ATTENDANCE
Present On Leave
Bids and Awards Committee
1. Merlie D, Membrere - Chairperson 1. Michelle M. Villanueva - Member
2. Natalia B. Dalaten - Vice-Chairperson 2. Junica Shiera F. Manicdao - Secretariat Member
3. Atty. Jennifer V. Peralta - Member
4. Jojie Corrine F. Ayson - Member
5. Joyce Anne S. Sabado - TWG Chairperson
6. Engr. Jonathan J. Laroza - TWG Member
7. Josie F. Quinit - TWG Member
8. Aple Madayag-Panes - Head, BAC Secretariat
9. Julie O. Ebreo - Secretariat Member
10. Jasmin U. Prades - Secretariat Member
Responsible
Agenda Topics/Issues/Concerns Raised/Discussed Agreements/ Recommendation
Unit/ Staff
1 Preliminaries PD Membrere called the meeting to order at 01:00 PM and presided the meeting after the
determination of a quorum.
2 Presentation and approval Ms. Panes presented the agenda as follows: Ms. Ayson recommended to include
of meeting agenda Presentation of Designation Orders for CY 2024 the following items in the agenda
Presentation of 2023 Accomplishments under “Other Matters”:
Updates on Early Procurement Activities Possible Training/ Seminar
Updates on the Submission of FY 2023 Reports for BAC
Responsible
Agenda Topics/Issues/Concerns Raised/Discussed Agreements/ Recommendation
Unit/ Staff
Other Matters Supplies of BAC
Revisiting the Functions of
the BAC
Annual Procurement Plan
for FY 2024
Office Order No. 008 - Reconstitution of the DTI Regional Bids and Awards
Committee - Technical Working Group
o Status quo
4 Presentation of 2023 Ms. Panes presented the accomplishments of the BAC for FY 2023 as follows: Posting of award notices at BAC Secretariat
Accomplishments PhilGEPS
Indicator Target Acco % Acco post approved BAC
No. of complete procurement plan consistent with 6 6 100% Resolution and Notice of
budget of the office/ agency, monitoring report and Award even without the
other PBB Compliance reports submitted within the confirmation of the winning
prescribed time bidder to comply with the 3
Percentage of procurement projects successfully 100% 100% 100% calendar days prescribed
processed/facilitated/completed/monitored within time in posting award
allowable time notices in the PhilGEPS
Percentage of Jos/Pos/Contracts submitted to COA 100% 97% 97% post approved contracts and
within prescribed time (within 5 days after issuance) Notice to Proceed (NTP)
Percentage of award notices posted within the 100% 50% 50% within 15 calendar days
prescribed time (15 CDs) after issuance of the NTP
No. of meetings facilitated/ conducted 100% 100% 100%
Responsible
Agenda Topics/Issues/Concerns Raised/Discussed Agreements/ Recommendation
Unit/ Staff
5 Status of Procurement Ms. Panes presented the following: Noted by the body
Projects for 2023
Status No. of Public No. of AMP
Bidding Projects projects
Awarded and completed delivery 1 38
Failed Bidding 2
Cancelled 1
All PhilGEPS posting were updated and awarded contracts were delivered before the year
2023 ended.
6 Updates on Early EPA for the renewal of lease contract for the five offices of DTI Region 1 was successfully Noted by the body
Procurement Activities undertaken. All notices of award were posted in the PhilGEPS
7 Updates on the Submission All due GPPB Reports and PBB Compliances were submitted to GPPB-TSO within the Noted by the body
of FY 2023 Reports prescribed time together with the pdf and excel files and Posting Certificate.
8 Other Matters Possible Training/ Seminar for BAC
The following are procurement training opportunities posted by AGIA: