Professional Documents
Culture Documents
Title of the project activity Rang Dong Oil Field Associated Gas Recovery and Utilization
Project
Version number of the PDD 9.0
Sectoral scope and selected Sectoral scope 10 - Fugitive emission from fuels (solid, oil and
methodology(ies), and where gas)
applicable, selected standardized Methodology – AM0009 Version 2.1
baseline(s)
The purpose of the project activity is the recovery and utilization of gases produced as a by-
product of oil production activities at the Rang Dong oil field, located about 140 kilometres off the
south-eastern coast of Vietnam.
Prior to 2002, this by-product gas was disposed at the platform via a combustion process known in
the industry as flaring. During this process, waste gas was burned on site to produce a waste
stream consisting largely of CO2 but also containing uncombusted remnants of the original waste
stream. The amount of by-product gas not burned depends on the efficiency of the flare
equipment.
Project activity includes construction of a gas pipeline and compressor facilities to recover and
transport the by-product gas, which would otherwise have been flared. As a result of this reduction
in flaring activities, CO2 emission has been reduced. The gas recovered is processed into dry gas
(mostly CH4), as well as LPG (butane and propane), and condensate (hydrocarbon molecules
containing five or more carbons). The dry gas is supplied to nearby power plants (Phu My and Ba
Ria) and will be sent to a local fertilizer plant, whereas LPG (Liquid Petroleum Gas ) and
condensate is consumed domestically as home cooking fuel and is used to produce gasoline.
The baseline scenario is the continued flaring of the associated gas produced from Rang Dong
fields. The baseline scenario is determined by assessing and comparing four possible baseline
scenarios in addition to the project scenario from the view points of legislative issues, technical
issues and economical attractiveness as summarized below and elaborated in B.4:
(a) Legal issue: Pursuant to Petroleum Law, the Vietnamese Government allowed the flaring of
associated gas in Block 15-2 to support crude oil production. Therefore, recovery of associated
gas is not required by law, though the Government prefers efficient use of its natural resources
to help reduce its dependence on imported fuel.
(b) Commercial viability: As explained in further detail below, the commercial viability of the
project would be questionable without the availability of CERs.
(c) Lack of sufficient alternatives: Direct venting of CH4 and other produced gasses to the
atmosphere is prohibited by the Vietnamese Government. Re-injection of associated gas into the
oil reservoir can be carried out in order to enhance oil recovery, but it is not carried out since gas
injection is more expensive and less efficient than water injection. Furthermore, there is no
conclusive proof that such gases would not eventually be emitted to the atmosphere (this may
result in emission of CH4, a more potent GHG than the CO2 associated with flaring).
Consumption of associated gas at the oil field for the purpose of onsite power generation is an
activity currently being carried out but the amount utilised is small compared to the amount
recovered. Recovery, land transport and utilization of gas (which is the project activity) is not
considered commercially attractive relative to other investment opportunities.
In conclusion, the emission reductions would not occur in the absence of the proposed project
activity.
Construction of the gas pipeline and compressor enables the transport and use of associated
gases that would otherwise have to be flared (ie. burned and emitted as CO2) for security and
economic reasons. Installation of compressor is required since it is difficult to transport the gases
by wellhead pressure alone. Since compression is required for gas transportation only, installation
of the compressor facility does not result in increased production of gases beyond what would
Rang Dong oil field, about 140km off the coast of south-eastern Vietnam (see attached map).
The project takes place offshore. The nearest major city is Vung Tau City, administrative centre of
Baria – Vung Tau Province, where the gas processing plant is located 140 km from Rang Dong oil
field.
m
0
Ho Chi Minh
10
m
20 m
Ho Chi Minh
60
m
50
Vung Tau
10° 10°
0m
Rang Dong
2 00
oil field
1000 m
8° 8°
South-eastern
coast of Vietnam
106° 108° 110°
The technology consists of a pipeline and a compressor facility. The pipeline was constructed in
full compliance with environmental regulations, and was subject to an environmental impact
assessment (please see section D). The compressor facility was installed on an existing facility in
October 2003, and thus there was no need to construct additional facilities such as a wellhead
platform. Therefore, the impact to the environment was kept to a minimum. No other additional
construction (e.g. facilities for sweetening) was necessary.
Specification
Pipeline 46.5km in length, from Rang Dong oil field to Bach Ho oil field (to be
connected to the existing pipeline from Bach Ho to onshore gas
processing plant)
- Design life: 30 years
- ANSI rating: ANSI class 600
- MAOP: 100barg (1450psig)
- Design flow rate: 4.5 million Nm3/d
- Material: API 5L X 65
- Outside diameter: 16”
- Corrosion allowance: 3mm (0.125in)
Compressor Currently anticipated specification:
facility - Turbine power: 9,104kW (35dec C)
- Compressor speed: 13,768
- BKW inc GB loss 8,711
- Efficiency 82.4%, 76,5%
Project Scheme
1
Phuong Dong Certificate of Handover dated 29 July 2008 and Daily Executive Report dated 24 August 2008
2
Commercial Discovery was made on 3rd May 2007
3
Design capacity of compressor and pipeline are 2.4 and 4 million m3 per day while expected exportable gas quantity of Rang Dong and Phuong Dong is less than
3
1.6 million m per day
4
Clause 7.1 (c) of JOA
7
Notice of Su Tu Vang First Gas
8
The confidential agreement between JVPC and PVGas for exchanging data in preparation for connection work was signed on 1st Aug 2007.
9
The design capacity of Rang Dong-Bach Ho pipeline is 4 million m3 per day while maximum exportable gas quantity of Rang Dong, Phuong Dong and Su Tu Vang
fields is 2.5 million m3 per day.
10
Notice of Ca Ngu Vang First Gas dated 15 Oct 2008 and Gas Deliver Receipt Report 2010 dated 28 March 2011.
These above post registration changes require certain revisions to the monitoring plan as described in section B6.1 to ensure that the level of
accuracy or completeness in the monitoring and verification process is not reduced; However, such changes would not adversely affect the
conclusions of the validation report of the registered PDD as further explained in detailed in relevant sections hereinafter.
(*1) Vietnam Oil and Gas Group, the Vietnamese State oil and gas company duly established
under the laws of Vietnam and having its registered office at 18 Lang Ha Street, Hanoi,
Vietnam (hereinafter referred to as “Petrovietnam”);
(*3) Japan Vietnam Petroleum CO., LTD, a company established and existing under the laws of
Japan and having its registered office at 6-3, Otemachi Chome, Chiyoda-Ku, Tokyo 1005-8163,
Japan (hereinafter referred to as “JVPC”)
(*4) ConocoPhillips (U.K.) Gama Limited, a company incorporated under the laws of England
(Registration No 3716310) and having its registered office at Portman House, 2 Portman
Street, London W1H6DU (hereinafter referred to as “ConocoPhillips”)
The contact for CDM Project Activity is Japan Vietnam Petroleum Co. Ltd.
None
The project activity is developed with reference to the approved baseline and monitoring
methodology AM0009 / Version02.1:” Recovery and utilization of gas from oil wells that would
otherwise be flared”
- Gas at oil wells is recovered and transported in pipelines to a process plant where dry gas, LPG
and condensate are produced;
- Energy required for transport and processing of the recovered gas is generated by using the
recovered gas;
- The products (dry gas, LPG and condensate) are likely to substitute in the market the same type
of fuels or fuels with a higher carbon content per unit of energy;
- The substitution of fuels due to the project activity is unlikely to lead to an increase of fuel
consumption in the respective market;
- In the absence of the project activity, the gas is mainly flared;
- Data (quantity and fraction of carbon) is accessible for the products of the gas processing plant
and for the gas recovered from other oil exploration facilities in cases where these facilities supply
recovered gas to the same gas processing plant.
The post registration changes as described in the section A.3 happened outside of project
boundary and have no direct relation to the project activity. The same existing compressors and
pipelines constructed under project activity continue being used to recover and transport the gas
from Rang Dong and new fields to shore without necessity to make any modification to the design
or operation parameters of the existing systems. The scheme and condition of the project activity
remain unchanged; therefore there isn’t any impact of the post registration changes to the
applicability and application of approved methodology AM0009 version 02.1.
The facilities which are under the control of the Project Participants are as follows:
•Facilities currently installed and being developed at the Rang Dong oil field
•Transportation facilities (pipeline from Rang Dong oil field to Bach Ho oil field)
Figure B-3: Diagram of project boundary, infrastructure and monitoring points with CDM project
activity
Boundary of
project activity B
Rang Dong oil field Gas
processing
Su Tu Vang plant
CO2 CO2 Oil field
On-site
X2
Flaring
consumption
Recovery C X’
Production Transportation
Oil A1 A
wells X
Back Ho
Oil field
A2
Phuong Dong Ca Ngu Vang Rong & DoiMoi
oil field Oil field Oil field
Legend:
Baseline infrastructure
Baseline Project Post registration Project infrastructure
infrastructure infrastructure changes Post registration changes
(1) Options
The following options are conceivable:
•Option 1: Release to the atmosphere at the oil production site (venting).
•Option 2: Flaring at the oil production site.
•Option 3: On-site consumption.
•Option 4: Injection into the oil reservoir.
•Option 5: Recovery, transportation, processing and distribution to end-users.
(2) Criteria
The following criteria are chosen:
•Legal issues (are the options permitted by law or agreement?)
•Economic- attractiveness (are the options economically attractive?)
