BILL OF QUANTITY

PROYEK : HOTEL & RESORT SANTIKA GARUT


OWNER : PT.SUMBER BERKAT INDONESIA
PEKERJAAN : ELEKTRIKAL
PERIODE : JANUARY 2024
LOKASI : GARUT

HARGA TOTAL
NO. URAIAN PEKERJAAN SAT VOL. SATUAN HARGA KETERANGAN
(Rp.) (Rp.)

(I) ELEKTRIKAL / LISTRIK

I SAMBUNGAN DAYA

A PENYAMBUNGAN DAYA TEGANGAN RENDAH ( PLN )


- Biaya Penyambungan ( BP ) KVA 197.0 - (By. Owner)

- Uang Jaminan Pelanggan ( UJL ) KVA 197.0 - (By. Owner)

- Biaya Administrasi Pengurusan Sambungan Daya PLN +KVA


Sertifikat Layak
197.0Operasi 5,471,402 5,471,402 (Kontraktor)

SUB TOTAL I 5,471,402

II PERALATAN UTAMA DAN KABEL FEDDER

A PANEL-PANEL TEGANGAN RENDAH


- PUTR PUTR unit 1 - -
- GENSET, 250 kVa, Type Silent c/w Tanki Solar 2000 liter ? Lot 1 - -
- SDP-UTAMA HOTEL unit 1 - -
- - PP-LANTAI DASAR unit 1 - -
- - - MCB-BOX KAMAR unit 22 - -
- - PP-LOUNGE unit 1 - -
- - PP-POWER KITCHEN unit 1 - -
- - PP-LANTAI 1 unit 1 - -
- - - MCB-BOX KAMAR unit 23 - -
- - PP-LANTAI 2 unit 1 - -
- - - MCB-BOX KAMAR unit 20 - -
- - PP-LANTAI ATAP unit 1 - -
- - - PC-BOOSTER PUMP unit 1 - - By.Pompa
- - - PC-HEAT PUMP unit 1 - - By.Pompa
- - PP-LIFT PENUMPANG unit 1 - -
- - - PC-LIFT PENUMPANG unit 1 - - By.Lift
- SDP-UTAMA VILLA unit 1 - -
- - PP-VILLA 1 unit 1 - -
- - PP-VILLA 2.A unit 1 - -
- - PP-VILLA 2.B unit 1 - -
- - PP-VILLA 2.C unit 1 - -
- - PP-VILLA 3 unit 1 - -
- SDP-UTAMA PLUMBING unit 1 - -
- - PC-POMPA TRANSFER unit 1 - - By.Pompa
- - PC-STP unit 1 - - By.Pompa
- - PC-POMPA CHUMBER unit 1 - - By.Pompa
- SDP-KOLAM RENANG VILLA unit 1 - -
- - SDP-VILLA 1 unit 1 - -
- - PP-KOLAM VILLA 2.A unit 1 - -
- - PP-KOLAM VILLA 2.B unit 1 - -
- - PP-KOLAM VILLA 2.C unit 1 - -
- - PP-KOLAM VILLA 3 unit 1 - -
- - PC-HEAT PUMP 1 & 2 unit 1 - - By.Heat Pump
- - PC-HEAT PUMP 3 & 4 unit 1 - - By.Heat Pump
- - PC-HEAT PUMP 5 & 6 unit 1 - - By.Heat Pump
- - PC-HEAT PUMP 7 & 8 unit 1 - - By.Heat Pump
- - PC-SUMPIT 1 & 2 unit 1 - - By.Pompa
- SDP-KOLAM RENANG BESAR unit 1 - -
- - PP-KOLAM RENANG BESAR unit 1 - -
- - PP-KOLAM RENANG KIDS unit 1 - -
- - PC-HEAT PUMP 1 & 2 unit 1 - - By.Heat Pump
- - PC-SUMPIT 1 & 2 unit 1 - - By.Pompa
- PP-LUAR 1 unit 1 - -

B GROUNDING SYSTEM
1 Grounding Panel PUTR (Max 1 Ohm) unit 1 3,955,256 3,955,256
Posisi di sekitar luar gedung
- Alat Bantu ( 1 Lot )
- Rod 3/8" ( 1 Set )
- Bak Kontrol 400 x 400 x 400 mm Beton Bertulang ( 1 Lot )
- Kabel BC 1 x 95 mm² + Pipa PVC Ø 32 mm (1 1/4") ( 6 m )

2 Grounding Genset (Max 1 Ohm) unit 1 3,955,256 3,955,256


Posisi di sekitar luar gedung
- Alat Bantu ( 1 Lot )
- Rod 3/8" ( 1 Set )
- Bak Kontrol 400 x 400 x 400 mm Beton Bertulang ( 1 Lot )
- Kabel BC 1 x 95 mm² + Pipa PVC Ø 32 mm (1 1/4") ( 6 m )

3 Grounding Lift ( Max 1 Ohm ) unit 1 5,065,901 5,065,901 By.Lift


Posisi di sekitar luar gedung
- Alat Bantu ( 1 Lot )
- Rod 3/8" ( 1 Set )
- Bak Kontrol 400 x 400 x 400 mm Beton Bertulang ( 1 Lot )
- Kabel BC 1 x 95 mm² + Pipa PVC Ø 32 mm (1 1/4") ( 9 m )

