Professional Documents
Culture Documents
SPEC's ITEM
NO. Description Unit Qty Unit Cost Amount
CHECKED BY:
ATTY. SUZETTE A . MAMON
MA. EVELYN G. RIVERA Acting Provincial Administrator
Engineer III
PART A - EARTHWORKS
IV. Embankment from Structure Excavation 31.20 cu.m 10,590.00 1,270.80 1,059.00 22.00%
II. Reinforcing Steel (Grade 40) #REF! kgs #REF! #REF! #REF! 22.00%
III. Formworks and Falseworks #REF! sq.m. #REF! #REF! #REF! 22.00%
IV. Doors and Windows Installation 82.33 sq.m. 164,287.80 19,714.54 16,428.78 22.00%
VIII. Structural Steel Roof Framing 1.00 L.S 155,295.30 18,635.44 15,529.53 22.00%
PART D - ELECTRICAL
- - - - -
I. SITEWORKS
20.00 pcs 2" x 2" x 12' Coco lumber (10pcs) P 135.00 /pc P 2,700.00
8.00 kgs Assorted CWN (2",3",4") P 57.00 /kg P 456.00
5.00 rolls 1/8" x 100m Nylon String P 30.00 /roll P 150.00
Sub-total P 3,306.00
Labor:
1 Construction Foreman 660.00 /day for 1.00 day P 660.00
2 Laborer 361.00 /day for 1.00 day P 722.00
Sub-total P 1,382.00
B. EARTHWORKS
QTY = 109.70 cu.m.
B. PLASTERING WORKS
Total Area = #REF! sq.m.
Materials:
#REF! bags Portland Cement P 279.00 /bag P #REF!
#REF! cu.m. Washed sand P 700.00 /cu.m. P #REF!
Sub-total P #REF!
Labor:
1 Project Engineer 400.00 /day for 9.00 days P 3,600.00
1 Construction Foreman 400.00 /day for #REF! days P #REF!
2 Mason 325.00 /day for #REF! days P #REF!
4 Laborers 275.00 /day for #REF! days P #REF!
Sub-total P #REF!
V. STEEL WORKS
Qty = 1.00 Lot
Materials:
#REF! pcs. 5mm THK 38mmX38mm Angle Bar P 804.00 /pc. P #REF!
10.00 kgs. Welding Rod P 125.00 /kg. P 1,250.00
5.00 pcs. 4" Cutting Disk for steel P 80.00 /pc. P 400.00
3.00 pcs. 1/8" 6m Flat Bar P 190.00 /pc. P 570.00
14.00 pcs. 12mmØ x 4" expansion bolt P 60.00 /pc. P 840.00
Sub-total #REF!
Labor:
1 Project Engineer 550.00 /day for 2.00 days P 1,100.00
1 Construction Foreman 400.00 /day for 2.00 days P 800.00
1 Welder 325.00 /day for 2.00 days P 650.00
2 Laborer 275.00 /day for 2.00 days P 1,100.00
Sub-total P 3,650.00
Equipment Rental:
1 Welding Machine 300.00 /day for 2.00 days P 600.00
1 Cut - off Machine 300.00 /day for 2.00 days P 600.00
Sub-total P 1,200.00
B. PAINTING WORKS
Concrete Surfaces = #REF! sq.m.
Metal Surfaces = #REF! sq.m.
Floor Surfaces = #REF! sq.m.
Materials:
#REF! gals Concrete Primer and Sealer P 465.00 /gal P #REF!
#REF! gals Megacryl Latex Semi-gloss - 1 coat P 465.00 /gal P #REF!
#REF! gals Megacryl Latex Semi-gloss - 1 coat P 465.00 /gal P #REF!
#REF! gals Aqua Shield Plus (Waterproofing) P 320.00 /gal P #REF!
6.00 pcs. Paint Roller P 120.00 /pc P 720.00
6.00 pcs. Paint Brush 4" P 64.00 /pc P 384.00
ITEM QTY. UNIT DESCRIPTION UNIT COST TOTAL COST
For Ficem Board Surfaces
4.00 gals Paint Thinner P 342.00 /gal P 1,368.00
5.00 pcs. Paint Brush 4" P 64.00 /pc P 320.00
#REF! gals Galvanized Wash Primer P 670.00 /gal P #REF!
#REF! gals Metal Primer-Red Oxide P 375.00 /gal P #REF!
1.00 gals Paint Thinner P 342.00 /gal P 342.00
2.00 pcs. Paint Brush 4" P 64.00 /pc P 128.00
Sub-total P #REF!
Labor:
1 Project Engineer 550.00 /day for 1.00 days P 550.00
1 Construction Foreman 400.00 /day for 3.00 days P 1,200.00
3 Painter 325.00 /day for 3.00 days P 2,925.00
3 Laborer 275.00 /day for 3.00 days P 2,475.00
Sub-total 7,150.00
C. WINDOW INSTALLATION
Total Area = #REF! sq.m.
Materials:
#REF! pcs. 12" x 12" Concrete Louver Blocks P 40.50 /pc. P #REF!
#REF! bags Portland Cement P 279.00 /cu.m. P #REF!
#REF! cu.m Washed Sand P 700.00 /cu.m. P #REF!
Sub-total P #REF!
Labor:
1 Construction Foreman 400.00 /day for 3.00 days P 1,200.00
2 Mason 325.00 /day for 3.00 days P 1,950.00
4 Laborers 275.00 /day for 3.00 days P 3,300.00
Sub-total P 6,450.00
D. DOOR INSTALLATION
Materials:
4 set - 2.8m x 2.1m Roll-up Door with complete accessories P 12,500.00 /set P 50,000.00
Sub-total P 50,000.00
NOTE: Price Indicated includes installation fee and with complete accessories
E. SPECIAL ITEMS
Materials:
4.00 pcs. 0.40m x 0.40m Exhaust Fan P 4,000.00 /gal P 16,000.00
Sub-total P 16,000.00
NOTE: Price Indicated includes installation fee and with complete accessories
Sub-total P #REF!
Labor:
1 Construction Foreman 400.00 /day for 1.00 days P 400.00
2 Laborers 275.00 /day for 1.00 days P 550.00
Sub-total P 950.00
ITEM QTY. UNIT DESCRIPTION UNIT COST TOTAL COST
B. CONCRETE WORKS
Qty = #REF! cu.m
Materials:
#REF! bags Portland Cement P 279.00 /bag P #REF!
#REF! cu.m Washed sand P 700.00 /cu.m P #REF!
#REF! cu.m Screened Gravel P 900.00 /cu.m P #REF!
20 bd. ft 2" x2" X12' Coco Lumber (5pcs) P 28.00 / bd.ft P 560.00
5.00 kgs Assorted CW Nails (2",3",4",5") P 65.00 /kg P 325.00
#REF! pcs 10mmØ x 6m RSB P 149.25 /pc P #REF!
7.00 kgs #16 G.I. Tie Wire P 90.00 /kg P 630.00
Sub-total P #REF!
Labor:
1 Construction Foreman 400.00 /day for 3.00 days P 1,200.00
2 Masons 325.00 /day for 3.00 days P 1,950.00
4 Laborers 275.00 /day for 3.00 days P 3,300.00
Sub-total P 6,450.00
C. MASONRY WORKS
Materials: Qty = #REF! cu.m
#REF! pcs. 4" CHB P 15.00 /pc P #REF!
#REF! bags Portland Cement P 279.00 /cu.m. P #REF!
#REF! cu.m Washed Sand P 700.00 /cu.m. P #REF!
#REF! pcs. 10mmØ x 6m RSB P 149.25 /pc P #REF!
Sub-total P #REF!
Labor:
1 Construction Foreman 400.00 /day for 2.00 days P 800.00
2 Mason 325.00 /day for 2.00 days P 1,300.00
4 Laborers 275.00 /day for 2.00 days P 2,200.00
Sub-total P 4,300.00
D. PLUMBING WORKS
Materials: Qty = 1.00 cu.m
#REF! pcs. 75mm PVC Pipe P 483.00 /pc P #REF!
#REF! pcs. 100mm PVC Pipe P 650.00 /pc P #REF!
12 pcs. PVC 90Deg Elbow P 97.00 /pc P 1,164.00
3 cans. Pipe Solvent (200cc) P 129.00 /can P 387.00
6 pcs. Stainless Floor Drain P 100.00 /pc P 600.00
Sub-total P #REF!
Labor:
1 Construction Foreman 400.00 /day for 2.00 days P 800.00
1 Plumber 325.00 /day for 2.00 days P 650.00
2 Laborers 275.00 /day for 2.00 days P 1,100.00
Sub-total P 2,550.00
ITEM NO. DESCRIPTION MATERIAL COST LABOR COST EQUIPMENT COST/RENTAL TOTAL COST
II. SITEWORKS
A. LAYOUT AND STAKING 3,306.00 1,382.00 4,688.00
B. EARTHWORKS #REF! 12,300.00 #REF!
III. CONCRETE WORKS #REF! 54,600.00 22,092.00 #REF!
ITEM ESTIMATED MARK-UPS IN PERCENT (%) TOTAL MARK-UP VAT TOTAL TOTAL UNIT
DESCRIPTION QTY. UNIT
NO. DIRECT COST OCM PROFIT % VALUE INDIRECT COST COST COST
(6) (7) (8) (9) (10) (11) (12)
(1) (2) (3) (4) (5) (13)
#REF! 10% #REF! (5) x (8) (5) + (9) x (5%) (9) + (10) (5) + (11)
1. #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
5 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
6 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
7 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
8
9
10
GRAND TOTAL #REF! #REF! #REF! #REF! #REF! #REF! #REF!