Gas production Quoted from the production profile in the Full Field
Development Plan
Gas price Agreed price and escalated by the agreed ratio in the PSC
Amendment
Profit sharing Profit (gas sales minus cost recovery) shared between project
participants and host country as agreed in the PSC
Amendment.
Analysis of the Project Participants by above parameters have concluded that the IRR for
recovery and land transport of associated gas is about 8 to 9%, considering the cost of the
compressor and pipeline, as well as revenue from gas sales. This IRR is based on the
assumption that all of the produced gas is to be sold to the power plants. This is not likely,
11
The average carbon content of associated gas exported from Rang Dong field to shore before (Rang Dong
gas only) and after (Rang Dong and Phuong Dong gas) over the same period of 2.5 years are 0.683 and
0.682 kg-C/m3 respectively.
12
Paragraph 2 page 8 of Vietnam Analysis Report dated 9 May 2012 by EIA
13
Article 38.2 of Amendment to Petroleum Law ref. 10/2008/QH12 dated 3th June 2008 specifies “Ministry of
Industry and Trade shall be responsible to make decisions on flaring associated gas”. Article 28.3 of
Decision 84 dated 15th December 2010 amending Regulation on Petroleum Production ref. 163 dated 7th
September 1998 stipulated “an Operator shall submit to the Ministry of Industry and Trade for consideration
and approval of the associated gas flaring plan for each year with respect to field”
14
EIA report “Vietnam Analysis Briefs” dated 9th May 2012, page 5, paragraph 3.
CDM consideration
(1) Project history
As the operator of the Rang Dong oil field, JVPC is responsible for leading the CDM project
activity. Nippon Oil Group (hereinafter referred to as “Nippon”), to which JVPC belongs, has
been actively studying and implementing GHG management practices since beginning of
2000. That work, which includes efforts to implement the CDM, is summarized below.
(a) Drivers for GHG emission reduction in Japan
Japan and the Kyoto Protocol
Under the terms of the Kyoto Protocol, Japan has the obligation to reduce its national GHG
emissions to 6% below its 1990 baseline emissions. When the Kyoto Protocol was drafted
As mentioned in section B.2, the baseline scenarios, the project emission sources and the
greenhouse gases included in the project boundary have been identified according to methodology
AM0009 (version 2.1). The project emission reduction is equal to the difference of the baseline
emissions, project emissions and leakage emissions.
The project activity meets with applicability condition of the AM0009 version 2.1 described below:
- Gas at oil wells is recovered and transported in pipelines to a process plant where dry gas, LPG
and condensate are produced;
- Energy required for transport and processing of the recovered gas is generated by using the
recovered gas;
- The products (dry gas, LPG and condensate) are likely to substitute in the market the same type
of fuels or fuels with a higher carbon content per unit of energy;
- The substitution of fuels due to the project activity is unlikely to lead to an increase of fuel
consumption in the respective market;
- In the absence of the project activity, the gas is mainly flared;
- Data (quantity and fraction of carbon) is accessible for the products of the gas processing plant
and for the gas recovered from other oil exploration facilities in cases where these facilities supply
recovered gas to the same gas processing plant.
Baseline Emissions:
Baseline emission consists of four elements:
With:
mcarbon, A', y VA, y Wcarbon, A, y VA1, y Wcarbon, A1, y
Where:
BLy Are the baseline emissions during the period y in tons of CO2 equivalents.
mcarbon, A', y Is the carbon quantity recovered at point A attributed to Rang Dong oil field
during the period y in ton.
V a,y Is the volume of gas recovered from the oil field at point A in Figure D2-1
during the period y in m3.
w carbon, A, y Is the average content of carbon in the gas recovered at point A in Figure
D2-1 during the period y in kg-C/m3.
V A1, y Is the volume of gas recovered from Phuong Dong oil field at point A1 in
Figure B6-1 during the period y in m3.
Wcarbon, A1, y Is the average content of carbon in the gas recovered at point A1 in Figure
B6-1 during the period y in kg-C/m3.
Fugitive emission of CH4 could be considered in the course of flaring, however, for the interest of
conservativeness, it is not taken into account.
15
The result of Uncertainty Study conducted by accredited third party METCO concluded that the uncertainty
of Phuong Dong gas flow meter at MBD-120 is ±3% (section 2.1.4.5 page 28)
The baseline scenario, as explained at section B4, is based on the continuation of flaring of
associated gas at oil field. The scenario would, if required after the legislative movement at
COP/MOP, take into consideration of future possibility of revision. Currently there is no sign
that Vietnam regulation would require stopping the flaring of associated gas. Therefore,
regulatory changes related to flaring will be monitored every year.
Technical improvement of gas injection is not expected as explained at section B4. However,
the project activity will continue monitoring of technical improvement, which is considered to
be a risk to the baseline.
