CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 4 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP

TABLE OF CONTENTS
COVER .............................................................................................................................................................................. 1
TABLE OF CONTENTS........................................................................................................................................................ 4
1.0 PURPOSE / / TUJUAN ....................................................................................................................................... 5
2.0 SCOPE // LINGKUP ........................................................................................................................................... 5
3.0 DEFINITIONS // DEFINISI .................................................................................................................................. 5
4.0 RESPONSIBILITIES // TANGGUNG JAWAB......................................................................................................... 6
5.0 TOOLS AND EQUIPMENT // PERALATAN DAN PERLENGKAPAN ....................................................................... 7
6.0 MATERIALS // BAHAN ...................................................................................................................................... 9
7.0 HEALTH, SAFETY, ENVIRONTMENT (HSE) // KESEHATAN DAN KESELAMATAN KERJA (K3) .............................10
8.0 PERSONAL PROTECTIVE EQUIPMENTS // ALAT PELINDUNG DIRI ..................................................................11
9.0 WORK METHODOLOGY // METODE KERJA ....................................................................................................12
11.0 REFERENCE DOCUMENT // DOKUMEN REFERENSI .......................................................................................14

4
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 5 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP
1.0 PURPOSE / / TUJUAN
To ensure that the pabrication of support tray cable and support piping is performed safely, efficiently
and in accordance with good work practice, as per Lamipak project job specification required. The
procedure is intended to provide general application guidance and establish quality control during
preparation and installation, resulting in good test results.
//Untuk memastikan bahwa pembuatan support tray cable dan support pipa dilakukan dengan Benar,
efisien dan sesuai dengan praktik kerja yang baik, sesuai dengan spesifikasi pekerjaan project Lamipak yang
dipersyaratkan. Prosedur ini dimaksudkan untuk memberikan panduan aplikasi umum dan menetapkan
kontrol kualitas selama persiapan dan pemasangan, sehingga menghasilkan hasil pengujian yang baik.
2.0 SCOPE // LINGKUP
This method statement is always be Fabrication Suport tray cable and Suport Pipe on the Lamipak
Indonesia New Plant Project, Cikande Banten. Accordance with the project specifications, manufacturer's
recommendations, drawings and regulations.
//Pernyataan metode ini berlaku untuk semua kegiatan pabrikasi support tray cable dan support pipa yang
akan dipasang di Proyek Pabrik Baru Lamipak Indonesia, Cikande Banten. Sesuai dengan spesifikasi proyek,
rekomendasi pabrikan, gambar, dan peraturan.
3.0 DEFINITIONS // DEFINISI

The supply of waste water from the Production Room uses Galvanized pipes and PVC pipes to the
concrete/concrete tank, then treated/processed leading to the separation stage is towards the sediment
tank, flocculant tank. Then it is processed repeatedly using a Water waste treatment system or can be
abbreviated as WWTP, until it becomes clean water and is ready to be used again.
To supporting of the pipes and cables. Support for cable trays and pipe is made using angle bar and
UNP.

// Suplai Air limbah dari Ruang Produksi menggunakan pipa Galvanize dan Pipa PVC Menuju Bak beton
/ Kongkrit, kemudian di olah / di proses menuju ketahap pemisahan yakni menuju pada tangki sendimen
tank, flocculan. Kemudian di proses berulang kali dengan sistim Water waste treatment atau dapat
disingkat dengan WWTP, hingga menjadi Air bersih dan siap untuk di manfaatkan kembali.
Untuk Memperkuat tanahan Beban berat yang di berikan pada pipa dan Kabel maka di buatlah Suport
atau tahanan Tray cable dan Suport pipa menggunakan Besi Siku dan UNP.

5
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 6 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP
4.0 RESPONSIBILITIES // TANGGUNG JAWAB
4.1 Project Manager // Manajer Proyek
Project Manager (MEP) will be responsible to manage, execute, complete, and handover the
construction activities within approved budgets and resources in compliance with Project Requirements as
specified in Project Specifications.
//Manajer Proyek (MEP) akan bertanggung jawab untuk mengelola, melaksanakan, menyelesaikan,
dan menyerahkan kegiatan konstruksi sesuai dengan anggaran dan sumber daya yang disetujui
berdasarkan persyaratan yang telah ditentukan dalam spesifikasi proyek.

