resistance earthed system)
Negative earth fault (for resistance earthed system)
Undervoltage fault
Overvoltage fault
The setting of these fault relays shall be adjustable. No local audible alarms are
required.
A voltage-free common repeat alarm shall be provided for remote indication.
A lamp "test" push button shall be provided.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 163 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
disconnection of any circuits when in use. A fixed signal injection device shall
be permanently installed and connected to each section of the busbars. Any
fixed devices required for each circuit and a hand-held detector unit shall be
provided. Two (2) sets of portable equipment shall be provided for the plant. A
detailed description of the equipment offered shall be included with the Bid.
UPS system
General
The 400/230V UPS system shall supply the power for following loads:
Plant DCS
Fire alarm system
PLC panel
Control power for equipment
Ect
The UPS system consists of two (2) independent systems as follows:
400/230V UPS system for Unit #1 and half of Common loads
400/230V UPS system for Unit #2 and half of Common loads
Each UPS system consists of 1x100% charger, 1x100 inverter, static switch
and bypass transformer.
The input voltage: 400V, 50Hz and 220V D.C. system
Output voltage: 400/230VAC, 50Hz
Capacity: not less than 25kVA
Discharge Duration : 30 minute
UPS Units (others than Emergency Lighting Supplies)
Unless otherwise specified, each UPS system shall consist of two (2) 100%
rated UPS units which shall be provided as a "stand-by redundant UPS with
bypass" and each mains input circuit shall have a separately switched supply.
The A.C. UPS units shall comply with IEC 60146-4, as amended and
supplemented by this Request for Proposal.
They shall be mounted indoors in an equipment room or other similar
environment and shall have an enclosure classification of at least IP 42.
The room shall be an air conditioned room (non hazardous location) and in the
event of the air conditioning system failing the UPS units shall be capable of
operating with an external ambient air temperature of 40°C for a period of not
less than ten (10) hours.
All internal devices shall be designed with a temperature margin allowance to
address the build-up of heat inside the equipment enclosures in which these
devices are mounted.
Each UPS unit shall comprise a rectifier, a battery and an inverter, each as
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 164 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
specified in this section of the Request for Proposal. The A.C. input and A.C.
output shall be isolated from each other and the A.C. output neutral point shall
be solidly earthed.
The UPS units shall be arranged with a mains bypass supply, an electronic
transfer switch and a maintenance bypass circuit.
Where the UPS input and output voltages are different, a dry-type transformer
complying with the applicable section of this Request for Proposal shall be
provided in the mains bypass and the maintenance bypass circuits. Three phase
transformers shall have a connection symbol Dyn11.
The Contractor shall optimise the rated voltage of the battery and its float
voltage, boost voltage and end voltage, unless there is a specified requirement
for a D.C. load to be supplied from the UPS unit.
The UPS unit(s), transfer switch (es) and A.C. output distribution board(s) shall
be supplied as a single suite of panels.
The A.C. output conditions and UPS units shall not be worse than the following:
Frequency: ± 2%
Voltage (steady state): ± 1%
Voltage (dynamic response): ± 10% in response to a step load change
of 100% rated output, and shall be restored to within steady state limits within
1 second.
Total harmonic voltage distortion: 5% when supplying a linear load.
The output UPS units shall be in synchronism with output maintenance bypass
circuit
The alarm of UPS units shall be displayed at UPS panels; the common alarm
(all failure and abnormal states) shall be display on operation console monitor
with active horn and beacon at center control room.
At UPS panel shall be displayed minimum of: Charger ON/OFF, inverter
ON/OFF, synchronous signal, static switch bypass ON/OFF, maintenance
transformer bypass ON/OFF, high temperature, rectifier failure, and inverter
failure.
At UPS panel shall be displayed minimum of: Charger ON/OFF, inverter
ON/OFF, synchronous signal, static switch bypass ON/OFF, maintenance
transformer bypass ON/OFF, high temperature, rectifier failure, and inverter
failure.
Input and output voltage meters, output frequency meters shall be displayed on
DCS panel, the digital meter shall be used.
The A.C. loads may contain total harmonic current distortion of up to 50%, as
generated typically by switched mode power supply units (SMPS).
UPS Units for Emergency Lighting Supplies
Unless otherwise specified, each UPS system shall consist of one (1) 100% rated
UPS unit which shall be provided as a "stand-by UPS with bypass".
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 165 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The A.C. UPS units shall comply with IEC 60146-4, as amended and
supplemented by this Request for Proposal.
The UPS units shall be mounted indoors in a switchgear room or other similar
environment, and shall have an enclosure classification of at least IP 42.
The room shall be an air conditioned room (non hazardous location) and in the
event of the air conditioning system failing the UPS units shall be capable of
operating with an external ambient air temperature of 40°C for a period of not
less than ten (10) hours.
All internal devices shall be designed with a temperature margin allowance to
address the build-up of heat inside the equipment enclosures in which these
devices are mounted.
Each UPS unit shall comprise a rectifier, a battery and an inverter, each as
specified in this section of the Request for Proposal.
Each UPS unit shall be arranged with a mains bypass supply, an electronic
transfer switch and a maintenance bypass circuit.
Where the UPS input and output voltages are different, a dry-type transformer
complying with the applicable section of this Request for Proposal shall be
provided in the maintenance bypass circuit. Three phase transformers shall have
a connection symbol Dyn 11.
The Contractor shall optimise the rated voltage of the battery and its float
voltage, boost voltage and end voltage.
The UPS unit and A.C. output distribution board shall be supplied as a single
suite of panels.
The battery cubicles may be mounted alongside, where approved by the
Engineer.
The A.C. output conditions and UPS units shall not be worse than the following:
Frequency: ± 2%
Voltage (steady state): ± 2.5%
Voltage (dynamic response): ± 10% in response to a step load change
of 100% rated output and shall be restored to within steady state limits within
1 sec.
Total harmonic voltage distortion: 5% when supplying a linear load.
The output UPS units shall be in synchronism with output maintenance bypass
circuit
The alarm of UPS units shall be displayed at UPS panels; the common alarm
(all failure and abnormal states) shall be display on operation console monitor
with active horn and beacon at center control room.
At UPS panel shall be displayed minimum of: Charger ON/OFF, inverter
ON/OFF, synchronous signal, static switch bypass ON/OFF, maintenance
transformer bypass ON/OFF, high temperature, rectifier failure, and inverter
failure.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 166 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
At UPS panel shall be displayed minimum of: Charger ON/OFF, inverter
ON/OFF, synchronous signal, static switch bypass ON/OFF, maintenance
transformer bypass ON/OFF, high temperature, rectifier failure, and inverter
failure.
Input and output voltage meters, output frequency meters shall be displayed on
DCS panel, the digital meter shall be used.
The A.C. loads may comprise any type of lighting source (e.g. tungsten filament,
discharge lighting, etc.) and may contain harmonic current distortion.
Inverters
Inverters shall have current limiting characteristics. They shall control the
output voltage in synchronism with the mains bypass voltage, while the mains
supply remains within the specified frequency limits. Outside these frequency
limits the inverter shall revert automatically to its own internal frequency
control. Following restoration of the mains frequency to within the specified
limits, the inverter shall automatically re-synchronise to the mains supply.
The inverter, when operating in isolation, shall be capable of producing
sufficient short-time current to cause a distribution circuit switch device with a
current rating not less than 10% of the inverter's rated output current to rupture
within 5 ms without initiating changeover of the transfer switch, where installed..
The inverter output, as measured at its output terminals, shall lie within the
specified limits, when operating continuously under the following conditions:
With the types of load(s) specified or required
With any load between no-load and rated output
With any power factor between unity and 0.7 lagging
With a d.c. input voltage between the battery boost voltage and end voltage.
Where 3-phase output is specified or required, and when supplying a linear load,
the mismatch between phase voltages shall not exceed 1% and the angular
displacement of the phase voltages shall not exceed 120° ± 1°.
Static Transfer Switch
The electronic transfer switches shall comply with IEC 60146-5 as amended and
supplemented by this Request for Proposal.
The transfer switches shall be rated to match the outputs of the UPS units and
the mains bypass supply in terms of both continuous rating and short term time
rating.
The transfer time shall not exceed 1 ms. The transfer shall normally be
synchronous, but the transfer switch shall be capable of an asynchronous
operation. Transfer between UPS units and from a UPS unit to the mains bypass
circuit shall be initiated
automatically or manually. Transfer from the mains bypass circuit to a UPS unit
shall only be initiated manually.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 167 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
A. C. Distribution Boards
Each UPS system shall be provided with an output distribution board, which
shall comply with the requirements of IEC 60439, as amended and
supplemented by this Request for Proposal.
The switchboards shall be metalclad and shall have a minimum enclosure
classification IP 42. The floor of the switchroom shall not form part of the
enclosure. The busbars shall be insulated.
The switches and contactors shall comply with IEC 60947, as amended and
supplemented by this Request for Proposal. The switches and contactors shall
be rated 25% higher than the design circuit load current, subject to a minimum
rating of 25A.
Switches shall have an utilisation category of AC22 for incoming and bus
section circuits, AC23 for outgoing circuits and AC3 for contactors.
Each A.C. switchboard shall incorporate the following equipment, as applicable:
+ Incoming supply switch-disconnector;
Bus section switch-disconnector (or interconnector switch-disconnectors),
as applicable;
MCCB/MCB for each outgoing circuit;
Motor starters;
Under and overvoltage alarm relays (one per busbar section);
Busbar voltmeters (one per busbar section).
Alarm indicating lamps shall be provided on each section of the switchboard
for the following conditions:
Undervoltage fault + Overvoltage fault
The settings of these fault relays shall be adjustable. No local audible alarms are
required. A voltage-free common repeat alarm shall be provided for remote
indication.
A lamp test pushbutton shall be provided.
Motor starters shall comply with the requirements for LV motor starters as
specified under section for LV Switchgear.
Tests
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 168 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
independent authority.
The type test certificates and results of the tests shall be included in the Bid.
The battery room shall comply with the requirements of AS 3011.1-1992 and
AS 2676 1-1992.
This clause shall be applied for whole power plant where batteries are installed.
The battery room temperature shall be maintained at 20oC.
Battery Installation Safety Requirements
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 169 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The emphasis shall always be on providing a safe installation.
Drawings to be provided by the Contractor during the Contractor
The following drawings shall be provided by the Contractor during the contract.
Detailed layout of the battery room showing important dimensions including
distances between of batteries and door openings.
Detailed layout of 220 V DC switch boards
Detailed layout of DC switchroom
Detailed layout of UPS modules
Details of safety signs for battery room
Single line Diagrams of the 220V DC and 230V AC UPS systems.
Electrical diagram detail drawings of all control, distribution board and
power converter system.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 170 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
7.11 CABLING, WIRING, CABLE SUPPORT SYSTEM
Standards
The Bidder/Contractor shall be responsible for the planning and setting out of
all cabling work within his area of responsibility. The cabling installation shall
be confined to exclusive air spares in the principal cabling areas. Where
necessary, cables may be installed underground in which case a conduit system
shall be used. Directly buried systems shall not be used.
To achieve this requirement, the Bidder/Contractor shall design and submit for
approval an overall cabling strategy showing how the rationalisation of field
signals can be achieved.
When planning cable type and routes (racking, conduits etc) the
Bidder/Contractor shall comply with the following requirements:
All control and instrumentation cables shall be marshaled as much as possible
in the fields to ensure that a minimum of cables will be routed to the control
system in the CCR Building.
All multi-core cables for control and instrumentation shall be terminated at the
I/O marshalling cubicles on the first floor. Then preformed cables shall be used
between the I/O marshalling cubicles and the ICMS control.
Cables shall also be segregated to ensure in the event of damage (e.g. fire) to a
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 171 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
section of a cable system that a minimum of plant is affected (e.g. duty and
standby supply cables shall be installed via separate routes).
Cables shall also be separated to ensure electromagnetic compatibility between
various types of cables. For this purpose all cables are to be categorised into
four types, namely:
(1) Maintain a database of cable types to be used with the details of cables including
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 172 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
but not limited to voltage rating, number of cores and core size.
(2) Maintain a database of each cable scheduled for installation including but not
limited to type, route, estimated length, actual length and reference drawings.
(1) Conductor material shall be untinned copper complying with IEC 60228.
(3) Except in cables supplying movable plant such as trippers, control and power
conductors shall not be included in the same cable.
(4) All cables shall be suitable for correct and safe operation in the environmental
conditions in which they will be installed.
(5) Cables shall not be jointed except in long runs where production lengths cannot
be manufactured to the desired length
(6) Cables which are run underground shall be installed in conduits. Cables shall
not be direct buried except with the express approval of the Owner.
Where it cannot be demonstrated that a cable run is either directly
accessible/visible or that it is effectively contained and sealed (e.g. in a conduit
fire sealed at both ends), metallic armouring shall be used as a means of
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 173 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
preventing damage from attack by vermin (rodents). Armoured cables shall in
addition be provided with an overall PVC sheath. The armour shall be
galvanized steel wire armour except for single core cables in which case it shall
be aluminum wire armour.
Cables cores and earth wires shall be coloured as per current Vietnamese
standards, eg. red, yellow, blue and black for phase colour and neutral.
Selection of Cable Conductor Cross-Sectional Area
The cross sectional area of cables shall be selected by the Bidder/Contractor
using the following criteria:
(1) To ensure that cable temperatures do not exceed acceptable levels (as nominated
by the manufacturer). The cross sectional area shall be such that the continuous
current rating of the cable (in the most onerous part of the installation) is higher
than the rating of the device protecting the cable (e.g. miniature circuit breaker
etc.).
However, the Bidder/Contractor shall also pay special attention to the sizing of
cable cores (in particular to the control cables and instrumentation cables) to
ensure that they are not oversized and become a burden to the cabling system.
To achieve this requirement, the Bidder/Contractor shall estimate the required
size of cable cores for control and instrumentation cables and make a formal
submission to the Owner for approval prior to the ordering of cables.
(2) The voltage drop at equipment load terminals due to cable impedance shall be
less than 5% of nominal voltage.
(3) During the starting of large motors, short-term voltage excursions of up to 10%
may be experienced at the source of supply. The total allowable voltage drop at
equipment load terminals under these conditions including cable impedance volt
drop shall be limited to 15% of nominal voltage.
Note: For motor loads these requirements may need to be more stringent
depending on the nature of the process (e.g. conveyor belts, slurry pumps, valves
etc.) or the motor manufacturer requirements for the proper and safe operation
of any particular motor.
The cable shall be suitable to withstand without any damage the maximum
through fault current for the maximum duration. The duration shall be the
operating time of the secondary protection (i.e. back up relay) for relay protected
systems.
M.V. Power Cables - XLPE Insulated Power Cables
Cross linked polyethylene (XLPE) cables shall be used in 11kV Systems. The
cables shall comply with the following:
(1) Single or three core cables of 12/24kV voltage grade shall be used on the 11kV
system.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 174 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
screen, XLPE insulated, hand thermosetting material semi-conductive
insulation screen, fire retardant low smoke (FRLS), copper wire screen, PVC
sheath, galvanized steel or aluminum wire armour and PVC black outer sheath.
And, the FRLS characteristic of PVC sheath as per ASTM E662 will be applied.
These cables must have phase identification colour coding
(3) The adhesion between the semi-conductive insulation screen and the insulation
shall be designed to be hand stripped without preconditioning (i.e. no heating
required).
(4) The copper wire screen shall be sized for light duty. If 3 core high voltage cables
are used then the cores shall be individually screened.
(5) The cables shall be manufactured by competent companies for which type test
certificates shall be available to show compliance with IEC60502.
(7) Single core cable should be applied for motor’s feeders of rating above 1500kW.
Multiple core cables should be applied for motor’s feeders of rating including
and less than 1500 kW.
L.V. Power Cables - XLPE Insulated Power Cables
The following requirements on XLPE insulated power cables shall apply:
Cables shall be used on 400/230V A.C and D.C systems. PVC/XLPE
insulated cables shall be manufactured in accordance with IEC60502 having
stranded, copper conductors, grade PVC insulation, 0.6/1kV voltage grade,
separation tapes and black PVC sheath, fire retardant low smoke (FRLS),
with galvanized steel or aluminum wire armour and black PVC outer sheath.
And, the FRLS characteristic of PVC sheath as per ASTM E662 will be
applied.
These cables must have phase identification colour
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 175 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Control Cables
The following requirements on control cables shall apply:
Cables shall be manufactured in accordance with IEC60502 having stranded
copper conductors, PVC insulation, 0.6/1kV voltage grade, separation taped,
black PVC sheath, fire retardant low smoke (FRLS), galvanized steel wire
armour and PVC outer sheath with circular cable construction.
