You are on page 1of 5

LAFARGE JOJOBERA GU EXPANSION PROJECT

METHOD STATEMENT
Method Statement for (Description & location):
TT5 STRUCTURAL ERECTION
1 Document details and control:

Approved
Rev Date Prepared by Designation Signature Signature
by
0 15/12/2011 SHEKHAR ENGINEER
1

2 Individual/s in charge & responsible for supervising the Activity


and the Safety of the activity(Whether line manager /safety
personnel)(Contractor / LIPL)
Occupation /
SN Name Surname Signature Company
Designation
1 SHEKHAR MUKHERJEE ENGINEER L&T
2

3A. Detailed step-by-step sequence of activities and tasks involved in


performing the task:(Work procedure for crane lifting)
1) Assembly member or individual member will shift from yard to erection
location by hydra or crane.
2) Ensure proper welding before shifting the assembly member.
3) 200T crane will place as per lifting plan.
4) Member/assembly member will lift as per approved load chart.
5) In erection time presence of Rigging person must required.
6) Ensure proper lifeline before erection.
7) Workmen will use rectractable fall arrestor by using web sling for anchorage
point.
8) Member/assembly member will place and make proper alignment and do
the necessary welding.
9) Guy rope will fix if required.Do not realise the guy rope before tie beam
fixing.
10) Provide barrication before erection and ensure nobody will enter the
barrication while erection.
11) Ensure proper supervision.
12) Place the fire extinguisher near the working place.
13) Workmen will reach the working place by using permanent stair of existing
MFH,DOCA tower and 442BC 32 walkway or TT5 column step ladder.

Drafted by ManieTaljaard Page 1


3B. Detailed step-by-step sequence of activities and tasks involved in
performing the task:(Work procedure for Manually lifting)
14) Assembly member or individual member will shift from yard to erection
location by hydra or crane.
15) Ensure proper welding before shifting the assembly member.
16) Chain Pulley (3T,2Tand 1T) will place for lifting.
17) Rope pulley with 25mm dia PPE will place for small member lifting (ie below
200kg).
18) Ensure proper anchorage for lifting tools.
19) Member/assembly member will lift by lifting tools.
20) In erection time presence of Rigging person must required.
21) Ensure proper lifeline before erection.
22) Workmen will use rectractable fall arrestor by using web sling for anchorage
point.
23) Member/assembly member will place and make proper alignment and do
the necessary welding.
24) Provide barrication before erection and ensure nobody will enter the
barrication while erection.
25) Ensure proper supervision.
26) Place the fire extinguisher near the working place.
27) Workmen will reach the working place by using permanent stair of existing
MFH,DOCA tower and 442BC 32 walkway or TT5 column step ladder.

WAH:
1. Sup. Must inform the responsible in charge of the area before to
start any
Job.
2. Sup. Must have been training to analyse all any risk and must be
sure
that

Any job could be done as safely as possible in a location before to


start it.
(Ex: to avoid to work above each other).
3. Sup. Must inform the team about any risks in the location where they
have To work.

Drafted by ManieTaljaard Page 2


4. Sup. Must check that all workers use WAH PPE according the
standards
LAFARGE rules.
5. Sup. Must check any WAH PPE equipments before to use it and fill
out aSafety harnesses registers.
6. Sup.must install the PPE safely for the workers.Retractable fall
arresters must be installed above each work platform. -1 Retractable fall
arresters =1 man
7. Man basket and cherry picker must be use at first measure when it
is Impossible to install any WAH PPE safely.
8. All the workers must have completed and succeed in the
WAHcourse Training.
9. All the workers must follow the Lafarge safety rules at site.

4. Potential hazards and risks associated with the work activities and
control measures – to be detailed in the Risk Assessment form:

5. In the event of a sudden change in original scope of work/activity –


re-submit a new method statement and Risk Assessment for the
activity:

5- Relevant Legislation; i.e. Construction Regulations, etc:


 FACTORY ACT 1948.
 BOCW 1996.
 LIPL G2.
5- Names && Qualifications of personnel who may inspect and
approve work area, conditions, methods, protective measures
and equipments to be used: (who is authorised to approve
other than scaffold and rigging operation).

Occupation /
SN Name Surname Qualification
Designation
1 SHEKHAR MUKHERJEE Engineer BE

8. Training requirements for personnel involved in this activity,


including specialised training for specific tasks to be added:

Required
SN Type of Training
YES NO
1 JOB CLEARENCE
2 Work at Height 
3 Hot work (cutting & welding) 
4 MATARIAL HANDLING 

Drafted by ManieTaljaard Page 3


9. List of workmen who will be performing activity and are trained
or to be trained for the task:
Trained
SN Name Surname Occupation Signature
YES NO
1
2

3

4

5

6

10. Details of permits required for the task; i.e. WAH, etc:

1. JOB CLEARENCE PERMIT.


2. HOT WORK PERMIT
3. HEIGHT WORK PERMIT
4. LIFTING WORK PERMIT.
5. FHRA
11. Identify all resources required to perform the task and
inspections required:

Required Inspection Frequency


SN Equipment type
YES NO Daily Weekly Monthly Quarterly
1 SLING
2 D- SHACKLE  
3 CUTTING TORCH  
4 WELDING MACHINE  
5. Chain Pulley  
6 Rope Pulley and PPE Rope  

12. Identify all Personal Protective Equipment required to perform


the task:

Drafted by ManieTaljaard Page 4


Required
SN Equipment type
YES NO
1 Safety Helmet 
2 Gloves 
3 Safety goggles 
4 Reflective jacket 
5 Welding shield 
6 Cutting torch goggles 
7 Confined Space testing 
8 DUST NOSE MASK 

13. Document sign off and approval by Contractor Management and


Lafarge:

Approved
Name & Surname Designation Date Signature
YES NO
Contractor Safety
S. K. PATRA Contractor Site manager
LIPL First Line Engineer
LIPL Safety
H.K. SAHA LIPL Manager
WAH Expert
C.N.K.PRASAD HOD MECHANICAL

Drafted by ManieTaljaard Page 5

You might also like