MARIAH KATHY D. DE OCAMPO JEB A. ESCARILLA ROMEO C. ANDIG GRACIANITO L. LUCERO, MM, CESE
Engineering Assistant Engineer IV PGADH-PEO PGDH-PEO
Project Title: #REF!
Location: #REF!
BACK UP COMPUTATION
II. SITEWORKS
A. LAYOUT AND STAKING
Item No. of Set Length Width
Main Building 1 10.00 15.00
Plant Box 2 1.50 4.00
Ramp 2 1.20 6.70
Front Stair 1 0.60 6.30
Total Area
B. EARTHWORKS
A. Excavation
Item No. of Set Length Width Height
Column Footing 23 1.50 1.50 1.60
Stiffener Column 4 0.50 0.50 0.95
Between Line3&4 WF1 (H) 1 1.40 0.40 0.70
Along Line 4 WF1 (H) 2 1.20 0.40 0.70
(Plant Box) 2 7.00 0.40 0.70
( Ramp ) 2 9.10 0.40 0.70
( Front Stair - WF2 ) 1 6.30 0.30 0.50
Along Line A (V) 2 0.60 0.30 0.70
Between Line A & B (V) ( WF1) 1 1.45 0.40 0.70
Stair Footing 1 1.20 0.60 0.65
Footing Tie Beam
Along Line 1 (H) (15-(5*1.5))=7.5 1 7.50 0.25 0.80
Along Line 2 (H) (2*(3-1.5))=3 1 3.00 0.25 0.80
Along Line 3 (H) (15-(5*1.5))=7.5 1 7.50 0.25 0.80
Along Line 4 (H) (15-(5*1.5))=7.5 1 7.50 0.25 0.80
Along Line A (V) (10-(3*1.5))=5.5 1 5.50 0.25 0.80
Along Line B (V) (10-(3*1.5))=5.5 1 5.50 0.25 0.80
Along Line C (V) (2*(3-1.5))=3 1 3.00 0.25 0.80
Along Line D (V) (2*(3-1.5))=3 1 3.00 0.25 0.80
Along Line E (V) (3-1.5) = 1.5 1 1.50 0.25 0.80
Along Line F (V) (10-(3*1.5))=5.5 1 5.50 0.25 0.80
Concrete Slab 1 15.00 10.00 0.10
Concrete Canopy Foundation 5 0.40 0.60 0.70
Total Volume for excavation
B. BACKFILL
Item No. of Set Length Width Height
volume excavated
Deductive Volume (structure)
Column Footing 23 1.50 1.50 0.40
Column 23 0.30 0.30 1.20
Stiffener Column ( Footing ) 4 0.50 0.50 0.30
Stiffener Column 4 0.10 0.30 0.40
Between Line3&4 WF1 (H) 1 1.40 0.40 0.30
( Masonry above ) 1 1.40 0.10 0.40
Along Line 4 WF1 (H) 2 1.20 0.40 0.30
( Masonry above ) 2 1.20 0.10 0.40
(Plant Box) 2 7.00 0.40 0.30
( Masonry above ) 2 7.00 0.10 0.40
( Ramp ) 2 9.10 0.40 0.30
( Masonry above ) 2 9.10 0.10 0.40
( Front Stair - WF2 ) 1 6.30 0.30 0.30
Project Title: #REF!
Location: #REF!
( Masonry above ) 1 6.30 0.10 0.20
Along Line A (V) 2 0.60 0.30 0.30
( Masonry above ) 2 0.60 0.10 0.20
Between Line A & B (V) ( WF1) 1 1.45 0.40 0.30
( Masonry above ) 1 1.45 0.10 0.40
Stair Footing 1 1.20 0.60 0.40
1 1.20 0.15 0.25
Footing Tie Beam
Along Line 1 (H) 1 7.50 0.25 0.40
Along Line 2 (H) 1 3.00 0.25 0.40
Along Line 3 (H) 1 7.50 0.25 0.40
Along Line 4 (H) 1 7.50 0.25 0.40
Along Line A (V) 1 5.50 0.25 0.40
Along Line B (V) 1 5.50 0.25 0.40
Along Line C (V) 1 3.00 0.25 0.40
Along Line D (V) 1 3.00 0.25 0.40
Along Line E (V) 1 1.50 0.25 0.40
Along Line F (V) 1 5.50 0.25 0.40
Concrete Slab 1 15.00 10.00 0.10
Concrete Canopy Foundation 5 0.40 0.60 0.35
( Masonry Above ) 5 0.40 0.40 0.35
Total of Deductive Volume
Filing Materials from excavated Structures 121.70 - 51.39 =
FILLING MATERIALS
Item No. of Set Length Width Height
Main Building 1 15.00 10.00 0.35
Ramp
Front Stairs
Total Volume of 2
Total Volume of Filling Materials = 70.31 + 53.55 =
Shrinkage Factor
Total Volume
Volume To be Borrowed = ( 75% of Cut Materials - Volume of Filling Materials needed )
= 75 % ( 121 ) - 155 = 64.25
GRAVEL BEDDING
Item No. of Set Length Width Height
Column Footing 23 1.50 1.50 0.10
Stiffener Column 4 0.50 0.50 0.10
Between Line3&4 WF1 (H) 1 1.40 0.40 0.10
Along Line 4 WF1 (H) 2 1.20 0.40 0.10
(Plant Box) 2 7.00 0.40 0.10
( Ramp ) 2 9.10 0.40 0.10
( Front Stair - WF2 ) 1 6.30 0.30 0.10
Along Line A (V) 2 0.60 0.30 0.10
Between Line A & B (V) ( WF1) 1 1.45 0.40 0.10
Stair Footing 1 1.20 0.60 0.10
Concrete Slab 1 15.00 10.00 0.10
Concrete Canopy Foundation 5 0.40 0.60 0.10
Total Volume
III. CONCRETE WORKS
Item 900 (1)c2 : Footing and Slab on Fill
Item No. of Set Length Width Height
Column Footing 23 1.50 1.50 0.30
Stiffener Column ( Footing ) 4 0.50 0.50 0.20
Project Title: #REF!
Location: #REF!
Between Line3&4 WF1 (H) 1 1.40 0.40 0.20
Along Line 4 WF1 (H) 2 1.2 0.40 0.20
(Plant Box) 2 7.00 0.40 0.20
( Ramp ) 2 9.10 0.40 0.20
( Front Stair - WF2 ) 1 6.30 0.30 0.20
Along Line A (V) 2 0.6 0.30 0.20
Between Line A & B (V) ( WF1) 1 1.45 0.40 0.20
Stair Footing 1 1.20 0.60 0.30
1 1.20 0.15 0.90
Concrete Slab 1 15.00 10.00 0.10
Concrete Canopy Foundation 5 0.40 0.60 0.25
Canopy ( Ground Floor ) 1 26.70 0.60 0.10
3 1.40 0.60 0.10
1 9.00 0.60 0.10
Canopy ( Second Floor ) 1 36.20 0.60 0.10
1 3.00 0.60 0.10
Total Volume
Item No. of Set Length Width Height
Item 900 (1)
Column ( Ground ) 23 0.30 0.30 5.25
Column ( Second ) 21 0.30 0.30 5.30
Stiffener Column 4 0.10 0.30 7.45
Along Line A (V) 1 5.50 0.25 0.20
Footing Tie Beam
Along Line 1 (H) 5 3.00 0.25 0.40
Along Line 2 (H) 2 3.00 0.25 0.40
Along Line 3 (H) 5 3.00 0.25 0.40
Along Line 4 (H) 5 3.00 0.25 0.40
Along Line A (V) 3 3.00 0.25 0.40
Along Line B (V) 3 3.00 0.25 0.40
Along Line C (V) 2 3.00 0.25 0.40
Along Line D (V) 2 3.00 0.25 0.40
Along Line E (V) 1 3.00 0.25 0.40
Along Line F (V) 3 3.00 0.25 0.40
Lintel Beams ( Above FTB )
Along Line 1 (H) 5 3.00 0.30 0.10
Along Line 2 (H) 2 3.00 0.30 0.10
Along Line 3 (H) 5 3.00 0.30 0.10
Along Line 4 (H) 5 3.00 0.30 0.10
Along Line A (V) 3 3.00 0.30 0.10
Along Line B (V) 3 3.00 0.30 0.10
Along Line C (V) 2 3.00 0.30 0.10
Along Line D (V) 2 3.00 0.30 0.10
Along Line E (V) 1 3.00 0.30 0.10
Along Line F (V) 3 3.00 0.30 0.10
Lintel Beams ( Above WF1 )
Between Line 3&4 (H ) 1 1.40 0.30 0.10
Between Line A & B 1 1.45 0.30 0.10
Floor Beam 1 10 3.50 0.30 0.40
25 3.00 0.30 0.40
Floor Beam 2 2 3.50 0.30 0.50
Floor Beam 3 2 3.00 0.25 0.40
2 1.50 0.25 0.40
1 1.00 0.25 0.40
Project Title: #REF!
