Professional Documents
Culture Documents
Course Instructor
Lec. Saad Fawad Azim
Assigned Date:
January 1, 2024
Submission Date:
January 22, 2024
Table of Contents
Design Specification....................................................................................................................4
2 |1 0
Complex Engineering Problem National University of Technology
Problem Statement
Complex
Knowledge Relevant
Course Course Complex Engineering Problem-
area CEP Activities CLO &
Code. Title Problem (CEP) solving
Attributes PLO
attributes
In groups of 3-5, the students, have to analyze
soil mechanics principles for soil compaction, to
Graham BUILDS (Pvt) Ltd. has complete the following tasks:
undertaken a road infrastructure 1. Select a burrow location and the soil
project near Rawat. It wants to sublet sample for testing
a small patch of its roadwork and has 2. Find out the soil classification (This is
invited companies to bid on labour- being done simultaneously, by the student
rate. You, being a private geotechnical in the OEL) and the modified proctor MDD
contractor, have been invited to bid for 3. Select appropriate Soil compaction
Depth of machinery for your works
the compaction of the roadway. You
Knowledge 4. Calculate the total hours and the
have to submit the Bid within 30 days
Required, associated costs for all machinery. For
of the invitation. The project is to be
WK3 productivity charts, use any resource
completed within 5 months. The
(Engineering Depth of analysis material which may be included in the
complete design of the project has
Soil Fundamentals), required, bibliography of the report. For Bid. [Take CLO-2
CE 3112 been approved by the design
Mechanics WK4 MARR as 12%, overheads as 10%, (PLO-2)
consultant. The project start date is
(Engineering Range of consumables as 5% and income
25th January 2024. The design
Specialization) Conflicting (withholding) tax as 7%]
consultant has only provided the end 5. submit a detailed report for the soil
Requirements,
specification of the compaction effort. compaction method specification and
The complete method specification proposed bid containing the following:
Interdependence
including the soil type, procurement, a. Introduction / Project Description
and compaction is your responsibility. b. Problem Description
The client (Graham BUILDS (Pvt) Ltd.) c. Objectives
will supply the soil which you select d. Methodology and method
specification
from the burrow site to the
e. Data Analysis, Bid and Result
Construction site, and will provide fuel f. Limitations
for the machinery at the site g. Recommendations
h. References/Bibliography
6. Present/defend his/her method and bid
3 |1 0
Complex Engineering Problem National University of Technology
Design Specification
a. A two-way road, having one lane on each side. The length of the road is 1.5 km and the design width is 10 meters
including a 1-meter shoulder on both sides.
b. Emulsified Asphalt Surface Course = 10 cm
c. Base = 15 cm; 60 % coarse aggregate, 40 % sand
d. Sub Base = 22 cm; 40 % coarse aggregate, 60 % sand
e. Sub Grade = 45 cm; subgrade is divided into three zones, A, B, and C, top to bottom, 15 cm each, respectively.
Zone C required compaction is 90% MDD. Zone B Required Compaction is 93% MDD. Zone A reuiqred
compaction is 95% MDD.
f. The side slope is 1: 2.5
g. Provide camber at 3%
h. Prime Coat, Tack Coat, and Seal Coat will be provided
i. Design Elevation of the Road is 1505 feet.
j. The current Elevation of the ground is 1500 feet (All fill below subgrade will be compacted at 90% MDD)
4 |1 0
Complex Engineering Problem National University of Technology
5 |1 0
Complex Engineering Problem National University of Technology
Knowledge Profiles
6 |1 0
Complex Engineering Problem National University of Technology
7 |1 0
Complex Engineering Problem National University of Technology
8 |1 0
Complex Engineering Problem National University of Technology
9 |1 0
Complex Engineering Problem National University of Technology
10 |1 0