Electrical Installation and Maintenance – Grade 9
Quarter 4th – Module 15: Board Wiring 3 - Installing one lamp controlled by two
3-way switch using Rigid Non-Metallic Conduit
Edition, 2020

Republic Act 8293, section 176 states that: No copyright shall subsist in
any work of the Government of the Philippines. However, prior approval of the
government agency or office wherein the work is created shall be necessary for
exploitation of such work for profit. Such agency or office may, among other things,
impose as a condition the payment of royalties.

Borrowed materials (i.e., songs, stories, poems, pictures, photos, brand


names, trademarks, etc.) included in this module are owned by their respective
copyright holders. Every effort has been exerted to locate and seek permission to use
these materials from their respective copyright owners. The publisher and authors
do not represent nor claim ownership over them.

Published by the Department of Education Division of Pasig City

Development Team of the Module


Writer : Vicente B. Lao
Editor : Gerardo D. Guevara
Reviewer : Gerardo D. Guevara
Illustrator : Edison P. Clet
Layout Artist :
Management Team: Ma. Evalou Concepcion A. Agustin
OIC-Schools Division Superintendent
Aurelio G. Alfonso, Ed. D.
OIC-Assistant Schools Division Superintendent
Dr. Manuel A. Laguerta
Chief Curriculum Implementation Division
Education Program Supervisors
Education Program Supervisors
1. Librada L. Agon, Ed. D. EPP/ TLE
2. Liza A. Alvarez, Science
3. Bernard R. Baltao, Araling Panlipunan
4. Joselito E. Calos, English
5. Norlyn D. Conde, Ed. D. MAPEH
6. Wilma O. Del Rosario, LRMS
7. Ma. Teresita E. Herrera, Ed. D. Filipino
8. Perlita M. Ignacio, Ph. D. ESP/ SPED
9. Dulce O. Santos, Ed. D. Kinder/ MTB
10.Teresita P. Tagulao, Ed. D. Mathematics
Printed in the Philippines by (School)
Department of Education – Division of Pasig City
Office Address : (School address)
Contact No. :
E-mail Address :

2
TLE 9
ELECTRICAL INSTALLATION
& MAINTENANCE

Quarter 4
Module15
INSTALL ELECTRICAL LIGHTING
SYSTEMS, AUXILIARY OUTLETS AND
LIGHTING FIXTURES (60) (EL)

LESSON 15: Board Wiring 3 - Installing one lamp controlled


by two 3-way switch using Rigid Non-Metallic Conduit
LO2. Install electrical systems, auxiliary outlets and lighting
fixtures.
2.3.2 Circuit using 3-way switches in 2 locations

3
Introductory Message

For the facilitator:

Welcome to the Electrical Installation and Maintenance Grade 9 Self Learning


Module on Board Wiring 3 - Installing one lamp controlled by two 3-way switch
using Rigid Non-Metallic Conduit

This module was collaboratively designed, developed and reviewed by educators from
Schools Division Office of Pasig City headed by its Officer-In-Charge Schools Division
Superintendent, Ma. Evalou Concepcion A. Agustin in partnership with the Local
Government of Pasig through its mayor, Honorable Victor Ma. Regis N. Sotto.
The writers utilized the standards set by the K to 12 Curriculum using the Most
Essential Learning Competencies (MELC) while overcoming their personal, social,
and economic constraints in schooling.

This learning material hopes to engage the learners into guided and independent
learning activities at their own pace and time. Further, this also aims to help learners
acquire the needed 21st century skills especially the 5 Cs namely: Communication,
Collaboration, Creativity, Critical Thinking and Character while taking into
consideration their needs and circumstances.

In addition to the material in the main text, you will also see this box in the body of
the module:

Notes to the Teacher


This contains helpful tips or strategies that
will help you in guiding the learners.

As a facilitator you are expected to orient the learners on how to use this module.
You also need to keep track of the learners' progress while allowing them to manage
their own learning. Moreover, you are expected to encourage and assist the learners
as they do the tasks included in the module.

