Cable pulling and Termination Damaging the cable wire. Use rollers to lessen the force exerted Project in charge/Supervisor
during the cable pulling. Provide cover to should always on site to monitor the
19 the path when cable cross to stones and
accuracy of work performed.
grave bed.
Testing and commissioning Electric shock/electrocution, Ensure that proper PPE is used, rubber
Exposed to energized terminal, Fire, gloves, rubber mat and insulated ladder.
Burn,Explosion Fire extinquisher in placed. Barricade the
area with signage. Tag all breakers and
23
switches. Disconnected terminals shall be
covered with adequate separation to aviod
live contacts.
11/22/2022
JOFFORD A. LALIN SEMD Principal Engineer