Location: #REF!
Second Floor Slab 1 7.00 15 0.125
1 3.00 11 0.125
Roof Beam 1 2 3.50 0.30 0.40
7 3.00 0.30 0.40
Roof Beam 2 4 3.50 0.30 0.50
2 3.00 0.25 0.40
Total Volume
Volume
82.80
0.95
0.40
0.68
3.92
5.10
0.95
0.26
0.41
0.47
1.50
0.60
1.50
1.50
1.10
1.10
0.60
0.60
0.30
1.10
15.00
0.84
121.70
Volume
121.70
20.70
2.49
0.30
0.05
0.17
0.06
0.29
0.10
1.68
0.56
2.19
0.73
0.57
0.13
0.11
0.03
0.18
0.06
0.29
0.05
0.75
0.30
0.75
0.75
0.55
0.55
0.30
0.30
0.15
0.55
15.00
0.42
0.28
51.39
70.31
Volume
52.50
0.58
0.47
53.55
123.86
25%
154.83
cu.m.
Volume
5.18
0.10
0.06
0.10
0.56
0.73
0.19
0.04
0.06
0.07
15.00
0.12
22.19
Volume
15.53
0.20
0.11
0.19
1.12
1.46
0.38
0.07
0.12
0.22
0.16
15.00
0.30
1.60
0.25
0.54
2.17
0.18
34.85
Volume
10.87
10.02
0.90
0.28
1.50
0.60
1.50
1.50
0.90
0.90
0.60
0.60
0.30
0.90
0.45
0.18
0.45
0.45
0.27
0.27
0.18
0.18
0.09
0.27
0.05
0.05
4.20
9.00
1.05
0.60
0.30
0.10
13.13
4.13
0.84
2.52
2.10
0.60
72.82
no. of pcs
109.00
183.00
147.00
157.00
134.00
3.00
21.00
17.00
no. of pcs
27.00
no. of pcs
12.00
no. of pcs
98.00
no. of pcs
125.00
no. of pcs
51.00
no. of pcs
36.00
no. of pcs
176.00
no. of pcs
28.00
no. of pcs
1.00
1.00
2.00
12.00
57.00
4.00
11.00
6.00
no. of pcs
369.00
64.00
no. of pcs
247.00
no. of pcs
Area
169.05
155.82
113.00
No. Of pcs
265.00
244.00
91.00
83.00
Area
29.80
11.00
No. Of pcs needed
66.00
57.00
Area
17.25
6.90
17.25
17.25
10.35
10.35
6.90
6.90
3.45
10.35
106.95
38.00
No.of Pcs
227.85
63.00
No.of Pcs
558.00
153.00
Area
12.00
4.80
12.00
12.00
7.20
7.20
4.80
4.80
2.40
7.20
#NAME?
#NAME?
#NAME?
#NAME?
No.of Pcs
#NAME?
#NAME?
No.of Pcs
#NAME?
#NAME?
Area
36.00
122.50
6.90
3.22
1.15
169.77
59.00
No.of Pcs
327.55
90.00
No.of Pcs
752.40
207.00
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
#REF!
#REF!
d. Gravel Bedding
Qty = 22.20 cu.m.
Materials:
23.40 cu.m. Gravel Bedding @ 100mm THK (w/ Additional 5%) P 850.00 /cu.m. P 19,890.00
Sub-total P 19,890.00
Labor:
1 Construction Foreman 400.00 /day for 4 days P 1,600.00
4 Laborers 295.00 /day for 4 days P 4,720.00
Sub-total P 6,320.00
Equipment Rental
1 Plate Compactor 984.00 /day for 2 days P 1,968.00
Minor Tools 632.00
Sub-total P 2,600.00
Item 900(1)c2: Structural Concrete for Footing and Slab on Fill (Class A, 28 days)
Qty = 34.85 cu.m
Materials:
318 bags Portland Cement P 230.00 /bag P 73,140.00
18.0 cu.m Washed sand P 850.00 /cu.m P 15,300.00
35.0 cu.m Screened Gravel P 980.00 /cu.m P 34,300.00
Sub-total P 122,740.00
Labor:
1 Construction Foreman 400.00 /day for 5 days P 2,000.00
5 Mason 365.00 /day for 5 days P 9,125.00
6 Laborers 295.00 /day for 5 days P 8,850.00
Sub-total P 19,975.00
Equipment Rental:
1 Concrete Vibrator 730.00 /day for 5 days P 3,650.00
1 Bagger mixer 1,376.00 /day for 5 days P 6,880.00
Minor Tools 1,997.50
Sub-total P 12,527.50
Item 900(1): Structural Concrete for Footing Tie Beam, Column and Lintel Beam (Class A, 28 days)
Qty = #NAME? cu.m
Materials:
#NAME? bags Portland Cement P 230.00 /bag P #NAME?
#NAME? cu.m Washed sand P 850.00 /cu.m P #NAME?
37.0 cu.m Screened Gravel P 980.00 /cu.m P 36,260.00
Sub-total P #NAME?
Labor:
1 Construction Foreman 400.00 /day for 5 days P 2,000.00
10 Mason 365.00 /day for 5 days P 18,250.00
12 Laborers 295.00 /day for 5 days P 17,700.00
Sub-total P 37,950.00
Equipment Rental:
1 Concrete Vibrator 730.00 /day for 5 days P 3,650.00
1 Bagger mixer 1,376.00 /day for 5 days P 6,880.00
Minor Tools 3,795.00
Sub-total P 14,325.00
#REF!
#REF!
Sub-total P #NAME?
Labor:
1 Construction Foreman 400.00 /day for 16 days P 6,400.00
10 Carpenters 365.00 /day for 16 days P 58,400.00
12 Laborers 295.00 /day for 16 days P 56,640.00
Sub-total P 121,440.00
Materials:
#NAME? pcs 10mmø x 6m RSB P 143.00 /pc P #NAME?
#NAME? pcs 12mmø x 6m RSB P 206.00 /pc P #NAME?
#NAME? pcs 16mmø x 6m RSB P 367.00 /pc P #NAME?
#NAME? pcs 20mmø x 6m RSB P 565.00 /pc P #NAME?
#NAME? kg #16 G.I Wire P 74.00 /pc P #NAME?
Consumables (5% of Materials Cost) P #NAME?
Sub-total P #NAME?
Labor:
1 Construction Foreman 400.00 /day for 9 days P 3,600.00
10 Steelman 365.00 /day for 9 days P 32,850.00
12 Laborers 295.00 /day for 9 days P 31,860.00
Sub-total P 68,310.00
Equipment Rental:
1 Bar Cutter 1,758.00 /day for 5 days P 8,790.00
1 Bar Bender 2,812.00 /day for 5 days 14,060.00
Minor Tools 6,831.00
Sub-total P 29,681.00
IV MASONRY WORKS
QTY : = #NAME? sq.m
A. MASONRY WALL
Materials:
#NAME? pcs. 4" x 8" x 16"CHB P 15.00 /pc P #NAME?
#NAME? bags Portland Cement P 230.00 /cu.m. P #NAME?
#NAME? cu.m Washed Sand P 850.00 /cu.m. P #NAME?
#NAME? pcs. 10mmØ x 6m RSB P 143.00 /pc P #NAME?
#NAME? kgs #16 G.I. Tie Wire P 74.00 /kg P #NAME?
Sub-total P #NAME?
Labor:
1 Construction Foreman 400.00 /day for 4 days P 1,600.00
4 Mason 365.00 /day for 4 days P 5,840.00
5 Laborer 295.00 /day for 4 days P 5,900.00
Sub-total P 13,340.00
Equipment Rental:
1 One Bagger- Mixer 1,376.00 /day for 4 days P 5,504.00
Minor Tools 1,334.00
Sub-total P 6,838.00
#REF!
#REF!
Name of Project: Construction of Power House with Scheme of Work Demolition Works, Carpentry Works
Transformer of Rep. Pedro G. Trono Concrete Works, Masonry Works
Memorial District Hospital
Location of Project: ### Painting Works
Appropriation P #REF!
Appropriation Act Capital Outlay F.Y. 2018
Project No.