4.2 Site Manager // Manajer Lapangan


Responsible for the implementation of good work procedures at the site and also to ensure that all
necessary resources are available, such as manpower, tools, and materials. The site manager must be able
to maintain the harmony at the site, so that the project can run smoothly, safely, as scheduled, and within
budget.
//Bertanggung jawab atas penerapan prosedur kerja yang baik di site dan juga memastikan bahwa
semua sumber daya yang diperlukan tersedia, seperti tenaga kerja, alat, dan bahan. Site manager harus
dapat menjaga keharmonisan di lokasi, sehingga proyek dapat berjalan dengan lancar, aman, sesuai
jadwal, dan sesuai anggaran.
4.3 MEP // Mechanical Electrical And Plumbing Engineer
Responsible for the overall of MEP-Mechanical Electrical And Plumbing work. Ensure that related
documents have been submitted and approved, and ensure that related parties have received the
information and can carry out the work in accordance with the applicable procedures and regulations.
//Bertanggung jawab atas keseluruhan pekerjaan MEP-Mechanical. Memastikan bahwa dokumen
terkait telah disampaikan dan disetujui, serta memastikan bahwa pihak terkait telah menerima informasi
tersebut dan dapat melaksanakan pekerjaan sesuai dengan prosedur dan ketentuan yang berlaku.
4.4 Quality Control Supervisor // Pengawas Kualitas Pekerjaan
Responsible for inspection and verification that the installation has been properly implemented and
the inspection is carried out according to the approved Inspection Test Plan in a timely manner, and also
for ensuring that the QC documents have been signed by all authorized parties.

6
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 7 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP
//Bertanggung jawab untuk inspeksi dan verifikasi bahwa pemasangan telah diterapkan dengan benar
dan inspeksi dilakukan sesuai dengan Rencana Uji Inspeksi yang disetujui secara tepat waktu, dan juga
untuk memastikan bahwa dokumen QC telah ditandatangani oleh semua pihak yang berwenang.
4.5 Foreman // Mandor
Responsible for the preparation of works and supervise the workers in the site, and ensures that the
workers work in accordance of applicable procedures and HSE has been implemented.
//Bertanggung jawab atas persiapan pekerjaan dan mengawasi pekerja di lokasi, serta memastikan
pekerja bekerja sesuai prosedur yang berlaku dan HSE telah diterapkan.

4.6 HSE Officer // Petugas HSE


Responsible for the implementation of all safety requirements and to ensure that the works are
undertaken in a safe and proper manner, all in accordance with the approved HSE Plan.
//Bertanggung jawab atas penerapan semua persyaratan keselamatan dan untuk memastikan bahwa
pekerjaan dilakukan dengan cara yang aman dan benar, semuanya sesuai dengan Rencana HSE yang telah
disetujui.
5.0 TOOLS AND EQUIPMENT // PERALATAN DAN PERLENGKAPAN

Cutting Well
//Alat Potong

Drille machine/ grinder


//Alat Bor, Grinda

7
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 8 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP

Wrench set
//Set kunci pas

Ladders & Scaffolds


//Alat tangga kerja ketinggian

Hammer, Brush
//Palu

Welding Machine
//Mesin las,

Weld Mask
//Kedok Las

Gloves //Sarung Tangan

8
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 9 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP

CIG Eye Protection Angler// Kacamata safety

6.0 MATERIALS // BAHAN

Electrode
//Kawat Las

Paint Brush // Kuas cat

Paint anti rust or zinchromate/ Cat


anti karat

9
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 10 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP

Paint primer // cat dasar

Bolt, Nut, Washer

UNP 100 X 50 X 5 mm
UNP 50 X 30 X 4 mm
UNP 80 X 50 X 5 mm

Angel bar MS50 X 4 MM


Angel bar MS40 X 4 MM

7.0 HEALTH, SAFETY, ENVIRONTMENT (HSE) // KESEHATAN DAN KESELAMATAN KERJA (K3)
Starting instructions will be given by the supervisors at the start of each activity to explain the
methodology of works and to communicate safe working procedures to the operatives. Toolbox talk
meetings will be held for each crew, on group or employees, regarding HSE Policies for related works.

10
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 11 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP
//Instruksi awal akan diberikan oleh pengawas pada awal setiap kegiatan untuk menjelaskan
metodologi pekerjaan dan mengkomunikasikan prosedur kerja yang aman. Toolbox meeting akan
diadakan untuk setiap kru, dalam kelompok atau karyawan, mengenai kebijakan HSE terhadap pekerjaan
terkait.
8.0 PERSONAL PROTECTIVE EQUIPMENTS // ALAT PELINDUNG DIRI

Safety helm
//Pelindung kepala

Safety Shoes
//Pelindung kaki

Safety Vest
//Rompi pelindung

Safety Gloves
//Pelindung tangan

Eye protector
//Pelindung mata

Fire extinguisher
//Pemadam api ringan

Full body harness


//Sabuk pengaman tubuh

11
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 12 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP

Safety Lifelines
//Tali pengaman

9.0 WORK METHODOLOGY // METODE KERJA


9.1 Prepare the documents needed //Persiapkan dokumen yang dibutuhkan;
- Permit to work //Izin kerja
- Shop drawing //Gambar kerja
- Job safety analysis //Analisa bekerja aman
- Method statements //Metode kerja
- Site clearances or site handover report //Laporan kesiapan lokasi
9.2 Ensure the workers informed and understand the works //Pastikan para pekerja sudah diinfokan dan
paham dalam bekerja
9.3 Prepare the materials and the tools //Persiapkan peralatan dan material
9.4 System Metode Pabrication support Tray cable and support piping // Metode sistim pembuatan
support tray cable dan support pipa.
9.4.1 UNP And Angel Bar

The UNP and angle bar that used must be applicable specifications and drawings.//Besi UNP dan
Besi siku yang dipergunakan harus sesuai spesifikasi dan gambar yang berlaku.

