Date: 16 July 18
Dear Sir,
We hereby submit the Development strategy report for formal approval. The document has been updated (as required) to suit the project &
URPL requirement. Document includes the following.
1) Introduction 2) Design 3) Procurement 4) Planning
5) Construction 6) H&S Quality 7) Communication
Revanth N
………………………… ………………………… …………………………… ………………
Name Designation Signature Date
S No. CONTENTS
1 Introduction
2 Design Management
3 Procurement Management
4 Resource Planning
5 Construction Management
7 Communication Protocol
3
1.0 INTRODUCTION
4
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Location: UNIVERSITY OF
HYDERABAD GOCL
KONDAPUR
Located in the Cyber district of
Gachibowli area of Hyderabad.
Situated on main Kondapur WHITEFIELD
AREA
road.
Surrounded by: IIIT
SILICON
VALLEY
HYDERABAD
Botanical garden on the NORTH
YOUSUFGUDA
Platina on the South East. GACHIBOWLI
RAIDURGAM
Hyatt Regency on the East.
Proposed 5-Star hotel on the
West. MANIKONDA
N
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Tower - B
Tower - A
Planter
Stepped
Landscape
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Botanika Tower A&B is a IGBC PLATINUM certified RCC structure Residential Apartment building located
in Gachibowli, Rangareddy District, Hyderabad with total Built-up area of 6,04,852 sqft and Saleable
area of 4,08,004 sqft.
Area Statement:
Site area : 3.33 acres
Scope of works for the Residential Apartment building constitute the following:
Structure
Consists of RCC structure from Foundation to Terrace, Blockwork, Plastering, Waterproofing, etc.
Facade Works
Consists of UPVC sliding doors, windows and ventilators and MS Railings up to 1m height for corridors
and balconies. Textured paint finish for external wall surfaces as per Architects design.
10
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Synergy accords high importance to intense interaction within the Design Team members.
Passenger Lifts
Tower A Tower B
No. of Lifts : 2 3
Capacity : 680 kg / 10 pax 680 kg / 10 pax
Speed : 1.75 mps 1.75 mps
No. of Stops : 4B+G+20 (25 stops) 4B+G+20 (25 stops)
Machine room : MRL (Machine Room Less) MRL (Machine Room Less)
Service Lifts
Tower A Tower B
No. of Lifts : 1 1
Capacity : 1020 kg 1020 kg
Speed : 1.75 mps 1.75 mps
No. of Stops : 1B+3P+G+20 (25 stops) 1B+3P+G+20 (25 stops)
Machine room : MRL (Machine Room Less) MRL (Machine Room Less)
PHE – M/s. Premier Engineering Consultants & Engineers would be required to provide :
Approval drawings / details, as required for submission to sanctioning authorities.
Recommendation of water and storage requirements, domestic water supply and irrigation systems.
Sewage, storm water and rain water disposal scheme.
Recommendation on selection of pumps with makes, specification, etc.
Recommendation on cut-out locations and size required for services penetration into RCC elements.
Recommendation on type of Sewage Treatment Plant and Water Treatment Plant.
Spatial requirements for various equipment, piping and distribution.
Centralized UG Tanks for full project with 2 days storage capacity in UG Tanks & 1/3rd days at
terrace level.
Main Sources of water is to be tapped from Municipal water supply line & bought out water shall
also be considered in absence of Municipal water.
Water Supply is through gravity system for all floors. In addition top three floors will have booster
pumps to maintain the required pressure.
Treated water supply for flushing through gravity system for all floors. In addition top three floors
will have booster pumps to maintain the required pressure.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
PHE Consultant – M/s. Premier Engineering Consultants & Designers would be required to provide :
Fire Fighting Static Water tank of 200 KLD is proposed.
Domestic Raw water UG sump of 100 KLD is proposed.
Domestic Treated water after softening UG sump of 100 KLD is proposed.
Domestic water over head tank of 25 KLD is proposed at Tower-A.
Treated Water over head tank only for flushing of 7 KLD is proposed at Tower-A.
Domestic water over head tank of 32 KLD is proposed at Tower-B.
Treated Water over head tank only for flushing of 10 KLD is proposed at Tower-D.
Centralized STP (Capacity: 140 KLD) for all towers has been proposed with Membrane Bio Reactor
(MBR) technology. STP treated water shall be used for flushing and irrigation.
Sanitary Fixtures and CP fittings (low flow) to meet IGBC requirements.
Refer Annexure 4 for approved DBR.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Fire fighting Consultant– M/s. Premier Engineering Consultants& Designers would be required to
provide :
Approval drawings / details, as required for submission to sanctioning authorities.
Inputs on approval related criteria / parameters - which can impact architectural design.
Recommendation of water and storage requirements.
Comments on architectural design on whether it is as per fire norms.
To confirm that all fire escape staircases meet fire norms.
HT panels
Equipment provided at point of Supply 11KV HT RMU Panel with 2No’s 630A VCB Incoming and 4 No’s
630A LBS outgoings
Transformers
Type of Enclosures Acoustic enclosure located inside the main building located
in basement floor level
Type of Controls AMF with PLC control, Auto start, auto synchronizing & auto
load sharing provision.