Desirable starting date:
Type of Work to be constructed % of TOTAL No. of working days to complete:
1 SITEWORKS P 197,008.00 #REF! Manpower / Equipment Requirements
2 CONCRETE WORKS P #REF! #REF! 1 Project Engineer
3 ### P #NAME? #NAME? 2 Construction Foreman
4 ### P #NAME? #NAME? 3 Carpenter
5 ### P #NAME? #NAME? 4 Painter
6 ### P Err:509 Err:509 5 Steelmen
7 ### P Err:509 Err:509 6 Mason
8 7 Skilled Laborer/Laborer
9 8 Bagger Mixer
10 9 Concrete Vibrator
TOTAL P #REF! #REF! 10
CHECKED BY:
II. SITEWORKS
A. LAYOUT AND STAKING
Item No. of Set Length Width Area
Main Building 1 10.00 15.00 150.00
Total Area 150.00
B. EARTHWORKS
A. Excavation
Item No. of Set Length Width Depth Volume
Column Footing 23 1.50 1.50 1.60 82.80
Stiffener Column 2 0.50 0.50 1.05 0.53
Between Line3&4 WF1 (H) 1 1.15 0.40 0.70 0.33
Along Line A (H) 2 0.60 0.30 0.70 0.26
Between Line A & B (V) ( WF1) 1 1.20 0.40 0.70 0.34
Stair Footing 1 1.20 0.60 0.65 0.47
Footing Tie Beam
Along Line 1 (H) (15-(5*1.5))=7.5 1 7.50 0.25 0.80 1.50
Along Line 2 (H) (2*(3-1.5))=3 1 3.00 0.25 0.80 0.60
Along Line 3 (H) (15-(5*1.5))=7.5 1 7.50 0.25 0.80 1.50
Along Line 4 (H) (15-(5*1.5))=7.5 1 7.50 0.25 0.80 1.50
Along Line A (V) (10-(3*1.5))=5.5 1 5.50 0.25 0.80 1.10
Along Line B (V) (10-(3*1.5))=5.5 1 5.50 0.25 0.80 1.10
Along Line C (V) (2*(3-1.5))=3 1 3.00 0.25 0.80 0.60
Along Line D (V) (2*(3-1.5))=3 1 3.00 0.25 0.80 0.60
Along Line E (V) (3-1.5) = 1.5 1 1.50 0.25 0.80 0.30
Along Line F (V) (10-(3*1.5))=5.5 1 5.50 0.25 0.80 1.10
Concrete Slab 1 15.00 10.00 0.10 15.00
Total Volume for excavation 109.70
B. BACKFILL
Item No. of Set Length Width Height Volume
volume excavated 109.70
Deductive Volume (structure)
Column Footing 23 1.50 1.50 0.40 20.70
Column 23 0.30 0.30 1.20 2.49
Stiffener Column 2 0.50 0.50 0.30 0.15
Stiffener Column Footing 2 0.30 0.10 0.40 0.03
Between Line3&4 WF1 (H) 1 1.40 0.40 0.30 0.17
( Masonry above ) 1 1.40 0.10 0.40 0.06
Along Line A (H) 2 0.60 0.30 0.30 0.11
( Masonry above ) 2 0.60 0.10 0.20 0.03
Between Line A & B (V) ( WF1) 1 1.45 0.40 0.30 0.18
( Masonry above ) 1 1.45 0.10 0.40 0.06
Stair Footing 1 1.20 0.60 0.40 0.29
1 1.20 0.15 0.25 0.05
Footing Tie Beam
Along Line 1 (H) 1 7.50 0.25 0.40 0.75
Along Line 2 (H) 1 3.00 0.25 0.40 0.30
Along Line 3 (H) 1 7.50 0.25 0.40 0.75
Along Line 4 (H) 1 7.50 0.25 0.40 0.75
Along Line A (V) 1 5.50 0.25 0.40 0.55
Along Line B (V) 1 5.50 0.25 0.40 0.55
Along Line C (V) 1 3.00 0.25 0.40 0.30
Along Line D (V) 1 3.00 0.25 0.40 0.30
Along Line E (V) 1 1.50 0.25 0.40 0.15
Along Line F (V) 1 5.50 0.25 0.40 0.55
Concrete Slab 1 15.00 10.00 0.10 15.00
Total of Deductive Volume 44.27
Filing Materials from excavated Structures = 109.70 - 44.27 = 65.43
FILLING MATERIALS
Item No. of Set Length Width Height Volume
Main Building 1 15.00 10.00 0.35 52.50
Total Volume of 2 52.50
Total Volume of Filling Materials = 65.43 + 52.50 = 117.93
Shrinkage Factor 0.15
Total Volume 135.62
Volume To be Borrowed = ( 75% of Cut Materials - Volume of Filling Materials needed
= 75% (109.30) - 147.42 = 53.35 cu.m.
GRAVEL BEDDING
Item No. of Set Length Width Height Volume
Column Footing 23 1.50 1.50 0.10 5.18
Stiffener Column 2 0.50 0.50 0.10 0.05
Between Line3&4 WF1 (H) 1 1.40 0.40 0.10 0.06
Along Line A (H) 2 0.60 0.30 0.10 0.04
Between Line A & B (V) ( WF1) 1 1.45 0.40 0.10 0.06
Stair Footing 1 1.20 0.60 0.10 0.07
Footing Tie Beam
Along Line 1 (H) 5 3.00 0.25 0.10 0.38
Along Line 2 (H) 2 3.00 0.25 0.10 0.15
Along Line 3 (H) 5 3.00 0.25 0.10 0.38
Along Line 4 (H) 5 3.00 0.25 0.10 0.38
Along Line A (V) 1 10.00 0.25 0.10 0.25
Along Line B (V) 1 10.00 0.25 0.10 0.25
Along Line C (V) 2 3.50 0.25 0.10 0.18
Along Line D (V) 2 3.50 0.25 0.10 0.18
Along Line E (V) 1 3.00 0.25 0.10 0.08
Along Line F (V) 1 10.00 0.25 0.10 0.25
Total Volume 7.90
III. CONCRETE WORKS
Item 900 (1)c2 : Footing and Slab on Fill
Item No. of Set Length Width Height Volume
Column Footing 23 1.50 1.50 0.30 15.53
Stiffener Column Footing 2 0.50 0.50 0.20 0.10
Stair Footing 1 1.20 0.60 0.30 0.22
Second Floor Slab 10 3.5 3 0.125 13.13
4 3 3 0.125 4.50
Total Volume 33.47
Item No. of Set Length Width Height Volume
Item 900 (1)
Column ( Ground ) 23 0.30 0.30 5.25 10.87
Stiffener Column 2 0.10 0.30 4.45 0.27
Footing Tie Beam
Along Line 1 (H) 5 3.00 0.25 0.40 1.50
Along Line 2 (H) 2 3.00 0.25 0.40 0.60
Along Line 3 (H) 5 3.00 0.25 0.40 1.50
Along Line 4 (H) 5 3.00 0.25 0.40 1.50
Along Line A (V) 3 3.00 0.25 0.40 0.90
Along Line B (V) 3 3.00 0.25 0.40 0.90
Along Line C (V) 2 3.00 0.25 0.40 0.60
Along Line D (V) 2 3.00 0.25 0.40 0.60
Along Line E (V) 1 3.00 0.25 0.40 0.30
Along Line F (V) 3 3.00 0.25 0.40 0.90
Lintel Beams ( Above FTB )
Along Line 1 (H) 5 3.00 0.30 0.10 0.45
Along Line 2 (H) 2 3.00 0.30 0.10 0.18
Along Line 3 (H) 5 3.00 0.30 0.10 0.45
Along Line 4 (H) 5 3.00 0.30 0.10 0.45
Along Line A (V) 3 3.00 0.30 0.10 0.27
Along Line B (V) 3 3.00 0.30 0.10 0.27
Along Line C (V) 2 3.00 0.30 0.10 0.18
Along Line D (V) 2 3.00 0.30 0.10 0.18
Along Line E (V) 1 3.00 0.30 0.10 0.09
Along Line F (V) 3 3.00 0.30 0.10 0.27
Floor Beam 1 10 3.50 0.30 0.40 4.20
25 3.00 0.30 0.40 9.00
Floor Beam 2 2 3.50 0.30 0.50 1.05
Floor Beam 3 2 3.00 0.25 0.40 0.60
1 1.50 0.25 0.40 0.15
1 1.40 0.25 0.40 0.14
1 1.00 0.25 0.40 0.10
Sub- Total 38.47
( Stairs' Step )
No of Steps = 19
Rise = 0.167
Run = 0.3
Length = 1.2
Area 2
Length 7.18
Width 1.2
Depth 0.15
Volume = 1.2924 cu.m.
Total Concrete Volume = 3.29868 cu.m.
