BAGATALE: DETAILED SUMMARY OF THE ENTIRE PROJECT - FINAL (As at 29th March 2024)
QUOTED Construction BALANCE
WORK DESCRIPTION AMT. & ADV Status Req. this time FRONT BOUNDARY WALL Front Boundary Wall 1463-III dated 13.10.2023 and Painting Qtn 1464-III dated 13.10.2023 787,540 Completed Advance paid for approved works - 50% (Advance No 02) (393,770) 393,770
HOUSE RENOVATION PART 01
House Renovation Part 1 Qtn 1471 dated 21.10.2023 6,142,915 Completed Advance paid for approved works - 50% (Advance No 01) (3,071,458) 3,071,458
HOUSE RENOVATION PART 02
House Renovation Part 2 Kitchen & Pantry Qtn 1473 a dated 10.11.2023 1,470,000 Completed House Renovation Part 2 New Additions Qtn 1473 d dated 10.11.2023 - Rs. 115,000 1,752,554 Completed House Renovation Part 2 Internal Repairs Qtn 1473 b dated 10.11.2023 911,800 Completed Advance paid for approved works - 50% (Advance No 03) (2,067,177) 2,067,177
HOUSE RENOVATION PART 03
PART 03 - Strengthening Dining Area Slab Qtn 1480 dated 13.12.2023 1,185,000 Completed PART 03 - Reinstate the finishing upon strenthening the Dining Area Slab Qtn 1481 dated 13.12.2023 782,500 Completed PART 03 - Remove damage area & increaser the height of rear Boundary wall Qtn 1482 dated 13.12.2023 953,640 Completed PART 03 - Flower trough on new balcony and other additional works Qtn 1483 dated 13.12.2023 348,750 Completed Advance paid for approved works - 37.31% (Advance No 04, 4.5M - 3.28M) (1,220,000) 2,049,890
HOUSE RENOVATION PAINTING
PAINTING OPTION 02 (Waterproofed Painting - 5 coat & 3 coat systems) - Qtn 1473 c dated 25.11.2023 2,472,360 Completed Advance paid for approved works - 80% (Advance No 05, (4,500,000 - 1,649,163- 872,949) (1,977,888) 494,472 REAR BOUNDARY WALL ADDITIONAL FOR DEMOLISH & BUILD Additional amount for Rear Boundary Wall - Fully Demolish & Build- Qtn 1486 dated 04.01.2024 1,890,861 Completed Advance paid for approved works - 46.17% ( Advance No 05, 4,500,000 - 1,649,163- 1,977,888) (872,949) 1,017,912 PAINTING OF SIDE BOUNDARY WALLS Painting of side boundary walls - Qtn 1502 dated 26.01.2024 376,753 Completed Advance paid for approved works - 50% (included in 3,000,000 advance pay) (188,377) 188,377 NEW GUTTERS & DOWNPIPES, DAMAGED VALANCE BOARD REPLACE & OVERALL PAINTING Remove existing gutters & downpipes, replace damaged valance boards, clean & painting vallance boards, supply & fix new gutters & downpipes- Completed 792,750 Qtn 1501 dated 26.01.2024 Advance paid for approved works - 75% (included in 3,000,000 advance pay) (594,563) 198,188 REAR PASSAGE/FLOWER TROUGH WATER PROOFING Rear passage/flower trough water proofing - Qtn 1498 dated 13.01.2024 387,700 Completed Advance paid for approved works - 50% (included in 3,000,000 advance pay) (193,850) 193,850 GRILL & IRON WORKS Grill & Iron Works - Qtn 1488 dated 11.01.2024 441,000 Completed Advance paid for approved works - 75% (included in 3,000,000 advance pay) (330,750) 110,250 RIGHT SIDE CHAIN LINK FENCE AND REAR SIDE FENCE MACHING THE EXISTING Right Side Chain Link Fence and rear fence maching the existing - Qtn 1497 dated 13.01.2024 1,775,000 Completed Advance paid for approved works - 75% approx (included in 3,000,000 advance pay) (1,332,461) 442,539 REAR BATHROOM MODIFICATION, GUARAGE FLOOR RAISE, MOTOR ROOM & PLUMBING Bathroom modifications, guarage floor raise, new motor room & plumbing - Qtn 1503 dated 28.01.2024 720,000 Completed Advance paid for approved works - 50% (included in 3,000,000 advance pay) (360,000) 360,000 POWDER R. VANITY, GUTTER - SS CHAINS, BED 01 BALCONY WALL TITANIUM, DEBRIS REMOVAL Powder R vanity, SS chains - Gutters, Bed 01 bal wall Til & remove debris - Qtn 1512 dated 12.02.2024 296,780 Completed Advance paid for approved works - 0% - 296,780 LEFTSIDE PERIMETER FENCE Left side perimeter fence - Bagatale Road - Qtn 1466 R dated 19.02.2024 1,693,443 Completed Advance paid for approved works - 50% (846,722) 846,722 SUPER TITANIUM PASTE APPLICATION Super Titanium paste application - Bagatale Road - Qtn 1515 dated 04.03.2024 394,940 Completed Advance paid for approved works - 0% - 394,940 FINAL STAGE ADDITIONAL WORKS Final stage additional works - Qtn 1524R dated 29.03.2024 439,150 Completed Advance paid for approved works - 0% - 439,150
Total approved quotes till date 26,015,436
Total advance paid (13,449,963) Balance after paying advance for all quoted works till date 12,565,473