And, the FRLS characteristic of PVC sheath as per ASTM E662 will be
applied.
These cables must have phase identification colour
Cables shall have 25% (1/4 cycle) overlapped aluminum/polyester laminated
tape screen with 7/0.3 tinned copper drain wires. For relay/contact type
systems operating at 230V A.C. or D.C. the cables need not be screened.
Cable cores shall be coloured and each core shall be uniquely numbered at a
spacing not exceeding 100mm.
At least 2 cores or 10% of total number of cores of a cable (whichever is
greater) shall be provided as spares. This does not apply to a five-core cable.
The conductor cross sectional area for relay/contact type systems shall be
sized to meet the max voltage drop of 5%.
The minimum conductor cross sectional area for solid state type system shall
be 0.5mm2.
The Bidder/Contractor shall pay attention to the sizing of cable cores to
ensure that they are not oversized and become a burden to the cabling system.
To achieve this requirement, the EPC Bidder shall estimate the required size
of cable cores and make formal submission to the Owner prior to the ordering
of cables.
Instrumentation Cables
The following requirements shall apply to instrumentation cables:
The instrumentation cables shall have stranded, copper conductors with PVC
insulation, overall screened and PVC black sheath and galvanized steel wire
armour and PVC black outer sheath. The cores shall be formed a twisted pair
or twisted triples depending on the application.
The cables shall have an overall screen. For added immunity against
electrical interference the individual pairs of triples may also be screened.
The screens shall be an aluminum/polyester laminate taped with a minimum
7/0.25mm tinned copper drain wire.
Each twisted pair or twisted triple shall be colour and number coded.
The minimum cross sectional area of the conductors shall be 1.5mm2 for
single pair or single triple cable and 0.5mm2 for multi pair or multi triple
cable. For “resistance temperature device” (RTD) circuits the cross sectional
area shall be such that voltage drop along the cable is minimised to ensure
the required RTD accuracy.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 176 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
At least 1 pairs (or triples) or 10% of total number of pairs (or triples) or a
cable shall be provided as spares. This does not apply to single pair or single
triple cable.
Communication Cables
Cables shall be manufactured in accordance with IEC 61158
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 177 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(1) Co-axial cables
(a) Co-axial cables between switchyard line coupling equipment and
communications room (outdoors) shall have:
75 ± 3 impedance 7/0.4mm bunched tinned copper conductor, solid
polyethylene dielectric, plain copper wire braid screen, PVC sheathed,
galvanized steel wire braid armour and PVC sheathed overall.
The armouring shall consist of a single braid (94% coverage factor) of 0.5mm
galvanized steel wire.
The outer PVC sheath shall have a normal radial thickness of 1.3mm.
Maximum overall diameter of the cable shall be 14.6mm (14.3mm nominal).
(b) Co-axial cable within communications room (indoor) shall have:
75 ± 3 impedance 7/0.2mm bunched tinned copper conductor, solid
polyethylene dielectric, plain copper wire braid screen and PVC sheathed
overall.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 178 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
welding and scuffing of the cable sheaths.
(5) Cables shall be provided with supports located as close as is practicable to the
point of termination of the cable. Cables shall be fixed to trays/ladders by
approved clamps or cable ties . Cables in vertical risers shall be adequately
supported throughout the run at intervals not exceeding 2m to prevent undue
strain where the cables leave the riser. Cables shall be clamped at the point
where they enter or leave a cable tray ensuring that no high stress concentration
is placed on the cable sheath. Metal buckle slips shall not be used. Supports shall
be provided in cable pits to ensure cables do not sag, are kept off the bottom and
do not impede access.
(6) All power cables above 6 mm2 shall be individually supported. Power cables
6mm2 and less and control, instrumentation and communication cables may be
individually supported or supported in groups not exceeding ten.
(7) Single core power cables forming part of a three-phase system shall be rigidly
held in trefoil formation by approved metallic clamps. Such cable installation
shall be suitable to withstand the maximum short circuit forces for the maximum
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 179 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
duration without damage to ladder or clamp, or risk of injury to personnel. Type
test certificates of the installation (i.e. comprising cable, clamps, ladder supports
including straight runs and right angle bends) shall be available as proof of the
adequacy of the proposed system. The spacing of the clamps shall be in
accordance with the test certificates.
(8) Cables shall be identified at each end both of cable by identification tags. The
material shall be made of stainless steel.
(9) Where more than one single core cable per phase is used, each trefoil formation
shall contain a cable of each phase.
(10) The identification tags for cables of trefoil groups shall include a suffix
consisting of a letter to represent the phase of the cable (for example suffix A to
show phase A). A further suffix consisting of a number shall also be used when
more than one cable per phase is used (for example A1).
(11) Power cable installation at motor terminal boxes shall be provided with a
suitable support system for the cable and terminal box (if of the detachable type)
while the motor is removed for maintenance. Such support system must not
interfere with maintenance access for the motor, the driven device and
associated accessories.
(12) Joining of cables is not permitted unless otherwise approved. Any cable joint or
termination must be carried out by qualified personnel. The cable jointers must
be in possession of a valid jointing certificate from the respective manufacturer
of cable joints/terminations.
(14) Where the use of cable changing boxes for power cables are approved the boxes
shall be capable of withstanding the appropriate short circuit forces due to the
maximum through fault for the maximum duration without damage. The boxes
shall be air insulated, provided with an earth terminal and a label identifying the
circuit origin..
(15) During installation cable drums shall be protected to ensure the cable is not
damaged. Additionally, to prevent the ingress of moisture, the cable ends on
drums shall be capped with a heat shrink cover whenever cable pulling is
suspended. The drum operation shall be either automatically or manual. It is not
allowed to just simply pull the cable off the drum. The cable must be always
rolled off the drum to avoid any coiling of the cable.
(16) When the cable comes of the drum, cable rollers have to be used. The rollers
shall ensure that the cable doesn’t touch the ground during pulling operation.
The following shall be observed with the use of cable rollers
(17) A sheet steel guard protective system shall be provided around cable
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 180 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
ladder/trays and other cable support systems in the following locations:
Within two metres of the floor and in any location where cables may be
exposed to mechanical damage; or
Where cables on tray pass under or adjacent to pipes containing fluids (other
than water);
In areas which are subject to fire hazards (i.e. rubbish accumulation,
oil/grease areas, chemical areas).
Where materials could accumulate onto cables in such quantities to cause a
de-rating or chemical attack of the cable (e.g. coal dust, ash etc.).
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 180 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(19) Surface Electrical Cable Conduits
Surface electrical cable conduits and fittings shall be galvanized steel or
heavy duty UPVC.
All conduits shall be of sufficient size to permit the easy drawing in or
removal of any one conductor while others are in place. The minimum size
conduit permitted is 20mm.
Conduits shall be concealed, where possible by installing in concrete slabs,
false ceiling or cavities or by chasing into walls. All conduit chases in walls
shall be vertical or horizontal; racked chases will not be permitted. Conduits
must be installed parallel to structural members, wall, doors, etc., and must
not be installed across tiled surfaces, not be diagonal, oblique, slanting,
Where surface conduit is installed over painted surfaces, the conduit shall be
painted using primer, undercoat and finish coat to match the surrounding
surface finish. Surface run conduit shall be protected from mechanical
damage. Where rooms/location are required to be aesthetic/beautiful as CCR/
Office, Meeting room, Control room,.. the conduits installation shall be
embedded.
Standard bends, sets or inspection type fittings shall be used and each
inspection fitting shall be provided with a gasket of an approved material. In
runs involving 4mm2 conductors or larger, standard bends or sets shall be
used in lieu of elbows. Conduits shall not be set more than twice between any
two inspection fittings or draw-in points. Where conduit runs exceed 25m
additional draw-in boxes shall be provided at intervals of 25m.
Conduit shall be fastened in position by means of hot-dipped galvanized steel
double-sided saddles. Where conduit spans between two support points
double-sided saddles with removable fastenings shall be used. Method of
attachment to concrete surfaces shall be to an approved method. Saddles shall
not be spaced more than 2m apart.
The ends of all conduit shall be free of burrs, slag, burrs, sharp edges, debris,
mill scale, swarfs, scobs). Threads on the ends of conduit shall be true and
clean. Running threads shall not be used.
All metallic conduits shall be terminated by screwing into or securely lock-
nutting to the respective accessory.
All conduits shall be installed complete with galvanized steel draw wires.
All conduits shall be erected in position before the draw-in of conductors is
commenced. During construction, the Bidder/Contractor shall ensure that the
open ends of conduits are sealed with plastic or metal caps.
All conduits terminating in masonry walls shall be terminated in single or
multiple gang flush mounted boxes. The wall boxes shall be complete with
standard phone outlet flush plates.
Flexible metallic conduit may be used in ‘difficult’ areas where rigid conduit
is not practical. Flexible conduit and fittings shall be able to be coiled without
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 181 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
damage or reduction in cross sectional area and shall be suitable for the
environment in which they are installed.
Galvanized steel conduits and fittings shall be hot dipped galvanized. The
conduit shall be earthed at the distribution board by means of an earth clip
and a direct connection to the main earthing conductor.
Heavy-duty UPVC conduit joints shall be made using a solvent type glue as
recommended by the manufacturer of the conduit.
Underground Electrical Cable Conduits, Pits and Trenches
The following shall apply to underground electrical conduit systems:
All conduits and fittings shall be heavy duty UPVC to comply with IEC
60614. Conduits shall be installed underground, rigidly encased in concrete
and backfilled to provide a neat surface finish. The top of the conduits shall
not be less than 600mm from the surface.
The conduits shall be at 100 mm or 150 mm nominal size. Smaller size
conduits may be used in specific areas if there is no likelihood of future cable
installation.
All conduit runs shall be straight. A cable pulling pit shall be constructed
every 50 metres or less and wherever conduits change direction. Bends shall
be used to terminate conduits into a haunching but generally shall not be used
elsewhere unless approved.
For every conduit run at least one conduit shall be provided for
communications.
For every conduit run at least one conduit or 20% of total number of conduits
(whichever is greater) shall be provided as spare for future use.
Cable pulling pits shall be constructed of reinforced concrete of adequate size
and strength to cater for pulling practices and minimum bending radius of
cables. Pit covers shall be heavy duty to cater for expected loads, depending
on location.
Where cable trenches are provided inside buildings, they shall be of reinforced
concrete construction and fitted with heavy-duty metallic, sealed covers to cater
for the maximum traffic load expected.
All cable trench, pits shall be provided with drainage facility to keep them free
from water. Trenches and ducts shall be sloped to permit gravity drainage,
where possible, into the normal site drains. Where drainage by gravity is not
possible, the trench, duct or pit shall be provided with drainage sump(s) and
sump pumps. Sump pumps shall be complete in all aspects including discharge
piping which shall terminate at a location approved by the Owner. Two (2) nos.
sump pumps with 100% duty each shall be permanently installed at each sump
location and each pump designed to empty the trench. The sump pump operation
shall be controlled automatically from the water level in the sump.
Note. Contractor shall provide the cable trench from Quang Trach I TPP to
Quang Trach 500kV Switchyard to connect the cable for interlocking,
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 182 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
controlling and necessary cable, signal to complete the Project
Cables - Termination
Cable Glands
(1) Glands for electrical enclosures shall be metallic, metric, weatherproof and
flameproof suitable for the type of cable and having facilities to terminate the
cable wire armour. The seal receptacle shall be tapered to provide a tight seal
on to the cable as the gland nut is tightened. Concentric variable diameter
sealing rings are not acceptable. Each size (diameter) of cable shall be fitted
with the correct size gland as nominated by the supplier of the gland. Cable
glands shall be installed on gland plates provided with the enclosure. Correct
size holes shall be drilled to accept the various gland sizes.
(3) Wire armouring on control cable shall be earthed at one end only.
Crimping
(1) Crimping of a lug to the conductor shall be carried out using an approved type
tool. The tool shall be so designed as to prevent release until the correct degree
of crimping has been attained.
(2) Hexagonal crimps shall be used on cables 25 mm2 cross sectional area and
larger. The die identification code shall be impressed onto these crimp lugs. The
crimp shall take into consideration the fact that some conductor may be
compressed. To ensure a correct crimp, the compression tool, die and lugs shall
be compatible, preferably of the same manufacture.
(3) The crimping method shall meet the test methods and requirements of IEC
61238-1.
Power cable termination
(1) The type of lug used shall be suitable for the conductor size as nominated by the
manufacture taking into consideration that the conductor may be compressed.
The lugs shall be electro tinned copper except that bi-metallic lugs may be used
where one mating surface is aluminum. .
On equipment where there is a likelihood of contact with oils or compounds
(e.g. transformer cable boxes) all lugs shall be totally sealed (e.g. solder sealed)
to prevent ingress into the cable conductor.
(2) Low voltage power cables shall be terminated using shrinkable sleeves or self
amalgamating tape. The barrel of the lug shall be insulated.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 183 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(3) The following shall apply for termination of high voltage cables:
The cables shall be terminated in dry (i.e. air insulated) type terminal boxes.
If electrical clearances are inadequate, subject to approval, a H.V. compound
shall be used. The compound shall be suitable for the type of cable used
The cables shall be terminated using a dry type termination system having a
stress relief mechanism. The termination system shall be compatible with the
cable and lug being used and shall be capable of passing all relevant tests
stated in the standard appropriate to the cable (e.g. IEC 60502 for XLPE cable)
Type test certificates for the complete termination system shall be made
available.
The terminating procedure shall be performed strictly in accordance with
recommendations of the supplier of the termination kit.
Cable copper wire screens shall be twisted together, taped, fitted with a lug
and terminated to earthing facilities as below.
After the completion of installation and termination of power cables and prior
to energising, the cables shall be tested to ensure fitness for service. The
minimum tests required shall be an insulation resistance, continuity and H.V.
tests at levels appropriate to the grade of cable.
Fire and smoke stopping
(1) A fire and smoke stopping system shall be provided on all openings through
which cables penetrate. This shall include conduit ends, openings in walls,
floors or ceilings, cable risers, under all electrical enclosures and switchboards
and any other area which will prevent the spread of fire.
(2) On vertical cable systems (i.e. cable risers) the fire and smoke stopping system
shall be applied every 3 metre intervals to prevent a chimney effect.
(3) The fire and smoke stopping system shall be applied after all known cables have
been installed through a particular opening. During the construction phase (i.e.
during installation of cable) a temporary fire protection system shall be applied
(e.g. fire plug pillows). The temporary fire protection system shall be totally
removed just prior to the installation of the permanent fire and smoke stopping
system.
(4) If an additional cable needs to be installed through an existing fire and smoke
stopping seal then a minimum sized hole shall be drilled or cut (not bashed) to
accommodate the cable. The seal shall then be restored to its original
performance by applying the same fire and smoke stopping material in a manner as
recommended by the supplier of the material.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 185 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(5) The fire and smoke stopping system shall comply with the following
requirements:
Compliance with ISO 834 for a 2 hour rating;
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 186 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The materials used shall not be affected by water, shall not emit nauseating
or toxic substances and shall be vermin proof and shall not deteriorate or
shrink with age;
The materials used shall be of such composition and construction that they
can be penetrated to permit the installation of new cables and can be resealed
without the need for total replacements;
The use of asbestos, asbestos products or ceramic fibres is prohibited;
Any permanent damming or reinforcing material shall not reduce the rating
of the system;
Any temporary damming material shall be removed;
Any supporting steelwork shall be galvanized and installed such that a
magnetic circuit is not created around single core cables; giá đỡ mạ kẽm
Cables shall be ‘unbundled’ to ensure that the interstices of cables will be
adequately sealed.
This Clause covers all connections for voltages not exceeding 400 V nominal
and contained within enclosures such as switchboards, control cubicles and
interpanel wiring. It does not include connections within specific components
such as relays, circuit breakers etc.
Installation
All wiring shall be carried out in accordance with wiring diagrams or
connection lists so that the arrangement of the wiring is consistent throughout
the plant and identical for those parts of the plant performing the same duties.
Wiring shall be enclosed in ducts or conduits or supported on trays and shall
be neatly and securely bunched and cleated unless enclosed on all sides. The
bunching of wiring shall be accomplished by means of punched plastic string
lacing. Metal buckle type clips shall not be used. The total number of wires
in any one bunch shall not exceed 20 and the strapping or lacing of the wiring
shall be carried out at intervals of approximately 150 mm. Wherever wiring
is cleated to metalwork, it shall be insulated from the metal surface and shall
be cleated by means of insulated straps. All wiring shall be left sufficiently
long and neatly looped to allow a fresh termination to be made should the original
termination device break off. Joints in conductors shall be made only at terminals.