C KABEL FEEDER UTAMA


1 Dari Trafo gantung ke PUTR :
- NYY 4 x (2 x 1c x 240 mm2) + BC 185 mm2 m 17 3,072,219 52,227,726

2 Dari Genset ke PUTR :


- NYY 4 x (2 x 1c x 240 mm2) + BC 185 mm2 m 12 3,072,219 36,866,630

3 Dari PUTR ke :
- SDP-Utama Hotel
NYFGBY 4 x 240 mm2 m 27 2,809,521 75,857,067
- SDP-Utama Villa
NYFGBY 4 x 35 mm2 m 126 453,882 57,189,132
- SDP-Utama Plumbing
NYFGBY 4 x 50 mm2 m 86 593,650 51,053,917
- SDP-Utama Kolam Renang Villa
NYFGBY 4 x 50 mm2 m 171 593,650 101,514,184
- SDP-Utama Kolam Renang Besar
NYFGBY 4 x 50 mm2 m 74 593,650 43,930,115
- PP-Luar 1
NYFGBY 4 x 10 mm2 m 129 156,349 20,169,027

4 Dari SDP-utama Hotel ke :


- PP-Lantai Dasar
NYY 4 x 35 mm2 + BC 25 mm2 m 9 469,365 4,224,281
- PP-Lounge
NYY 4 x 10 mm2 + BC 6 mm2 m 49 143,809 7,046,660
- PP-Power Kitchen
NYY 4 x 25 mm2 + BC 16 mm2 m 49 339,664 16,643,517
- PP-Lantai 1
NYY 4 x 35 mm2 + BC 25 mm2 m 16 469,365 7,509,834
- PP-Lantai 2
NYY 4 x 35 mm2 + BC 25 mm2 m 19 469,365 8,917,928
- PP-Lantai Atap
NYY 4 x 25 mm2 + BC 16 mm2 m 32 339,664 10,869,236
- PP-Lift Penumpang
NYY 4 x 25 mm2 + BC 16 mm2 m 35 339,664 11,888,226

5 Dari PP-Lantai Dasar ke :


- MCB-Box Kamar.1
d/kabel NYY 3 x 4 mm2 m 15 43,968 659,523
- MCB-Box Kamar.2
d/kabel NYY 3 x 4 mm2 m 19 43,968 835,396
- MCB-Box Kamar.3
d/kabel NYY 3 x 4 mm2 m 20 43,968 879,364
- MCB-Box Kamar.4
d/kabel NYY 3 x 4 mm2 m 27 43,968 1,187,142
- MCB-Box Kamar.5
d/kabel NYY 3 x 4 mm2 m 29 43,968 1,275,078
- MCB-Box Kamar.6
d/kabel NYY 3 x 4 mm2 m 36 43,968 1,582,856
- MCB-Box Kamar.7
d/kabel NYY 3 x 4 mm2 m 53 43,968 2,330,315
- MCB-Box Kamar.8
d/kabel NYY 3 x 4 mm2 m 54 43,968 2,374,283
- MCB-Box Kamar.9
d/kabel NYY 3 x 4 mm2 m 61 43,968 2,682,061
- MCB-Box Kamar.10
d/kabel NYY 3 x 4 mm2 m 63 43,968 2,769,997
- MCB-Box Kamar.11
d/kabel NYY 3 x 4 mm2 m 71 43,968 3,121,743
- MCB-Box Kamar.12
d/kabel NYY 3 x 4 mm2 m 63 43,968 2,769,997
- MCB-Box Kamar.13
d/kabel NYY 3 x 4 mm2 m 61 43,968 2,682,061
- MCB-Box Kamar.14
d/kabel NYY 3 x 4 mm2 m 54 43,968 2,374,283
- MCB-Box Kamar.15
d/kabel NYY 3 x 4 mm2 m 53 43,968 2,330,315
- MCB-Box Kamar.16
d/kabel NYY 3 x 4 mm2 m 46 43,968 2,022,538
- MCB-Box Kamar.17
d/kabel NYY 3 x 4 mm2 m 45 43,968 1,978,569
- MCB-Box Kamar.18
d/kabel NYY 3 x 4 mm2 m 37 43,968 1,626,824
- MCB-Box Kamar.19
d/kabel NYY 3 x 4 mm2 m 36 43,968 1,582,856
- MCB-Box Kamar.20
d/kabel NYY 3 x 4 mm2 m 29 43,968 1,275,078
- MCB-Box Kamar.21
d/kabel NYY 3 x 4 mm2 m 28 43,968 1,231,110
- MCB-Box Kamar.22
d/kabel NYY 3 x 4 mm2 m 21 43,968 923,332

6 Dari PP-Power Kitchen ke :


- Power Mesin Kitchen 1 (Provsum)
d/kabel NYY 4 x 4 mm2 m 30 57,302 1,719,046
- Power Mesin Kitchen 2 (Provsum)
d/kabel NYY 4 x 4 mm2 m 30 57,302 1,719,046
- Power Mesin Kitchen 3 (Provsum)
d/kabel NYY 4 x 4 mm2 m 30 57,302 1,719,046
- Power Mesin Kitchen 4 (Provsum)
d/kabel NYY 4 x 4 mm2 m 30 57,302 1,719,046
- EF-Kitchen
d/kabel NYY 4 x 6 mm2 m 116 80,317 9,316,816
- FAF-Kitchen
d/kabel NYY 4 x 6 mm2 m 9 80,317 722,856