Project Emissions
Source of project emission is composed of five elements, in which “CO2 emission caused by
combustion” and “CH4 emission caused by fugitive emission” will be taken into consideration in
accordance with AM0009 version 2.1. The reasons are explained below:
<Five elements of GHG emission>
- CO2 emission caused by combustion
- N2O emission caused by combustion
- CH4 emission caused by uncombusted associated gas
- CH4 emission caused by fugitive emission
- CH4 emission from transport of the gas in pipelines when accidental events occur
Point B Quantity of dry gas that is produced in the gas VB,dry gas,y (m3 / year)
processing plant at point B
Point B Average content of carbon in dry gas at point B w carbon,B,dry gas,y (kg-C /
m3)
Quantity of carbon in each substance is derived by multiplying the quantity of each substance
with the average carbon content of each substance.
(d) Calculation of CO2 emission of leakage
Leakage from the project occurs since exported gas must be processed before being used as
power plant fuel and other products. It is assumed here that the carbon equal to the difference
1
PECO 2,other , fuel , y m fuel, y NCV fuel EFCO 2, fuel
1000 Fuels
(2)
Where:
PE CO2, other fuels, y Are the CO2 emission due to consumption of other fuels than the recovered
gas due to the project activity during the period y in tons of CO2
m fuel, y Is the quantity of a specific fuel type that is consumed due to the project
activity during the project y in kg.
NCV fuel Is the net calorific value of the respective fuel type in kJ/kg
EF CO2, fuel Is the CO2 emission factor of the respective fuel type in kg CO2/kJ
Since PE CO2, other fuels, y is any fuel purchased externally in case of emergency; it is not used for
calculation. The primary purpose of the data is for emergency preparedness.
where:
PE CH4, plants oil field, y Are the CH4 emissions from the project activity in the Rang Dong oil field
during the period y in tons of CO2 equivalents.
GWPCH4 Is the approved Global Warming Potential for CH4.
T equipment, oil field Is the operation time of the equipment in hours
w CH4, A, y Is the average CH4 weight fraction in the respective stream in kg-CH4/kg
EF equipment Is the appropriate emission factor from Table B6-1 in kg/hour/equipment
(b) CH4 emission from transport of the gas in pipeline under the normal operation condition
Fugitive emission from pipeline is negligible since the pipeline was constructed using the
state-of-the art material: API 5L X 65 is used and ANSI rating is ANSI class 600. Furthermore,
responsibility of maintenance and operation is strictly defined among project participants as
attached and pipeline is kept in a good condition.
In the interest of conservativeness, however, fugitive emission (containing CH4) through the
pipeline is calculated using the parameters contained in the study by the U.S. Environmental
Protection Agency (EPA-453/R-95-017, Table 2-4) as per AM0009 version 2.1.
1
PECH 4 , pipeline , y GWPCH 4 wCH 4, pipeline EFequipment Tequipment , pipeline
1000 equipment
(4)
where:
PE CH4, pipleline, y Are the CH4 emissions from the project activity during the transport of the
associated gas in pipeline under the normal operation condition during the
period y in tons of CO2 equivalents.
GWPCH4 Is the approved Global Warming Potential for CH4.
w CH4, pipeline, y Is the average CH4 weight fraction in the respective stream in kg-CH4/kg
EF equipment Is the appropriate emission factor from Table B6-1 in kg/hour/equipment
T equipment,pipeline Is the operation time of the equipment in hours
PECH 4, pipeline , accident GWPCH 4 (VA,t , accident Vremain , accident ) WCH 4, pipeline , accident (5)
with:
VB ,accident t accicdent F (t 2 t1 ) F
Pp Ts
Vremain,accident d 2 L
Ps T p
where:
PECH4, pipeline, accident Are the CH4 emission from the project activity due to transport of
the recovered gas in the pipeline when the accidental event
happens in tons of CO2 equivalents.
GWPCH4 Is the approved Global Warming Potential for CH4.
VA, t, accident Is the volume of gas supplied from the oil well at point A from the
time the gas leakage started until the shutdown valves closed the
pipeline in m3.
Vremain,accident Is the volume of gas remaining in the pipeline after the shutdown
valves close the pipeline in m3.
W CH4, pipeline, accident Is the average CH4 weight fraction in the gas recovered at point A
in ton-CH4/㎥
taccident Is the time difference between t1 and t2 determined as “retention
time” in seconds.
t1 Is the time the gas leakage caused by the accident occurred. “t1”
is determined based on the continuous monitoring data such as
pressure etc.
t2 Is the time that the shutdown valves closed both the upstream
and downstream pipeline. “t2” is determined based on the
operation data.
F Is the flow rate of gas supplied from the oil well at point B in
m3/seconds.
d Is the radius of the pipeline in meters. The data is derived from P
& I (Piping and Instrument).
π Is the ratio of the circumference of a circle to its diameter.
