GENERAL NOTES:-

1. DISCREPENCY AMONGST THIS STRUCTURAL DRG. THE CORRES-


PONDING ARCHITECTURAL DRAWINGS AND THE AGREEMENT
ITEM IF ANY, SHALL BE GOT RECONCILED BEFORE EXECUTION.
2. ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED.
3. NO DIMENSION ARE TO BE SCALED OUT FROM DRAWING, ONLY
FIGURE WRITTEN DIAMENSIONS SHALL BE FOLLOWED.
4. DIAMENSION ARE TO BE VERIFIED AT SITE BEFORE EXECUTION
OF WORK.
5. VARIOUS APPLICABLE PROVISIONS OF I.S. :456-2000 SHALL BE
FOLLOWED FOR R.C.C WORK.
6. CEMENT CONCRETE MIX SHALL BE OF DESIGN MIX OF M-25
FOR ALL STRUCTURAL WORK AS PER CPWD SPECIFICATIONS AND
RELEVENT I.S. CODE AND AGREEMENT.
7. ALL REINFORCEMENT SHALL BE OF HIGH YIELD STRENGTH THERMO
MECHANICALLY TREATED BARS.(Fe-500D) TMT CONFORMING
TO IS-1786.
8. REINFORCEMENT SHALL HAVE NOMINAL COVER
EXCLUDING PLASTER OR OTHER DECORATIVE FINISH
AS FOLLOWS :-
a) FOR PILE SHAFT :- 50MM
b) FOR COLUMN :- 40MM
c) FOR BEAM :- 30MM
d) FOR PILE CAP :- 75MM
NOMINAL COVER TO REINFORCEMENT SHALL BE THICKNESS
OF CONCRETE COVER TO ALL STEEL REINF INCLUDING
TYPICAL SECTION OF SLAB SECONDARY REINF ALSO.
9. NOT MORE THAN 50% OF BARS SHALL BE SPLICED AT ONE SECTION
IN COLUMNS AND BEAMS.
10. THE TOP OF ALL GRADE BEAMS SHALL BE AT 150MM
ABOVE FORMATIONG/FINISHED GROUND LEVEL.
11. IF ANY ACTUAL SUB SOIL CONDITION DURING EXCAVATION DIFFER
FROM AS REPORTED OR LOOSE STRATA FOUND THE SAME MAY BE
REPORTED TO THIS OFFICE BEFORE EXECUTION.
12. LOAD CARRYING CAPACITY OF PILE HAS BEEN ADOPTED AS 510 KN
FOR 500 MM DIA PILE AS PER SOIL TEST REPORT.
A) PILE SHOULD PROJECT 50MM MIN. INTO THE PILE CAP.
B) LENGTH OF PILE IS 25.00M BELOW BOTTOM LEVEL OF PILE CAP.
13. NOT MORE THAN ONE THIRD OF TOTAL NOS OF MAIN BARS SHALL
BE OVER LAPPED AT ANY SECTION OF COLUMN.
d d
14. DEVELOPMENT LENGTH OF REINFORCEMENT BARS SHALL BE
IN TENSION-- 49X DIA. OF BAR.
IN COMPRESION -- 39X DIA. OF BAR
LAP LENGTH--- 49 X DIA. OF BAR.
15. LAP SHALL BE STAGGERED AND AVOIDED AT THE POINTS OF
MAXIMUM BENDING.
16. ALL BRICK WALLS SHALL BE RAISED AFTER THE SHUTTERING OF
HOOP SPACING d/4 OR 8 d b BEAM AND SLAB BELOW ARE REMOVED.
WHICHEVER IS LESS 17. LAP SPLICE SHALL BE IN CENTRAL HALF OF COLUMN LENGTH AND
SHALL PROPORTIONED AS TENSION SPLICE.
CLEAR SPAN (L)
d b = DIAMETER OF LONGITUDINAL BAR 18. TIES/STIRRUS SPACING IN ENTIRE SPLICE LENGTH IN COLUMN
SHALL NOT EXCEED 100 C/C.
19. MINIMUM LENGTH OF THE BARS USED IN THE SLAB AS
REINFORCEMENT SHALL BE 2Ld, WHERE 'Ld' IS THE DEVE-
-LOPMENT LENGTH OF THE BAR.
20. LAP SHALL NOT BE PROVIDED IN A BEAM WITHIN A DISTANCE OF
2d FROM JOINT FACE.
21. BOTTOM MOST LAYER OF REINFORCEMENT IN FOOTING SHALL BE
PLACED ALONG THE SIDE WHICH ONE IS HAVING LARGER
OUTSTAND BEYOND THE COLUMN/ PEDESTAL FACE.
22. IN COLUMN REINFORCEMENT, LARGER DIAMETER REINFORCEMENT
BAR SHALL BE PLACED AT CORNER WHENEVER TWO DIFFERENT
DIA OF BAR ARE USED.
24. DETAILING OF REINFORCEMENT SHALL BE AS PER SP-34, IS-456-2000 &
IS-13920-2016.
10$ @ 150 C/C
BOTH WAYS
75
115
2NOS-12$ MAX 600
150 2L-8$ @ 90 C/C O/o THE CHIEF ENGINEER
TYP. REINFORCEMENT DET. OF 600 WIDE CPWD, AGARTALA.
2NOS-12$ RCC SHELF IN KITCHEN
CHECKED BY :- RE-CHECKED BY :- APPROVED BY :-
230
2NOS-12$
2L-8$ @ 90 C/C A.E.E./CPWD E.E./CPWD CE/CPWD/AGARTALA.
150
PROJECT :- C/o 'A' TYPE SCHOOL BUILDING FOR
3NOS-12$
60° KV AT LAMPHELPATE, IMPHAL
JOB :- STRUCTURAL DRAWING.
(BEAM BARS & STIRRUPS NOT TITLE :- GENERAL NOTES & TYPICAL
(STIRRUP NOT SHOWN) SHOWN FOR CLARITY) DETAILS.
DRG.NO. :- CE/AGT/KV/LAMPHAL/G+2/ 00 (A)