Professional Documents
Culture Documents
MOS/042024/PFF000098/004.00
NOVA Systems Engineering
Testing & Commissioning
Method of Statement
Fire Alarm System
Approved By
Client/Consultant Comments
Table of Contents
Chapter (01) – Objective........................................................................................................................................................ 3
Chapter (02) – Tools Required............................................................................................................................................4
Chapter (03) - Documents References.............................................................................................................................5
Chapter (04) – Pre-Commissioning Procedure............................................................................................................6
Chapter (05) - Commissioning Procedure......................................................................................................................7
Chapter (06) – Test for Fireman’s Telephone System..............................................................................................8
a)
Ensure that no damage has occurred between mechanical completion & pre-commissioning. Repair / replace
damaged components, if any.
1. Cable Testing: Upon completion of installation & inspection of cables they will be Menu tested as
follows:
a. Upon completion of glanding of the cables, the cables will be tested with a standard industrial insulation
tester.
b. The tests shall be carried out to check for short circuits between conductors & between conductors and the
outer sheath. If each core cannot be identified, they will be phased to determine each core at both ends&
will be suitably marked.
2. Ensure that the smoke detectors, speakers, bells, strobes & fireman’s telephone jack are identified
location wise and service wise.
3. Ensure that the wiring termination to the Fire Alarm Panels are complete & correct polarity is
maintained for all field devices.
4. Ensure that wiring termination to the voice evacuation panels for speakers and fire man’s
telephones are complete & correct polarity are maintained at all field devices.
5. Ensure that the Fire alarm cables are pretested for continuity before termination.
6. Ensure that the earthing of the Fire Alarm panels & voice evacuation panels has been completed.
7. Ensure the availability of power supply to the fire alarm panels & voice evacuation panels.
8. Check the presence of batteries in all Fire alarm panels.
9. Check for the proper location & mounting height of all the manual call points.
10. Check all field devices are properly supported & secured.
11. Check for proper identification of all Fire alarm cables.
Is there a risk of accidental activation of the fire alarm system during testing?
Are proper protocols in place to prevent false alarms during testing?
Is there a procedure for responding to accidental activation or false alarms?
Environmental Hazards
Are testing activities conducted in areas with proper ventilation to avoid
exposure to smoke or fumes?
Are there any environmental factors, such as extreme temperatures or humidity,
that could affect testing?
Equipment Safety
Are all testing tools and equipment properly maintained and in good working
condition?
Are there any risks associated with using ladders or elevated platforms during
testing, and are proper safety precautions in place?
Personnel Safety
Are personnel conducting the testing trained in fire safety procedures and
emergency response?
Is there a procedure for evacuating the area in case of an emergency during
testing?
Communication and Coordination
Is there clear communication between testing personnel and building occupants
or other contractors?
Are testing activities coordinated with other ongoing work to minimize
disruptions and ensure safety?
Documentation and Reporting
Is there a system in place for documenting testing procedures, results, and any
issues encountered?
Are incidents or near misses during testing promptly reported and investigated?
Security
Are there any security risks associated with testing the fire alarm system, such
as access to sensitive areas or information?
Are proper security measures in place to prevent unauthorized access to the
system during testing?
Emergency Preparedness
Is there a plan in place for responding to emergencies or unexpected events that
may occur during testing?
Are personnel trained in emergency response procedures and aware of their
roles and responsibilities?
Regulatory Compliance
Is testing conducted in accordance with relevant regulations, codes, and
standards?
Are there any specific requirements or regulations related to fire alarm system
testing that need to be followed?