As far as is practicable, wires operating at the same voltage shall be grouped
together at the terminals.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 187 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Fuses shall be included in the wiring to provide adequate protection for all
circuits and sub-circuits.
Wire Construction
Insulation shall be in accordance with the requirements of IEC 60502 for each
voltage grade.
All conductors shall be untinned annealed copper complying with IEC 60228.
Each conductor shall have at least seven strands.
The conductor cross sectional area shall be suitable for each circuit ensuring
that temperatures do not exceed acceptable levels (as nominated by the
wiring manufactures) under any normal or abnormal mode of operation.
In all cases, the minimum size conductor shall be:
1.5 mm2 for under 5 metre lengths
2.5 mm2 for over 5 metre lengths
0.5 mm2 for solid state type circuits
Termination
Conductors shall be terminated onto terminals using crimped electrical
connectors.
The connectors shall be manufactured from annealed copper and shall be
electro tin plated. The size and thickness shall be such as to provide a robust
and low electrical resistance connection.
The connector shall be compatible with the size of the conductor as nominated
by the manufacturer of the connector.
The connector and the crimping tool shall be compatible. The tool shall be of
the type which cannot release until the crimping action is satisfactorily
completed.
The variety of electrical connectors used will depend upon the terminal
facilities and shall comply with the following:
Ring type termination lugs shall be used for terminating to stud type terminals.
No more than two terminations per stud may be made.
Lip blade termination lugs shall be used for terminating to ‘insulation shrouded,
screw clamp’ type terminals. Two terminations per terminating facility may be
made.
U shaped termination lugs may be permitted subject to specific approval on
selector switches, auxiliary contacts of relays and similar small equipment where
the terminating facility consists of a set screw screwing into a rectangular tab and
which is fitted inter alia with a rectangular washer. The rectangular washer is to
be formed to a shallow U shape and fitted to the rectangular tab terminal so that
it cannot rotate. The U shape termination lug shall be a force fit over the thread
of the set screw and shall be inserted between the tab terminal and the rectangular
washer.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 188 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The wiring associated with external circuits shall be connected to terminal
strips which shall be conveniently arranged to facilitate the termination of the
incoming cables. This requirement shall apply to spare contacts on contactors,
relays, control switches, and similar equipment.
Unless otherwise approved, not more than three earth leads shall be
terminated at one terminal. Where more than three earth connections are
required, an earth bar of cross sectional area not less than 25 mm x 3 mm
fitted with studs shall be provided. Control switches, instruments, relays and
similar equipment associated with any one circuit shall have their earth
terminals bonded together and connected directly to the earth bar or terminal
as applicable. Each such connection shall be identified clearly at the earth bar
of each terminal end. The earth connection for each current transformer (or
group of current transformers) and each voltage transformer shall be
connected to the earth bar or terminal through isolating links of an approved
type. Current transformer earth links shall be fitted in an approved position
adjacent to the associated sets of current test links.
A current test link and a voltage test terminal shall be provided in each “phase”
and neutral connection of current and voltage transformers. The conductor
from the current transformer shall be connected to the bottom terminals of
the movable link (if panel mounted) or left hand side (if rail mounted).
Wire identification
Both ends of every wire shall be fitted with approved white non-flammable
plastic ferrules having recessed identifying numbers and/or letters filled with
a suitable black paint to correspond with the numbering on wiring diagrams.
The ferrules shall encircle the wire. Stamped number tags, plain ferrules
marked on the surface only with ink or paint and similar methods will not be
accepted. All ferrules shall be fitted to read from left to right and be the
correct way up irrespective of the side from which the wire approaches the
terminal. Where the wire approaches the terminal from above or below, the
ferrule marking shall read from bottom to top.
If a conductor identification is made up of more than one single ferrule, the
ferrules shall be of approved type which interlock or which grip the cable
insulation firmly.
Ferrules used with crimp type terminals shall be of the “gripping” type, or
figure ‘8' type with slide in ferrules (i.e. they shall not require the cable
insulation to be stripped to permit installation.
In addition red ferrules engraved TRIP or T shall be fitted to trip circuit
wiring as follows:
At outgoing terminals of the circuit all wires connecting to the trip coil.
At other panels or cubicles remote from the circuit cubicle, intertripping wires at
outgoing terminals connecting to a trip circuit.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 189 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Terminal Strips, Blocks, Plug Connectors
This clause covers the arrangements to be made for connecting between cables
and the internal connections of enclosures.
Terminal Block
Terminal blocks shall be of the moulded insulation type suitable for mounting
on a rail via a snap action. The insulation shall be made from thermosetting
plastic material. The types shall be as follows:
The terminal blocks shall be fully shrouded, fitted with screw clamps and spring
loaded. They shall be suitable to accept two back to back lip blade lugs at each
terminating point.
Bolted connections shall be provided suitable to accept a ring lug at each
terminating point. A cover shall be provided to prevent contact with the otherwise
exposed parts of the terminal. Mounting of the connection assembly shall be
sufficiently secure to ensure that it cannot be pulled apart using the terminated
cable i.e. rail mounting is generally unacceptable. Đầu cốt vòng
The terminals shall be suitable to withstand 2kV rms for 1 minute between
terminal to terminal and terminal to rail. The insulation resistance shall not
be less than 100 M (at 1kV).
Terminal strip
Terminal strips shall be arranged in vertical rows. In the case of floor
mounting equipment, they shall be not less than 250 mm above floor level.
For ensuring adequate access for the termination of cables, the supports for
terminal rails within enclosures shall be designed such that the terminals
stand clear of the panelwork by approximately 100 mm. The terminals shall
be arranged so that at least 150 mm is provided between rows.
For ease of location of a terminal, a barrier shall be provided between every 10
terminal blocks. The terminal blocks shall be firmly secured in the mounting
rail using end plates and clamps.
At least 10% spare terminal blocks shall be provided for future use.
Each terminal strip shall be uniquely identified e.g. TS1, TS2 etc. Each
terminal in each strip shall be identified by numbers i.e. starting from ‘1' for
the top terminal and consecutively numbered downwards. Furthermore, those
terminals operating at potentials exceeding 110 volts (e.g. anti-condensation
heaters) shall be labeled to warn of the higher voltages.
Termination on Components
Termination provisions on components shall generally consist of studs, nuts and
lock washers. However, in certain instances where this is not practicable the
following shall apply:
Screws with screwdriver slots and hexagon heads shall be provided. Screws
with alternative head types or requiring the use of tools other than a parallel
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 190 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
tip screwdriver will not be permitted unless specifically approved. Each
screw shall be provided with a spring washer.
Components provided with solder-lug connections shall be mounted on plug-
in trays or shall be provided with a wiring harness arranged for connection to
approved terminals or high quality plug and socket connectors.
If the use of plug and socket connectors is permitted, approved means shall
be provided to ensure that the plug is retained firmly in the socket and can be
inserted one way only. If several plug and socket combinations are located
together they shall be arranged so that incorrect connections cannot be made
Power and Control Cables
(1) General
For hazardous areas and directly buried cables, multi core cables must have
galvanized steel armour and single core cables must be aluminum wire armour.
Cables must be adequately sized with design margins for the factors of full load
current, short circuit current, voltage drops during starting and running
condition and derating factors due to ambient temperature and grouping /
method of installation. Motor starting conditions must be as specified in IEC
60034.
Minimum size of power cables must not be less than 2.5sq. mm for copper
conductor. Minimum size of control cables must be not less than 1.0 sq. mm.
20% spare cores must be provided in all control cables except two (2) cores or
one (1) pair cable.
Cables must be delivered in non-returnable cable drums having ends of each
length of cable properly sealed before dispatching.
All cable runs must be continuous. Control and instrumentation cables may be
interconnected for marshalling purpose in suitable enclosures.
Outdoor cables shall be laid in air in ductbank or cable trench or cable tunnel
and shall be supported by cable trays/ladder for their entire length or shall be
laid in concrete ductbank with manholes. Where manholes and cable trench or
cable tunnels can become flooded with water for extended periods the cable
construction shall be selected and designed to prevent the ingress of water
including the provision of water blocking tapes.
The cables must include measures to prevent insect damage e.g. cables exposed
to direct sunlight must have ultra-violet resistant over sheaths. Control and
instrumentation cables must be capable of withstanding the voltage transients
associated with unsuppressed coils etc.
Cables must have either copper or aluminum conductors with extruded
insulation/sheath in accordance with internationally recognized standards, and
be of the following or equivalent types:
All MV cables must be of stranded annealed copper conductor, XLPE
insulated, screened, , fire retardant low smoke (FRLS) overall PVC sheathed
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 190 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
type with IEC 60502. And, the FRLS characteristic of PVC sheath as per
ASTM E662 will be applied. These cables must have phase identification
colour coding.
All LV(400V) power cables must be of 1100 V grade stranded annealed
copper conductor, XLPE insulated, extruded FRLS PVC outer sheath. And,
the FRLS characteristic of PVC sheath as per ASTM E662 will be applied.
These cables must have phase identification colour coding.
Control cables must be of multi-core 600-volt, grade 1.0mm2 stranded
annealed copper conductor, PVC insulated, FRLS, and PVC sheathed type.
And, the FRLS characteristic of PVC sheath as per ASTM E662 will be
applied. These cables must have core identification coding.
Fire resisting cable tested to the highest test temperature in IEC 60331 must
be used for essential circuits such as lubricating oil pump, turning gear motor,
jacking oil pump, control circuit for generator circuit breaker, turbine trip
locks out as a minimum required to remain functional in the event of a fire.
Mineral insulated cable must be used for fire detection and fire fighting
equipment.
All cables supplied including signal, control, fibre optic, communication,
Ethernet and LAN cables shall be suitably protected against rodents and
insects. This specification is especially applicable to the outer PVC layer of
the cable.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 192 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
incorporate suitable personnel access and emergency escape routes and
emergency lighting.
Heavy duty galvanized steel ladder rack or perforated tray must be used for
cable support on major cable routes. For minor routes where the weight is not
high, a light duty galvanized steel cable support system may be used.
All cables must be installed in a neat and orderly manner as far as possible
arranged to allow removal of any single cable in a run without undue
disturbance to adjacent cables. Adequate support must be provided with bearing
surfaces free from sharp edges. The cables must be protected against mechanical
and other potential hazards e.g., heat sources, at vulnerable positions. Cable
minimum bending radii must not be exceeded.
Single core cable must be installed in either trefoil or flat formation and secured
using cleats. The method of cleat must ensure that cables are restrained to
prevent damage during short-circuit conditions whilst allowing movement due
to thermal cycling at bends.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 193 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Information to be provided
Applicable standards
The Bidder/Contractor, at an early stage in the Project before the Site works
commence shall undertake a survey of the ground resistivity over the whole Site
to ascertain general and specific values. The survey shall also establish
requirements for cathodic protection. A report of the values measured shall be
submitted to the Engineer for approval.
Based on the survey the Bidder/Contractor shall then prepare a detail design for
the complete above and below grade earthing system, lightning protection
system, bonding system and earth electrodes for the entire Project for approval
by the Owner.
The design shall be based on the interconnection to form one (1) complete
system of all of the metalwork forming part of the equipment or structures
associated with the Power Plant and with the 500kV EHV Overhead line tower
which is not normally live, the steel reinforcing in foundations and a buried
equipotential conductor laid round any structure which has not got a reinforced
foundation connected to the below grade earthing system.
The installation shall also embody the recommendations made in Vietnamese
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 194 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
standards and shall be designed to ensure that the earthing resistance prescribed
for operation under Vietnamese standards are not exceeded.
All steel frame and reinforcing steelwork shall be connected to this grid.
Cable screens and armour shall be earthed
Thereafter the Bidder/Contractor shall supply, erect, install, test and
commission the earthing system to the satisfaction of the Engineer.
The installed earthing and bonding system shall fulfil the following basic
requirements:
Maintain a low overall resistance of the earth mass to limit the Plant potential
rise and ensure protective relay operation in the event of an earth fault.
Provide ground connections to all electrical apparatus, enclosures and
structural steelwork adequate to carry prospective ground fault currents
without excessive heating or fire risk.
Limit potential differences within the Power Plant Site and within one (1)
meter thereof in the event of earth fault current originating from within or
outside the Plant to ensure the safety of Personnel and eliminate interference
or damage to sensitive electronic circuits.
Provide lightning protection.
The installation shall be to modern engineering practice and shall embody the
recommendations made in IEEE 80 and IEEE 665 and shall be designed to
ensure that the maximum step and touch voltages prescribed in these standards
are not exceeded under fault conditions.
The installation shall also embody the recommendations made in Vietnamese
standards and shall be designed to ensure that the earthing resistance prescribed
for operation under Vietnamese standards are not exceeded 0.5 Ohm (Vietnam
Electrical Equipment Regulation 2006 (Part I))
The Bidder/Contractor shall be entirely responsible for the complete earthing
system and the connections to cover the whole Power Plant area including the
related parts of 500kV EHV Switchyard, perimeter fence and the associated
inter-connections to ensure that all Station apparatus is securely and safely
connected to the earthing system.
The Bidder/Contractor shall include facilities to isolate major sections of the
earthing grid such that the earth resistance of each section can be measured at
any time in the future
The Bidder/Contractor shall provide electrical isolation at all Site boundaries
for all metallic or conducting pipework by means of insulating flanges and the
pipes shall be wrapped in a suitable insulating material 2 meters either side of
the flange.
The Bidder/Contractor shall also ensure that any fencing connected to the
perimeter is not constructed of a metallic conducting material within 2m of the
Site fencing.
Any reference to the cross-sectional area of earthing conductors in this section
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 195 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
relates to the minimum size of conductors that will be accepted. Modifications
or improvements if called for by the Owner to ensure full compliance with this
Functional Requirement and the related stnadards shall be installed at no extra
cost.
All bonding wires shall have a yellow/green sheath
All underground in soil earthing conductors shall be bare stranded copper
conductor
All aboveground earthing conductors shall be PVC copper
The Bidder/Contractor shall also provide the necessary earthing pit to to connect
to the main earthing grid of Quang Trach II Power Plant Project in the future.
The Bidder/Contractor shall also provide the necessary earthing pit to to connect
to the main earthing grid of Quang Trach 500kV Switchyard
Earthing system for 500kV Tower of 500kV EHV Overhead Line from Quang
Trach TPP to Quang Trach 500kV Switchyard shall be provided.
Methods of installation
Main areas of the Plant shall be provided with a below grade earthing grid
consisting of bare stranded copper conductor or tinned copper-strip with minim
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 196 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
cross section 240 mm2 unless otherwise agreed by the Owner and the conductor
shall be buried at a depth of 0.6 - 0.8 metres. The mesh size shall depend on the
earth resistivity and the need to control step and touch voltages and may vary in
different parts of the Site.
To this main earthing grid, earth rods shall be bonded at intervals and at the base
of surge arrestors and lightning conductors and additional earth rods shall be
added to the system as required to reduce the earthing resistance and/or the
touch and step voltages to the required limits.
The earth rods shall consist of extensible solid copper rods, 20 mm diameter and
shall be driven to a total depth of at least 3m. The connection between the
individual sections shall be conductive throughout and this connection shall not
become loose or less effective once the electrode has been driven into the soil.
The rods shall have hardened steel tops, coupling pieces and caps to facilitate
driving by power hammer.
All earth rods shall be terminated in a junction test box . The box shall be
approximately 450mm x 300mm and 300mm deep. Each box shall have a
withdrawable concrete lid/cover. The required copper links and connecting
bolts shall be supplied with each box.
All metallic items of the Plant and structures shall also be connected and
integrated into the main earthing grid. This shall include steel reinforcing where
it is used in ground slabs for equipotential grading and arrangements shall be
made in good time for reinforcing in concrete foundations of steel columns, oil
tanks, transformers etc. to be bonded accordingly. Connections shall be by
copper strip, cable or flexible braid. The normal lapping and wiring together of
the reinforcing is considered adequate for electrical continuity provided that
each successive level of rebar is wired to the lower level at each junction.
Isolated sections of reinforcing will not be acceptable.
All steel frame and reinforcing steelwork shall be connected to this grid at
intervals of not more than 16m and at least two (2) in each case.
For large buildings which do not have a structural steel frame the
Bidder/Contractor shall design and install a system of supplementary copper
earth conductors. The supplementary earth conductors shall be copper bars or
cable which shall be bonded to the reinforcing steel at each floor and shall be
interconnected so that there are at least two (2) independent paths to the
outdoors earthing system from any piece of equipment. The size of the copper
bars and/or cable shall be subject to approval by the Owner.