4
For the learner:

Welcome to the Electrical Installation and Maintenance 9 Self-Learning Module on


Board Wiring 3 - Installing one lamp controlled by two 3-way switch using Rigid Non-
Metallic Conduit. The hand is one of the most symbolized part of the human body. It
is often used to depict skill, action and purpose. Through our hands we may learn,
create and accomplish. Hence, the hand in this learning resource signifies that you
as a learner is capable and empowered to successfully achieve the relevant
competencies and skills at your own pace and time. Your academic success lies in
your own hands!

This module was designed to provide you with fun and meaningful opportunities for
guided and independent learning at your own pace and time. You will be enabled to
process the contents of the learning material while being an active learner.

This module has the following parts and corresponding icons:

Expectation - These are what you will be able to know after


completing the lessons in the module

Pre-test - This will measure your prior knowledge and the


concepts to be mastered throughout the lesson.

Recap - This section will measure what learnings and skills


that you understand from the previous lesson.

Lesson- This section will discuss the topic for this module.

Activities - This is a set of activities you will perform.

Wrap Up- This section summarizes the concepts and


applications of the lessons.

Valuing-this part will check the integration of values in the


learning competency.

Post-test - This will measure how much you have learned from
the entire module.

5
EXPECTATION
Upon completion of this lesson, you are expected to:

1. understand the safety procedures on wiring installation of one lamp


controlled by two 3-way switch using rigid non-metallic conduit
2. draw the wiring connections of one lamp controlled by two 3-way switch
using rigid non-metallic conduit.
3.value the importance of understanding safety procedures wiring installation
of one lamp controlled by two 3-way switch using rigid non-metallic conduit.

PRE – TEST
Direction: Choose the letter of the best answer. Write the answer on your
notebook.

1. The minimum allowable work`s space around electrical equipment is


________ inches deep.
A) 36 B) 48
C) 24 D) 30
2. A Safety Electrical One Line Diagram should be used to ______________ all
sources of electrical energy.
A) Identify B) Castigate
C) Evaluate D) Modify
3. Gloves used for electrical protection must be electrically tested every…
A) 3 months B) 6 months
C) 12 months D) Never
4. What is PPE?
A) Pulse Protection Equipment B) Physical Protection Equipment
C) Physical Pulse Event D) Personal Protective Equipment
5. One of the main functions of personal protective grounds is to provide a
_______ impedance path for a short circuit.
A) High B) Low
C) Smooth D) Adequate

6
RECAP
Procedures in Installing one lamp controlled by two 3-way switch using Rigid
Non-Metallic Conduit

1. Prepare the necessary tools, materials and equipment.


2. Wear appropriate PPE.
3. Mark on the wiring board the location of the safety switch, utility boxes,
and junction boxes.
4. Fasten the safety switch and PVC boxes with wood screws at the desired
locations.
5. Prepare the PVC conduit for installation.
6. Install and connect ends of PVC pipe to the electrical boxes, safety
switch.
7. Support the conduit with conduit clamps or straps.
8. Place the cover of junction box, utility box, and convenience outlet.
9. Perform good housekeeping.
10. Have your teacher check your work.

LESSON

Board Wiring 3 - Installing one lamp controlled by two 3-way


switch using Rigid Non-Metallic Conduit

Actual Connection Diagram of One lamp controlled by two 3-way switches in


different locations

7
Safety Procedures to Follow During Wire Installation

When installing any type of wire or wiring system, there is always risk
involved. These risks of course include harming yourself, someone else or loss
of property if the wires are not properly installed or necessary precautions are
not taken.

There are a few proactive measures you should take when you are working
with or installing wires. Keeping the following tips in the forefront of your
mind will help to make sure you do not cause any harm to your property and
keep you safe at the same time.

Make Sure the Power is Off

Check the breaker or power source and make sure the power is always off
before starting any electrical work. Lock the breaker if possible or if cannot,
make sure everyone in the area knows it is turned off for a reason and leave
an easily noticeable note that you are working on the electricity. It’s logical
but critical for a safe work environment.

Wear Safety Glasses and Protective Clothing

Covering your eyes is a must when dealing with electricity. You do not want
sparks or other debris to get in your eyes. Also, wearing long shirts, pants,
gloves, and thick soled shoes are also a good idea. If the environment is
outdoor or large scale, working on a project like laying pipeline with tracer
wire, a hard hat may also be needed along with other construction
environment safety gear.