7 Dari PP-Lantai 1 ke :
- MCB-Box Kamar.1
d/kabel NYY 3 x 4 mm2 m 17 43,968 747,460
- MCB-Box Kamar.2
d/kabel NYY 3 x 4 mm2 m 21 43,968 923,332
- MCB-Box Kamar.3
d/kabel NYY 3 x 4 mm2 m 22 43,968 967,301
- MCB-Box Kamar.4
d/kabel NYY 3 x 4 mm2 m 30 43,968 1,319,046
- MCB-Box Kamar.5
d/kabel NYY 3 x 4 mm2 m 31 43,968 1,363,015
- MCB-Box Kamar.6
d/kabel NYY 3 x 4 mm2 m 38 43,968 1,670,792
- MCB-Box Kamar.7
d/kabel NYY 3 x 4 mm2 m 49 43,968 2,154,442
- MCB-Box Kamar.8
d/kabel NYY 3 x 4 mm2 m 55 43,968 2,418,252
- MCB-Box Kamar.9
d/kabel NYY 3 x 4 mm2 m 57 43,968 2,506,188
- MCB-Box Kamar.10
d/kabel NYY 3 x 4 mm2 m 64 43,968 2,813,965
- MCB-Box Kamar.11
d/kabel NYY 3 x 4 mm2 m 65 43,968 2,857,934
- MCB-Box Kamar.12
d/kabel NYY 3 x 4 mm2 m 71 43,968 3,121,743
- MCB-Box Kamar.13
d/kabel NYY 3 x 4 mm2 m 65 43,968 2,857,934
- MCB-Box Kamar.14
d/kabel NYY 3 x 4 mm2 m 64 43,968 2,813,965
- MCB-Box Kamar.15
d/kabel NYY 3 x 4 mm2 m 57 43,968 2,506,188
- MCB-Box Kamar.16
d/kabel NYY 3 x 4 mm2 m 55 43,968 2,418,252
- MCB-Box Kamar.17
d/kabel NYY 3 x 4 mm2 m 48 43,968 2,110,474
- MCB-Box Kamar.18
d/kabel NYY 3 x 4 mm2 m 47 43,968 2,066,506
- MCB-Box Kamar.19
d/kabel NYY 3 x 4 mm2 m 39 43,968 1,714,760
- MCB-Box Kamar.20
d/kabel NYY 3 x 4 mm2 m 38 43,968 1,670,792
- MCB-Box Kamar.21
d/kabel NYY 3 x 4 mm2 m 31 43,968 1,363,015
- MCB-Box Kamar.22
d/kabel NYY 3 x 4 mm2 m 30 43,968 1,319,046
- MCB-Box Kamar.23
d/kabel NYY 3 x 4 mm2 m 23 43,968 1,011,269

8 Dari PP-Lantai 2 ke :
- MCB-Box Kamar.1
d/kabel NYY 3 x 4 mm2 m 17 43,968 747,460
- MCB-Box Kamar.2
d/kabel NYY 3 x 4 mm2 m 21 43,968 923,332
- MCB-Box Kamar.3
d/kabel NYY 3 x 4 mm2 m 21 43,968 923,332
- MCB-Box Kamar.4
d/kabel NYY 3 x 4 mm2 m 38 43,968 1,670,792
- MCB-Box Kamar.5
d/kabel NYY 3 x 4 mm2 m 39 43,968 1,714,760
- MCB-Box Kamar.6
d/kabel NYY 3 x 4 mm2 m 35 43,968 1,538,887
- MCB-Box Kamar.7
d/kabel NYY 3 x 4 mm2 m 56 43,968 2,462,220
- MCB-Box Kamar.8
d/kabel NYY 3 x 4 mm2 m 63 43,968 2,769,997
- MCB-Box Kamar.9
d/kabel NYY 3 x 4 mm2 m 64 43,968 2,813,965
- MCB-Box Kamar.10
d/kabel NYY 3 x 4 mm2 m 55 43,968 2,418,252
- MCB-Box Kamar.11
d/kabel NYY 3 x 4 mm2 m 64 43,968 2,813,965
- MCB-Box Kamar.12
d/kabel NYY 3 x 4 mm2 m 56 43,968 2,462,220
- MCB-Box Kamar.13
d/kabel NYY 3 x 4 mm2 m 55 43,968 2,418,252
- MCB-Box Kamar.14
d/kabel NYY 3 x 4 mm2 m 48 43,968 2,110,474
- MCB-Box Kamar.15
d/kabel NYY 3 x 4 mm2 m 46 43,968 2,022,538
- MCB-Box Kamar.16
d/kabel NYY 3 x 4 mm2 m 39 43,968 1,714,760
- MCB-Box Kamar.17
d/kabel NYY 3 x 4 mm2 m 38 43,968 1,670,792
- MCB-Box Kamar.18
d/kabel NYY 3 x 4 mm2 m 31 43,968 1,363,015
- MCB-Box Kamar.19
d/kabel NYY 3 x 4 mm2 m 29 43,968 1,275,078
- MCB-Box Kamar.20
d/kabel NYY 3 x 4 mm2 m 22 43,968 967,301