Connections shall also be made to steel piping in the foundations of the Station
structures in such a way that this steelwork also functions as an earthing
electrode.
Large plant situated in buildings shall each be enclosed by an earthing conductor
(i.e.: equipotential conductor) connected to the main below grade earthing grid
at a minimum of two (2) points.
For large electrical plant and for main structures, cable or strip with the same
size as the main earthing grid conductor shall be used.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 197 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
A conductor of minimum cross-section 240mm² (unless otherwise agreed by the
Engineer) shall be buried around any structure, tank, lamp-post or similar
equipment which has not got a reinforced foundation connected to the earthing
system. This conductor shall be approximately 1 m. from the equipment and 0.6
- 0.8 metres deep. It shall be connected to the below grade earthing system at
intervals of not more than 10m.
Two (2) fully sized inter-connections shall be provided to the earthing system
of the 500kV HV Switchyard/Quang Trach II. The earthing pit shall be provided
to connect the earthing cable.
All risers from the below grade earthing system to above grade equipment shall
be duplicated with a minimum of two (2) separate fully sized connections shall
be installed to address the risk of corrosion. The connections shall be provided
to different points of the earthing grid.
Above grade earthing system.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 200 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
at two (2) points.
The housing of the operating mechanisms shall be earthed as near as possible to
the operating handle. Bolts and nuts provided for earth current carrying
connections of different cubicles shall be clearly marked.
Each LV equipment or compartment, if sheet metal enclosed, shall include
facilities for the connection of a portable earthing equipment of approved design
with flexible cables to be clamped on to the phase conductors by means of
insulated earthing poles for subsequent grounding.
Portable earthing equipment is not acceptable for MV switchgear.
Power cables
The armour or shield of power and control cables shall be earthed by connecting
a flexible braid to the shield.
Power cables shall be earthed as below.
- All cables installed within 1,000m: Earthed at one end
- All cables installed over 1,000m: Earthed at both ends
And cable end boxes shall be earthed with copper connection on one (1) of the
mounting bolts.
Motors
Motors shall be earthed via separate earthing conductor of the power cable.
Motors shall relate to the earthing grid at two (2) points.
Lightning arrestors
Lightning arrestors shall be connected to the earthing grid with minimum of
(02) earthing cable connections (unless otherwise agreed by the Engineer). The
metal structure on which the arrestor is mounted shall be separately earthed.
In addition, earthing rods shall be driven adjacent to the lightning arrestor
connection to the earthing grid to provide the lowest possible earthing resistance
of the grid at this point.
Oil and water storage tanks and piping
The function of tank earthing is to provide discharge for static electricity and
lightning protection, and therefore requires a maximum earthing resistance of
0.5 ohm typically. However, if electrical equipment (e.g. : stirrers, are mounted
on the tanks) a normal low resistance connection shall be provided
All tanks shall be earthed to local earthing electrodes and to the main below
grade earthing grid at a minimum of two (2) diagonal points.
Piping shall be earthed at all service points. Flange connections shall be
provided with links to ensure earthing continuity. The relevant rules of IEC and
VDE shall be observed.
For earthing of trucks supplying oil, provisions shall be provided at every
unloading bay for quick fixing of a flexible connection to the earthing grid.
Structural steel
All structural steels shall be connected with the below grade earthing grid at
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 201 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
several points. A single structure shall be earthed at both legs, square structures
shall be earthed at two (2) points diagonally across from each other. For a
structure consisting of several bays, each leg shall be earthed.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 202 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Steel parts for local push-button stations, control cubicles, power sockets,
lighting fixtures etc. without conductive connection to other earthed steel
structures shall also be connected to the earthing grid with specified copper
conductors.
Lamp posts
Metallic lamp posts shall be earthed via the PE conductor of the feeder cables.
The lamp posts will be earthed at two points directly to the plant earthing system
via earthing GV copper conductor. However, with independent standing light
poles that cannot be connected to the plant earthing system at 2 points, an copper
earthing loop of about 2 metres diameter shall be buried
0.6 - 0.8 meters deep around each post and connect to lamp post via opposite
two point.
Emergency Diesel Generator
The diesel generator star point shall be connected to the station earth grid. The
body of EDG shall be earthed at least two points.
Main Generator
The main generator shall have its star point earthed through a high impedance
earthing system to limit the earth fault current to approximately 30 amp. The
high impedance earthing system shall be via a short time rated distribution
transformer loaded on the LV side by a resistor.
The turbo-generator unit shall be fitted with a shaft earthing monitoring system
which shall be connected to the station earth grid via one point only which shall
have a low impedance to high frequency currents
Isolated Phase Busduct (IPB), Generator Circuit Breaker (GCB)
The Structure of IPB and Generator Circuit Breaker (GCB), Earthing switches
of GDB shall be earthed at least 02 points
Fences
All internal fences shall be bonded to the main below grade earthing grid.
Steel fences surrounding electrical equipment/areas are to be protected in
accordance with the regulations of VDE-0141/7.76.
Safety considerations
The methods detailed in IEEE 80 and IEEE 665 shall be adopted to achieve a
safe installation. Touch potentials shall be limited to give a "let-go" body current
below 9mA. Additional earth connections shall be made as necessary. Outside,
crushed rock shall be used near electrical Plant to ensure high surface resistivity.
An electrode resistance of the main earthing grid system, separate from any
other earthing grid system, shall comply with the allowable touch and step
voltage in IEEE 80 and IEEE 665 and comply with the electrical regulations,
codes and standards including Vietnamese standards.
Cable trenches, tunnels, raceways and risers
A main copper earthing conductor shall be provided for each route and to which
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 203 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
all steelwork shall be bonded..
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 204 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Pipelines
Pipelines entering the Site shall be fitted with a length of electrical insulation
over the pipe two (2) meters each side of the fence, and an insulating flange at
the boundary. This prevents dangerous potentials occurring between pipe and
earth both within and outside the Site.
Surge suppression devices or earthing cells shall be fitted across insulators.
Cathodic protection
Where pipelines are fitted with cathodic protection, motorised valves shall be
connected to the main earth grid and insulated from the pipeline with insulated
flanges. The two (2) pipeline flanges shall be bonded across the central insulated
portion.
Cathodic protection shall not be applied to the copper earthing circuits unless
unavoidable because of the build-up of electrolytic products which will tend to
insulate buried copper from ground.
If segregation of cathodic protection and copper earthing circuits is
impracticable a requirement to re-test earthing connections after a 12 month
period and install additional electrodes as necessary shall be a mandatory
requirement.
Earthing for control and instrumentation equipment
The earthing arrangements shall be divided into two (2) classes, one concerned
with personnel safety, the other with signal accuracy.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 206 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The Down conductors shall be duplicated from air-termination shall be
directly connected to main grid by copper conductor and they shall be
adequately protected from mechanical damage. They will be intended to
conduct lightning current from the air-termination system to the earth-
termination system. Test point shall be provided to check the lightning
protection system.
The distance between conductor/ lightning strip/ air terminal and the roof
shall not less than 400mm.
All ladder/handrail shall be earthed to main grid
All lightning protection systems shall be strongly interlinked with the below
grade earthing system at a minimum of two (2) points
Lightning Risk Assessment Calculation shall be submitted to Owner for
approval.
7.13 MOTORS
General
The LV motors shall be defined as the rotating electrical ones, suitable for the
operation on the 400/230V A.C rating less than 200kW, three phase, 50Hz or
D.C 220V supply. Some small motors may be defined as the rotating electrical
ones, suitable for the operation on the 400V/230 A.C, three phases, 50Hz
The MV motors shall be defined as the rotating electrical ones, suitable for the
operation on three phase, 50Hz A.C supply at voltages of 11kV or higher, rating
from 200kW and above.
Relevant standards
They include the following which relate to the manufacture and testing of
rotating electrical machines:
IEC 60034 Rotating Electrical Machines
IEC 60044 Current Transformers for Measurement and Protection
BS 4999 General Requirements for Rotating Electrical Machines
BS 5000 Specification for Rotating Electrical Machines of
Particular Types or for Particular Applications
IEC 60529 Classification of Degrees of Protection Provided by
Enclosures for Electrical Equipment
IEC 60894 Guide for a Test Procedure for the Measurements of Loss
Tangent of Coils and Bars for Machine Windings.
All motors shall fully comply with technical requirements of this specification,
IEC 60034 and BS 5000 Part 40 whether they are essential or non-essential
drives.
Duty, rating and motor clarification.
Motors shall be suitable for maximum continuous rating. IEC 60034 or NEMA,
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 207 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Duty Type S1. Motor enclosure and terminal boxes to be installed indoors and
outdoors shall have degree of protection as follows :
Indoor : IP54
Outdoor : IP56
Vacuum switchgear is used for 11kV motors and the Bidder/Contractor shall
design all 11kV motors to be equipped with surge absorber and with adequate
insulation margin between turns, for the motor design life, to cover the stress
and fatigues due to the re-striking voltages associated with the making and
breaking of currents using vacuum technology. Sample coils are to be tested to
IEC60034.15.
The AC motors shall be capable of continuous operation under the service
condition at any frequency between 47.5 and 52 Hz and rated voltage ±10%.
Unless otherwise specified, the motors shall be capable of continued operation
of 75% of the nominal voltage at 47.5 to 52 Hz for a period of 5 minutes without
injurious heating. In the event of loss of supply, all motors shall be suitable for
restarting against the full residual voltage in the motor winding during motor
run-down.
During the starting of large motors, short-term voltage excursions of up to 10%
may be experienced at the source of supply. The total allowable voltage drop at
equipment load terminals under these conditions including cable impedance volt
drop shall be limited to 15% of nominal voltage.
Unless otherwise approved A.C. motors shall be three-phase cage induction type
with a rated speed based on manufacturer's recommendation and suitable for
starting direct- on-line. If any special starting equipment is required, it shall be
provided by the Bidder/Contractor with the associated motor and
interconnecting cabling
The duty point load of the motor shall be not more than 90% of its nameplate
rating.
The frequency of starting requirement specified in Vietnamese standard and
IEC 60034 -12 shall be subject to the following conditions:
The torque requirements shall be those service conditions likely to cause the
longest starting period.
The terminal voltage shall be 85% of the rated supply voltage during the
starting.
If it is possible for a motor to be driven in the reverse direction e.g. by back flow
through the associated pump, the motor shall be suitable for starting safely when
it is running at maximum reverse speed.
Four consecutive starts from cold state up to full speed must be possible, the
second start must be possible immediately after the first, the third 20 minutes
after the second and the fourth 20 minutes after the third.
DC motors shall be suitable for operation on two-wire unearthed systems. They
shall be supplied for drives required to operate in an emergency (e.g. for
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 208 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
ensuring that main turbine-generator and steam generator auxiliary plant parts
such as bearings will not be damaged between failure of A.C. supply and the
plant coming to rest) or when otherwise specified.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 209 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
DC motors rated at less than 1.0 kW shall be suitable for starting direct-on-line.
Larger D.C. motors shall be suitable for starting with two step or three step
starters. The Bidder/Contractor shall design the motor starters, to limit motor
starting current to twice rate full load current.
DC motors shall be capable of driving the associated plant continuously under
the most onerous service conditions when the voltage at the motor terminals
varies within the limits 90% and 110% of the system rated voltage, and of
running satisfactorily for one hour under the most onerous service conditions
when the voltage at the motor terminals is 85% of the system rated voltage.
Insulation systems
Unless otherwise approved the insulation system used on all motors shall be
rated at Class F (IEC 60034-1), but the limit of temperature rise shall not exceed
that nominated in IEC 60034-1 for Class B insulation.
For 11kV motors, the Bidder/Contractor shall design the insulation system used
on all motors to cope with the stress and fatigues due to the re-striking voltages
associated with the making and breaking of currents using vacuum technology.
For MV motors the insulation system used shall be vacuum pressure
impregnation (VPI) technology. The windings and connectons are isolated with
Mica-based tape. When the windings are in place the whole stator shall be
impregnated in the vacuum pressure impregnation process.
The insulation system shall not use natural rubber insulation around motor leads.
Windings
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 210 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Corona protection details of the slot portion including coil tape details and its
application together with thickness and details of slot liners. Tapes shall
extend beyond the slot entrance.
Stress grading at slot exit, details of tape and application and extent beyond
slot.
End winding insulation, details of taping and curing method including sealing
tape.
Bracing details of the end windings including gap filler between coils, surge
ring insulation and method to eliminate mechanical stress on coils at slot
entrance/exit.
The Bidder/Contractor shall describe the method of bracing end windings. The
quality of bracing on all high voltage motors shall be suitable for re-energising
the motor on to a supply at 105% rated voltage with a minimum of 85% of
residual flux in the stator. The windings and leads shall be braced and blocked
to prevent loosening of any part of the winding. In this regard attention shall be
given in vertical motors to prevent winding migration.
All motor windings shall be brought out to terminal boxes of approved type. On
high voltage motors all six ends of the windings shall be brought out, three on
each side of the motor.
Stator
The design of medium voltage motor stator cores shall be such that periodic re-
tightening to ensure tight cores is not required. It is preferred that welded
construction, spring-loaded bolts or dished cantilever type pressure plates be
used.
On medium voltage motors core tooth supports shall be positively anchored to
the stator pressure plates by welding or mechanical interlocking, e.g.
hammerhead. Heavy section tooth supports shall not be spot-welded to
laminations. However, the practice of spot-welding light I or L section spacers
to provide vent ducts is acceptable provided the quality control methods applied
are acceptable.
On medium voltage motors there shall be positive means of locating stator cores
against circumferential or axial movement. Any locking keys, dowel pins etc.,
should be so fitted that in the event of movement the locking device does not
fall out of its location.
Rotor
Attention shall be paid to the design of cage type windings. All welded
components or assemblies shall be stress relieved and cage end rings shall be
simultaneously brazed.
The Bidder/Contractor shall describe in detail the arrangement of the cage end
rings and cage bars on high voltage motors and shall provide information giving
service experience with the design offered.
On medium voltage motors the rotor lamination clamping plates shall be
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 211 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
positively anchored to the motor spider. Heavy section tooth supports shall not
be spot-welded to end laminations.
Motor enclosure and cooling
All motors shall be totally enclosed. The degree of protection to IEC 60529
provided by the enclosure shall be IP 54 for indoor motors and IP 56 for outdoor
motors.
In all cases except special instances, the primary coolant shall be air. The
preferred secondary coolant is air but water is acceptable, subject to the approval
of the Owner, where manufacturer’s standard or the overall pump/
motor/bearings system requires water to achieve an optimum standard design.
All motors provided with filtered air cooling or heat exchangers shall have a
contact making thermometer fitted in the internal air circuit at the outlet of the
air from the air cooler. Where contact-making thermometers incorporating
mercury switches are used, they shall be mounted away from the motor housing
to prevent mal-operation due to vibration. The contacts shall be rated for alarm
initiation.
Bearings
Motor bearings shall be suitable for the application and details shall be provided
for approval.
Thermocouples shall be provided by the manufacturer for monitoring the metal
temperatures of bearings of all auxiliaries and the associated driving motors
where the motor rating is 40 kW or above for indication, computer monitoring
and/or alarm raising purposes.
All motors rated at 2000 kW and above shall be fitted with sleeve type bearings
and all vertical motors rated at 1500 kW and above shall be fitted with segmental
pad type thrust bearings on the top and sleeve guide bearings at the bottom. The
bearings on the motor and the driven device shall be of similar design.
Bearing thermocouples shall be terminated in the same terminal box as the
winding temperature detectors.
All MV motors shall have one pedestal insulated from the frame. For motors
with double shaft extension a combination of one insulated bearing and one
insulated coupled is preferred.
Anti-Condensation Heaters
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 212 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
the motor windings and insulating materials will be maintained at a temperature
not less than 6ºC above ambient temperature.
Heat shall be transferred to the windings by convection from heaters mounted
on the motor frame. Heaters fastened to the windings are not acceptable. The
surface temperature rise of the heaters shall not exceed 200ºC above ambient.
With the motor stopped and all heaters in service the temperature rise of the
insulation shall be within 10C - 30C.
The switchgear controlling the heaters will be arranged to Auto ON/OFF. A
permanent warning label shall be fitted in a prominent position on the motor
indicating that heater supply remains alive even when the main motor power
connections are disconnected
Winding temperature detectors
Motors rated 120 kW and above shall be provided with a copper constantan
thermocouple (which will be used in measuring winding temperature) in a coil
slot corresponding to each phase of the winding.
All MV motors shall be provided with six embedded temperature detectors to
provide stator winding temperature detection. These temperature detectors may
be the thermocouple or resistance type, two per phase placed between coil sides
within the slots at locations of greatest running temperature.
