Professional Documents
Culture Documents
• Waterproofing defined
• Importance
• Methods ( Conventional )
• Methods ( Modern)
• Waterproofing of Basements
• Terraces
• Bathrooms & W C
• Chemicals used for waterproofing treatment
• Role of Consultants
Background
• The most widely and effectively used construction
material in world today is concrete, beside steel and
wood.
• Making good concrete in the laboratory is not at all
difficult.
• But at the site, it is possible to make concrete
waterproof.
• Ideally, the concrete is supposed to be watertight, if it
is done in a manner in which all the parameters are
followed strictly.
• But, in practice, concrete is quite porous
Waterproofing Meaning
• “Any system or material(s), which helps in preventing
ingress of water into structures can be broadly termed as
waterproofing.
FLOOR TREATMENT
Before starting the treatment ensure that the P.C.C concrete is done on a wall
completed / strong substrate.
1. Clean the floor area thoroughly with wire brushing, washing , chipping etc.
to expose the hard surface.
2. Prepare mortar of waterproof under lay as below •Cement : sand ( 1:4 )
3. Admixed the cement sand mortar with chemical i.e DICHTAMENT DM @
200 gms per bag of cement .
4. Now , lay the admixed C.M 1:4 on the cleaned in surface as an under lay (25
mm to 30 mm thick)
5. Lay the Shahabad ( 2' o" X 1.5/or 2.00”X 2.00" ) on the wet underlay with
staggered joints keeping the width of the joints between 25mm
Methodologies
1. Next day or later on -Clean the joints between the shahabad & fill
the recesses with washing clean aggregates ( 10 mm size to 25 mm
i.e graded )
2. Prepare grout slurry as below . Cement : Water : non -shrink
admixture ( Einpresshil powder 1.5 kg + 0.5%per bag of cement.
3. Pour the grouting slurry into the joint of tile and flush the joint
filling full now the surface is ready to receive Top Overlay.
4. Make the top overlay mortar same as underlay i.e C.M . 1:4 +
admixture as.(a) DICHTAMENT DM@ 200 gms/per bag of cement .
5. Lay the top overlay mortar on top of Shahabad tile floor and smooth
finish or keep surfaced i.e fine broom or tile finish or as directed.
6. Cure the floor by ponding water for at least 7 day's . This completes
the treatment on floor.
7. After curing the floor can be used to lay RCC Raft.
Methodologies
• Wall Treatment
This treatment is to be done after the RCC floor ( Raft ) & RCC walls
are cast .
1. Surface preparation is to be done after the RCC floor ( Raft) & RCC
wall are cast, loose slurries , timber embedment's protruding nail or
binding wire etc. and wire-brush the surface ready for the treatment. If
any through-holes are kept for formwork, they should be grouted with
non shrink grout.
2. Now lay Shahabad tile to the wall with cement paste tabs of
approximately 2" to 4: Φ and press and fix tile keeping ½" clear gap
between RCC wall & tile surface ( This gap is required for slurry
grouting)
3. Ensure that only one layer of tiles are fixed with staggered joints with
joint widths 15 mm to 20 mm.
4. Ensure that only one layer of tile is done every day.
5. The joints between lad is should be filled up with cement paste with non
-shrink admixture i.e. EH @ 0.5% by cement .
Methodologies
1. Grouting of gap between tile & RCC wall ( Prepare the slurry grout as )
Cement + water +Einpresshilfe EH ( Non shrink chemical) 1: 4 : 0.5% by
cement wt. (1/4 kg per bag of cement ) Now pour this grout into the gap
between the tile & RCC wall. Continue pouring till it is full.Allow it to set
for 6 to 8 hrs. or more as the case may be.
2. After sizable area of tile fixing is done ( say up to a ht of 6' or so ; then it is
ready to receive a dash coat ( which is required for bonding of water proof
jacket as a finishing coat .
3. Dash coat ( chat ) lay a rough cost or dash coat of C :M 1:3 .
4. Next day - cure the are by sprinkling water for 2 or 3 days.
Water proofing jacket plaster :-
This is a finishing waterproof plaster on wall - tile- cladding & is done in
C: M 1:4 admixed with (a) DICHTAMENT DM @ 200 gms per bag of
cement .
CURE THE AREA for a minimum period of 7 days.
Box Type Waterproofing
Box Type Waterproofing ( Basement waterprofing)
Limitations/Disadvantages
• Use of Shahabad tiles, joints should be grouted properly or else the
leakage would be from the joints.
• It is a labour intensive work for which it requires more time for
installation
• Waterproofing membrane such as Bituminous, polymer modified
bituminous of APP (Atactic Poly Propylene) SBS (Styrene Butadine
Styrene), PVC, HDPE can be used for basements.
• Since APP membrane is torch applied, it requires more skilled
labour and a protective screed to avoid any damages to the
membrane.
• SBS is cold applied by simply sticking with a paste. But it is not
suitable for high water table. It also requires a screed for protection
• HDPE is the best material for waterproofing in high water table.
Modern Techniques in Waterproofing
• Modern technique aims to understand the functional
behavior of the structure, understand the properties of
the available materials to arrive at a system, which is
best suited for the structure and incorporate the design
stage itself.
• A single product or technique is not usually enough,
involvement of various bodies and techniques in
coordination is essential for making structures
waterproof.
• For success of any system, the building structure should
have sufficient and efficient control joints if the slabs
dimensions are more than twenty meter in any
direction.