9 Dari PP-Lantai Atap ke :


- PC-Booster Pump
d/kabel NYY 3 x 2,5 mm2 In conduit 20 mm m 29 35,006 1,015,186
- PC-Heat Pump
d/kabel NYY 4 x 10 mm2 + BC 6 mm2 m 25 35,006 875,160
- EF-Lantai Atap 1
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 8 35,006 280,051
- EF-Lantai Atap 2
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 20 35,006 700,128
- EF-Lantai Atap 3
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 17 35,006 595,109
- EF-Lantai Atap 4
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 34 35,006 1,190,218
- EF-Lantai Atap 5
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 43 35,006 1,505,275
- EF-Lantai Atap 6
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 53 35,006 1,855,339
- EF-Lantai Atap 7
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 60 35,006 2,100,384
- EF-Lantai Atap 8
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 18 35,006 630,115
- EF-Lantai Atap 9
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 27 35,006 945,173
- EF-Lantai Atap 10
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 35 35,006 1,225,224
- EF-Lantai Atap 11
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 45 35,006 1,575,288
- EF-Lantai Atap 12
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 52 35,006 1,820,333
- EF-Lantai Atap 13
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 60 35,006 2,100,384

10 Dari PP-Lift Penumpang ke :


- PC-Lift Penumpang
d/kabel NYY 4 x 10 mm2 + BC 6 mm2 m 12 143,809 1,725,713

11 Dari SDP-Utama Villa ke :


- PP-Villa 1
d/kabel NYFGBY 4 x 10 mm2 m 35 156,349 5,472,217
- PP-Villa 2.A
d/kabel NYFGBY 4 x 10 mm2 m 26 156,349 4,065,075
- PP-Villa 2.B
d/kabel NYFGBY 4 x 10 mm2 m 10 156,349 1,563,491
- PP-Villa 2.C
d/kabel NYFGBY 4 x 10 mm2 m 12 156,349 1,876,189
- PP-Villa 3
d/kabel NYFGBY 4 x 10 mm2 m 14 156,349 2,188,887

12 Dari SDP-Utama Plumbing ke :


- PC-Pompa Transfer 1 & 2
d/kabel NYY 4 x 25 mm2 + BC 16 mm2 m 15 339,664 5,094,954
- PC-STP
d/kabel NYY 4 x 16 mm2 + BC 10 mm2 m 12 106,349 1,276,189
- PC-Pompa Chumber
d/kabel NYY 4 x 6 mm2 + BC 4 mm2 m 22 91,111 2,004,442

13 Dari SDP-Kolam Renang Villa ke :


- PP-Kolam Villa 1
d/kabel NYY 4 x 6 mm2 + BC 4 mm2 m 12 91,111 1,093,332
- PP-Kolam Villa 2.A
d/kabel NYY 4 x 6 mm2 + BC 4 mm2 m 14 91,111 1,275,554
- PP-Kolam Villa 2.B
d/kabel NYY 4 x 6 mm2 + BC 4 mm2 m 16 91,111 1,457,776
- PP-Kolam Villa 2.C
d/kabel NYY 4 x 6 mm2 + BC 4 mm2 m 18 91,111 1,639,998
- PP-Kolam Villa 3
d/kabel NYY 4 x 6 mm2 + BC 4 mm2 m 20 91,111 1,822,220
- PC-Heat Pump 1 & 2
d/kabel NYY 4 x 35 mm2 m 40 842,885 33,715,396
- PC-Heat Pump 3 & 4
d/kabel NYY 4 x 35 mm2 m 44 842,885 37,086,936
- PC-Heat Pump 5 & 6
d/kabel NYY 4 x 35 mm2 m 44 842,885 37,086,936
- PC-Heat Pump 7 & 8
d/kabel NYY 4 x 35 mm2 m 48 842,885 40,458,475
- PC-Pompa Sumpit 1 & 2
d/kabel NYY 4 x 10 mm2 + BC 6 mm2 m 19 768,571 14,602,843

14 Dari SDP-Kolam Renang Besar ke :


- PP-Kolam renang Besar
d/kabel NYY 4 x 6 mm2 + BC 4 mm2 m 21 91,111 1,913,331
- PP-Kolam renang Kids
d/kabel NYY 4 x 6 mm2 + BC 4 mm2 m 22 91,111 2,004,442
- PC-Heat Pump 1 & 2
d/kabel NYY 4 x 35 mm2 m 12 842,885 10,114,619

15 Dari PC-Pompa Transfer ke :


- Pompa Transfer.1
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268
- Pompa Transfer.2
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268

16 Dari PC-Pompa Booster ke :


- Pompa Booster.1
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268
- Pompa Booster.2
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268

17 Dari PC-Heat Pump 1 & 2 ke : (Area Villa)


- Pompa Heat Pump 1
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268
- Pompa Heat Pump 2
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268

18 Dari PC-Heat Pump 3 & 4 ke : (Area Villa)


- Pompa Heat Pump 1
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268
- Pompa Heat Pump 2
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268

19 Dari PC-Heat Pump 5 & 6 ke : (Area Villa)


- Pompa Heat Pump 1
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268
- Pompa Heat Pump 2
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268