Connections to temperature detectors shall be terminated in a separate terminal
box.
The temperature shall be indicated on DCS for monitoring.
General construction
A separate terminal box shall be provided for the power supply cables, each
group of secondary connections (e.g. thermocouples and current transformers)
and the anti-condensation heaters. They shall be mounted and facilities provided
to enable cables to approach on the right hand side of the motor when viewed
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 213 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
from the driving end.
Terminal boxes shall be of fabricated steel construction and shall provide the
same degree of protection as that of the associated motor.
Terminal boxes which are split in more than one direction and in which the
gaskets meet to form a “T” junction will not be accepted. Cover gaskets shall
be fixed firmly to either the cover or the box.
Cable entry of terminal box shall be metric type.
Power cable terminal boxes and terminals
Power supply cable terminal boxes shall comply with the requirements of BS
4999, Part 145.
For MV motors the power cable terminal boxes shall be the pressure relief type
with the vents arranged in such a way that the force of an explosion within the
box cannot cause injury to personnel. They shall be phase segregated type to
restrict any electrical breakdown to an earth fault. They shall be so rated that
they will safely carry through faults of the levels and times expected to be
present. They shall be fitted with dryness indicators using silica-gel or other
similar material.
For motors rated more than 1000kW at 11kV, the Bidder/Contractor shall
supply and install in the neutral terminal box a three-phase set of differential
protection current transformers to IEC 61869.
The current transformers shall be toroidal in shape and installed with suitable
brackets, clamping plates, removable sections of phase connections etc. A
secondary connections terminal box containing stud connections shall be
provided on the neutral terminal box in an approved position.
Rating plates for the current transformers shall be attached to the outside of the
neutral terminal box.
Low voltage motors shall have power terminals of the stud type of minimum
diameter 8mm.
Power supply cable terminal boxes shall be provided with cable sealing glands,
cable lugs and internal supports all suitable for use with the cable to be provided.
Cable lugs shall be suitable for use with copper cable.
Terminal boxes shall be suitable for dry type terminations
Secondary Terminal Boxes and Terminals
Plant which includes brushes shall be kept to a minimum and shall be provided
only if specified.
Brushgear shall be arranged so that brushes may be changed quickly. The
tensioning gear shall be arranged so that brush pressure will not change
appreciably with brushwear. Current loading in all brushes connected in parallel
shall be effectively equal.
Screws or nuts which must be loosened in changing brushes shall be captive.
Under normal conditions of running and starting, the brushgear shall run
without sparking injurious to sliprings, commutators or brushes.
Bidder/Contractors shall describe:
What provision would be made to guard against slipring and commutator
flashover and when the plant is required to start after extended periods at
standstill.
What maintenance is necessary to prevent flashover?.
What maintenance is necessary when the motor is subjected to long periods
of running at light loads and no load.
Brushgear compartments shall be separated from the rest of the machine. Their
ventilation system shall be such that the brushgear compartment is under
positive pressure. The ventilation system shall be arranged to remove carbon
dust and so prevent the dust being deposited on insulation surfaces, and shall be
provided with inlet filters to prevent pollution of cooling air. The air inlet and
discharge shall be arranged to prevent the ingress of water into the enclosure.
Such separate compartments shall be provided with their own anti-condensation
heaters
Name plate
Each motor shall have a permanent stainless steel nameplate. The information
shall include the number of phases, type of enclosure, output, kind of rating
(continuous, etc), angular speed in RPM, frequency, voltage, power factor, full
load current, serial number, model, insulation class and manufacturer’s name.
The Manufacturer Nameplate shall be also applied for all electrical equipment
such as: Generators, Switchgears, IPBs, Transformers, etc.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 210 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
7.13.18 Motor Starting Current
The direct starting current ratio at Locked rotor status, rated voltage and rated
frequency shall never exceed the following values including tolerance.
Rated voltage Starting current Remarks
11kV 500% of In Boiler Feed Pump
System only
600% of In
400V or below 700% of In 20kW and above
800% of In Below 20kW
DC Motor 200% of In Based on 7.10.1.1 – (4)
(In = Motor rated current at full load)
General
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 210 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Bidder/Contractor shall design and provide one 400/230V electric system to
service the distribution of power to anti-condensation heaters at site.
Bidder/Contractor shall design and provide one lighting system for site to enable
the identification and safe operation of plant and equipment and movement of
personnel.
The lighting system will supply the illumination for office, control room,
electrical equipment, indoor/outdoor area, road, etc. of power plant.
The normal power will be supplied from 400/230VAC system.
The emergency lighting, EXIT lighting shall be supplied from DC (battery) or
UPS to ensure the illumination for the safe passage of personnel and for the
plant to be operated safely in the event of loss of normal AC source. This system
shall be so designed as a maintained system supplied normally from AC source
and switching over to UPS system when disconnecting to the normal source.
The small power, maintenance box shall be provided to supply the power for
small load, mobile equipment and maintenance through the single phase and
three phase power socket.
Lighting in hazardous areas shall be designed to service special usage purposes.
Light fittings and installations in hazardous areas shall comply with relevant
Vietnamese and international standards. Any area that contains combustible
or/and hazardous materials shall be considered as “hazardous area” such as:
Coal handling area such as pulverizer and bunker floor.
Hydrogen generation house area.
Chemical area.
Chemical laboratory.
Fuel oil storage area
Battery room
Etc.
Air craft lights shall comply with Vietnamese standards and relevant
international standards issued by the International Civil Aviation Organization.
The power supplies for the stack lighting shall be dual supplies to be taken from
the 230Vac UPS system to ensure a continued operation in all system conditions)
Power and light circuits shall be spread over the three phases to minimise phase
current unbalance at the main switchboard.
The lighting and small power system will generally comprise as below: Normal
AC Lighting System, Emergency AC Lighting System, emergency DC lighting
system
PVC insulated wires of 450/750 V voltage grade shall be used for building
lighting (CCB, water treatment control building, ESP&FGD control building,
coal handling control building, …).
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 211 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
XLPE cables of 0.6/1 kV voltage grade shall be used for outdoor lighting
(turbine, boiler, steel structure of ESP, FGD, coal yard, transfer tower, belt
conveyor, ware house, work shop,..).
In case of failure of normal A.C. Supply, Emergency A.C. lighting and exit signs
shall be provided in all power plant such as buildings, boiler, turbine, coal
handling system, ESP, FGD, … etc for general visibility, safe movements and
operation of important auxiliaries.
EXIT lighting fixture shall be installed at the door/location where easy to escape
in case emergency condition. The emergency evacuation light or direction light
shall be installed at the cable gallery, corridor, conveyor,… where required to
evacuate to the EXIT way.
Lighting in hazardous areas shall be specifically designed for use in the Class,
Zone and Division of those areas. Lighting at hazardous areas shall be according
to the relevant International and Vietnamese standards for hazardous areas.
General requirements on lighting
Bidder/Contractor shall design and install one lighting system for the CCR of
the plant with the following features:
Minimum glare to fit with the screen based control equipment.
In combination with local lighting.
Minimizing the light reflection.
Lighting directly on to the control tables and panels.
Light dimmers shall be provided for all lights.
The following lighting types shall be used:
Tubular fluorescent lamps.
Mercury vapour lamps.
High pressure sodium lamps.
Light fittings for hazardous areas
Aircraft warning lighting
The light fittings of each type of lighting shall be of the same make and type
through out the entire site to achieve uniformity and minimize the number of
spare parts.
The LED light shall be priority using.
(1) For offices, meal rooms, locker rooms and W.C., tubular fluorescent lamps shall
be installed on the floor with light control louvre panels. Wall mounted switches
shall be provided at entrance/exit of offices, conference rooms and others.
(2) All lighting system shall be designed to fit with the operation in tropical
environment with the appropriate protection level of IP against the ingress of
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 212 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
insects, moisture and rainwater.
(3) All luminaires shall be positioned to allow reasonable access for lamp changing
and it shall be possible to change lamps with the assistance of a two metre step
ladder. Fittings in the ground level areas may be mounted at heights not in
excess of seven metres above floor level. Luminaries support brackets and
support columns shall be hot dipped galvanized after fabrication and shall be
designed to give adequate support for the luminaries.
(4) For turbine house, Workshop Areas and large open spaces, high pressure
sodium lamps shall be used with some fluorescent fittings to allow for discharge
lamps to run up.
(5) For areas where access is limited by plant and piping or where exposed to the
weather, mercury vapour reflector fittings in conjunction with fluorescent fitting
shall be used and mounted on columns
(6) Where using high pressure mercury vapour fittings are used they shall be
installed at the minimum height above the access way or working areas:
Capacity Height
(8) Lighting control equipment shall be located externally to the light fittings where
possible to reduce the generated heat and to provide better sealing against
insects.
(9) The installation of wiring and cable conduit shall be suitable with tropical
environment and shall provide the protection against the destroy of vermin.
(10) Strong lighting shall be provided in places where work is required to be carried
out regularly in locations outside the buildings. Lighting level shall be selected
based on functions.
Lighting level table:
Normal lighting Emergency
(Lux) lighting
(Lux)
CCR 500 50
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 213 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Office 400 50
WC 300 10
Meal room 200 10
Laboratory 600 10
Workshop 320 10
Locker room 100 10
Switchrooms (electrical) 350 10
Cable floor 240 10
Turbine house
Main turbine house lighting 300 10
Walkway 100 10
Boiler house 160 10
Coal Plant Operational areas (ship 200 10
unloader, stacker, reclaimer, transfer
tower,)
Indoor plant building 160 10
Coal storage 150 10
Tunnels (if required) 50 10
Access and stairs 100 10
Outdoor storage tanks 20 10
External Plant Building,Control panel 160 10
Street Lighting Security 50 10
Telephone booths 320 10
Transformer yard 160 20
The lighting level of other areas shall be selected in accordance with the related
standards.
Lighting levels shall be achieved at a height of 1 meter from the floor.
Bidder/Contractor shall carry out the inspection of different locations selected
by the Owner during the construction phase and the last time when the unit be
put into operation.
Lighting in the power house area shall be switched at switchboard by circuit
breakers. Lighting shall be designed so that the lighting levels shall be gradually
increased when the breakers are closed.
Additionally, all local push button stations, control stations and panels,
instrument racks, hand-operated equipment like valves etc, shall if required due
to the low surrounding illumination levels, be lit separately by means of suitable
fluorescent lamps, mounted on poles or at adjacent structures, to obtain at least
200 lux illumination level
Illuminated Exit Signs and emergency lightings
The illuminated exit signs and emergency lighting shall include maintained self-
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 214 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
contained units and shall be designed and installed compliantly with relevant
IEC standards (with battery and charger included or connection to UPS or DC)
All floors of platforms, stairways, doors of the power house area shall be
classified as “requiring for exits” and “EXIT” signs shall be required to be
installed.
Each emergency lighting shall have two tubular florescent lamps. The
emergency lighting shall be connected to 230V busbar of the UPS system and
in case this source in trouble, one tubular florescent lamp shall be maintained
by internal battery.
All emergency lighting shall have the following features:
Fittings shall be supplied with switch devive terminal blocks.
Fittings shall be supplied with about 20,000 hours life time lamps.
Fittings shall be implemented at safe height.
Fittings shall be power factor corrected to 0.9 p.f.
Fittings shall be supplied with electronic starters
Fittings shall be provided with internal associated battery charger. The
battery shall be housed in a separate enclosure.
Illuminated exit sign shall comprise battery in separate enclosure.
All illuminated exit signs shall be fitted with switch devive terminal blocks.
Emergency light, EXIT Light, emergency evacuation light or direction ligh
shall maintained at least two hours
Small power and maintenance box (Single and Three phase supply)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 215 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Power plug and power socket shall be fitted.
Maintenance box, power socket shall be designed to fit with the operation in
tropical environment with the protection level shall be at least IP56 against the
ingress of insects, moisture and rainwater
The appropriate locations of maintenance box shall be at least as follows:
Every floor of Turbine
Every boiler feed pump
Generator step-up transformer compartment
Every Unit Auxiliary Transformer
Every floor of Boiler
Every air heaters.
Coal conveyor
Coal storage
ESP area
FGD area
Ash area
Diesel area
BOP
CW pump station
Warehouse/Workshop
Fuel Oil area
Other required location shall ensure the power for maintenance will nominate
by Owner
Other requirements.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 216 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Distribution board
Distribution board for lighting and power circuit using front wiring circuit
breakers shall be provided.
The distribution boards shall comply with the requirements of wiring
regulations and shall be designed to fit with the operation in tropical
environment with the appropriate protection level of IP56 and against the
ingress of insects, moisture and rainwater
Incoming supply module shall be segregated from the outgoing blocks and
the distribution busbars shall be insulated or shrouded to prevent accidental
contact with live bars.
Separate outgoing blocks shall be provided for lighting, power and
emergency lighting.
Separate grouping of circuit breakers shall be provided for lighting, power
supply and emergency lighting. Each busbar shall be protected by
MCCB/MCB.
Distribution boards shall be suitable for bottom cable entry.
Main insulators shall be centrally placed above its group of sub-circuits.
Provision shall be made at each circuit breaker to enable attachment of an
isolation tag when the circuit is isolated for maintenance.
In addition, circuit requirements for lighting and power detailed in this
section each distribution board shall have 25% of total number of poles
allocate as spares
The Load of Distribution shall be assigned to ensure the balance load for
three phase.
7.15 CATHODIC PROTECTION SYSTEM
Each fully automatic control cathodic protection system shall consist of the
following:
Anodes, control electrodes, reference testing points with necessary racks and
insulation flanges;
Control cubicle, rectifying transformer, control devices, instrumentation and
alarm;
Connection cable between control cubicle, rectifying transformer and
anodes, control electrodes, reference points and fixed reference electrodes;
Auxiliary anodes with junction boxes, testing piers and interconnection cable
at suitable positions;
Mobile testing equipment/facilities including a measured device with
independent power and high impedance amperemeter and voltmeter.
Design criteria
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 218 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
adequate number of test points on underground structures shall be provided as
part of the works to facilitate conducting of field measurements after the
installation of the underground structures and piping.
All underground piping and structures shall be bonded to the station earth grid
to eliminate the possibility of hazardous potential during electrical system faults
or lightning. Where isolating joints are incorporated in the cathodic protection
design then discharge gaps shall be installed on the isolation sections.
All cathodic protection system shall be inspected, tested and commissioned at
site under the Owner’s witness.
Protection voltage
Each system shall ensure the protection voltage ranging from -0.85V to -1.5V
for Cu /CuSO4 battery for all structures and protected carbon steel equipment.
Designed lifetime
The selection of either the impressed current or galvanic anode system shall be
based on the current requirements and soil resistivity and accessibility of
components for maintenance.
Current requirements for cathodic protection shall be designed with an adequate
design margin such that adequate current distribution can be achieved with
small changes in parameters.
Galvanic Anodes
Galvanic anodes shall only be provided if the following parameters are satisfied
by calculation.
Soil resistivity is low.
Type of anode is capable of continuously supplying the maximum current
demand.
Because of the variation of performance over time special backfills (aimed at
providing a lower anode resistance to remote earth than the original soil) shall
be used.
For the calculation of anode resistance to remote earth reference to Clause 4.2.2
of CP 1021:1973 shall be consulted.
Sacrificial anodes shall be clearly marked with the type of material (trade name)
the anode mass.
Impressed Current Systems
Impressed current systems shall be fed from automatic potential control three
phase rectifiers/transformer sets. The output voltage shall be adjustable from
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 219 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
zero to maximum rated output. Instrumentation of voltage and current shall be
provided. Two 100% duty rectifier units shall be provided. The automatic
potential control shall be provided making use of suitable permanent reference
electrodes carried close to the structure being protected. Because of the risk of
an explosion due to hydrogen evolution, the potential shall be continuously
monitored and suitably alarmed. Ground beds shall be designed that satisfy the
following:
Its mass and quality are sufficient to last for the design life of the system.
Variation of soil conditions over the design life of the system.
The resistance of the ground bed allows for the predicted current demand to
be met under all soil conditions.
Remote from the structure being protected to provide uniform current
distribution.
The top of the anode bed shall be at least 1 metre below ground level.
Calculations shall be provided to provide the basis of the chosen resistance to
remote earth of the ground bed.
Individual anode currents shall be monitored to determine their performance
and contribution to the entire bed.
Anodes provided shall have materials nominated, its trade identification, and
mass.
Anode materials shall be selected from the following:
graphite
high silicon iron/chromium alloy
magnetite
metal oxide plated metal
platinised titanium/miobium.
The selection of the anode material shall be based on current requirements,
corrosion of anode by the soil and economic considerations.
