Bagacay House Project Timeline Davao City

The document outlines a project schedule for building the Bagacay House with activities labeled A through K. It will take place from May to September and includes site works, earthworks, concrete works, masonry works, and more. The estimated workers needed ranges from 2 to 9 over the months.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views1 page

Bagacay House Project Timeline Davao City

The document outlines a project schedule for building the Bagacay House with activities labeled A through K. It will take place from May to September and includes site works, earthworks, concrete works, masonry works, and more. The estimated workers needed ranges from 2 to 9 over the months.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

PROJECT : BAGACAY HOUSE

LOCATION: Sitio Basak, Mintal, Davao City


OWNER: Mr. Cardo Dalisay
DATE: May 7, 2022

ACTIVITY ESTIMATED IMMEDIATE DATE


ACTIVITY DESCRIPTION
CODE DURATION (days) PREDECESSORS May June July August September
A Site Works 7 - 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Site Clearing 1 - 2
Site Cut & Filling 5 2
Gravel Base 1 1
B Layouting & Temporary Facilities Installation 3 A
Barracks/Personnel Break House 3
Perimeter Fence 1
Outhouses 1
Signages 1 5
C Earthworks 23 B
Excavations 1 3
Foundation 15 2 2 2
Water and Drainage 2 2
D Concreteworks 37 C
Formworks 3 3
Column Casting 14 3 3
Slab-on Grade 15 2 2
Stairs Forming and Casting 5 2
E Masonryworks 9 D
Block Layering 2 3
Plastering 7 3
F Lumber and Formworks 10 E
Column and beam installation 2 4
Flooring installation 3
Wall framing 5 4
G Roof Works 9 B, C, D, E
Framing 7 4
GI Sheet Installation 2 3
H Auxillary Works 3 F, G
Plumbing 3 3
Electrical 3 3
I Finishing 2 H,G
Wall surface preparation 1
Paint 1 3
J Furnishing 3 H,I
Toilet Installation 1
Sink Installation 1 2
Door Installation 1
Kitchen Cabinets Installation 2
Window & louver Installation 3 3
K Project Turnover 1
Total Workers 5 5 7 2 2 6 3 2 2 2 3 4 4 4 4 3 9 5 0