REQUEST FOR APPROVAL

THAI TAKENAKA INTERNATIONAL LIMITED


Project : GSA Next 01 Ref.No : 522803-01-CXMS-EL-0002-002
Submitted Date : 11 April 24
Need Reply Date : 18 April 24
Subject : Method Statement of CxL1 Test & Commissioning for Low Volt Panel Board
Description : Commissioning Method Statement
Trade / Discipline : Electrical
Specification No. : N/A SUB-CONTRACTOR (EE) : THAI SEMCON CO.,LTD.

Attached sheet : 218 pages Signature : Signature : Palakorn


(Included this page) TTI (Mr. Narongphat S.) Originator : Mr.Palakorn L.
Attn : AURECON From : Thai Takenaka International Limited
For Designer Opinion For Approval
For Information See notes Signature :
Notes
(Mr.Atsushi Yakushijin)
Project Director
Date :

Attn : Thai Takenaka International Limited From : Designer, Aurecon


Approved Make correction as noted and Proceed
Disapproved Make correction as noted and Resubmit Signature :
Notes
( )

Date :

From :Cx Consultant, Sygna

Signature :

( )

Date :

From : PMCM, Aurecon

Signature :

( )

Date :

From : Owner, GSA

Signature :

( )

Date :
NEXT01-PROJECT Data center1
Reply for clarify comment
Reference : 522803-01-CXMS-EL-0002-001
Method Statement of CxL1 Test & Commissioning for Low Volt Panel Board

REPLY FOR CLARIFY COMMENT

Sr. Comment Location Reply


The certificate on Verification of Refer to Appendix C Test for IEC61439 (4000A With rated
Temperature rise test shall be diversity factor equal 1 for outgoing circuits) Refer to
1 provided according to IEC61439 Cover Page Verification of Temperature rise test section 9 Clause
10.10.2.3.5 for information. See on Page 215-218
Verify continuity of the protective
circuit item 13 of sheet 14, suggestion
of testing to be 2 cubicles per panel as
2 minimum. If those panels are consist of Cover Page Supplier Acknowledge and process.
cubicle over 8 cubicles the testing
shall be provided 3 cubicles or 25% of
the panels.

BSTS panels were canceled refer to Rectified follow comment.


3 RFAM-EL-0021-001_Low Cover Page
Voltage switchboard
Testing forms shall be revised to
reflected to RFAM-EL-0021- Acknowledge and update in FWT testing form of each panel.
4 001_Low voltage switchboard, ie no.of Cover Page See on Page 31 - 36
CB, CB rating.
MOS to be cross checked with Rectified follow comment.
5 Cover Page
approved ECMS points lists
All panel drawing and SoO to be
6 approved, referenced and issued Cover Page We will confirm with designer about SoO before FWT testing.
in advance of FWT.
All trip settings to be aligned and
We will follow approved SCCS/ discrimination study
7 checked against approved Cover Page
for all trip setting.
SCCS/discrimination study
Please provide calibration certificates SMBE provide calibration schedule of testing equipment
8 Cover Page
in date.
All breakers should have specific Rectified follow comment.
9 Cover Page
tagging
Key interlock shall have defined For DB & LVDC no need key interlock
10 Cover Page
tagging