HVAC Consultant – M/s. BBN Escendo Consulting Pvt Ltd would be required to provide :
It is proposed to have VRF System for air conditioning of Flats.
Outdoor units of VRF system will be installed in the utility balcony. Hi wall indoor units are selected
for various rooms.
Cost Analysis and recommendation on system.
Configuration of systems for HVAC design.
Recommendation for Basement Ventilation scheme and fan sizing.
Spatial requirements for various equipment spaces - indoor and outdoor.
Interface details and other services.
26
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
3.1 Strategy
Packages that have the higher lead-time and those required on priority are recommended to be finalized
asap. These are:
The Consultants will be required to issue the Tender Documents for floating of package:
Elevators
Critical, since lead-time is very high.
In consultation with the Architect and in concurrence with Client, lift specifications and finishes
will be required to be finalized first.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
1 Excavation 24 Mar 18
3 Electrical 17 Nov 18
5 Plumbing 7 May 19
7 Elevators 30 Sep 19
9 HVAC 03 Dec 19
18 DG Sets 17 Apr 20
19 FAPA 23 Apr 20
Step 1
Pre-qualification: Contractors who have executed jobs of similar nature will be interviewed and pre-
qualified by Developer and Synergy. Workload and resource availability should be one of the key
factors for pre-qualification. Pre-qualification reports will be shared with Client.
Step 2
Client Approval: Final short-listing of each Package Vendor will then be done in consultation with the
Developer. The list will be firmed-up after receiving final approval from the Client.
Step 3
Final BoQ and technical specifications prepared by the Consultants will be reviewed and agreed prior to
issue of Tender. The tender document will then be prepared and issued by Synergy as per Tender
Schedule.
Step 4
On receipt of closed tenders from Tenderers, the same will be opened in Synergy office in the presence
of Developer Representative.
Step 5
The same shall be issued to the Developer during Tender Opening Event.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Step 6
Detailed Techno-Commercial negotiation will be held by Synergy . The Client may choose to attend.
Step 7
Based on final tender negotiation, name of recommended Vendor will be forwarded to the Developer.
This will be accompanied by a detailed Tender Recommendation Report, containing tender comparison
sheets, budget reconciliation, etc., will accompany this.
Step 8
On approval by the Developer, the Vendor for the Package will be finalized.
Step 9
Draft Notice of Award will also be sent to the Client. The Client will only be required to print the same
on the letterhead and issue to the finalized Contractor.
Refer Table on next page for flow chart on the entire tendering process.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Synergy to prepare:
By Synergy By Tenderers By Synergy
• Award reco
• Tender Report
• Final Tender
Comparisons
Approval by • Draft NoA
Universal
Realtors Pvt Ltd
Tender opening
Draft Tender BoQ,
Specs, Scope & Value Final Approval
Engg to be completed By URPL / Synergy
By URPL
By Synergy By Synergy
34
4.0 RESOURCE PLANNING
35
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
The following are the key issues which have been addressed while planning the construction:
Site logistics to proposes with minimum hindrance to existing facility.
Any restriction on RMC vehicular movement to be factored
Lift core area to start on priority for early roof top out.
LEED measures like tire wash and stilt pit to be considered.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
BOTANIKA
PHASE-I BIT-III
BOTANIKA
TOWER A&B
BIT-IV
RADISSON
DLF IT PARK HOTEL
N
37
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Rock Excavation :
Ensure design efficiency to reduce extent of excavation.
Basement Extent :
Adjacent to site boundary hence reducing space for construction logistics.
Construction Entry :
Direct entry to proposed project from main road.
Batching plant :
No space available to install batching plant for project.
Hoists :
Adequate deployment of Material Hoist
38
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Material Stockyard
Construction Access
Proposed BOTANIKA
Tower A&B
BOTANIKA Phase-I
39
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Tower crane
Inactive area
1 no. 50.0 M Tower
Crane
Tower crane
Steel Yard/Shuttering&
active area
Scaffolding Yard/
Material yard
QA/QC Lab
PMC/Client
office
DG Yard Tower-B
STP
Tower-A
Labor access point
Labor Toilet
Months 2 4 6 8 10 12 2 4 6 8 10 12 2 4 6 8 10 12 2 4 6 8 10 12
EXCAVATION
CONCRETE &
BLOCKWORK
MEP WORKS
INTERIOR
WORKS
COMMON
AREA FINISHES
LANDSCAPE/
EXTERNAL
DEVELOPMENT
HANDOVER /
CLOSEOUT
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Concrete pumps:
Sized for 80 meters head.
Recommended 2 + 1 number of concrete pumps.
Reinforcement steel:
Total steel quantity : 2,700 MT.
4.5 MT/day with Steel work duration of 20 months for tower area
1 Reinforcement yard is planned.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Cranes:
1 no. tower crane proposed as per site logistics (with 50m boom) to cover all the entire block.
The tower crane will be mainly used for transportation of reinforcements & form work material
shifting.
Hoists:
2 no. of material hoist is planned for building for the ease of movement of material.