Total Volume = 38.47 + 3.30 = 41.77
Reinforced Steel Bars
Item No. of Set unit/length Length Total Length no. of pcs
Column Footing
16 mm ØMatt Bars 23 18 1.50 621.00 109.00
Column ( Ground )
20mm ØVertical Bars 23 8 5.25 966.00 184.00
10mmØ Lateral Ties 23 80 0.98 1803.20 317.00
Stiffener Column Footing
12 mm ØMatt Bars 2 6 0.50 6.00 1.00
Stiffener Column
12mm ØVertical Bars 2 3 4.45 26.70 5.00
10mmØ Lateral Ties 2 24 0.58 27.84 5.00
Item No. of Set unit/length length total length no. of pcs
Wall Footing Main RSB - 10mm Ø
Between Line3&4 WF1 (H) 1 3 1.40 4.20
Along Line A (H) 2 3 0.60 3.60
Between Line A & B (V) ( WF1) 1 3 1.45 4.35
Total overall length for 10mmø bars 12.15
total number of 10mm ø bars 3.00
Item No. of Set no. unit length length total length no. of pcs
Wall Footing Transverse Bar - 10mmØ
Between Line3&4 WF1 (H) 1 6 0.40 2.40
Along Line A (H) 2 3 0.30 1.80
Between Line A & B (V) ( WF1) 1 6 0.40 2.40
Total overall length for 10mmø bars 6.60
total number of 10mm ø bars 2.00
Item No. of Set no. unit length length total length no. of pcs
Footing Tie Beam main bars - 16mmø RSB
Along Line 1 (H) 5 6 3.00 90.00
Along Line 2 (H) 2 6 3.00 36.00
Along Line 3 (H) 5 6 3.00 90.00
Along Line 4 (H) 5 6 3.00 90.00
Along Line A (V) 2 6 3.50 42.00
1 6 3.00 18.00
Along Line B (V) 2 6 3.50 42.00
1 6 3.00 18.00
Along Line C (V) 2 6 3.50 42.00
Along Line D (V) 2 6 3.50 42.00
Along Line E (V) 1 6 3.00 18.00
Along Line F (V) 2 6 3.50 42.00
1 6 3.00 18.00
Total overall length for 16mm øbars 588.00
total number of 16mm ø bars 104.00
Item No. of Set unit/length length total length no. of pcs
Footing Tie Beam Stirrups - 10mmø RSB Bars
Along Line 1 (H) 5 26 0.88 114.40
Along Line 2 (H) 2 26 0.88 45.76
Along Line 3 (H) 5 26 0.88 114.40
Along Line 4 (H) 5 26 0.88 114.40
Along Line A (V) 2 30 0.88 52.80
1 26 0.88 22.88
Along Line B (V) 2 30 0.88 52.80
1 26 0.88 22.88
Along Line C (V) 2 30 0.88 52.80
Along Line D (V) 2 30 0.88 52.80
Along Line E (V) 1 26 0.88 22.88
Along Line F (V) 2 30 0.88 52.80
1 26 0.88 22.88
Total overall length for 10mm øbars 721.60
total number of 10mm ø bars 127.00
Item No. of Set unit/length length total length no. of pcs
Lintel beams Main RSB - Above FTB
Along Line 1 (H) 5 3 3.00 45.00
Along Line 2 (H) 2 3 3.00 18.00
Along Line 3 (H) 5 3 3.00 45.00
Along Line 4 (H) 5 3 3.00 45.00
Along Line A (V) 2 3 3.50 21.00
1 3 3.00 9.00
Along Line B (V) 2 3 3.50 21.00
1 3 3.00 9.00
Along Line C (V) 2 3 3.50 21.00
Along Line D (V) 2 3 3.50 21.00
Along Line E (V) 1 3 3.50 10.50
Along Line F (V) 2 3 3.50 21.00
1 3 3.00 9.00
Total overall length for 12mm øbars 295.50
total number of 12mm ø bars 52.00
Item No. of Set unit/length length total length no. of pcs
Lintel Beams ( Stirrups ) - Above FTB
Along Line 1 (H) 5 21 0.30 31.50
Along Line 2 (H) 2 21 0.30 12.60
Along Line 3 (H) 5 21 0.30 31.50
Along Line 4 (H) 5 21 0.30 31.50
Along Line A (V) 2 25 0.30 15.00
1 21 0.30 6.30
Along Line B (V) 2 25 0.30 15.00
1 21 0.30 6.30
Along Line C (V) 2 25 0.30 15.00
Along Line D (V) 2 25 0.30 15.00
Along Line E (V) 1 25 0.30 7.50
Along Line F (V) 2 25 0.30 15.00
1 21 0.30 6.30
Total overall length for 10mm øbars 208.50
total number of 10mm ø bars 36.00
Item No. of Set unit/length length total length no. of pcs
Dowell Bars Connecting From Wall Footing To Matt Bars
Along Line 1 (H) 5 9 0.35 15.75
Along Line 2 (H) 4 9 0.35 12.60
Along Line 3 (H) 10 9 0.35 31.50
Along Line 4 (H) 5 9 0.35 15.75
Along Line A (V) 2 10 0.35 7.00
1 9 0.35 3.15
Along Line B (V) 4 10 0.35 14.00
2 9 0.35 6.30
Along Line C (V) 4 10 0.35 14.00
Along Line D (V) 4 10 0.35 14.00
Along Line E (V) 2 9 0.35 6.30
Along Line F (V) 2 10 0.35 7.00
1 9 0.35 3.15
Between Line3&4 WF1 (H) 2 5 0.35 3.50
Between Line A & B (V) ( WF1) 2 5 0.35 3.50
Total overall length for 10mm dia bars 157.50
total number of 10mm dia bars 28.00
Stair Reinforcement
Item No. of Set unit/length length total length no. of pcs
16mmØ RSB
Continuous Bars 1 10 1.20 12.00
Cross Bars 1 7 0.55 3.85
Main Bars 1 5 2.21 11.05
1 9 7.18 64.62
Extra Bars (16mm dia ) 4 15 1.20 72.00
Top Bars (16mm ) 1 2 1.00 2.00
Bottom Bars (16mm ) 1 2 1.00 2.00
Total length 167.52
Total Number 30.00
12mm Ø RSB
Temperature Bars (12mm dia ) 1 52 1.20 62.40
2 13 1.20 31.20
3 3 1.20 10.80
Extra Dowell Bars 2 9 0.45 8.10
Total length 112.50
Total Number 20.00
10mm Ø RSB
Chair Bars ( 10mm dia ) 21 9 0.75 141.75
Nosing Bars (10mm dia ) 1 21 1.20 25.20
Total length 166.95
Total Number 30.00
BEAM REINFORCEMENTS
Item No. of Set unit/length length total length no. of pcs
Floor Beam 1
Top bars 10 4.00 3.50 140.00
Bottom bars 10 4.00 3.50 140.00
Cut Bars 10 8.00 0.90 72.00
10 4.00 1.92 76.80
Top bars 25 4.00 3.00 300.00
Bottom bars 25 4.00 3.00 300.00
Cut Bars 25 8.00 0.80 160.00
25 4.00 1.62 162.00
Floor Beam 2
Top bars 2 5.00 3.50 35.00
Bottom bars 2 5.00 3.50 35.00
Cut Bars 2 10.00 0.90 18.00
2 5.00 1.92 19.20
Total overall length for 20mm dia bars 1458.00
total number of 20mm dia bars 256.00
Floor Beam 3
Top bars 2 5.00 3.00 30.00
Bottom bars 2 5.00 3.00 30.00
Cut Bars 2 4.00 0.70 5.60
2 2.00 1.62 6.48
Top bars 2 5.00 1.50 15.00
Bottom bars 2 5.00 1.50 15.00
Cut Bars 2 4.00 0.38 3.04
2 2.00 0.50 2.00
Top bars 1 5.00 1.00 5.00
Bottom bars 1 5.00 1.00 5.00
Cut Bars 1 4.00 0.25 1.00
1 2.00 0.33 0.66
Total overall length for 16mm dia bars 118.78
total number of 16mm dia bars 21.00
Item No. of Set unit/length length total length no. of pcs
Floor Beam Stirrups
Floor Beam 1 10 35 0.64 224.00
10 35 0.30 105.00
Floor Beam 1 25 31 0.64 496.00
25 31 0.30 232.50
Floor Beam 2 2 35 0.64 44.80
2 35 0.30 21.00
Floor Beam 3 2 35 0.64 44.80
2 35 0.25 17.50
Floor Beam 3 2 22 0.64 28.16
2 22 0.25 11.00
Floor Beam 3 1 12 0.64 7.68
1 12 0.25 3.00
Total overall length for 10mm dia bars 1235.44
total number of 10mm dia bars 217.00
Second Floor Slab Reinforcements
Item No. of Set unit/length length total length no. of pcs
Floor Slab
12mm dia Temperature Bars
Horizontal (3/0.3)+1=11 10 11 3.50 385.00
Vertical (3.5/0.4)+1=13 10 13 3.00 390.00
Horizontal (3/0.3)+1=11 3 11 3.00 99.00
Vertical (3.0/0.4)+1=11 3 11 3.00 99.00
Horizontal (2/0.3)+1=8 3 8 3.00 72.00
Vertical (3.0/0.4)+1=11 3 11 2.00 66.00
12mm dia Cut Bars
Along Line A (V) 2 7 0.75 10.50
1 6 0.75 4.50
Along Line B (V) 2 7 1.50 21.00
1 6 1.50 9.00
Along Line C (V) 2 7 1.50 21.00
1 6 1.50 9.00
Along Line D (V) 2 7 1.50 21.00
1 6 1.25 7.50
1 6 0.50 3.00
Along Line E (V) 2 7 1.50 21.00
1 6 1.50 9.00
Along Line F (V) 2 7 0.75 10.50
1 6 0.75 4.50
Along Line 1 (H) 5 6 0.88 26.25
Along Line 2 (H) 5 6 1.75 52.50
Along Line 3 (H) 4 6 1.63 39.00
1 6 0.88 5.25
Along Line 4 (H) 3 6 0.75 13.50
1 5 0.75 3.75
12mm dia Extra Bars 0
Along Line B (V) 2 25 0.90 45.00
1 21 0.90 18.90
Along Line C (V) 2 25 0.90 45.00
1 21 0.90 18.90
Along Line D (V) 2 25 0.90 45.00
1 21 0.90 18.90
Along Line E (V) 2 25 0.90 45.00
Along Line F (V) 2 25 0.90 45.00
1 6 0.90 5.40
Along Line 1 (H) 5 6 0.90 27.00
Along Line 2 (H) 5 21 0.90 94.50
Along Line 3 (H) 5 21 0.90 94.50
Total overall length for 12mm dia bars 1905.85
total number of 12mm dia bars 335.00
SUMMARY FOR REINFORCED STEEL BARS
Item Standard Weight Total Weight (kg)
10mmø Bars
765.00 3.70 2830.50
12mmø Bars
413.00 5.33 2201.29
16mmØ RSB
264.00 9.47 2500.08
20mmØ RSB
440.00 14.80 6512.00
Total Weight of Reinforced Steel Bars 14043.87
MASONRY WORKS
Item No. of Set Length Width Height Area
A. CHB Wall
Along Line 1 (H) 5 3.00 1.00 15.00
Along Line 2 (H) 2 3.00 1.00 6.00
Along Line 3 (H) 2 3.00 1.00 6.00
3 3.00 0.60 5.40
Along Line 4 (H) 2 3.00 1.00 6.00
3 3.00 0.60 5.40
Along Line A 2 3.50 1.00 7.00
1 3.00 1.00 3.00
Along Line B 1 5.05 1.00 5.05
1 4.95 1.00 4.95
Along Line C 2 3.50 1.00 7.00
Along Line D 2 3.50 1.00 7.00
Along Line E 1 3.00 0.60 1.80
Along Line F (V) 1 10.00 1.00 10.00
Total Area to be filled of CHB 89.60
Total Area to be filled by 4" CHB =
= 89.60 sq.m.