• Crystalline Waterproofing System
• Flexible membrane waterproofing system
Crystalline Waterproofing System
• The method of treatment involves saturating with water the
surface to be treated.
• Then mixing two and half volume of the powder with one
volume of water to form neat consistency hot slurry.
• This slurry is brush applied on the saturated surface. The
active ingredients in the slurry pass through the water
bearing capillaries and react with calcium oxide present in
the concrete to form insoluble crystals, which effectively
block the capillaries.
• Further the chemical ingredients of the product remain in
concrete to reactivate the process of crystallisation and
when a new capillary is developed.
• This system of waterproofing, the water retaining structures
is practiced in most of the developed countries
Crystalline Waterproofing System
• The waterproofing effect is based on two simple reactions, one chemical
and one physical. Concrete is chemical in nature. When a cement particle
hydrates, the reaction between water and the cement causes the concrete
to become a hard, solid mass.
• The reaction also generates chemical by-products such as calcium
hydroxide, sulfates and carbonates of sodium potassium and calcium as well
as un-hydrated or partially hydrated cement particles all of which reside in
the capillary tracts of the concrete.
• Crystalline waterproofing introduces another set of chemicals to the
concrete. When these two chemical groups, the by-products of cement
hydration and the crystalline chemicals, are brought together in the
presence of moisture, a chemical reaction occurs. The end product of this
reaction is a non-soluble crystalline formation.
• This crystalline formation can only occur where moisture is present, thus it
will only form in the pores, capillary tracts, and shrinkage cracks of the
concrete. Wherever water goes, crystalline waterproofing will form filling
the pores, voids and cracks.
Crystalline Waterproofing System
• Cracks if any should be cut into ‘V’ shaped grooves one inch wide and
proper size width & depth Cut honey combed areas back to sound concrete.
• Repair these areas first by priming with crystalline waterproofing slurry and
then by filling them with crystalline modified mortar produced by mixing
crystalline waterproofing powder OPC and zone II sand in the proportion of
1:1:4 and water enough to produce a stiff consistence paste. Allow the
repair mortar to dry.
• Thoroughly sprinkle water on the area to be treated till the surface
becomes saturated. Some recommend overnight ponding for effective
results
• Prepare crystalline waterproofing slurry by mixing the powder and water in
the proportion of two and half volume of powder to one volume of water to
form a hot slurry. Brush apply this slurry on the water saturated surface in
two coats.
• When the second coat is still wet plaster the surface with 1 : 4 cement sand
mortar admixed with an integral waterproofing compound and cure
properly.
Flexible Membrane Waterproofing System
• The main product used in this system, comprises two
components one liquid and the other is a powder packed roughly
in the proportion of 1:4 by weight. The liquid component is an
acrylic emulsion and the powder component is a polymer-
modified cement with film forming chemicals and fillers
• When these two ingredients namely the pre-weighed powder
and the liquid are mixed together an uniform slurry results.
• This slurry is brush applied on the roof surface, which upon drying
forms a flexible film. Since there is cement in this product, its
compatibility with concrete is excellent.
• The film further allows the breathing of the concrete without any
hindrance hence there is no problem of its de-lamination from
the concrete surface.
• This film being flexible takes care of the deflections in the slab
and the movements caused because of primary or secondary
settlements, movements due to wind loads and temperature
stresses developed in the concrete
Flexible Membrane Waterproofing System
• Cracks if any should be cut into ‘V’ shaped grooves of
a proper size in depth. Cut honey combed areas back
to sound concrete.
• Repair these areas with a stiff paste of fibre reinforced
polymer repair mortar generally sold in the name of
crack fill.
• Mix the powder and the liquid components of the
product to form an uniform slurry and brush apply
this slurry on the surface to be waterproofed.
• When the waterproofing coating is still tacky apply 1 :
4 cement sand screed and cure normally
Coating not an easy way to waterproofing
• Podiums are structures that may contain a combination of trafficable surfaces (cars, fire
tenders, pedestrian / cycling pathways and other similar abrasive loads), garden / plantation
areas and other general public use areas.
• Waterproofing driven on podiums is the biggest challenge in a successful waterproofing
program for a building. Normally the waterproofing systems used are highly elastomeric in
nature, which makes them unsuitable in traffic conditions for abrasion resistance. Under traffic
loads, the applied membranes often fail, leading to costly repairs.
• The inherent problem here, is that the elastomeric waterproofing system is applied to the bare
slab and covered with a floating wearable screed that acts both as protection to the
waterproofing and a means to providing a slope. Casting this screed layer and the vacuum
dewatering process used to enhance the abrasion resistance, causes the screed layer to crack.
Further traffic movements cause the cracks to widen and eventually allow water ingress into
the system, which further causes waterproofing problems below the podium slab. This damage
mechanism is seen in driven-on podiums as well as in car park structures.
• Further effects of this damage mechanism are that water along with dripping car fluids / oils,
fuel and the abrasive loads, cause damage to the resin-based waterproofing system under the
screed, allowing penetration of water through the podium slab and the areas below.
• In roof gardens, the damage from the roots of growing plantations, damage the waterproofing
system, allowing penetration of water through the podium slab and the areas below.
The Solution Trafficable Podiums
4. Design Flaws
• When large size unprotected openings are provided
in the rain beating side, consider junctions
• Staircase landings should be well protected from
spilling over of rain water through the ventilation
openings
• The members of the R.C.C. grid designed with joints
and junctions are required to be properly covered.
LIST OF SOME RELEVANT INDIAN STANDARD