Always Test First

Use a voltage tester to test the wires and connections before you begin working
on them to make sure they are indeed dead. This will allow you to accurately
judge the work that needs to be done and select the product and tools you
need to use.

Have the Right Tools On Hand

As with any job, you need the correct tools to complete it properly and do it
with safety in mind. Having the right tools for a wire installation is
detrimental. Some tools include: a voltage tester, wire cutters, wire and cable
strippers, needle nose pliers, continuity tester, and others. For large scale jobs

8
such as installing ground cables, you may need a wire trencher or other
digging equipment or heavy machinery.

Check Your Work

Before you close-up the hole or call the job done, check your work. The last
thing you want is there to be a loose connection and the whole project to go
up in flames literally. Electrical fires are known to spark at any time and cause
considerable damage and tragedy. Pull on the connections to make sure they
are secure. Turn on the electricity and make sure everything works correctly
and starts up without incident. Also, check the casings with a voltage tester
to make sure they are not electrified. Use the right insulators for longer life
spans too.

ACTIVTIES

Part I
Directions: draw the wiring connections of one lamp controlled by two 3-way
switch using rigid non-metallic conduit in your notebook.

9
Part II
Directions: draw the pictorial wiring connections of one lamp controlled by
two 3-way switch using rigid non-metallic conduit in your notebook.

WRAP – UP

1. Before you close-up the hole or call the job done, Why do need to check
your work?
_____________________________________________________________________
_____________________________________________________________________
2. Why do you need to understand the safety procedures of the wiring
installation of one lamp controlled by two 3-way switch using rigid
non-metallic conduit?
3. _____________________________________________________________________
___________________________________________________________________

10
VALUING

I have learned _____________________________________________________________


I realized __________________________________________________________________
From now on ______________________________________________________________

POST TEST

Direction: Choose the letter of the best answer. Write the answer on
your notebook.

1. The minimum allowable work`s space around electrical equipment is


________ inches deep.
A) 24 B) 30
C) 36 D) 48
2. Gloves used for electrical protection must be electrically tested every…
A) 3 months B) 6 months
C) 12 months D) Never
3. What is PPE?
A) Pulse Protection Equipment B) Physical Protection Equipment
C) Personal Protective Equipment D) Physical Pulse Event

4. One of the main functions of personal protective grounds is to provide


a _______ impedance path for a short circuit.
A) High B) Low
C) Smooth D) Adequate

5. A Safety Electrical One Line Diagram should be used to ______________


all sources of electrical energy.
A) Modify B) Castigate
C) Evaluate D) Identify

11
KEY TO CORRECTION

D 5.
B 5.
B 4. D 4.
C 3. B 3.
B 2. A 2.
B 1. D 1.
POSTTEST PRE-TEST

ACTIVITY PART I ACTIVITY PART II

12
REFERENCES
Printed materials:
• CUETO, Marino C. and CABUSORA, Roman A. Jr., “Technology & Livelihood
Education – Module 1 Learner’s Material, IA-Electrical Installation &
Maintenance”, Prinpia Co., Ltd., First Edition 2018.
• VALLARTA, Hector M. and CABUSORA, Roman A. Jr., “K to 12 Basic
Education Curriculum Technology & Livelihood Education Learning Module
Electrical Installation & Maintenance Exploratory Course

Websites:
• Ask the Electrician. “Basic Residential Electrical Wiring”. Accessed Oct. 26,
2020
https://ask-the-electrician.com/basic-home-wiring-diagrams.html
• Performancewire. “Safety Procedures to Follow During Wire Installation”.
Accessed Oct. 26, 2020
https://www.performancewire.com/safety-procedures-to-follow-during-wire-
installation/
• wikihow. “How to Install Electrical Conduits”. Accessed Oct. 26, 2020
https://www.wikihow.com/Install-Electrical-Conduits
• familyhandyman. “Installing PVC Conduit”. Accessed Oct. 26, 2020
https://www.familyhandyman.com/list/installing-pvc-conduit/

13

You might also like