Table 3-5 Length of Reinforcing Bars for CHB in meters
Vertical Reinforcement Horizontal Reinforcement
Spacing
Length of bars in meter Spacing Layer Length oif Bars in meter
cm. per block per sq.m. per block per sq.m.
40 0.235 2.93 2 0.264 3.3
60 0.171 2.13 3 0.172 2.15
80 0.128 1.6 4 0.138 1.72
(Siplified Construction Estimate 2000 Edition, page 99) *total length = CHB area x factor
Item Spacing Factor CHB Area Total Length No of PCs
Vertical 0.6 2.13 89.60 190.85 34.00
Horizontal 2nd Layer 3.3 89.60 295.68 52.00
total number of 10mm ø bars 86.00
SUMMARY OF DIRECT COST
DESCRIPTION QTY. UNIT Materials Cost Labor Cost
OTHER GENERAL REQUIREMENTS
Permits and Clearances 1.00 lot 14,400.00
Project Billboard/Signboard 2.00 each 8,694.00 5,052.00
TOTAL OTHER GENERAL REQUI
PART A - EARTHWORKS
I. Layout and Staking 186.10 sq.m. 3,830.00 1,882.00
II. Structure Excavation 48.20 cu.m 25,866.00
IV. Embankment from Structure Excavation 31.20 cu.m 8,622.00
V. Gravel Fill 7.50 cu.m 9,750.00 1,882.00
TO
PART B - PLAIN AND REINFORCED CONCRETE WORKS
I. Structural Concrete (Class A) 91.35 cu.m 333,026.00 153,650.00
II. Reinforcing Steel #REF! kgs #REF! #REF!
III. Formworks and Falseworks #REF! sq.m. #REF! #REF!
TO
PART C - FINISHING AND OTHER CIVIL WORKS
I. Masonry Works #REF! sq.m. #REF! #REF!
II. Plastering Works #REF! sq.m. #REF! #REF!
III. Ceiling Works 153.76 sq.m. 30,395.00 33,296.00
IV. Doors and Windows Installation 160,220.00 3,698.00
A.1 Doors 45.99 sq.m. 94,970.00 3,698.00
A.2 Windows with Installation 36.34 sq.m. 65,250.00
V. Tile Works 168.48 sq.m. 78,186.47 42,800.00
VI. Painting Works #REF! sq.m. #REF! 65,900.00
VII. Railings 127.09 ln.m. 13,158.00 7,332.00
VIII. Structural Steel Roof Framing 1.00 L.S 101,188.50 43,632.00
IX. Roofing Works 58.58 sq.m. 80,742.73 25,260.00
X. Plumbing Works 1.00 L.S 111,444.10 83,970.00
XI. Catch Basin 12,319.39 13,066.00
a. Excavation 0.90 cu.m. 1,882.00
b. Concrete Works 0.14 cu.m 1,776.39 4,450.00
c. Masonry Works 1.28 sq.m 550.00 3,666.00
d. Pipes and Fittings 9,993.00 3,068.00
XII. Septic Vault 36,895.50 22,192.00
a. Excavation 6.60 cu.m. 4,756.00
b. Concrete Works 0.90 cu.m 13,878.50 10,998.00
c. Masonry Works 22.08 sq.m 18,984.00 3,666.00
d. Plastering Works 44.16 sq.m. 4,033.00 2,772.00
TO
PART D - ELECTRICAL
I. ELECTRICAL WORKS 1.00 L.S 244,252.00 82,464.00
A. Panel Board 16,692.00
14,400.00
5,052.00 13,746.00
TOTAL OTHER GENERAL REQUIEREMENTS 13,746.00
1,882.00 5,712.00
25,866.00 2,586.60 28,452.60
8,622.00 1,968.00 10,590.00
1,882.00 984.00 12,616.00
TOTAL PART A 57,370.60
No.of
Designation No. of Days Daily Rate Amount
Person
1. Labor
No.of
Designation No. of Days Daily Rate Amount
Person
1. Labor
No.of
Designation No. of Days Daily Rate Amount
Person
1. Labor
Sub-Total for 3
583,353.75
Total Direct Cost 696,946.55
OCM #REF! #REF!
Contractor's Profit (10%) 10% 69,694.66
VAT (5%) 5% #REF!
Total Cost #REF!
Total Unit Cost #REF!
LOCATION : #REF!
ITEM NO. : 903 (2) Production Rate 1.851
DESCRIPTION : Formworks and Falseworks Unit of Measurement : sq.m/day
No.of
Designation No. of Days Daily Rate Amount
Person
1. Labor
Installation
a. Construction Foreman 1.00 7.00 660.00 4,620.00
b. Skilled Laborer 6.00 7.00 467.00 19,614.00
c. Unskilled Laborer 18.00 7.00 361.00 45,486.00
Stripping
a. Construction Foreman 1.00 3.00 660.00 1,980.00
b.Unskilled Laborer 19.00 3.00 361.00 20,577.00
Sub-Total for 3
104,956.00
Total Direct Cost 206,460.70
OCM #REF! #REF!
Contractor's Profit (10%) 10% 20,646.07
VAT (5%) 5% #REF!
Total Cost #REF!
Total Unit Cost #REF!
DETAILED ESTIMATE OF UNIT COST
No.of
Designation No. of Days Daily Rate Amount
Person
1. Labor
No.of
Designation No. of Days Daily Rate Amount
Person
1. Labor
TOTAL PART A P
Materials:
#REF! bags Portland Cement P 192.00 /bag P
#REF! cu.m Washed Sand P 1,167.00 /cu.m. P
Sub-total P
Labor:
1.00 Construction Foreman 890.00 /day for #REF! days P
2.00 Skilled Laborer 644.00 /day for #REF! days P
4.00 Unskilled Laborer 496.00 /day for #REF! days P
Sub-total P
Equipment Rental:
Minor Tools P
Sub-total P
1.80mx2.10m Kiln Dried Panel Door with Lever Type Knob and
2.00 set P 4,800.00 /set P
Hinges on 2"x4" Wooden Door Jamb, Single Leaf, Swing Type
0.90mx2.10m Kiln Dried Panel Door with Lever Type Knob and
2.00 set P 4,200.00 /set P
Hinges on 2"x4" Wooden Door Jamb, Single Leaf, Swing Type
0.80mx2.10m Kiln Dried Panel Door with Lever Type Knob and
4.00 sets P 4,200.00 /set P
Hinges on 2"x4" Wooden Door Jamb, Single Leaf, Swing Type
0.70mx2.10m Kiln Dried Panel Door with Lever Type Knob and
1.00 set P 4,200.00 /set P
Hinges on 2"x4" Wooden Door Jamb, Single Leaf, Swing Type
1.00mx2.10m Kiln Dried Panel Door with Lever Type Knob and
6.00 set P 4,200.00 /set P
Hinges on 2"x4" Wooden Door Jamb with Aluminum Guide
1.00mx2.10m Kiln Dried Panel Door with Lever Type Knob and
2.00 sets P 2,785.00 /set P
Hinges on 2"x4" Wooden Door Jamb, Single Leaf, Swing Type
Sub-total
Labor:
1.00 Construction Foreman 660.00 /day for 2 days P
1.00 Skilled Laborer 467.00 /day for 2 days P
2.00 Unskilled Laborer 361.00 /day for 2 days P
Sub-total P
Equipment Rental:
Minor Tools (10% of Labor Cost) P
Sub-total P
Total for A.1
A.2 Windows with Installation
Qty = 36.34 sq.m.