L Is the length of the pipeline in meters. The data is derived from P
& I (Piping and Instrument).
Pp Is the pressure in the pipeline when the shutdown valves close
both the upstream and downstream of the pipeline in atm.
Version 05.0 Page 30 of 69
CDM-PDD-FORM
Ps Is the standard pressure in atm.
Tp Is the temperature in the pipeline when the shutdown valves close
both the upstream and downstream of the pipeline in Centigrade.
Ts Is the standard temperature in Centigrade.
Leakage
(1) CO2 emission due to fuel combustion for recovery, transport and processing of the gas
Emission outside of the project boundary occurs upstream of shipping point. Most of the emission
is caused by the operation of Dinh Co Gas Processing Plant. Dinh Co Gas Processing Plant has
the following components that emit CO2
・ Three Gas turbine generators (Two are for operation use and one is for stand-by)
・ One Diesel generator (stand-by)
・ Flare header
Emissions from the gas processing plant can be calculated under the assumption that the
difference between the carbon contained in the associated gas imported into the gas processing
plant and the carbon contained in the products (dry gas, LPG and condensate) is released into the
atmosphere as CO2. This emission figure represents the amount of CO2 emission caused by in-
house consumption and flaring of associated gas upstream of shipping point of the gas products.
G as S crubber
V -101
Inlet C om presser
V 01011A ~D → K -1011A ~D → E-1015A ~D
Flare header
D ehydrator
V -06A /B
S lug C atcher
S C -01、S C -02 S ales G as
G as P rocessing P lant
G PP
G as turbine generator
LP G 、C ondensate
LP G
D rain Flare
C ondensate T ank
TK -21 C ondensate
P roduced W ater
Flush D rum
V -52
O ff S pec.
B urn P it C ondensate B ullet
V -21C
Since associated gas exported from Rang Dong oil field and Bach Ho oil field are mixed and
processed simultaneously, it is necessary to take into account only CO2 emission occurring as a
result of gas exported from Rang Dong oil field from the project activity. Therefore, the CO2
emissions attributable to gas exported from Rang Dong oil field and Bach Ho oil field upstream of
with
m carbon, A, y = V A,y * w carbon, A, y
m carbon, A’, y = V A,y * w carbon, A, y – VA1,y * w carbon, A1, y
m carbon, B, y = V dry gas, B, y * w carbon, dry gas, B, y+ m LPG, B, y * w carbon, LPG, B, y+ m condensate, B,y * w carbon,
condensate, B, y
m carbon, X, y = V X,y * w carbon, X, y
m carbon, X2, y = V X2,y * w carbon, X2,
Where:
PE CO2,gas,y Are the CO2 emissions from the project activity due to combustion,
flaring or venting of recovered gas during the period y in tons of CO2.
m carbon, A, y Is the quantity of carbon in the recovered gas from the project area at
point A in Figure B6-1 during the period y in kg.
m carbon, A’, y Is the quantity of carbon attributable to Rang Dong oil field at point A in
Figure B6-1 during the period y in kg.
m carbon, B, y Is the quantity of carbon in the products (dry gas, LPG, condensate)
leaving the gas processing plant at point B in Figure B6-1 during the
period y in kg.
m carbon, X, y Is the quantity of carbon in the recovered gas from Bach Ho oil field at
point X in Figure B6-1 during the period y in kg.
V dry gas, B, y Is the volume of dry gas that is produced in the gas processing plant
(Point B Figure B6-1) during the period y in m3.
m LPB, B, y Is the quantity of LPG that is produced in the gas processing plant
(Point B Figure B6-1) during the period y in kg.
m condensate, B, y Is the quantity of condensate that is produced in the gas processing
plant (Point B Figure B6-1) during the period y in kg.
V A, y Is the volume of gas recovered at point A Figure B6-1 during the period
y in m3.
V A1, y Is the volume of gas recovered at point A1 Figure B6-1during the period
y in m3. As explained in equation (1), accuracy level of Phuong Dong
gas flow meter (3%) is lower than the level of existing monitoring plan
(1%), the difference in accuracy which is 2% is deducted from the value
measured by the Phuong Dong gas flow meter at point A1. Such
adjustment is conservative as it will increase the Leakage and lead to
the reduction of CERs.
V X, y Is the volume of gas recovered at point X Figure B6-1 during the period
y in m3.
w carbon, A, y Is the average content of carbon in the gas recovered at point A in
Figure B6-1 during the period y in kg-C/m3.
w carbon, dray gas, B, y Is the average content of carbon in dry gas at point B in Figure B6-1
during the period y in kg-C/m3.
w carbon, LPG, B, y Is the average content of carbon in LPG at point B in Figure B6-1
during the period y in kg-C/kg.
w carbon, condensate, B, y Is the average content of carbon in condensate at point B in Figure B6-
1 during the period y in kg-C/kg.
w carbon, A, y Is the average content of carbon in the gas recovered at point X in
Figure B6-1 during the period y in kg-C/m3.