Attention shall be given to the integrity of the insulation of interconnecting
cables to ensure that they do not themselves corrode.
Voltage reference points
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 221 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Underground pipework auxiliary cathodic protection system
General
All components of underground pipework or other iron structures shall be
provided with external cathodic protection via an independent system.
The total surface area of underground components is relatively small and one
cathodic protection system using magnesium anodes shall be provided.
However, if required by soil characteristics or systematic geology, one forced
current cathodic protection system need to be provided to achieve the protection
grades as specified.
Description
A complete set of cathodic protection system shall consist of the followings:
Anodes for underground parts, junction box/testing piers, interconnection cable,
continuous circuit and contact conjunction, necessary flanges or other insulation
sets, mobile testing equipment/facilities including high impedance voltmeter
/amperermeter and battery.
Designed cathodic current
For coated underground steel structures, the design of the system shall base on
the cathodic current of 1mA/m2 for all protected surface area.
For non-coating underground steel structures or being temporarily coated, the
design of the system shall base on the cathodic current of 30mA/m2 for all
protected surface area.
Designed protection potential
The system shall provide protection to all underground carbon steel pipework
or other structures at protection potential ranging from -0.85V to -1.5V for
Cu/CuSO4 battery.
Design lifetime
The cathodic protection system shall be so designed with the minimum lifetime
of 30 years at continuous operation condition at specific designed cathodic
current density and at site environmental condition.
Anodes
Anodes shall be of magnesium alloy and be covered by gypsum/white
clay/Na2SO4. Terminal between anodes and cable shall be implemented in
suitable hole which coated by epoxy cover as approved. Accessories shall be so
designed to avoid interference from iron sheath of metal electrode cable. These
cables shall be suitably insulated with clamps covered by polyethylene and PVC
outer sheath.
Quick fix on cable/piping shall be carried out by thermal welding method or
equivalent. On the completion, piping coating shall be recovered as before and
cable terminal shall be covered and coated by mixtures which compatible with
piping coating.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 222 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Junction box and testing piers
Terminal between anodes and piping shall be carried out by coordinating
junction box/testing pier which is totally impermeable testing piers and be
protected against weather condition.
Terminal and unity terminal shall be provided on testing piers to facilitate the
measurement of anode current and pipe potential by specific portable
measurement equipment.
Additional testing piers shall be provided at important points and others in the
system that contact conjunction, closed circuit conjunction or insulation sets
shall be installed.
Portable testing equipment
Two Cu/CuSO4 batteries with interconnection cables, together with specified
testing piers shall be provided.
High impedance mobile digital voltmeter/amperemeter shall be so designed to
use batteries as specified to facilitate the measurement of pipe protection
potential and outfeeder of anode current via specific testing piers
7.16 TEST AND INSPECTION
General
Unless otherwise specified all tests listed in the relevant Standard shall be
carried out together with any additional tests required by the Specification.
Despite anything to the contrary contained in the Standard, all Type Test,
Special Test, Routine Tests, Sampling tests and other tests shall be carried out.
Subject to the Owner agreement, type test certificates which are adjudged
satisfactory may be accepted in lieu of repeating type tests.
All instruments to be used, in connection with these tests shall be calibrated
before tests. The Bidder/Contractor is requested to provide the calibration
certificates for each instrument used during these tests.
The Electrical equipment shall be tested and certificated in accordance with all
the relevant provisions of the IEC standard and Vietnam's code and standards
listed in this Section. The test items, acceptance values/criteria and Standard
shall be shown clearly on the Test Reports.
The test and commissioning for electrical shall also complied with regulations:
Decision No 25/QĐ-ĐTĐL dated 26th March 2019 issued by Electricity
Regulatory Authority of Vietnam (ERAV) regarding Testing procedure and
Testing supervision.
Decision No 1361/QĐ-EVN dated 07th November 2018 regarding the Test
and Commissioning Procedure for Surge Arrester/ Lightning Arrester,
Decision No 1362/QĐ-EVN dated 07th November 2018 regarding the Test
and Commissioning Procedure for AC Circuit Breaker
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 223 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Decision No 1363/QĐ-EVN dated 07th November 2018 regarding the Test
and Commissioning Procedure for Earthing system
All Type Test, Special Test, Routine Tests, Site Test, Sampling tests reports
shall be submitted to Owner.
Contractor shall be responsible to inform, submit the report of the root cause
analysis and remedial actions/ countermeasures for any
troubles/fails/damages/incident/defect work of electrical equipment to Owner
during the installation, testing and commissioning for information within 01
week after the trouble/incident occurred
Generator
The generator shall be subjected to tests are required to prove compliance with
specified requirements including IEC60034 to prove that it has been
manufactured correctly and for the determination of characteristics
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 224 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The generator shall be subjected to tests are required to prove compliance with
specified requirements including IEC60034 to prove that it has been
manufactured correctly and for the determination of characteristics.
(d) DC Winding Resistance measurement for Stator and Rotor windings
(e) High Voltage Tests (Power frequency withstand voltage test) for Stator and
Rotor windings
All parts of the generator shall be subjected to a high voltage test in accordance
with the requirements of IEC 60034.
(f) DC High voltage and leakage current test
(g) Temperature Rise
Tests shall be carried out to prove that the temperature rise of the various parts
of the generator is within the limits required by IEC 60034.
Temperature rise tests shall be carried out also at site in accordance with the
Requirements of Performance test to prove the guarantee of performance.
(h) Insulation Tests for Stator and Rotor windings
The Insulation Resistance (IR) of the stator and rotor windings shall be
measured with the windings cold and at the completion of the temperature
rise tests.
The Polarization Index (PI) of each stator phase winding and of the whole
winding shall be measured with the windings cold and hot.
Repetitive surge tests shall be carried out on the rotor winding to confirm the
integrity of interturn insulation.
The insulation of stator bars and coils shall be tested in accordance with IEC
60894.
Each phase of the stator windings shall be tested to determine its capacitance
(in nanofarads) to earth and dielectric loss angle (in milliradians) in 0.2 Un
steps from zero to rated phase-phase voltage, both raising voltage and
lowering voltage. Each test will involve energizing one phase winding with
the other phase windings earthed.
The same tests shall also be carried out with the three phase windings connected
to measure combined valves.
The report of test results shall include a description of the testing technique used,
the plant conditions (including gas and water coolant arrangements and
temperatures) and the test equipment used.
The Bidder/Contractor shall submit the proposed test procedure.
Each phase of the stator windings shall be tested to determine the levels of
Partial Discharge (PD) (in picocoulombs) of insulation in 0.2 Un steps from
zero to rated phase-phase voltage both raising and lowering voltage. Each
test will involve energizing one phase winding with the other phase windings
earthed.
The report of test results shall include a description of the testing technique
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 225 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
used, the plant conditions (including gas and water coolant arrangements and
temperatures) and the test equipment used.
The Bidder/Contractor shall submit the proposed test procedure
(i) Tests to Determine Generator Parameters
The Bidder/Contractor shall determine the following parameters for each
generator. The Bidder/Contractor shall nominate the tests to be performed to
determine the parameters with reference to IEC 60034 standard. Where a
nominated test is not in accordance with IEC 60034 standard, the
Bidder/Contractor shall justify its use.
The Bidder shall nominate expected values of the generator parameters
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 226 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 228 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(h) Shaft Current/Shaft voltage
Tests shall be carried out with the generator at rated speed and excited to rated
voltage on open circuit to prove that circulating shaft currents are prevented by
the bearing insulation and shaft earthing provided.
(i) Total Harmonic Distortion (THD) measurement
(j) Short circuit and open circuit test
(k) Generator online partial discharge monitoring test
(l) Generator capacity curve/ Generator Operation Zone test
Contractor shall submit the procedure and test for Generator capacity curve/
Generator Operation Zone to verify the actual maximum operation zone of
Generator under leading phase and lagging phase conditions. The Active and
Reactive Power shall be tested corresponding to 0.85 Lagging/0.9 Leading
power factor to show the expected generator MW/MVAR operating limits at
rated hydrogen pressure, rated Power. P/Q limiter is used to prevent the
generator from entering the unsteady operation area. The limit curve of
Generator Operation Zone shall be tested such that five reactive power values
are corresponding to five active power levels respectively (i.e. P=0%, P=25%,
P=50%, P=75%, P=100%).
(m) Sub-Synchronous Resonance protection
Contractor shall to provide the solution of protection relay, supplementary SSR)
to ensure the safety and stability operation of Quang Trach I TPP as well as
Power excitation damping control, Blocking Filter…) for Sub-synchronous
Resonance (Grid. Contractor shall submit all detailed calculation sheet, setting
sheet, technical solution, test to prevent the SSR phenomenon that could
possibly arise.
Testing of measurement of inertial constant of rotating mass (consists of turbine,
rotor of generator
(n) Testing for reactances and time constants of generator, including direct axis and
quadrature axis synchronous reactance (Xd, Xq), direct axis and quadrature axis
transient reactance(X’d, X’q), direct axis and quadrature axis subtransient
reactance (X’’d, X’’q), stator leakage reactance (X1),open circuit direct axis
transient time constant (T’d0), open circuit quadrature axis transient time
constant (T’q0), open circuit direct axis and quadrature axis subtransient time
constant (T’’d0, T’’q0)
(o) Etc.
Excitation system
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 229 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
standard.
With reference to the temperature rise test, the temperature rise must remain
within limits for a duty cycle no less than that specified in this Request for
Proposal Document.
(b) Excitation Transformer
The Bidder/Contractor shall carry out temperature rise tests at the works, using
a higher than rated current to prove that in-service rated temperature rises will
not be exceeded. The test current shall consider the extra losses due to
harmonics and shall be determined by reference to ANSI/IEEE C57.110.
(c) Complete Excitation System
The tests listed in the following sub-clauses, except for sub-clauses (a) and (b),
shall be carried out on both excitation systems. The tests listed din sub-clauses
(a) and (b) need only be carried out on the first manufactured system.
A Transfer Function Test shall be carried out on the excitation system for the
determination of all time constants, gains, input/output limits and frequency
response curves. The block diagram Drawing T-showing the transfer
functions of the excitation system shall be amended from the results of these
test and included in the test report.
An Excitation System Nominal Response Test shall be carried out to
determine the excitation system nominal response VE. The voltage error step
to be used in the test is 10% of rated voltage. Where the test is not in
accordance with IEC 60034-6-1standard, the Bidder/Contractor shall justify
its use.
Checks shall be carried out on the operational features of the automatic
excitation regulator; including automatic changeover from one controller to
another; and to manual operation of limiters; follow-up controls and alarms.
All other tests as necessary shall be carried out to prove compliance of the
excitation system with the specified requirements
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 230 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
arrange for variations in system voltage to permit reasonable reactive load
changes to be made on the generator. The Bidder/Contractor will make electrical
measurements to confirm the degree of compensation.
(e) The control system for coordinating reactive power loading generators shall be
proved to be able to carry out its function by in-service test. The Owner will
arrange for variations in reactive power demand on the generators for this test.
(f) With the generator on open circuit and under AVR control, changeover of the
AVR from one control function to another (i.e. auto-auto, auto-manual) shall be
proven for each fault condition.
(g) Excitation Transformer test (Excitation Transformer, Current Transformer)
(h) Plant Power System Stabilizer (PSS) function test
(i) Over-Excitation Limit (OEL) test
(j) Under-Excitation Limit (UEL) test
(k) All necessary tests shall be carried out to check the excitation system transfer
function block diagram
(l) The other test following Decision No 25/QĐ-ĐTĐL dated 26th March 2019
issued by Electricity Regulatory Authority of Vietnam (ERAV) regarding
Testing procedure and Testing supervision.
(m) Conditions and Excitation tests:
This test shall be carried out under condition that excitation system is set up at
Automatic Voltage Regulator (AVR) mode. Measurement signals include
Generator voltage, Active Power, Reactive Power, Excitation voltage,
Excitation current, output signal of AVR and output signal of PSS. List of tests:
Load Rejection test for Reactive Power
Test condition: Generator is operating with minimum Active power, under
excitation (Leading power factor -receiving Reactive power).
Test procedure: Carry out to open the Circuit Breaker (GCB). Measure the
Generator voltage and current, Excitation voltage and current,...
Test on Step Response when Generator is not connected to grid.
Test condition: Generator is operating in No-Load with GCB is opened
Test procedure: Suddenly change the reference voltage (at least 5% of Generator
terminal voltage) of AVR and hold for at least 10 second in case of increasing
and decreasing reference voltage.
Test on Step Response when Generator is connected to grid.
Test condition: Generator is operating with GCB is closing and generating Active
power in range 80~100% of rated Active power.
Test procedure: Suddenly change the reference voltage (at least 2% of Generator
terminal voltage) of AVR and hold for at least 10 second in case of increasing
and decreasing reference voltage. Carried out the test in two (02) cases: with
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 231 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
PSS put in service and without PSS put in service corresponding to two (02)
generating levels of Reactive power ( at least 40% difference of Reactive power)
Impulse test
Test condition: Generator is operating with GCB is closing and generating Active
power in range 80~100% of rated Active power.
Test procedure: Suddenly change the reference voltage (5% and 10% of
Generator terminal voltage) of AVR and hold for at least 100 milisecondes in
case of increasing and decreasing reference voltage. Carried out the test in two
(02) cases: with PSS put in service and without PSS put in service corresponding
to two (02) generating levels of Reactive power ( at least 40% difference of
Reactive power)
Gain Margin test of PSS
Test condition: Generator is operating with GCB is closing and generating Active
power in range 80~100% of rated Active power. PSS put in service.
Test procedure: Increase the stabilizer gain factor Ks of PSS until we observe the
fluctuation of the excitation voltage and current, generator voltage, active power,
reactive power.
For each value of Ks, the time will be hold at least 1 minute to measure the Gain
Margin of PSS.
Test on Frequency Response when Generator is not connected to grid.
Test condition: Generator is operating with GCB is opened. Carry out the test
with and without response signal of generator terminal voltage to AVR of
excitation system.
Test procedure: Put the frequency signals from 0.05Hz ~ 10Hz into AVR of
excitation system (maximum frequency step is 0.05Hz). Measure amplification
and phase angle deviation characteristic between generator voltage and reference
voltage of excitation.
Requirements for test/measurement equipment
Test equipment for excitation system test: recording equipment shall be had the
recording capacity at least 100 samples/second.
Digital recording.
(n) Requirements for frequency of test record for excitation and governor control
system
For excitation system tests:
Display results for wave record have to / must have at least resolution is
100 samples/second.
Results have to be showed by two (2) formats: hard-copy and soft-copy
(excel format or equivalent).
For governor system tests:
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 232 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Display results for wave record have to / must have at least resolution is
10 samples/second.
Results have to be showed by two (2) formats: hard-copy and soft-copy
(excel format or equivalent).500kV EHV Overhead line
The tests shall be conducted in accordance with IEC, Viet Nam Regulation.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 233 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Grease type test
Creep test
(b) Overhead Grounding wire
The inspection and testing shall be carried out on individual wires and stranded
conductors in conformity with IEC 61089
The test specimens shall be taken from 2% of the reels for conductors and from
at least two reels. The test specimens of component wire before stranding shall
be taken from 10% length so that the following tests can be carried out:
a.1 Hard Drawn Aluminum-Clad Steel wire
Appearance test
Diameter
Tensile test
Torsion test
Elongation test
b.1 Concentric Lay Stranded Aluminum-Clad Steel Conductor
Appearance test
Construction test
Weight
Tensile strength
For each test the contractor shall bear the travel expenses for the EMPLOYER
or his Representative. Related costs shall be contained in material prices.
For the earthwire, the Bidder shall provide certified test reports with the Bid for:
A stress-strain test
A breaking strength test
Test to demonstrate that jointing of individual steel wires meets the
requirements of IEC 61089.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 234 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Power Transformers
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 235 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Oil overpressure test (pressure defection test) on transformer to check against
leakages past joints and gaskets
On Load Tap Changer test
Frequency Response Analysis test
Bushing Current Transformer Test
Bushing test
Measurement of the power taken by the fans and oil pumps (Auxiliary losses)
Tests on bought out components/accessories such as Buchhloz relay,
temperature indicators, pressure relief devices, oil preservation system etc
On completion of the component parts, the transformer shall be completely
erected at the Contractor’s works to permit a final inspection to be made of the
mechanical and electrical assembly and for overall testing.
For all tests during which a transformer is excited either at normal or higher
frequency all thermal and gas sensing devices shall be connected so that any
abnormality may be detected.