Materials:
Sub-total
Total for A.2
Total for ITEM IV.
VII. Railings
Qty = 127.09 ln.m.
6.00 pcs 2"Ø x 6M G.I. Pipe P 1,443.00 /pc P
10.00 pcs 1/2"Ø x 6M G.I. Pipe P 400.00 /pc P
Consumables P
Sub-total
Labor:
1.00 Construction Foreman 890.00 /day for 2 days P
2.00 Skilled Laborer 644.00 /day for 2 days P
3.00 Unskilled Laborer 496.00 /day for 2 days P
Sub-total P
Equipment Rental:
Minor Tools P
Sub-total P
Labor:
1.00 Construction Foreman 890.00 /day for 10 days P
1.00 Skilled Laborer 644.00 /day for 10 days P
2.00 Unskilled Laborer 496.00 /day for 10 days P
Sub-total P
Equipment Rental:
Minor Tools P
Sub-total P
TOTAL FOR IX P
Sub-total P
Total for d
Equipment Rental
Minor Tools (10% of Labor Cost) P
Sub-total P
Total for b
c. Masonry Works 6"x8"x16" CHB = 22.08 sq.m
Materials:
276.00 pcs. 6" x 8" x 16"CHB P 21.00 /pc P
34.00 bags Portland Cement P 207.00 /bag P
1.00 cu.m Washed Sand P 1,030.00 /cu.m. P
23.00 pcs. 10mmØ x 6m RSB P 190.00 /pc P
10.00 kgs #16 G.I. Tie Wire P 75.00 /kg P
Sub-total P
Labor:
1.00 Construction Foreman 890.00 /day for 1 day P
2.00 Skilled Laborer 644.00 /day for 1 day P
3.00 Unskilled Laborer 496.00 /day for 1 day P
Sub-total P
Equipment Rental
1.00 One Bagger Mixer 1,376.00 /day for 1 day P
Minor Tools P
Sub-total P
Total for c
d. Plastering Works = 44.16 sq.m.
Materials:
13.00 bags Portland Cement P 192.00 /bag P
1.00 cu.m. Washed sand P 1,167.00 /cu.m. P
10.00 packs Waterproofing White Cement P 37.00 /pack P
Sub-total P
Labor:
1.00 Construction Foreman 890.00 /day for 2 days P
1.00 Unskilled Laborer 496.00 /day for 2 days P
Sub-total P
Equipment Rental
Minor Tools P
Sub-total P
Total for d P
TOTAL FOR ITEM XII P
TOTAL PART C P
PART D - ELECTRICAL
I. ELECTRICAL WORKS
A. Panel Board
1.00 unit Main: 160AT,2P,250Vac, 60hz, MCCB,12KAIC P 7,700.00 /unit P
Branches:
TOTAL PART D P
5,000.00
5,000.00
2,200.00
1,500.00
200.00
500.00
14,400.00
14,400.00
800.00
1,600.00
1,362.00
2,700.00
1,323.00
150.00
384.00
375.00
8,694.00
1,780.00
1,288.00
1,984.00
5,052.00
13,746.00
2,940.00
750.00
140.00
3,830.00
890.00
992.00
1,882.00
5,712.00
8,010.00
17,856.00
25,866.00
2,586.60
2,586.60
28,452.60
2,670.00
5,952.00
8,622.00
1,968.00
1,968.00
10,590.00
9,750.00
9,750.00
890.00
992.00
1,882.00
984.00
984.00
12,616.00
57,370.60
159,744.00
53,682.00
119,600.00
333,026.00
22,250.00
32,200.00
99,200.00
153,650.00
34,400.00
34,400.00
521,076.00
#REF!
#REF!
98,406.00
192,864.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
12,750.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
15,171.00
1,620.00
7,636.00
1,680.00
2,800.00
1,488.00
30,395.00
7,120.00
10,304.00
15,872.00
33,296.00
3,329.60
3,329.60
67,020.60
9,600.00
8,400.00
16,800.00
25,200.00
4,200.00
25,200.00
5,570.00
94,970.00
1,320.00
934.00
1,444.00
3,698.00
369.80
369.80
99,037.80
15,000.00
15,000.00
3,750.00
15,000.00
3,750.00
3,750.00
3,750.00
3,750.00
1,500.00
65,250.00
65,250.00
164,287.80
49,125.00
672.00
1,050.00
5,784.00
20,400.00
1,155.47
78,186.47
4,450.00
16,100.00
22,250.00
42,800.00
2,140.00
2,140.00
123,126.47
#REF!
21,472.00
#REF!
59,262.00
1,990.00
580.00
#REF!
#REF!
8,900.00
32,200.00
24,800.00
65,900.00
6,590.00
6,590.00
#REF!
8,658.00
4,000.00
500.00
13,158.00
1,780.00
2,576.00
2,976.00
7,332.00
733.20
733.20
21,223.20
44,608.00
23,606.00
12,100.00
9,456.00
6,600.00
4,818.50
101,188.50
5,340.00
11,592.00
26,700.00
43,632.00
9,384.00
1,090.80
10,474.80
155,295.30
55,045.00
2,470.00
-
2,090.00
3,186.00
1,500.00
10,050.00
3,600.00
450.00
2,351.73
80,742.73
8,900.00
6,440.00
9,920.00
25,260.00
2,526.00
2,526.00
108,528.73
11,500.00
2,142.00
8,592.00
3,795.00
1,311.00
240.00
240.00
405.00
7,340.00
345.00
92.00
276.00
1,200.00
600.00
194.00
924.00
900.00
174.00
512.00
180.00
410.00
274.00
336.00
380.00
200.00
2,128.10
44,690.10
864.00
225.00
350.00
78.00
120.00
325.00
1,000.00
300.00
1,500.00
4,762.00
19,944.00
6,394.00
18,712.00
4,160.00
1,250.00
5,440.00
1,680.00
460.00
1,000.00
2,952.00
61,992.00
13,350.00
22,320.00
48,300.00
83,970.00
4,198.50
4,198.50
199,612.60
890.00
992.00
1,882.00
188.20
188.20
2,070.20
460.00
85.00
196.00
96.80
780.00
74.00
84.59
1,776.39
890.00
3,560.00
4,450.00
445.00
445.00
6,671.39
240.00
207.00
103.00
550.00
890.00
1,288.00
1,488.00
3,666.00
1,376.00
366.60
1,742.60
5,958.60
9,129.00
864.00
9,993.00
1,780.00
1,288.00
3,068.00
306.80
306.80
13,367.80
28,067.99
1,780.00
2,976.00
4,756.00
475.60
475.60
5,231.60
1,728.00
583.50
1,170.00
242.00
3,696.00
350.00
1,179.00
735.00
945.00
750.00
2,500.00
13,878.50
2,670.00
3,864.00
4,464.00
10,998.00
1,099.80
1,099.80
25,976.30
5,796.00
7,038.00
1,030.00
4,370.00
750.00
18,984.00
890.00
1,288.00
1,488.00
3,666.00
1,376.00
366.60
1,742.60
24,392.60
2,496.00
1,167.00
370.00
4,033.00
1,780.00
992.00
2,772.00
277.20
277.20
7,082.20
62,682.70
#REF!
7,700.00
6,992.00
2,000.00
16,692.00
25,500.00
1,680.00
1,260.00
2,450.00
1,990.00
8,000.00
13,200.00
54,080.00
850.00
2,070.00
480.00
540.00
3,940.00
450.00
3,910.00
3,200.00
7,560.00
6,480.00
70,875.00
50,000.00
1,040.00
128,395.00
270.00
16,335.00
1,071.00
3,368.00
285.00
2,080.00
2,065.00
25,474.00
1,075.00
2,800.00
200.00
4,075.00
102.00
1,000.00
2,000.00
518.00
416.00
4,036.00
244,252.00
14,240.00
20,608.00
47,616.00
82,464.00
1,200.00
1,200.00
1,200.00
1,000.00
4,600.00
331,316.00
331,316.00
#REF!
No. of Unit /
Description No. of Sets Length per Unit Total Length
Set
2" x 4" x 12' Coco Lumber
Diagonal Bracing 1.00 2.00 3.60 7.20
Horizontal Brace 1.00 2.00 1.00 2.00
Post 1.00 2.00 3.20 6.40
Wooden Stake 1.00 2.00 0.45 0.90
TOTAL LENGTH 16.50 m
Number of pcs. of 2" x 4" x 12' Coco Lumber 5.00 pcs.