Below is the conversion factor based on the recent actual measured data:
(572 kg/m3) / (65.7kg/kmol) * (23.645 m3/kmol) = 206 m3(gas)/m3(liquid)
Where:
572 kg/m3: measured density of condensate in an average
65.7 kg/m3: measured molecular weight of condensate in an average
23.645 m3/kmol: standard m3 factor
Assumed that the molecular weight of the condensate is 25kg/kmol, the conversion
factor is 542. The composition of condensate (wcondensate X’,y) will be monitored to confirm
the conservativeness every month.
where:
PE CH4, plants processing, y Are the CH4 emissions from the project activity in the gas processing
plant during the period y in tons of CO2 equivalents.
GWPCH4 Is the approved Global Warming Potential for CH4.
T equipment, processing Is the operation time of the equipment in hours
Version 05.0 Page 33 of 69
CDM-PDD-FORM
w CH4, stream, processing Is the average CH4 weight fraction in the respective stream in kg-CH4/kg
EF equipment Is the appropriate emission factor from Table B6-1 in kg/hour/equipment
Emission Reduction
Emission reductions are calculated as the difference between baseline and project emissions,
taking into account any adjustment for leakage:
EF y = BL y – PE CO2, other fuel, y – PE CO2, gas, y – PE CH4, plants oil field, y – PE CH4, plants, y – PE CH4, pipeline, y –
PE CH4, pipeline, accident – Ly
(8)
with
PE CH4, plants, y = PE CH4, plants oil field, y + PE CH4, plants processing, y
Where:
EF y Are the emission reductions of the project activity, adjusted for leakage,
during the period y in tons of CO2 equivalents.
BLy Are the baseline emissions during the period y in tons of CO2 equivalents.
PE CO2, gas, y Are the CO2 emissions from the project activity due to processing of
recovered gas during the period y in tons of CO2 equivalents.
PE CO2, other fuels, y Are the CO2 emissions due to consumption of other fuels than the
recovered gas due to the project activity during the period y in tons of CO2
equivalents.
PE CH4, plants, y Are the CH4 emissions from the project activity at the gas recovery facility
and the gas processing plant during the period y in tons of CO2 equivalents.
PE CH4, pipeline, y Are the CH4 emissions from the project activity due to transport of the
recovered gas in the pipeline during the period y in tons of CO2 equivalents.
PE CH4, pipeline, accident Are the CH4 emissions from the project activity due to transport of the
recovered gas in the pipeline when accidental event occurs in tons of CO2
equivalents.
Ly Are any leakage emissions during the period y in tons of CO2 equivalent.
PE CH4, plants oil field, y Are the CH4 emissions from the project activity at the gas recovery facility
during the period y in tons of CO2 equivalents.
Choice of data or Upper limit value specified in Table 1.4 of Chapter 1 of Vol 2 of
Measurement methods 2006 IPCC Guidelines
and procedures
Purpose of data This value is applied for project emission calculation
Additional comment No comment
Choice of data or Upper limit value specified in Table 1.2 of Chapter 1 of Vol 2 of
Measurement methods 2006 IPCC Guidelines
and procedures
Purpose of data This value is applied for project emission calculation
Additional comment No comment
Baseline emissions at the oil field assumes that all of the associated gas is converted into CO2
either through flaring. The formulae (1) described in B6-1 is used to estimate the CO2 emission.
The estimation is based on the following data:
- The gas composition data: (Table B6-3-1)
- Projection of production volume of associated gas and export volume of associated gas:
Full Field Development Plan
Base case assumes that the probability of gas emissions exceeding this value is 50%; High
case assumes that such probability is 10%.
CO2 emission as a result of flaring or in-house consumption is calculated from the volume of gas
multiplied by its carbon content. Carbon content can be calculated from the fractional
composition using the following table
C Molecular Carbon
Source: Coordination Operation Procedure from Rang Dong – Bach Ho Pipeline Project between
JVPC-VSP-PVGC
(Doc Number: PVGC. OP. 904-Rev: 01 Page 8)
- Projection of production volume of associated gas and export volume of associated gas:
Table B6-3-2 is projection of baseline CO2 emission as a result of flaring based on Full Field
Development Plan. It is calculated using both Base Case and High Case production. The Base
Case is considered to be the most probable case as described in “(2) Projection of associated
gas production” in B.6.1 above. Baseline emissions at the oil field assume that all of the
associated gas is converted into CO2 either through flaring or in-house consumption.
Project Emissions:
(1) CO2 emission
It is expected that associated gas produced but not exported via pipeline is emitted as CO2,
through in-house consumption including fuel combustion for recovery which is already offset
from the baseline emission since baseline emission is based on the volume of gas monitored at
point A as per AM0009 version 2.1.