Dissolved gas analysis of oil shall be carried out prior to and after the power
frequency test, induced, partial discharge and the temperature rise test
Partial discharge tests shall be performed in turn upon each H.V. terminal. The
method of partial discharge measurement shall be one of the internationally
accepted methods employed to determine individual impulse magnitudes in PC
(apparent discharges as measured at the terminals), in accordance with the
relevant IEC recommendations.
The following partial discharge measurement shall be recorded during voltage
rising:
partial discharge level at 120% of rated voltage;
partial discharge level at 150% of rated voltage;
at minimum induced over voltage;
partial discharge level upon returning to 150% of rated voltage;
partial discharge level upon returning to 120% of rated voltage.
The test duration for recording the partial discharge measurements shall be
half (1/2) an hour for each measurement level.
The transformer will have failed the partial discharge test if the levels recorded
appreciably exceed:
60 pC at 120% of rated voltage;
300 pC at 150% of rated voltage
Other test (if any)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 237 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
The Bidder/Contractor shall state what testing facilities he has at the works to
carry out:
Electrical tests.
Mechanical tests to prove the strength, hardness and other physical qualities
of the materials employed in construction.
The Bidder/Contractor shall submit certified results of any design tests called
for in this Specification to which the works or any component parts thereof have
been subjected. the Owner/Engineer may accept any or all these tests in lieu of
those specified herein.
(b) Manufacturer
The Bidder/Contractor shall include in the proposal documents details of all
components which he proposes to have made by Manufacturer to the main
circuit breaker supplier and the names of such Manufacturer the place of
manufacture so that if required arrangements may be made for the necessary
inspection and testing of such components at the works of the Manufacturer.
(c) Complete Circuit Breakers - Design Tests
Design tests in accordance with IEEE Standard C37.013 shall be carried out.
The Bidder/Contractor shall submit certified results for the design test to the
Owner/Engineer. The certified results shall conform to the guarantees stated in
the Contract.
If the design tests have already been carried out the Owner/Engineer may accept
certificates in lieu of repeating those tests.
(d) Complete Circuit Breakers - Production Tests
Production tests shall be made on every circuit breaker in accordance with IEEE
Std C37.013, subject to the following additions. The test values and results shall
conform to the guarantees stated in the Contract. Prior to shipping adequate
production tests should have been performed to ensure that every component of
every circuit breaker has been correctly assembled and is functioning correctly.
In addition to the production tests the following shall be carried out:
An Ohmic resistance test on each trip and closing coil, and
A timing test on the auxiliary contacts to demonstrate correct operation and
relationship with the main contacts.
Insulation Resistance measurement
Leakage test with SF6 gas
Pressure test with SF6 gas
Contact resistance test
Resistance of coil
Power frequency withstand voltage test for main circuit and control circuit
Mechanical and Operation test
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 238 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Charging time for closing spring test
Auxiliary equipment test (fan, motor,..)
Voltage and Current Transformer test
Surge Arrester test
Capacitor test
Interlock test
Visual check (Name-plate, dimension,..)
Etc.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 239 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(e) Aluminum Welding Tests
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 240 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(f) Current and Voltage Transformer test
(g) Protection relay function test
(h) Control and Sequence Operation function test
These tests will include, but not limited to the following:
Open circuit test and automatic voltage regulator test.
Synchronizing and loading for three repeat tests.
Time duration from start to no-load, synchronization and full load
Remote starting
Local starting
Auto mode
Manual mode
Rotation test
Transfer test
Load test
Operation performance test
Etc.
Protection and metering system
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 241 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Protection systems shall then be subject to primary and secondary current
injection tests covering full calibration and placement in service.
Wiring check
Insulation resistance measurement
Operation check of the relay
Setting value check
Function check
Overall Interlock and Inter Trip Test
Fault Monitoring check
Secondary and Primary Injection test
Etc.
The calculation and setting value of protection relay for Generator, Generator
Step Up Transformer, Unit Auxiliary Transformer, 500kV OverHead Line shall
be accepted by National Load Dispatching Center (NLDC or A0).
AC system (11kV switchgears and 400/230V Switchboards)
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 242 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(2) Inspection and Test at Site
Following site assembly in final positions and the completion of connections,
testing shall include at least the following:
Point to point wiring checks.
Switch operational checks.
Mechanical racking interlock checks.
Primary circuit connections and phasing checks including power cabling.
Protection primary and secondary injection tests, operation, calibration and
interface checks.
Plant system functional checks including control, indication, alarms etc.
interface.
Power frequency HV tests for main and auxiliary circuit
Mechanical and Electrical interlock tests
Insulation resistance measurement.
Contact Resistance test
Protection relay test
(Voltage Transformer/ Current Transformer/Surge Arrester) Test
Auxiliary circuit test
Ect.
DC and UPS system
The tests shall be conducted in accordance with IEC 62040-3, 62046-1, IEC
60255-5
DC plant components shall be type, sample and routine tested in accordance
with the provisions of the relevant standards. In addition a discharge test to the
agreed Duty Cycle shall be carried out on each installed battery bank.
In addition to controlling and monitoring overall discharge current and voltage,
individual cell voltage shall be logged so that defective cells (if any) can be
identified. The metering accuracy shall be such that the overall battery bank
capacity can be declared to an accuracy of 0.5%.
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 244 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Material component/content test
Conductor resistance measurement
Cable diameter measurement
Insulation resistance measurement
Measurement of insulation, layer thickness, overall diameter.
Hot set test
High voltage test
Partial Discharge Test for MV cable and above
Water penetration test
Fire retardant test
Color marking check
Screen/ armour check
Cable support check ( Material test for cable support, Thickness of coating,
welding line, diameter of conduit, )
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 246 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Winding Resistance test
High Voltage test
Temperature rise test
Rotation check/ Phase sequence check
Thermal coupler/Temperature detector/ heater check
Lock rotor test
Vibration test
Overspeed test
Overload (Overcurrent) test
Shaft Voltage
Painting Insspection
In addition to the tests specified above, for low voltage motors, the following
tests shall be done for diagnostic information.
Insulation resistance and Absorption Ratio
No Load test
Winding Resistance test
Rotation check
Thermal coupler/Temperature detector/ heater check (if any)
Lock rotor test
Vibration test
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 248 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Protection Potential measurement
Protection Current measurement
Etc.
Current Transformer/ Voltage Transformer
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 249 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(1) Inspection and Test at Workshop
Material Verification
Dimension & Visual, Wiring
Insulation Resistance Test
Withstand Voltage Test
Leakage current test
Counter check
The Performance test for Auxiliary Power Consumption Load shall be complied
with Decision No. 52/QĐ-ĐTĐL dated on 04 August 2015 regarding the
procedure for measurement of Generator Characteristic of Coal Thermal Power
Plant in the Vietnam Competitive Generation Market.
The auxiliary power system shall be measured for unit and station load (11kV,
400/230V) that are being supplied from the Unit Auxiliary Transformer
(machine voltage to 11 kV). The total unit auxiliary kW load shall be measured
at the Unit Auxiliaries Transformer incoming power supply to a level of
accuracy is equal to or lower than 1.0% error. To achieve this, the necessary
incoming circuit metering current transformers, voltage transformer and meter
shall be class 0.2 accuracy for incoming power supply.
General
A list of spare parts, cross referenced to the various systems and items of
equipment (to include quantity recommended, quantity installed, drawing
reference number, drawing position and part number) and detailing the essential
operational spare parts supplied by the Bidder/Contractor for 2 years operation
from Provisional Acceptance Certificate of the plant, shall be provided in the
Schedules outlined in this Request for Proposal.
Contractors shall individually price major items in their spares lists, and provide
lump sums for minor groups of items. All spare parts and consumable lists shall
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 250 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
be provided in hard copy and electronic format.
The quantities of spares to be ordered and the time of placing an order shall be
at the discretion of the Employer.
The Bidder/Contractor shall also include in the Bid as an option a spare parts
agreement for 5 years of operation. This offer shall detail the scope of the spares
offered, guarantee delivery times to site, costs, form of agreement including
warranty of such parts.
As a guide only to the Bidder/Contractor, the following list is an example of the
coverage of spare parts that are expected by the Employer to be supplied for the
Power Plant to cover the first two years of operation. It is emphasized that the
list does not cover all the items that are likely to be required and consequently
it does not absolve the Bidder/Contractor from submitting their detailed
recommendations for all spares appropriate for the plant offered at the time of
Bid.
Essential spares shall comprise at least the items as listed below and as detailed
in the Essential Spares schedule for electrical plant. Optional spares shall be in
accordance with the manufacturers’ recommendations for parts which may fail
and require replacement.
Essential Spares
(1) Generator
(a) One (1) generator set of shaft journal bearings, comprising top and bottom
halves, complete with bolts, nuts and lock washers.
(b) One (1) generator set of bearing and pedestal insulation.
(c) One (1) turbo generator set of shaft earthing and voltage sensing brushes.
(d) Sufficient top and bottom stator winding bars to repair a fault in the worst
location; supply to include all associated items necessary to effect the repair
including hoses, fittings, wedges, packers.
(e) One (1) turbo generator set of generator access door and shield gaskets.
(f) One (1) turbo generator set of brush gear including arms, brush boxes, springs.
(g) One (1) generator set of sliprings.
(h) One (1) generator terminal bushing
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 251 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
(e) One (1) field circuit breaker set arcing tips.
(f) One (1) field circuit breaker set suppression resistors.
(g) One (1) field circuit breaker set closing and trip coils.
(8) Cables
One steel drum (wooden drums are not acceptable for spares usage) containing
250 metres of each type of 11kV cable. A separate steel drum shall be provided
for each cable size.
These shall be subject to agreement between the Contractor and the Owner and
shall be based on manufacturers’ recommendations.
Those optional spare parts which it is recommended should be purchased in
additional to those listed for Essential Spares to maintain the plant in an
operational condition.
These shall be subject to agreement between the Contractor and OWNER and
Part 2 – Chapter VII – Section 7 – Generator and electrical equipment page 253 of 255
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
shall be based on manufacturers’ recommendations.
As specified in Section 1, the Contractor shall list in Annex A those tools and
appliances which are essential for the maintenance of the plant.
The Contractor shall also list in Annex A those additional tools and appliances
which it is recommended should also be purchased.
Tools for maintenance of the Generator and the auxiliaries shall be provided as
follows:
(1) Generator
One (1) apparatus to maintain a breathable atmosphere inside the generator
during personnel access via manholes also to prevent the condensation of
moisture within the generator when the generator is de-gassed but not otherwise
open to atmosphere. A description of the proposed apparatus shall be included
in the Proposal Documents.
The Contractor shall supply consumables required for the equipment and
systems being provided under the Contract in accordance with Volume 2
and as generally listed below.
The Contractor shall add to these list consumables which it is considered
should also be purchased to maintain the plant in an operational condition.
Diesel house
Bottom ash
Circulating water pumping Station
FGD discharge basin
Ash Yard
Stacker/reclaimer
Hydrogen generating plant
Chlorine station
Power Transformers area
CCR
Power supply rooms and electric/electronic device rooms
Fuel Oil pump station
Ash pump houses
Main internal streets
Auxiliaries Boiler
video switching for the relevant video images at a pre-set time interval. It
shall be possible to set independent dwell time separately for each camera.
All cameras shall be IP camera type with available remote control Rotation,
Tilt, lens zoom and weatherproof camera housing to provide an electrical
enclosure classification of at least IP66. The housing shall incorporate
automatic lens washing (except the furnace flame viewing cameras which
will be air cooled and purged). Water supply points of 75 mm diameter shall
be taken at locations up to 50 metres away from each camera. Bidders shall
allow for breaking into the pipework and providing a local isolating valve.
For exterior cameras, the supply point shall be considered as underground
and approximately 30 metres shall be taken as underground.
Each system of cameras shall be arranged such that the whole of the area
under surveillance is viewed.
For each camera, provision shall be made for initiating alarms in the CCR
on the failure of power supply to the cameras, on high temperature in the
camera and on loss of cooling air pressure to the camera (where applicable).
Two local indicating lights, with electrical enclosure rating of IP66, shall
be provided local to each camera to indicate:
Power on (red)
Camera in alarm (amber).
Prefabricated plug-in cables for interconnecting TV camera, power supply,
TV monitors etc. shall be provided.
Cameras shall operate normally under conditions of high vibration and noise.
Each camera shall be equipped with a suitable pick-up tube, noise
suppression circuits, all necessary filters, iris control, automatic gain
Part 2 – Chapter VII – Section 8 – Control and instrumentation
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
control and automatic adjusting devices to provide an optimum video signal
for maintaining a high signal to noise ratio.
(1) Furnace Flame Viewing Cameras
In addition to the foregoing requirements, the furnace flame viewing
cameras shall provide direct viewing of the flame pattern in each furnace
by the operator in the CCR.
The cameras shall be mounted in such positions that all PF burners, all oil
burners and all ignitors, which are in service, can be identified on the
monitors.
Automatic light level adjustment shall be provided to give a clear picture
of the furnace flame at all boiler loads and with all combinations of burners
in service. Means to focus the camera remotely shall be provided.
The Contractor shall ensure that the camera is suitable for operation at the
highest air temperature likely to be experienced at the location where the
camera is mounted.
The optics shall be supplied with purge air to ensure that cleaning of the
windows is not required more frequently than every three months. The
optics shall be designed so that they may be cleaned quickly and safely by
operating staff without the necessity to use tools.
(3) The cameras and monitors shall be suitable to operate on single phase 230V ac power
supply. It shall be assumed that the power supply connection point is approximately 50
metres away for each of the cameras and approximately 15 metres away for each of the
monitors.
(4) Each monitor picture tubes shall be approximately 34 cm in size and shall produce a
clearly defined image when viewed by the operator seated at the control desk
approximately 1.5 m away. The picture non-linearity shall be less than 1%. The bezel
colour shall be to OWNER’s approval.
(6) The installation under the contract shall be complete and include all necessary fittings,
mounting poles (as necessary), foundations for the poles, power and signal cabling,
power supply units, any other electrical equipment, etc.
The CCTV system shall be provided a DVM system which shall have at
least the following functions:
Camera selection can start DVM video recording
DVM video recording parameters are based on the selected camera.
Separate configurable alarm for video recording functions
The video record should have event triggers: time, event and manual request.
It should be possible to embedded user diagrams into real time video pictures.
Tree menu structure to explore and select video cameras
On line adjustment for all video camera parameters
Small, middle and large size display windows
Grouping possibility for the camera windows on the screen (e.g.: four ¼ windows
shown at the same time).
Support for multi monitor displays
Easy review of video recording
Camera positioning, focus adjustment, and zooming function only from definable
workstations.
8.2.15.3 The thermal imaging camera
The thermal imaging cameras shall be provided including but not limit
NVRs (network video recorder), DVRs (digital video recorder) and display
station. The display station shall be installed at coal handling control room.
Eight (08) thermal imaging cameras shall be provided for total coal yard.
The signal shall be connected to coal handling control room.
The thermal imaging cameras shall be in accordance with the following:
Protection of degree At least IP66
Digital output for alarm (available for setting)
Camera positioning, focus adjustment, zooming function
Built-in 25 degree lens or better with both motorized focus and autofocus.
8.2.16.1 General
Clock system have been provided by Quang Trach I EPC Contract,
including: the complete clock system and shall comprise the following
items:
One GPS master clock comprising a GPS receiver, a GPS master clock and a
display unit
a standard time signal unit, an AC power frequency signal unit, a frequency
comparison unit, and a time indication unit.
Digital and analog slave clocks.
The contractor should provide the Digital and analog slave clocks, and
related workw to comply with Quang Trach I. These slave clocks will be
connected master clock, all equipment should be synchronizing with it.
One (1) GPS system have been provided in Quang Trach I project as a
master clock for time synchronization system in the power station. The
clock system equipment shall be housed in a floor-standing, metal-enclosed
Part 2 – Chapter VII – Section 8 – Control and instrumentation
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
cubicle and installed in the relay room (behind the CCR) of the
powerhouse.
Particulars
For the clock system shall be as follows:
(2) GPS receiver
: Less than 3 W
Power consumption
Component : Water-proof
: Less than 6 W
Power consumption
b) Counter
Part 2 – Chapter VII – Section 8 – Control and instrumentation
QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL REV.F
Output : Binary coded decimal
a) : In time difference
Frequency comparison
b) : 5 digits with monitoring
Output
c) : 0.01 second
Minimum digit
3 digits (1 digit for 1 min., 2 digits
d) Indication of time
for 10 sec. and 1 sec.)
difference
b) A display unit to indicate position, date and time in the system mimic board
c) An interface to output position, date and time for supervisory control system and
clock system
d) A power supply unit such as DC-AC inverter for GPS units in case of AC power
failure.
b) Analog type slave clock with two-pointer for wall-mounting (approx. 500 mm in
diameter).
a) 1 digital clock.
b) 1 analog clock
8.2.16.3 Execution
(1) Erection
The master clock has been installed in the relay room of Quang Trach I.
