96944/2022/CMD-II
सर्ी क्षेत्रीय/शाखा कायाभ लयों से अनोरोि है की वदशा वनदे शों का तत्काल प्रर्ाव से अनुपालन सुवनवित करें ।
आवित्य िास
िैज्ञावनक D
प्रमुख (के मू िी 2)
सभी क्षेत्रीय/शाखा कायाालय/प्रयोगशालाएँ / TXD/LRMD
The Competent Authority has approved the enclosed Guidelines for implementation.
All ROs/BOs are requested to ensure the implementation of the above Guidelines with
immediate effect.
(Aditya Das)
Scientist D
Head (CMD-2)
All ROs/BOs/Labs/TXD/LRMD
280
96944/2022/CMD-II
2. All BOs shall inform the Applicants and Licensees under their jurisdiction about
implementation of the above amendment within a week of issuance of these
guidelines.
3. The significant changes in the standard through this amendment as listed in the
Table are given for the purpose of general guidance. BOs shall ensure that the
product conforms to all the requirements, as applicable, as per the amendment.
Clause Change
Cl. 5.2, Table 1, Requirement for Mass of the sack with liner has been modified
Sl No. v), b),
Clause 8.4, (b) In the clause for sampling and criteria for conformity of a lot of
sacks (sampling requirements), the requirement for mass of the
individual sack or bale of 500 sacks has been modified
4. It is submitted that the above change has been effected through this amendment
since through earlier amendment no. 3 the thickness of the liner had been increased
due to which the mass of the sack with liner needs to be accordingly modified and
tolerances on mass specified. There is no change required in the existing product
manual/SIT on account of this amendment.
a) LICENSEES:
i) All Licensees shall implement the amendment by 13 Sept 2022. Any difficulty in
implementation shall be brought to the notice of CMD 2 at the earliest but in any
case at least 30 days before the last date of implementation.
ii) Applications which are recorded henceforth may be processed with or without
consideration of the amendment. Processing of Applications without consideration
of the amendment shall be permitted only upto 12 Sept 2022 and for such cases
Applicant shall give a declaration that they will implement the amendment by 13
Sept 2022
iii) Beyond 13 Sept 2022 no Licence shall be granted without consideration of the
amendment.
i) For change in scope of licence, the relevant provisions as given above for
Applicants shall apply.
ii) However, processing of such applications for change in scope of licence without
consideration of the amendment shall be permitted only upto the date of
implementation of the amendment by the licensee or upto 13 Sept 2022 whichever
is earlier.
Aditya Das
Sc. D
Head (CMD-2)
DDG (Certification)
183
91387/2022/PUB & SALES
TO
[Page 2, Table 1, Sl No. v), b), col (2) to (6)] — Substitute the following for the existing:
[Page 3, Clause 8.4, (b)] — Substitute the following for the existing:
‘b) The mass of the individual sack or bale of 500 sacks shall not be less than the lower specified
+6
limit. A tolerance of ± 6 percent for mass of individual sack without liner and percent for mass
−4
of individual sack with liner shall be applicable. For mass of bale of 500 sacks, a tolerance of ± 3
percent shall be applicable. However higher mass for individual sacks (with or without liner) and its
bale of 500 sacks can be accepted.’
(TXD 23)