=0.20+3-0.125-
Along Line 1&3(H) 2 7.00 5.18 0.40+2.80-0.3
72.45
=0.40+0.2+3-0.125-
Along Line 1-2(H) 1 2.00 5.68 0.3+2.80-0.3
11.35
Receiving-Conference Area
1 4 3.50 26.5 9.00
P=4*4+3*3.50
CR 1 2.00 1.20 6.40 3.00
Second Floor
DEDUCTIVE AREA
Classroom 1 1.00 0.98 0
Comfort Rooms (Second Floor) 1.00 0
Total Area for F1 = 289.49
9.5
4.75
1.26
1.01
0.29
0.78
0.15
0.54
1.2 1.2 1.2 1.2 1.2 0.72
6.72
0.5
0.59
0.15
1.2 1.55
2.75
FASCIA FRAME
1"X1"X6mm THK. Angular
VERTICAL & HO Bar
0.00 0.00
0.00 0.00
0.00 0.00
SUMMARY
Item Number of PCs Weight
6mmx2''x2'' Angle Bar 41.00 kgs
6mmx 1-1/2''x1-1/2'' 29.00 kgs
1.2mm thk x 2''x4'' C- Purlins 16.00 kgs
Item Units Unit/Length Length Total Length
1.2mm thk x
2 42.4 7.00
2''x4''
1.2mmC-thk
Purlins
x 𝑆_𝑛=n((𝑎_1+ 2 50.4 9.00
2''x4'' C- Purlins
Item 𝑎_𝑛)/2)
𝑆_𝑛=n((𝑎_1+
Width 1 Width 2 Height Units Area
Roofing 𝑎_𝑛)/2)
(Twin Rib) Roofing Sheets
Area = 2 units 1.1 10.5 5.05 2.00 58.58 sq.m.
Area = 2 units 9.5 5.09 2.00 48.36 sq.m.
Total 106.94 sq.m.
Ridge Roll
Area = 1 unit 2.1 x 0.5 1.00 1.05 sq.m.
Gutter
Area = 1 unit 0.81 x 7 = 11.34 sq.m.
Slab 2 1 1.50 5 9 9
1 1.80 5 10 10
1 2.00 5 11 11
2 3.50 5 19 38
68
Conc. Canopy
2 1.40 11 22
1 1.60 12 12
1 2.60 19 19
53
10
8
25
78 3.50 3.32 39
25 1.80 1.62 25
21 1.2 1.02 21
36
72
30
8
7
153
48
27
36
20
11
8
14
164
Length
4
1.1
3.5
0.975
3.5
0.975
2.1
0.975
Flywheel
No. Description Model Capacity Unit Rental Rate per Day
Horsepower
1 Earthmoving Equipment
Bulldozer D6H SERIES II PSDS/DD 165 PHP 27,032.00
Bulldozer w/ Ripper D6H SERIES II PSDS/DD 165 PHP 31,086.80
Payloader LX80-2C 1.50 / 1.95 cu.m. / yd³ 110 PHP 13,864.00
Motorized Road Grader G710A 140 PHP 17,384.00
Road Grader w/ Scarifier G710A 140 PHP 22,599.20
PHP -
2 Compaction Equipment PHP -
Pneumatic Tire Roller 9-WHL, 9.00X20, 4PR 10.00 mt 107 PHP 4,488.00
Vibratory Roller SD100DC 10.00 mt 125 PHP 14,768.00
Tandem Steel Roller CC421 10.10 mt 123 PHP 13,216.00
Plate Compactor 400 - 500 GASOLINE ENGINE 5 PHP 984.00
PHP -
3 Lifting Equipment PHP -
Service Crane w/ Crawler Crane ALL MODELS 21 - 25 mt 145 PHP 12,176.00
Crawler Crane w/ Bucket ALL MODELS 36 - 40 mt 190 PHP 18,259.20
Crawler Crane ALL MODELS 36 - 40 mt 190 PHP 15,216.00
Crawler Crane ALL MODELS 41 - 45 mt 190 PHP 17,208.00
Crawler Crane ALL MODELS 51 - 60 mt 275 PHP 22,224.00
Crawler Crane ALL MODELS 61 - 70 mt 275 PHP 28,576.00
Crawler Crane ALL MODELS 71 - 80 mt 285 PHP 28,760.00
Truck Mounted Crane ALL MODELS 31 - 35 mt 238 PHP 14,888.00
Truck Mounted Crane ALL MODELS 41 - 45 mt 246 PHP 20,848.00
Truck Mounted Crane w/ Bucket ALL MODELS 41 - 45 mt 246 PHP 25,016.00
Truck Mounted Crane ALL MODELS 51 - 60 mt 280 PHP 25,896.00
PHP -
4 Excavating Equipment PHP -
Backhoe SE 130 LC-2 0.80 / 1.04 cu.m. / yd³ 99 PHP 12,296.00
Backhoe w/ Breaker SE 130 LC-2 0.80 / 1.04 cu.m. / yd³ 99 PHP 15,984.80
Backhoe, Wheel Mounted PW60N-1 0.28 / 0.37 cu.m. / yd³ 50 PHP 7,376.00
PHP -
5 Foundation Equipment PHP -
Diesel Hammer K25 - DSL 7,500.00 kg-m PHP 10,288.00
Vibro Hammer DPD600T HYDRAULIC PILE DRIVER 60.00 ton 201 PHP 16,984.00
Vibro Hammer VIBRO FONCEUR, PTC25H1A 4,500.00 kg-m 272 PHP 24,552.00
Vibro Hammer MHF12 w/ Hyd. Power Pack 120.00 kg-m 300 PHP 32,944.00
C.M.V. TH18/65, 2000mmØ 65m Depth &
Drilling Rig 18000 kg-m Drill Torque
300 PHP 101,096.00
PHP -
6 Asphalting Equipment PHP -
Asphalt Distributor ROSCO/5 TON 3,000.00 USG 100 PHP 7,488.00
Asphalt Paver NF220BIIVDM 80 PHP 14,664.00
PHP -
7 Concreting Equipment PHP -
Concrete Screeder WACKER TRUSS SCREED 5.50 PHP 4,360.00
Concrete Paver COMMANDER III, FOUR-TRACK PHP 54,120.00
One Bagger Mixer 4-6 ft³/min PHP 1,376.00
Flywheel
No. Description Model Capacity Unit Rental Rate per Day
Horsepower
12 Shop Equipment
Welding Machine ELECTRIC DRIVEN / DC OUTPUT 500.00 AMP PHP 3,128.00
Welding Machine GAS / DIESEL DRIVER 300.00 AMP 48 PHP 2,968.00
14 Miscellaneous Equipment
Concrete Vibrator FLEXIBLE SHAFT TYPE 2" HEAD Ø w/ 5 AMPERE GASOLINE DRIVE UNIT PHP 730.00
Concrete Saw 14" BLADE Ø w/ 4 3/4" CUTTING DEPTH 7.50 PHP 261.04
Bar Cutter 25 mm MAXIMUM REBAR Ø (GRADE 40), SINGLE PHASE PHP 1,758.00
Bar Bender 25 mm MAXIMUM REBAR Ø (GRADE 40), THREE PHASE PHP 2,812.00
Tower Lights Tower Height= 28ft., No. of Lights = 4 x 1000 watts, HP = 10.50, PHP 4,348.00
Generator = 5 kW
15 Plants
Flywheel
No. Description Model Capacity Unit Rental Rate per Day
Horsepower
COMPLETE w/: CEMEN SILO AND SCREW CONVEYOR SYSTEM. WATER AND
SUPPLY SYSTEM. AGGREGATE STORAGE BINS w/ VIBRATORS AND
CONVEYORS SYSTEM. WEIGH HOPPER WITH ELECTRONIC LOADCELL FOR
Concrete Batching Plant PHP 14,076.00
AGGREGATES, CEMENT, WATER AND ADMIXTURE. CENTRAL TWINSHAFT
MIXER. HYDRAULIC SYSTEM AND COMPUTERIZED PLANT CONTROL
SYSTEM
Flywheel
No. Description Model Capacity Unit Rental Rate per Day
Horsepower
18 Others
SPT & Desanding Machine PHP 4,472.00
Power Broom, Towed Type WITH ENGINE 2 m WIDE 6 - 30 km/h SWEEPING CAPACITY PHP 1,044.32
Hyrdoseeding Machine PHP 7,616.00
Applicator Machine PHP 750.00
Kneading Machine PHP 1,500.00
Drop Hammer PHP 1,600.00
Drop Hammer w/ Accessories PHP 40,000.00
Cutting Outfit PHP 363.60
Bentonite Bin PHP 2,240.00
Bentonite Mixer PHP 1,384.00
Tremie Pipe Set PHP 2,560.00
Steel Wheel w/ Nylon Rope PHP 2,400.00
Pile Integrity Testing (Sonic) & Accessories (includes professional fee of Structural Engr.) PHP 520,000.00
Dynamic Pile Testing (includes professional fee of Structural Engr.) PHP 824,000.00
Pile Integrity Testing (Sonic) & Accessories (includes professional fee of Structural Engr.) PHP 296,000.00
Grinding Machine and Accessories PHP 603.04
Stressing (Jack) Machine PHP 20,000.00
Dolly PHP 9,992.00
Wood / Steel Ladder PHP 800.00
Improvised Bamboo w/ Bucket PHP 1,600.00
Asphalt Kettle/ Drum PHP 80.00