20 Dari PC-Heat Pump 7 & 8 ke : (Area Villa)


- Pompa Heat Pump 1
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268
- Pompa Heat Pump 2
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268

21 Dari PC-Sumpit 1 & 2 ke :


- Pompa Sum Pit 1
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268
- Pompa Sum Pit 2
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268

22 Dari PP-Kolam Villa 1 ke :


- PC-Pompa Sirkulasi
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 10 30,403 304,032
- Trafo AC ke DC 1
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238
- Trafo AC ke DC 2
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238

23 Dari PP-Kolam Villa 2.A ke :


- PC-Pompa Sirkulasi
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 10 30,403 304,032
- Trafo AC ke DC 1
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238
- Trafo AC ke DC 2
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238
24 Dari PP-Kolam Villa 2.B ke :
- PC-Pompa Sirkulasi
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 10 30,403 304,032
- Trafo AC ke DC 1
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238
- Trafo AC ke DC 2
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238

25 Dari PP-Kolam Villa 2.C ke :


- PC-Pompa Sirkulasi
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 10 30,403 304,032
- Trafo AC ke DC 1
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238
- Trafo AC ke DC 2
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238

26 Dari PP-Kolam Villa 3 ke :


- PC-Pompa Sirkulasi
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 10 30,403 304,032
- Trafo AC ke DC 1
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238
- Trafo AC ke DC 2
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238

27 Dari PC-heat Pump (Kolam Renang Besar) ke :


- Pompa Heat Pump.1
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268
- Pompa Heat Pump.2
d/kabel NYY 4 x 16 mm2 m 10 194,127 1,941,268

28 Dari PP-Kolam Renang Besar ke :


- PC-Pompa Sirkulasi
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 10 30,403 304,032
- Trafo AC ke DC 1
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238
- Trafo AC ke DC 2
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238

29 Dari PP-Kolam Renang Kids ke :


- PC-Pompa Sirkulasi
d/kabel NYM 3 x 2,5 mm2 dlm PVC Conduit Ø 20 mm² m 10 30,403 304,032
- Trafo AC ke DC 1
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238
- Trafo AC ke DC 2
d/kabel NYM 3 x 4 mm2 dlm PVC Conduit Ø 20 mm² m 8 44,030 352,238

D RACK KABEL/KABEL TRAY


1 LANTAI DASAR
- Ukuran : 400 x 100 mm2 m 100 459,354 45,935,400

2 LANTAI 1
- Ukuran : 400 x 100 mm2 m 65 459,354 29,858,010

3 LANTAI 2
- Ukuran : 400 x 100 mm2 m 65 459,354 29,858,010

4 LANTAI ATAP
- Ukuran : 400 x 100 mm2 m 60 459,354 27,561,240

E MATERIAL BANTU, Include : Lot 1 21,056,000 21,056,000


- Hanger
- Support
- Accessories

SUB TOTAL II 1,078,152,411

III INSTALASI PENERANGAN & STOP KONTAK

A LANTAI DASAR
1 Fixture / Armature Service Area
- Lampu Downlight LED 10 Watt bh 59 84,500 4,985,500
- Lampu Downlight LED 10 Watt c/w Battery bh 4 273,000 1,092,000
- Lampu Downlight LED 7 Watt bh 7 75,400 527,800
- Lampu T8 LED 1 x 18 Watt Tipe Balk bh 9 247,000 2,223,000
- Lampu T8 LED 2 x 18 Watt Tipe TKI bh 4 299,000 1,196,000
- Lampu T8 LED 2 x 18 Watt Tipe TKI + Battery bh 2 559,000 1,118,000
- Lampu Tangga Led 10 Watt bh 3 130,000 390,000
- Lampu Taman Led Tipe Spotlight 18 Watt bh 66 357,500 23,595,000
- Underwater Lamp LED 50 Watt bh 0 - -
- Saklar Tunggal bh 5 38,350 191,750
- Saklar Ganda bh 6 66,300 397,800
- Stop Kontak 1P Inbow 100 Watt bh 44 85,475 3,760,900
- Stop Kontak 1P Outbow 100 Watt bh 2 85,475 170,950
- Stop Kontak 1P Inbow 2x, 100 Watt bh 3 85,475 256,425
- Exhaust Fan Ceiling bh 4 103,910 415,642 By.VAC

2 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 172 305,561 52,556,492
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 49 302,250 14,810,250
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 4 302,250 1,209,000
dlm PVC Conduit Ø 20 mm²

3 Fixture / Armature Kamar Tipe Deluxe (22 Kamar)


- Lampu Spotlight 5 Watt bh 110 100,750 11,082,500
- Lampu Hallogen LED, 3 Watt bh 44 46,800 2,059,200
- Lampu Spotlight LED, 5 Watt bh 44 100,750 4,433,000
- Indirect Lamp LED Strip, 13 Watt/m m 286 19,500 5,577,000
- Saklar Tunggal bh 66 40,300 2,659,800
- Saklar Ganda bh 44 68,900 3,031,600
- Saklar Hotel bh 44 60,950 2,681,800
- Stop Kontak 1P Inbow 50 Watt bh 198 85,475 16,924,050
- Stop Kontak 1P Inbow 50 Watt (Stop Kontak Kerja) bh 22 85,475 1,880,450
- Air Conditioner bh 22 103,910 2,286,029 By.VAC
- Exhaust Fan Ceiling bh 44 103,910 4,572,058 By.VAC
- Keytag bh 22 103,910 2,286,029