Therefore, CO2 emission should be calculated only in case when other fuels than the recovered
gas is consumed in the boundary.
Based on (a), (b) and (c), the fugitive emission of CH4 will be:
(2.976 + 0.03147) * 50.1 % * 8.76 * 21 = 277 ton / year
Leakage
Some portion of associated gas supplied from Rang Dong oil field is consumed at the gas
processing plant to produce gas product. The formulae to estimate the CO2 emission is described
in B.6.1.
Where:
V a,y Is the estimated volume of gas recovered from the oil field at point A in
Figure B6-1 during the period y in m3.
w carbon, A, y Is the estimated average content of carbon in the gas recovered at point A in
Figure B6-1 during the period y in kg-C/m3.
15.1% Is the actual emission from the gas processing plant that occurred in 2002
which is based on the following calculation.
High Case:
Year Baseline emissions Project Leakage Emission reductions
(t CO2e) emissions (t CO2e) (t CO2e)
(t CO2e)
2001 73,665 23 11,153 62,489
2002 1,302,864 277 197,254 1,105,334
2003 1,899,610 277 287,601 1,611,732
2004 1,236,743 277 187,243 1,049,223
2005 1,137,328 277 172,192 964,860
2006 1,351,211 277 204,573 1,146,360
2007 1,547,202 277 234,246 1,312,679
2008 1,500,086 277 227,113 1,272,696
2009 1,429,840 277 216,478 1,213,085
2010 1,407,569 277 213,106 1,194,186
2011 1,150,069 254 174,120 975,695
Total 14,036,187 2,770 2,125,079 11,908,338
Total
number
of 10 years
crediting
years
Annual 1,403,619 277 212,508 1,190,834
average
over the
crediting
period
Data / Parameter F
VA, t, accident
Unit m3
Description Flowrate and volume of gas supplied from the oil well at point A in
the figure B6-1 from the time the gas leakage started until the
shutdown valves closed the pipeline
Source of data Quantity of recovered gas measured by flow meters at point A
Value(s) applied Ex-post monitoring
Measurement methods Measurement by Ultrasonic Flow Meters with pressure and
and procedures temperature compensation by pressure and temperature
transmitter. Archive: electronic
Uncertainty level: Low
Proportion of data to be monitored: 100%
Monitoring frequency Continuously
Calibration frequency: every 3 years in accordance with
Regulations relating to gas measurement issued by Petrovietnam in
2009 (article 7.5.2, page 21).
QA/QC procedures Consistency checks of measurement with commercial data
Purpose of data Project Emission
Additional comment Used in equation (5)
Data / Parameter t1
Unit Day/hour/minutes/second
Description The time when the gas leakage caused by the accident occurred
Source of data Recorded time when the gas leakage caused by the accident
occurred
Value(s) applied Ex-post monitoring
Measurement methods Measurement with e.g. operation controller. “t1” is determined
and procedures based on the continuous monitoring data such as pressure
Archive: electronic
Uncertainty level: Low
Proportion of data to be monitored: 100%
Monitoring frequency Continuously
QA/QC procedures Consistency checks of measurement with operation data
Purpose of data Project Emission
Additional comment Used in equation (5)
Data / Parameter t2
Unit Day/hour/minutes/second
Description The time when the shutdown valves closed both the upstream and
downstream pipeline
Source of data Recorded time when the shutdown valves closed both the upstream
and downstream pipeline
Value(s) applied Ex-post monitoring
Measurement methods Measurement with e.g. operation controller. “t2” is determined based
and procedures on the operation date
Archive: electronic
Uncertainty level: Low
Proportion of data to be monitored: 100%
Monitoring frequency Continuously
Data / Parameter Pp
Unit atm
Description The pressure in the pipeline when the shutdown valves close both
the upstream and downstream of the pipeline
Source of data Measured pressure in the pipeline
Value(s) applied Ex-post monitoring
Measurement methods Measurement with e.g. pressure meters
and procedures Archive: electronic
Uncertainty level: Low
Proportion of data to be monitored: 100%
Monitoring frequency Continuously
QA/QC procedures Consistency checks of measurement with operation data
Purpose of data Project Emission
Additional comment Used in equation (5)
Data / Parameter Tp
Unit Centigrade
Description The temperature in the pipeline when the shutdown valves close
both the upstream and downstream of the pipeline
Source of data Measured temperature in the pipeline
Value(s) applied Ex-post monitoring
Measurement methods Measurement with e.g. temperature meters
and procedures Archive: electronic
Uncertainty level: Low
Proportion of data to be monitored: 100%
Monitoring frequency Continuously
QA/QC procedures Consistency checks of measurement with operation data
Purpose of data Project Emission
Additional comment Used in equation (5)
16
No. 20 under Appendix of Decision 25/2007/QD-BKHCN dated 5th October 2007
(2) Calculation
Data is calculated at Health, Safety and Environment Division of JVPC Vung Tau. Director
General of JVPC Vung Tau is responsible for the result of calculation.