9.4.2 Paint //cat


¤ Before basic painting, each Cable Tray Support and Pipe Support is coated or smeared with
anti-rust (zincchromate) several times until evenly distributed, then after drying go to the
next stage.
//Sebelum pengecatan dasar setiap Suport Tray kabel dan Suport Pipa di lapisi atau di oleskan
dengan anti karat ( zinchromate ) beberapa kali sampai merata, kemudian sesudah kering
menuju ke tahap berikutnya.

12
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 13 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP
¤ Painting requires the same color and type as the specified shop drawing // Pengecatan
memerlukan warna dan type yang sama sesuai dengan Gambar yang telah di tentukan.
¤ Each coat of paint is repeated several times until the paint is evenly distributed on the Suport
Tray cable and Suport piping // Setiap pelapisan Cat diulang beberapa kali sampai merata
pada Suport Tray kabel dan Suport Pipa.
9.4.3 Unloading Iron UNP And Angel Bar //Unloding Besi UNP dan Besi siku
1. Before making Tray Cable Supports and Pipe Supports, prepare the tools and
materials that will be used // Sebelum pembuatan Suport Tray cable dan Suport pipa,
Persiapkan alat dan bahan yang akan digunakan.
2. Cut the cable tray and angel bar according to the dimensions shown in the Shop
drawing. // potong Tray cabel dan Angel bar sesuai ukuran yang terdapat pada
gambar kerja,
3. After cutting it according to the Shop drawing, clean off the “Gram” on the surface
materials, then welding is carried out evenly. and make sure there are no gaps
between the sides // Setelah di potong dengan sesuai ukuran yang ada pada gambar
kemudian, di bersihkan sisa hasil pemotongan pada Besi siku tersebut. Kemudian
pengelasan dilakukan secara merata, dan dipastikan tidak ada celah antara sisi nya.
4. After the desired shape of the Cable Tray Support and Pipe Support is finished, then
the welding results are finished, after finishing, proceed to the painting stage, after
painting, then a hole is made which is useful for attaching the support in the position
recommended on the working drawings.//Sesudah menjadi sesuai yang diinginkan
bentuk dari Suport Tray cabel dan Suport pipa kemudian di finishing hasil dari
pengelasan , setelah finishing lanjut ke tahap pengecatan, sesudah di cat , kemudian
dibuat lubang yang berguna untuk menempelkan support tersebut pada posisi yang
di anjurkan pada gambar kerja.

9.5. Accecories
1. U-bolt
2. Dynabolt
3. Longdrat
4. SDS ( Self Drilling Screw )

13
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 14 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP
10. JOB SAFETY ANALYSIS (JSA)

Hazards Done By
Job Step Sequence Controls and Checks Required
Identified Action By
- Tidak tergesah gesah pada saat
mobilisasi material/ Not in a hurry
when mobilizing materials
- Terjepit dan - pada saat menurunkan material di
1. Persiapan alat Tertimpa kordinasikan terlebih dahulu sesuai
kerja/ Tool material/ aba-aba/ at the time of unloading the SM/SPV/EHS
preparation Pinched and material coordinated in advance
crushed material according to the instructions
- Gunakan APD (sarung tangan) sesuai
dengan pekerjaannya/ Use PPE
(gloves) in accordance with the job

- Pastikan Pada saat Pemasangan pipa,


pada saat penaikannya harus
menggunakan Tambang dan Cenblock,
dan ikat dengan benar / Make sure at
- Kejatuhan Pipa /
the time of pipe installation, at the
Pipe Fallout
- Terkilir saat time of raising it must use rope or
angkat pipa/ Chain Block, and tie it correctly
Sprained when - Pastikan juga penggantung sudah
lifting pipe terpasang terlebih dahulu dan
2. Pemasangan Pipa - Terpercik Gram terpasang dengan benar./ Also make SM/SPV/EHS
/ Erection pipe pada saaat sure the hanger is installed first and
grerinda/ installed correctly.
Splashed Gram
on the grerinda - Pekerja yg berkompeten/ Competent
workers
- Gunakan alat pelindung diri sesuai
dengan pekerjaannya/ Use personal
protective equipment according to the
job.

11.0
REFERENCE DOCUMENT // DOKUMEN REFERENSI

14
PT. DIRGAMAYA DAYA
DHARMALAKSANA
Add:JL.Komjen Pol M. Jasin No.71
PT. LAMI PACKAGING INDONESIA Cimanggis Depok, Jawa Barat 16451

CONSTRUCTION METHOD
Document No. Rev. CONTRACT No.
Page 15 of 15
DDD-LMIND-09-DC-PLA-001 A WWTP
 DDD-LMIND-09-PP-DWG-005
 DDD-LMIND-09-MS-DWG-016
 DDD-LMIND-09-MM-LST-039

15