4 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 198 305,561 60,501,078
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Penerangan Indirect d/kabel NYM 3 x 2,5 mm² ttk 57 305,561 17,416,977
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 220 305,561 67,223,420
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Air Conditioner d/kabel NYM 3 x 2,5 mm² ttk 22 305,561 6,722,342
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 44 305,561 13,444,684
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Keytag d/kabel NYM 3 x 2,5 mm² ttk 22 305,561 6,722,342
dlm PVC Conduit Ø 20 mm²

B LANTAI 1
1 Fixture / Armature Service Area
- Lampu Downlight LED 10 Watt bh 25 84,500 2,112,500
- Lampu Downlight LED 10 Watt c/w Battery bh 2 273,000 546,000
- Lampu T8 LED 1 x 18 Watt Tipe Balk bh 2 247,000 494,000
- Lampu Tangga Led 10 Watt bh 3 130,000 390,000
- Step Light LED 12 Watt bh 2 156,000 312,000
- Lampu Exit LED 10 Watt + Battery bh 2 188,500 377,000
- Saklar Tunggal bh 4 38,350 153,400
- Saklar Ganda bh 2 66,300 132,600
- Stop Kontak 1P Inbow 100 Watt bh 8 85,475 683,800
- Stop Kontak 1P Inbow 2x, 100 Watt bh 2 85,475 170,950
- Exhaust Fan Ceiling bh 1 103,910 103,910 By.VAC

2 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 36 305,561 11,000,196
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 10 305,561 3,055,610
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²

3 Fixture / Armature Kamar Tipe Deluxe (23 Kamar)


- Lampu Spotlight 5 Watt bh 115 100,750 11,586,250
- Lampu Hallogen LED, 3 Watt bh 46 46,800 2,152,800
- Lampu Spotlight LED, 5 Watt bh 46 100,750 4,634,500
- Indirect Lamp LED Strip, 13 Watt/m m 299 19,500 5,830,500
- Saklar Tunggal bh 69 40,300 2,780,700
- Saklar Ganda bh 46 68,900 3,169,400
- Saklar Hotel bh 46 68,900 3,169,400
- Stop Kontak 1P Inbow 50 Watt bh 207 85,475 17,693,325
- Stop Kontak 1P Inbow 50 Watt (Stop Kontak Kerja) bh 23 85,475 1,965,925
- Air Conditioner bh 23 103,910 2,389,939 By.VAC
- Exhaust Fan Ceiling bh 46 103,910 4,779,878 By.VAC
- Keytag bh 23 103,910 2,389,939

4 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 207 305,561 63,251,127
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Penerangan Indirect d/kabel NYM 3 x 2,5 mm² ttk 60 305,561 18,272,548
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 230 305,561 70,279,030
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Air Conditioner d/kabel NYM 3 x 2,5 mm² ttk 23 305,561 7,027,903
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 46 305,561 14,055,806
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Keytag d/kabel NYM 3 x 2,5 mm² ttk 23 305,561 7,027,903
dlm PVC Conduit Ø 20 mm²

C LANTAI 2
1 Fixture / Armature Service Area
- Lampu Downlight LED 10 Watt bh 17 84,500 1,436,500
- Lampu Downlight LED 10 Watt c/w Battery bh 4 273,000 1,092,000
- Lampu T8 LED 1 x 18 Watt Tipe Balk bh 2 247,000 494,000
- Lampu Tangga Led 10 Watt bh 3 130,000 390,000
- Step Light LED 12 Watt bh 5 156,000 780,000
- Lampu Exit LED 10 Watt + Battery bh 2 559,000 1,118,000
- Saklar Tunggal bh 4 40,300 161,200
- Saklar Ganda bh 1 68,900 68,900
- Stop Kontak 1P Inbow 100 Watt bh 4 85,475 341,900
- Stop Kontak 1P Inbow 2x, 100 Watt bh 2 85,475 170,950
- Exhaust Fan Ceiling bh 1 103,910 103,910 By.VAC

2 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 33 305,561 10,083,513
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 6 305,561 1,833,366
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²

3 Fixture / Armature Kamar Tipe Deluxe (15 Kamar)


- Lampu Spotlight 5 Watt bh 75 100,750 7,556,250
- Lampu Hallogen LED, 3 Watt bh 30 46,800 1,404,000
- Lampu Spotlight LED, 5 Watt bh 30 100,750 3,022,500
- Indirect Lamp LED Strip, 13 Watt/m m 195 19,500 3,802,500
- Saklar Tunggal bh 45 40,300 1,813,500
- Saklar Ganda bh 30 68,900 2,067,000
- Saklar Hotel bh 30 68,900 2,067,000
- Stop Kontak 1P Inbow 50 Watt bh 135 85,475 11,539,125
- Stop Kontak 1P Inbow 50 Watt (Stop Kontak Kerja) bh 15 85,475 1,282,125
- Air Conditioner bh 15 103,910 1,558,656 By.VAC
- Exhaust Fan Ceiling bh 30 103,910 3,117,312 By.VAC
- Keytag bh 15 103,910 1,558,656

