Item Description Budget Contract Awarded Variations Projected Final Variance Payment To Date Balance Remarks
Sum Sub-Contract Sum Approved Anticipated Contract Sum Amount % Amount Val. Outstanding
S$ S$ S$ S$ S$ S$ S$ S$ No. S$
[a] [b] [c] [d] [e=a+c+d] [f=e-a] [g=f÷a] [h] [i=e-h]
A Builders & M&E Works 1,418,683.99 1,418,683.99 1,418,683.99 - 0.00% 17,815.52 2 1,400,868.47 Refer to Appendix 1
for variation list
C Named Sub-Contracts 367,597.65 367,597.65 367,597.65 25,600.00 5,218.50 398,416.15 30,818.50 181,424.82 216,991.33
.. Club House Fit-Out and M&E 350,093.00 350,093.00 350,093.00 25,600.00 5,218.50 380,911.50 30,818.50 8.80% 172,785.54 208,125.96
Installation Works NSC - IWA
.. Main Contractor's Profit 8,752.33 8,752.33 8,752.33 - - 8,752.33 - 0.00% 4,319.64 4,432.69
.. Main Contractor's Attendance 8,752.33 8,752.33 8,752.33 - - 8,752.33 - 0.00% 4,319.64 4,432.69
Total 1,806,281.64 1,786,281.64 367,597.65 25,600.00 5,218.50 1,817,100.14 30,818.50 1.73% 199,240.34 1,617,859.80
PROPOSED FAÇADE, HOTEL INTERIOR AND MEP IMPROVEMENT WORKS TO EXISTING CONSERVED SHOPHOUSES AT 28 ANN SIANG ROAD
FINANCIAL STATEMENT NO. 1 [AS AT END NOVEMBER 2022]
MAIN CONTRACT
VARIATIONS Appendix 1
A Approved Variations
1 1 15.11.2022 1R1 21.11.2022 Reconstruction of existing staircase to meet statutory requirements, including works to modify 2,310.00
existing steelworks
4 1 15.11.2022 1R1 21.11.2022 New 40amp isolator for coffee machine 997.50
6 1 15.11.2022 1R1 21.11.2022 Changes to entrance bulkhead and door closers 819.00
7 1 15.11.2022 1R1 21.11.2022 Lowering full height hose reel cabinet (367.50)
B Anticipated Variations
2,000,000.00
1,800,000.00
Cumulative Amount (S$)
1,600,000.00
1,400,000.00
1,200,000.00
1,000,000.00
800,000.00
600,000.00
400,000.00
200,000.00
-
1 2 3 4 5 6
Month Contractor's Projection dated 30
November 2022
Interim Payment