5.0 CONSTRUCTION MANAGEMENT
45
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
The Contractor will be required to, in consultation with Synergy, break-up the detailed schedule into
further sub-activities for a day-to-day monitoring. This micro schedule is extremely effective to
expedite critical sub-structure works, like retaining wall formwork movement, etc..
Material Monitoring
A complete and detailed monitoring of critical construction material and equipment is key to successful
implementation of project. Monitoring of material is critical for structure package, and also for all MEP
Package.
All Contractors are required to fill-up the format, to enable Synergy to monitor progress.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Manpower Monitoring
Critical for effective monitoring of the package. Contractors to submit labor histograms, which will be
reviewed and certified by the Synergy Project Manager. The Contractor will also be required to submit a
“Daily Labour Return” on a daily basis sustaining manpower deployment plan.
Housekeeping
Housekeeping maintenance register to be regularly updated.
Construction materials to be stacked in designated areas only.
Driveway & vehicle access routes to be demarcated and clear of any obstruction.
Garbage bins to be at designated locations.
Scrap construction material to be stacked temporarily in designated locations.
Water spillage / stagnation to be cleared-off.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Preparation, issuing and monitoring of detailed Punch list for each and every page.
Certifying completion of the Punch list.
Monitor submission and approval of all Project handover documents from the Contractor, namely:
• As Built drawings
• List of tools and tackles
• Operation & Maintenance Manuals
• Test certificates
• Guarantee / Warrantee
• Attic Stock
• Training Manuals
• Issue of Final Completion Certificates, on behalf of the Client.
• Certification and recommendation of Contractor’s final bills.
In addition Synergy is responsible to liaison with all contractors for arranging As-Built drawings,
Operation and Maintenance Manuals, Test Certificates, Guarantees etc.. These will then be handed over
to the Client, as a part of comprehensive Project closeout exercise.
6.0 QUALITY & SAFETY
50
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
6.1 Quality
Safety and Quality has to be imbibed in the process and not only controlled at a particular step or an
event. Quality Control and Assurance is Synergy prime responsibility. Necessary Systems are in place for
maintaining and assuring required quality standards.
To ensure that the end quality is achieved, continuous involvement is required to ensure the same from
commencement to completion. Following practices assist in assurance of satisfactory quality levels.
6.1 QA / QC Cell
QA / QC & Safety Cell established at Head Office/ site office will conduct regularly audits on all aspects
of construction to ensure compliance to procedures and specifications. Independent audit is conducted
fortnightly or as required. Cell advices site team and interacts with Client and Contractor on regular
basis. The team has powers to stop and suspend work on issues pertaining to Quality and Safety.
Method Statement
Proper and correct execution methodology not only assures quality output but also helps in achieving
efficiency.
Agencies working at site are required to get their methodologies approved. Each agency is required to
submit method statement detailing the way in which they propose to execute the work. The same is
then reviewed and approved by competent authority.
Design Approval
Recognizing the importance of the same, strict design approval procedures have been laid for critical
activities. Any agency working on site is required to get the design approved before commencement of
works. Applicable for mix design of concrete, formwork or any critical activities.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
6.1 QA / QC Cell
Material Approval
Using proper material is essential for achieving desired quality standards. Agencies working at site are
required to get the materials approved. Each agency is required to submit Material Approval Request for
various materials proposed to be used by them. The same are then reviewed and approved.
Mock-up
Mock-ups are the first critical activities at start of any Package works. Mock up provides assistance in
following areas:
Examining the practicality of design wrt execution
Foreseeing problems associated beforehand.
Working out the ways to counter the same.
Checklist
For assisting checking of various critical parameters during execution, checklists for activities have been
drawing out. This ensures that none of the parameters or stage checks are missed out. Pour card is also
an important checklist which gets signed off.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
6.1 QA / QC Cell
Non-Compliance Report (NCR)
If the finished product is not matching the quality criteria laid down, a NCR is issued to the concerned
agency by the Engineer-in-Charge.
A NCR is closed after the Engineer-In-Charge issuing the NCR is satisfied with rectification of Non-
conformity. The work is treated as incomplete for all purposes till the NCR has not been closed.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
6.2 Safety
Synergy is committed to ensure safe working conditions throughout the Project period. Contractors are
obliged to implement Synergy health and safety manual.
Refer attachment 9: EHS policy (Safety manual is part of all construction Contracts and hence not
enclosed as a part of this Report)
Project Manager is empowered to instruct contractor to stop work in any situation where circumstances
or method of working constitutes a threat to personal safety.
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
Implemented Implemented
57
BOTANIKA TOWER A&B, HYDERABAD
DEVELOPMENT STRATEGY REPORT
To ensure seamless communication and better Project Co-ordination on Design and Execution, Synergy
should be Single Point Contact between Consultant / Contractor and Client. This will be an effective tool
for implementation of the first-to-last approach and on behalf of Client, Synergy will deliver as a Single
responsible agency. This is important to achieve key objective of excellence in design, execution,
financial return and satisfaction.
Reporting
Synergy shall provide regular weekly & monthly status reports to Client highlighting the progress of the
project, performance of project against each package works, approved budgets, update / monitoring on
monthly payments, provide regular update on risk related issues.