4 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 135 305,561 41,250,735
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Penerangan Indirect d/kabel NYM 3 x 2,5 mm² ttk 39 305,561 11,916,879
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 150 305,561 45,834,150
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Air Conditioner d/kabel NYM 3 x 2,5 mm² ttk 15 305,561 4,583,415
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 30 305,561 9,166,830
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Keytag d/kabel NYM 3 x 2,5 mm² ttk 15 305,561 4,583,415
dlm PVC Conduit Ø 20 mm²

4 Fixture / Armature Kamar Tipe Suite (4 Kamar)


- Lampu Spotlight 5 Watt bh 16 100,750 1,612,000
- Lampu Hallogen LED, 3 Watt bh 8 46,800 374,400
- Lampu Spotlight LED, 5 Watt bh 40 100,750 4,030,000
- Indirect Lamp LED Strip, 13 Watt/m m 76 19,500 1,482,000
- Saklar Tunggal bh 8 40,300 322,400
- Saklar Ganda bh 16 68,900 1,102,400
- Saklar Hotel bh 8 68,900 551,200
- Stop Kontak 1P Inbow 50 Watt bh 44 85,475 3,760,900
- Stop Kontak 1P Inbow 50 Watt (Stop Kontak Kerja) bh 4 85,475 341,900
- Air Conditioner bh 8 103,910 831,283 By.VAC
- Exhaust Fan Ceiling bh 8 103,910 831,283 By.VAC
- Keytag bh 4 103,910 415,642

4 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 64 305,561 19,555,904
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Penerangan Indirect d/kabel NYM 3 x 2,5 mm² ttk 15 305,561 4,644,527
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 48 305,561 14,666,928
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Air Conditioner d/kabel NYM 3 x 2,5 mm² ttk 8 305,561 2,444,488
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 8 305,561 2,444,488
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Keytag d/kabel NYM 3 x 2,5 mm² ttk 4 305,561 1,222,244
dlm PVC Conduit Ø 20 mm²

D LANTAI ATAP
1 Fixture / Armature Service Area
- Lampu T8 LED 1 x 18 Watt Tipe Balk bh 5 247,000 1,235,000
- Lampu T8 LED 2 x 18 Watt Tipe TKI bh 10 299,000 2,990,000
- Saklar Tunggal bh 1 38,350 38,350
- Saklar Ganda bh 1 66,300 66,300
- Stop Kontak 1P Inbow 100 Watt bh 4 85,475 341,900

2 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 15 305,561 4,583,415
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 4 305,561 1,222,244
dlm PVC Conduit Ø 20 mm²

E VILLA.1
1 Fixture / Armature Service Area
- Lampu Spotlight 5 Watt bh 14 100,750 1,410,500
- Lampu Downlight LED 3 Watt bh 2 46,800 93,600
- Lampu Sorot Taman LED 18 Watt bh 4 357,500 1,430,000
- Wall Lamp LED 10 Watt bh 4 130,000 520,000
- Lampu Underwater LED 50 Watt bh 0 - -
- Indirect Lamp LED Strip, 13 Watt/m m 14 19,500 273,000
- Saklar Tunggal bh 3 40,300 120,900
- Saklar Ganda bh 5 68,900 344,500
- Saklar Hotel bh 2 68,900 137,800
- Stop Kontak 1P Inbow 100 Watt bh 11 85,475 940,225
- Air Conditioner bh 1 103,910 103,910 By.VAC
- Exhaust Fan Ceiling bh 2 103,910 207,821 By.VAC
- Keytag bh 1 103,910 103,910

2 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 30 305,561 9,166,830
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Penerangan Indirect d/kabel NYM 3 x 2,5 mm² ttk 3 305,561 855,571
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 11 305,561 3,361,171
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Air Conditioner d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 2 305,561 611,122
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Keytag d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²

F VILLA.2.A
1 Fixture / Armature Service Area
- Lampu Spotlight 5 Watt bh 14 100,750 1,410,500
- Lampu Downlight LED 3 Watt bh 2 46,800 93,600
- Lampu Sorot Taman LED 18 Watt bh 4 357,500 1,430,000
- Wall Lamp LED 10 Watt bh 4 130,000 520,000
- Lampu Underwater LED 50 Watt bh 0 - -
- Indirect Lamp LED Strip, 13 Watt/m m 14 19,500 273,000
- Saklar Tunggal bh 3 40,300 120,900
- Saklar Ganda bh 5 68,900 344,500
- Saklar Hotel bh 2 68,900 137,800
- Stop Kontak 1P Inbow 100 Watt bh 11 85,475 940,225
- Air Conditioner bh 1 103,910 103,910 By.VAC
- Exhaust Fan Ceiling bh 2 103,910 207,821 By.VAC
- Keytag bh 1 103,910 103,910

2 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 30 305,561 9,166,830
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Penerangan Indirect d/kabel NYM 3 x 2,5 mm² ttk 3 305,561 855,571
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 11 305,561 3,361,171
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Air Conditioner d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 2 305,561 611,122
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Keytag d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²

