Zubair Oil Field Development Project

EPC for Water Injection Network Installation

Contract No. 5000008451

Call – Off 03 ( Revision 0)

Issued 01st August 2016

Prefabrication and Installation of 11 WI Well Head


(OPTIONAL SoW) Civil and mechanical only w/o Ele/Ins

Page 1
ZUBAIR PROJECT – IRAQ – WI Network Installation

CALL OFF
To: Drake and Scull international PJSC Contract Ref.: 5000008451 – WI Network Installation.
Via Consolatico Superiore, 96/98
Call Off No.: 03 REV 0
P.O.box 65794 – Dubai - UAE

Att. Mr A. Eissa (PD) Prefabrication and Installation 11 WH hook up (OPTIONAL SoW)


Att. Mr M. Shaker (PM)
Attachments :

1) Description Of Work to be Performed


2) Call Off Calculation
3) ACV progress

Schedule & Milestones Effective Commencement date of this WO Commencement date:


15 September 2016

Scheduled Complete date: 31 May 2017

Work Order Values - TOTAL Value of previously approved Call Offs


$ 8,490,486.04

$ 8,041,711.26
Value of this Call Off (USD)

Cumulative Call off to Date (USD) $ 16,532,197.30

Description of the Work: Prefabrication and Installation of 11 WH hook up in accordance with 00250600BGSC95049- Appendix D Technical
Specification SOW REV 4 (Article 8 – Engineering, Procurement, Construction, pre-commissioning, commissioning and Start up) annexes,
deliverables and Appendix A – Compensation

Invoicing and payments – In accordance with the Terms and Conditions of Contract - 5000008451 – A1.1 WI-WEL-002 of Annex A1 of Appendix-
A.

Approved by Company Contract Holder Approved by Contractor Representative

Name Name

Signed Date Signed Date

Page 2
CALL OFF 03 REV 0

WI WH hook up INSTALLATION 11 (OPTIONAL SoW) 10” pipe 1500#

SUMMARY

ENGINEERING PROCUREMENT, INSTALLATION,PRE-COMMISSIONING, COMMISSIONING AND START UP OF WI WH

Please refer to the original SOW #00250600BGSC95049 - Appendix D Technical Specification SOW REV 4
Paragraph 2 Scope of Work Executive STRATEGY, paragraph 5.6 SoW for Water Injection Flowlines and paragraph 8
Engineering, Procurement, Construction, Pre-commissioning, Commissioning and Start up.

COMPANY requires to perform:

 No 11 WI WH Hook up (OPTIONAL SoW)

The WORK includes all the Project Management, Engineering, Procurement, Construction, Pre-Commissioning,
Commissioning and Start up.

COMPANY will free issue to CONTRACTOR the majority of material to be installed, as mentioned in Contract. CONTRACTOR
shall supply remaining material, minor and plant and consumables as described in Appendix D, Annexes of Appendix A and
deliverables.

CONTRACTOR shall supply material as required by appendix D and Appendix A and deliverables of the Contract based on
MTO that shall be checked and revised by Contractor during engineering phase.

CONTRACTOR shall be responsible to collect and transport issued material to his premises or installation place.

The CONTRACTOR, for this Scope of WORK shall be responsible for defining all the interfaces between these facilities and
other existing/new facilities.

The Work consist in Engineering, Procurement, Prefabrication, Installation, pre-commissioning, commissioning and start-up of
civil, mechanical, structural, piping, earthing, cathodic protection etc. of nr. 11 WI Well Head (Optional SoW) reduced
configuration w/o Elec/Inst. in accordance with 00250600BGSC95049 - Appendix D SOW for EPC - Construction of WI network
Installation. Scope included in A1.1 item WI-WEL-002 Well Head WI #1500 Annex A1 of Appendix-A.

For Project Management, Support activity, as built and mechanical completion rates have been recalculated based on % of
activities between the 2 (civil and mechanical and electrical and instrumental) and 3 groups (civil/mechanical prefabrication,
erection and Electrical/instrumental) of price breakdown.
Price Breakdown among the 3 group of disciplines have been fully agreed and approved by both parties, endorsed by
Contractor and incorporated in the Call off.

Details of the lines are defined below and also shown in the attached schedule (BoQ WI Lines Rev 0 04-7-2016 CO-2_3_4_5)
where completion dates milestone are forecasted. Company reserve the right in due time to change the lines according to Field
operation requirement.

Page 3
SCHEDULE

The Call Off Completion dates shall be as follow:


ZB-099 completion date 12/11/2016
ZB-075 completion date 12/11/2016
ZB-094 completion date 17/12/2016
ZB-219 completion date 17/12/2016
ZB-234 completion date 21/01/2017
ZB-207 completion date 21/01/2017
ZB-280 completion date 25/02/2017
ZB-272 completion date 25/02/2017
ZB-082 completion date 08/04/2017
ZB-297 completion date 28/05/2017
AH-21_3V completion date 28/05/2017
In case Contractor will not achieve the completion date LD’s shall be applied, counted on the portion of work value subject to
delay only.
All the works shall be completed in full compliance with Article 34 of the Contract General Conditions and Article 27 of the
Contract Special Conditions.

Page 4
PAYMENT BASIS
APPENDIX A - ANNEX A1.1 – WI Well hook up 10” pipe 1500# - LS (OPTIONAL SoW)

The above price WI-WEL-002 include Engineering, Procurement, Installation, pre-commissioning, commissioning and start-up
of 11 WI WH Hook up.

Page 5
Call Off 03 Calculation – WI Wells hook up 11 OPTIONAL SoW

Page 6
Contract Call Off Progress