(*) EIA: Environment Impact Assessment (Please referred to section F1) N/A: Not
Applicable
Japan Vietnam Petroleum Company determined the baseline, which is completed in 13/05/2005.
Hidetoshi Ohashi
Deputy General Manager
Project Coordination and Business Development Department
Japan Vietnam Petroleum Company Limited
3-12, Nishi-Shimbashi 1-chome, Minato-ku, Tokyo
105-8412, Japan
Telephone: 81-3-3501-0522
Fax: 81-3-3502-2692
E-mail: hidetoshi.ohashi@noex.eneos.co.jp
27 November 2001
15 years
Fixed
01 December 2001
10 years
Under the Law on Environmental Protection promulgated in 1993 and Circular 490/1998/TT-
BKHCNMT by the Ministry of Science, Technology & Environment (MoSTE – the current Ministry
of Natural Resources & Environment) organizations or individuals are required to submit an
Environmental Impact Assessment (EIA) to the State management agency for appraisal &
approval prior to construction or renovation in a production area. To meet the requirements, the
Environmental Impact Assessment which covers the entire activities of Full Field Development
Plan was submitted to MoSTE through Petrovietnam on 29th March 2002. An official meeting was
held in the MoSTE office on 7th May 2002, followed by approval by MoSTE on 20th June 2002.
The EIA is a comprehensive assessment for any development activities in Block 15-2, where Rang
Dong oil field is located. It includes appropriate mitigation measures in regard to environmental
protection during the project as well as regular environmental monitoring programs. The EIA for
Full Field Development Plan is in line with all relevant environmental law in Vietnam including “Law
on Environmental Protection” and “Regulations on Environmental Protection in Petroleum
Prospecting, Exploration, Field Development, Production, Storage, Transportation and Processing,
and Related Services”.
In describing significant impacts, a summary of the Environmental Impact Assessment (EIA) is
shown below.
Scope of activities and impacts examined in the EIA are as follows:
Pre-installation;
Construction/ installation & commissioning activities;
Drilling activity;
Production operation; and
Accidental events.
In evaluating the potential and significant impacts of the activities, the following items and factors
were taken into account during assessment:
Magnitude of impact (combining severity, scale, duration impact, and recovery ability of
the receiving environment);
Frequency of impact (probability occurrence);
Potential regulatory and legal exposure (legislation requirements);
Cost management (including technical difficulty of changing the impact); and
Community and stakeholder concerns, effects on the company’s public image.
The assessment of the above mentioned factors are described in quantitative terms wherever this
has been possible. A scoring system was also developed to assist the impact assessment. In
accordance with this scoring system, a value of impact frequency (probability occurrence) and
value of items (legislation requirement -Vl, cost management Vcm and community impact - Vc) is
scored from 1 to 4. Level of impact significance increases from scores 1 to 4.
Consultation with stakeholders and efforts to respond to their expectations will continue
-----
The approved methodology AM0009 version 2.1 is appropriate for Rang Dong oil field Associated
Gas Recovery and Utilization Project Activity (the project activity) since the methodology has been
developed specifically based on the project. Details are explained in section B.2
Table Appendix 4-2: Gas composition of associated gas from Rang Dong
C Molecular Carbon
atoms/mole composition Content
% t-C/1000 m3
0 0.000
n-C1 1 72.550% 0.367
n-C2 2 10.330% 0.105
n-C3 3 6.690% 0.102
n-C4 4 2.290% 0.046
so-C4 4 1.410% 0.029
n-C5 5 0.830% 0.021
iso-C5 5 0.790% 0.020
neo-C5 5 0.000
n-C6 6 1.010% 0.031
iso-C6 6 0.000
neo-C6 6 0.000
n-C7 7 0.720% 0.026
iso-C7 7 0.000
triptane 7 0.000
n-C8 8 0.260% 0.011
iso-C8 8 0.000
diiso-C8 8 0.000
8 0.000
n-C9 9 0.120% 0.005
iso-C9 9 0.000
C10 10 0.040% 0.002
iso-C10 10 0.000
diiso-
10 0.000
C10
CO2 1 0.040% 0.000
N2 0 0.420% 0.000
H2O 0 2.490% 0.000
Other 0.010%
Total 0.764
Source: Coordination Operation Procedure from Rang Dong – Bach Ho Pipeline Project Between
JVPC-VSP-PVGC
(Doc Number: PVGC. OP. 904-Rev: 01 Page 8)
* This is the typical data. Gas composition as well as volume will be monitored ex post basis.
Not applicable.
-----
Document information