Slave digital (D) or analog (A) type clocks shall be installed at the following sites:
a) One (A) in the hall of the powerhouse,
f) One flush-mounted clock (D) in the control board inside the switchyard control
room.
g) One (A) in all rooms in the Administration Building, Workshop and Warehouse,
Security Centre/ Gatehouse and all other remote buildings.
9.1 GENERAL
This section includes design, manufacture, factory test, inspection, supply,
delivery, unloading at Site, erection, installation, testing, commissioning and
guarantee by the Bidder/Contractor as part of this Contract for Communication
and SCADA/EMS system. Training on Site, and/or in the manufacturer’s works
for the Owner shall also be included for major items of Communication and
SCADA/EMS system.
The design and installation shall comply with the recommendations and
standards following:
ITU : International Telecommunication Unit
IEC : International Electrotechnical Commission
EIA/TIA : Electronic Industries Alliance/ Telecommunications Industry
Association Engineering Standards
IEEE : Institute of Electrical and Electronics Engineers
Data transmission protocol from Quang Trach I TPP (Quang Trach I TPP) to
Central Region Load Dispatch Centre (A3), National Load Dispatch Centre
(A0) have to obey IEC 60870-5-104 standard.
Stipulating the technical requirements and operation management of the
SCADA system are attached to the Decision No.55/QĐ-ĐTĐL dated August
22nd, 2017 of Direction of Electricity Regulatory Authority.
Decision No. 432/ĐĐQG-CN dated March, 20th 2017 Guiding and
Stipulating the agreement on connection of the communication system
operating the electric system.
The optical communication equipment has to adjust to the existing EVN
system and EVN regulation.
SCADA/EMS and Communication Agreement No. 215/ĐĐQG-CN+PT on
31st January 2018 signed between National Load Dispatch Centre (NLDC-
A0) and TPMB2.
9.2 COMMUNICATION SYSTEM
9.2.1 Scope of supply
Communication and SCADA/EMS system for Quang Trach I TPP shall be
provided the items including but not limited to the following:
Switchboard system and subcriber net: Main IP-PBX and Back-up Private
Automatic Branch Exchange (PABX) possible of synchronous dial up with
the EVN PABX Networks
UHF wireless communication system
Public Address system (message transfer)
Intrusion Alarm System
The contractor shall implement latest Data Signal List for SCADA/EMS system
approved by A0 and A3.
9.3.2 Scope of Supply
This contract includes for the following equipment as a minimum:
A network operational telephone system as specified elsewhere.
02 Gateways (01 main/01 back up) and 04 ports per gateway (01 port to A0,
01 port to A3, 01 port for EVN ‘s smart power grid in the future, 01 port for
spare) for the integration of SCADA/EMS systems.
Host Computer, Workstation, printer A4, A3, Switch, cabinet, Multi mode
Fiber Optic Cable, dual LAN network, spare parts and software…
Tele-protection signaling equipment as specified elsewhere.
HV of Transformer GT2
LV of Transformer GT1
LV of Transformer GT2
SIGNAL
TYPE No DATA TYPE NAME
S/S COMMON
Busbar1-22 kv
Busbar2-22 kv
Signal Total
UAT1A
UAT2A
UAT1B
UAT2B
G1
G2
1 F FREQUENCY 3 1 1 1
2 A MWh 0
3 A AMPERE 10 1 1 1 1 1 1 1 1 1 1
4 KV VOLTS 12 1 1 1 1 1 1 1 1 1 1 1 1
5 MW MEGAWATTS 10 1 1 1 1 1 1 1 1 1 1
6 MX MEGAVARS 10 1 1 1 1 1 1 1 1 1 1
7 LL P LOWLIMIITP 2 1 1
8 HL P HIGH LIMITP 2 1 1
ATM 9 LL Q LOW LIMIIT Q 2 1 1
10 HLQ HIGH LIMIT Q 2 1 1
11 TMW TOTAL MW 1 1
12 T MX TOTAL MVAR 1 1
13 TC TEMPARATURE 0
14 TPI TAP CHANGER 6 1 1 1 1 1 1
TOTAL PER BAY : 61 3 4 4 4 4 1 1 8 8 5 5 5 5 2 2
ATM-Total 61
1 ALARM DC SYSTEM 48V 1 1
2 ALARM DC SYSTEM 220V 1 1
3 ALARM AC SYSTEM 220V/ 380 1 1
4 ALARM SWITCHING EQUIPMENT NOT READY (AIR / OIL / SF6/MECHANICAL) 2 1 1
5 ALARM EQUIPMENT FAULT 8 1 1 1 1 1 1 1 1
6 OPERATED BUSBAR PROTECTION - MAIN 2 1 1
7 OPERATED BUSBAR PROTECTION - BACK-UP 0
8 OPERATED BREAKER FAILURE PROTECTION (FROM F86BF) 0
9 OPERATED OVERVOLTAGE PROTECTION 0
10 OPERATED UNDERVOLTAGE PROTECTION 0
11 OPERATED DISTANCE PROTECTION ZONE 1/TELEPRO. - MAIN (21 Z1 main) 0
12 OPERATED DISTANCE PROTECTION ZONE 2 - MAIN (21 Z2 main) 0
13 OPERATED DISTANCE PROTECTION - MAIN (21) 0
OPERATED DISTANCE PROTECTION ZONE 1/TELEPRO - BACK-UP (when applicable) (21 Z1 backup) 0
14 OPERATED DISTANCE PROTECTION ZONE 2 - BACK - UP (When applicable) (21 Z2 backup) 0
HV of Transformer GT2
LV of Transformer GT1
LV of Transformer GT2
SIGNAL
TYPE No DATA TYPE NAME
S/S COMMON
Busbar1-22 kv
Busbar2-22 kv
Signal Total
UAT1A
UAT2A
UAT1B
UAT2B
G1
G2
15 OPERATED DISTANCE PROTECTION - BACK - UP (When applicable) (21 Z1 backup) 0
16 OPERATED LINE DIFFERENTIAL PROTECTION (87L) 0
17 OPERATED DIRECTIONAL OVERCURRENT PROTECTION (67/67N) 0
18 OPERATED OVERCURRENT PROTECTION (50/50N) 0
19 OPERATED INTERTRIP SENT (85) 0
OPERATED INTERTRIP RECEIVED (85) 0
20 OPERATED AUTORECLOSE ORDER (79/25) 0
21 OPERATED EQUIPMENT OVERLOAD PROTECTION TRIP (49TRIP) 6 1 1 1 1 1 1
TSS-1B 22 OPERATED EQUIPMENT OVERLOAD PROTECTION ALARM (49 ALARM) 6 1 1 1 1 1 1
23 OPERATED EQUIPMENT (VOLTAGE) UNBALANCE PROTECTION 6 1 1 1 1 1 1
24 OPERATED EQUIPMENT DIFF. PROTECTION : DIFFERENTIAL STAGE (87) 6 1 1 1 1 1 1
25 OPERATED EQUIPMENT DIFFERENTIAL PROTECTION 6 1 1 1 1 1 1
26 OPERATED EQUIPMENT OVERCURRENT PROTECTION 6 1 1 1 1 1 1
27 OPERATED EQUIPMENT RESTRICTED EARTH FAULT PROTECTION 6 1 1 1 1 1 1
28 OPERATED BUCCHOLZ (96) 6 1 1 1 1 1 1
29 OPERATED WINDING TEMP. TRIP (26) 12 2 2 2 2 2 2
30 OPERATED WINDING TEMP. ALARM (26) 12 2 2 2 2 2 2
31 OPERATED OIL TEMP. TRIP (26) 6 1 1 1 1 1 1
32 OPERATED OIL TEMP. ALARM (26) 6 1 1 1 1 1 1
33 OPERATED PRESSURE RELIEF RELAY 6 1 1 1 1 1 1
34 OPERATED EQUIPMENT TRIP 4 1 1 1 1
35 LOCAL OPERATION MODE REMOTE / LOCAL 8 1 1 1 1 1 1 1 1
36 DISABLE RTU REMOTE CONTROL 1 1
37 OPERATED GENERATOR. DIFFERENTIAL 2 1 1
38 OPERATED GENERATOR. EARTH FAULT 2 1 1
39 OPERATED GENERATOR. OVERLOAD 2 1 1
40 OPERATED GENERATOR. EARTH FAULT 2 1 1
41 ALARM GENERATOR. OVERLOAD 2 1 1
TOTAL PER BAY : 128 4 0 0 0 0 18 18 9 9 17 17 17 17 1 1
TSS - TOTAL : 128
1 OPEN / CLOSE EARTHING SWTCH 4 2 2
2 OPEN / CLOSE DISCONNECTOR 2 1 1
HV of Transformer GT2
LV of Transformer GT1
LV of Transformer GT2
SIGNAL
TYPE No DATA TYPE NAME
S/S COMMON
Busbar1-22 kv
Busbar2-22 kv
Signal Total
UAT1A
UAT2A
UAT1B
UAT2B
G1
G2
TSD - TOTAL : 12
1 OPEN / CLOSE DISCONNECTOR 2 0 0 0 0 0 0 1 1 0 0
2 OPEN / CLOSE CIRCUIT BREAKER 2 0 0 0 0 0 0 1 1 0 0
4 SETPOINTVALUE GENERATOR. ACTIVE POWER CONTROL 2 1 1
5 SETPOINTVALUE GENERATOR. REACTIVE POWER CONTROL 2 1 1
6 SETPOINTVALUE GENERATORTERMINALVOLTAGE CONTROL 2 1 1
RCD-2B
7 START/STOP DIESEL GENERATOR START/STOP 0
8 RAISE / LOWER TAP CHANGER 6 1 1 1 1 1 1
TOTAL PER BAY : 16 0 0 0 0 0 1 1 5 5 1 1 1 1 0 0
RCD - TOTAL : 16
CONTENTS
i
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
ii
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
This Design Criteria is provided to make uniform engineering application guide for QUANG
TRACH I THERMAL POWER PLANT PROJECT. If there is any discrepancy between this
addendum and ‘QT1-GTR-E-001 GTR-E’, Supplier should submit clarification to Purchaser
or Supplier should consider more stringent requirement.
All equipment shall be designed for an operating life of at least 30 years and shall be suitable
for continuous maximum rating operation.
2.1 TEMPERATURE
2.2 HUMIDITY
Supplier should consider WIND & SEISMIC condition in ‘Clause 4.3 Site and Design
Conditions of QT1-L-M-100-04-00001 PLANT GENERAL DESIGN CONDITIONS’ for
Supplier’s design and clarify it for Client if Client asked.
Supplier shall submit anchor bolt / structural support strength calculation based on these data.
1 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
2 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
4.0 VARIATION
4.1 FREQUENCY
4.2 VOLTAGE
VOLTAGE VARIATION RANGE
CONDITION
* Un : System Nominal voltage
STEADY-STATE ± 10% of Un
3 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
[Note]
4 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
[NOTE]
5 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
A Yellow
B Green
3 PH C Red
Black (for direct earthing)
NEUTRAL
White (for isolated earthing)
LINE Yellow
NEUTRAL Black
1 PH
Note. If the busbar is tapped from 3ph busbar, color marker shall be
same with tapped busbar of 3ph.
+ Red
DC - Blue
NEUTRAL White
Yellow-Green
PROTECTIVE (longitudinally striped throughout the length)
EARTH (PE) Note. Sky-blue marking at the termination shall be made using
shrinkable tube.
6 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
A Yellow
B Green
3 PH C Red
Black (for direct earthing)
NEUTRAL
White (for isolated earthing)
LINE Yellow
NEUTRAL Black
1 PH
Note. If the busbar is tapped from 3ph busbar, color marker
shall be same with tapped busbar of 3ph.
+ Red
DC - Blue
NEUTRAL White
YELLOW-GREEN
PROTECTIVE EARTH (PE)
Transversally Striped throughout the length
[NOTE]
2) Horizontally arranged bus-bar : A-B-C-(N), 'Far to Near' or 'Left to Right' order when
viewed from operating corridor.
2. Color code application for Switchgear bus-bar and bus-duct will be as follows:
7 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
PHASE COLOR
CT CIRCUIT YELLOW
VT CIRCUIT BLUE
230V AC CIRCUIT RED
220V DC CIRCUIT GREY
GROUNDING CIRCUIT YELLOW-GREEN
BY
OTHER CIRCUIT
MANUFACTURER
8 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
- MOTOR RUNNING
- MOTOR STOPPED
9 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
CONTROL CABLE
INSTRUMENT CABLE
10 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
According to GTR-E clause 7.8.1, all protection relay of Supplier’s MV/LV SWGR system
shall communicate with RMS Station (Relay Monitoring and Setting Station). Configuration
diagram with scope of supply are shown as follows.
RMS STATION
[NOTE]
1. If Package Supplier supply MV SWGR with PLC system, relay setting shall be done by
RMS STATION as shown on configuration diagram but system shall be monitored by
PLC using hard wire & communication.
11 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
2. Based on configuration diagram, Supplier shall provide all necessary device including
FDF, adaptor, converter, patch code, connection materials of Purchaser’s cable connection
and etc.
Fibre Distribution Frame
3. All patch code should be breakout type.
5. All necessary Software & licence for protection relay shall be provided by Supplier.
6. MV SWGR Supplier shall provide technical support for design coordination with RMS
STATION Supplier.
7. MV SWGR Supplier shall provide Serpervising service during site test period between
RMS Station and MV SWGR.
10.1 Electrical clearance among secondary circuit live objects or between live objects and
grounding objects shall not be less than 4mm, and creepage distance shall not be less than
6mm.
10.2 The Supplier shall provide preventative measures for prevention of intrusion by insects.
10.3 Sunshade
The normal operational areas of outdoor panel/equipment shall be provided with sunshades.
The sunshades shall be adequately sized to protect the areas from direct sun radiation down to
45ºC to the horizontal. The sunshades shall give sufficient head clearance to permit walking
and working space for normal maintenance with adequate artificial lighting as necessary.
Small multiple cooling fan systems shall be provided for electronic control / protection cabinet.
Each fan is individually protected by MCCB/MCB, is provided with LED indication of fan
failure.
The sheet metal switchboards shall be constructed of folded and welded sheets of 2.0mm
minimum thickness and where equipment is to be mounted on a panel the thickness of the
sheet metal shall be sufficient to prevent vibration affecting the correct operation of the
equipment.
12 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
All cable entry of panels shall be equipped with non-magnetic blind plate. The plate shall be
sized enough for installation of cable gland of armoured cable and shall be partitioned into
minimum two or three as required by Purchaser.
All control panel, protection panels and SWGR/MCC shall have CT and VT test terminal
blocks (CTT & VTT). The CTT and VTT shall be mounted at front door and convenient for all
necessary test. Plugs and accessories for all CTT and VTT shall be provided considering
necessary test methods.
1) POWER CABLE
- Cable size > 95mm2 : Two hole type lug with 45mm hole distance
2) EARTHING WIRE
The thread type of rigid steel conduits, cable gland and all the others equipment including
Motor cable entry shall be Metric.
Exception may be allowed for package equipment when manufacturer request based on their
design standard for normal operation of package equipment. But in this case, the Supplier
should provide adaptors for Metric type connection.
13 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
Emergency
Description Power Supply Remark
Lighting Type
Normal AC power
Emergency lighting for with
Type 2
‘Other Area’ self-contained battery
pack (2 hours)
Normal AC power
with
Type 3 All EXIT lighting
self-contained battery
pack (2 hours)
- The emergency lighting for ‘Main Building Area’ where operators are regularly
resident will be powered from essential AC power source generated by emergency
diesel generator.
* Main Building Area
- Central control building
- Turbine house
- Laboratory & Water treatment building
- ESP/FGD control & Ash pump control building
- Coal handling control building
- Boiler (Boiler Tower)
- Fly Ash Silo
- Stack/Chimney (Internal Light)
- Under failure of normal power, lighting fixtures will still remain on for 2 hours via
self-contained battery pack. And, If the emergency diesel generator start power
supply to essential switchgear, the emergency lighting will be continuously operated
without interruption.
14 of 15
TWO(2) x 700 MW QUANG TRACH I THERMAL POWER PLANT
GENERAL TECHNICAL REQUIREMENT FOR ELECTRICAL Rev. F
The emergency lighting for ‘Other Area’ will be powered from normal AC power source
with self-contained battery pack (2 hours).
The EXIT lighting will be powered from normal AC power source with self-contained
battery pack (2 hours).
15 of 15