G VILLA.2.B
1 Fixture / Armature Service Area
- Lampu Spotlight 5 Watt bh 14 100,750 1,410,500
- Lampu Downlight LED 3 Watt bh 2 46,800 93,600
- Lampu Sorot Taman LED 18 Watt bh 4 357,500 1,430,000
- Wall Lamp LED 10 Watt bh 4 130,000 520,000
- Lampu Underwater LED 50 Watt bh 0 - -
- Indirect Lamp LED Strip, 13 Watt/m m 14 19,500 273,000
- Saklar Tunggal bh 3 40,300 120,900
- Saklar Ganda bh 5 68,900 344,500
- Saklar Hotel bh 2 68,900 137,800
- Stop Kontak 1P Inbow 100 Watt bh 11 85,475 940,225
- Air Conditioner bh 1 103,910 103,910 By.VAC
- Exhaust Fan Ceiling bh 2 103,910 207,821 By.VAC
- Keytag bh 1 103,910 103,910

2 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 30 305,561 9,166,830
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Penerangan Indirect d/kabel NYM 3 x 2,5 mm² ttk 3 305,561 855,571
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 11 305,561 3,361,171
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Air Conditioner d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 2 305,561 611,122
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Keytag d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²

H VILLA.2.C
1 Fixture / Armature Service Area
- Lampu Spotlight 5 Watt bh 14 100,750 1,410,500
- Lampu Downlight LED 3 Watt bh 2 46,800 93,600
- Lampu Sorot Taman LED 18 Watt bh 4 357,500 1,430,000
- Wall Lamp LED 10 Watt bh 4 130,000 520,000
- Lampu Underwater LED 50 Watt bh 0 - -
- Indirect Lamp LED Strip, 13 Watt/m m 14 19,500 273,000
- Saklar Tunggal bh 3 40,950 122,850
- Saklar Ganda bh 5 68,900 344,500
- Saklar Hotel bh 2 68,900 137,800
- Stop Kontak 1P Inbow 100 Watt bh 11 85,475 940,225
- Air Conditioner bh 1 103,910 103,910 By.VAC
- Exhaust Fan Ceiling bh 2 103,910 207,821 By.VAC
- Keytag bh 1 103,910 103,910

2 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 30 305,561 9,166,830
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Penerangan Indirect d/kabel NYM 3 x 2,5 mm² ttk 3 305,561 855,571
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 11 305,561 3,361,171
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Air Conditioner d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 2 305,561 611,122
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Keytag d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²

I VILLA.3
1 Fixture / Armature Service Area
- Lampu Spotlight 5 Watt bh 30 100,750 3,022,500
lampu Hallogen 5 Watt bh 4 61,750 247,000
- Lampu Downlight LED 3 Watt bh 4 46,800 187,200
- Lampu Sorot Taman LED 18 Watt bh 4 357,500 1,430,000
- Wall Lamp LED 10 Watt bh 9 130,000 1,170,000
- Lampu Underwater LED 50 Watt bh 0 - -
- Indirect Lamp LED Strip, 13 Watt/m m 54 32,250 1,741,500
- Saklar Tunggal bh 2 40,300 80,600
- Saklar Ganda bh 9 68,900 620,100
- Saklar Hotel bh 4 68,900 275,600
- Stop Kontak 1P Inbow 100 Watt bh 35 85,475 2,991,625
- Air Conditioner bh 2 103,910 207,821 By.VAC
- Exhaust Fan Ceiling bh 2 103,910 207,821 By.VAC
- Keytag bh 1 103,910 103,910

2 Instalasi
- Instalasi titik Penerangan d/kabel NYM 3 x 2,5 mm² ttk 39 305,561 11,916,879
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Penerangan Indirect d/kabel NYM 3 x 2,5 mm² ttk 11 305,561 3,300,059
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Stop Kontak d/kabel NYM 3 x 2,5 mm² ttk 35 305,561 10,694,635
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Air Conditioner d/kabel NYM 3 x 2,5 mm² ttk 2 305,561 611,122
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Exhaust Fan d/kabel NYM 3 x 2,5 mm² ttk 2 305,561 611,122
dlm PVC Conduit Ø 20 mm²
- Instalasi titik Keytag d/kabel NYM 3 x 2,5 mm² ttk 1 305,561 305,561
dlm PVC Conduit Ø 20 mm²

I MATERIAL BANTU, Include : lot 1 94,384,489 94,384,489


- Hanger
- Support
- Accessories

SUB TOTAL III 1,065,589,736

IV PENANGKAL PETIR
- Penangkal Petir System Electrostatic System lightning Protection, radius
Set 100 Meter.
1 9,396,000 9,396,000
Lengkap Dengan Peralatannya ( Lighting Control Terminal,
Terminal Mounting Ring, Insulating Mast,Cooper Earth Tape ). Standard NFC 17-102
Bahan Stainless Steel Anti Karat

- Tahanan ≤ 2 Ohm

- Lampu Obstruction 60 Watt Lengkap Photoelectric Swtich Set 1 1,370,250 1,370,250

- Kabel Penghantar NYA 2 x 35 mm² m 26 133,625 3,474,244

- Photo Electrik Switch Unit 1 2,789,800 2,789,800

- Grounding Sistem + Bak Kontrol 400x400x600 mm² Lot 1 2,268,734 2,268,734

- Izin Depnaker Lot 1 3,594,559 3,594,559

- Material Bantu Lot 1 1,144,679 1,144,679

SUB TOTAL IV 24,038,265

TOTAL PEKERJAAN ELEKTRIKAL & PENANGKAL PETIR 2,173,251,814