Electrical Installation and Maintenance – Grade 9
Quarter 4 – Module 11: Board Wiring no.1 – Installing Two Lamp Controlled by
Two Surface Type SPST using Knobs and Tube
First Edition, 2020

Republic Act 8293, section 176 states that: No copyright shall subsist in
any work of the Government of the Philippines. However, prior approval of the
government agency or office wherein the work is created shall be necessary for
exploitation of such work for profit. Such agency or office may, among other things,
impose as a condition the payment of royalties.

Borrowed materials (i.e., songs, stories, poems, pictures, photos, brand


names, trademarks, etc.) included in this module are owned by their respective
copyright holders. Every effort has been exerted to locate and seek permission to use
these materials from their respective copyright owners. The publisher and authors
do not represent nor claim ownership over them.

Published by the Department of Education Division of Pasig City

Development Team of the Self-Learning Module

Writer: Orlando A. Joven Jr.


Editor: Gerardo D. Guevara
Reviewers: Gerardo D. Guevara, Glenda B. Mira
Management Team: Ma. Evalou Concepcion A. Agustin
OIC-Schools Division Superintendent
Aurelio G. Alfonso EdD
OIC-Assistant Schools Division Superintendent
Victor M. Javeña EdD
Chief, School Governance and Operations Division and
OIC-Chief, Curriculum Implementation Division

Education Program Supervisors

Librada L. Agon EdD (EPP/TLE/TVL/TVE)


Liza A. Alvarez (Science/STEM/SSP)
Bernard R. Balitao (AP/HUMSS)
Joselito E. Calios (English/SPFL/GAS)
Norlyn D. Conde EdD (MAPEH/SPA/SPS/HOPE/A&D/Sports)
Wilma Q. Del Rosario (LRMS/ADM)
Ma. Teresita E. Herrera EdD (Filipino/GAS/Piling Larang)
Perlita M. Ignacio PhD (EsP)
Dulce O. Santos PhD (Kindergarten/MTB-MLE)
Teresita P. Tagulao EdD (Mathematics/ABM)

Printed in the Philippines by Department of Education – Schools Division of


Pasig City

2
EIM 9
Quarter 4
Self-Learning Module12
Board no.1- Installing Two
Lamp Controlled by Two
Surface Type SPST using
Knobs and Tube

3
Introductory Message

For the facilitator:

Welcome to the Electrical Installation and Maintenance Grade 9 Self-Learning


Module on Board Wiring no.1-Installing Two Lamp Controlled by Two Surface Type
SPST using Knobs and Tube!

This Self-Learning Module was collaboratively designed, developed and


reviewed by educators from the Schools Division Office of Pasig City headed by its
Officer-in-Charge Schools Division Superintendent, Ma. Evalou Concepcion A.
Agustin, in partnership with the City Government of Pasig through its mayor,
Honorable Victor Ma. Regis N. Sotto. The writers utilized the standards set by the K
to 12 Curriculum using the Most Essential Learning Competencies (MELC) in
developing this instructional resource.

This learning material hopes to engage the learners in guided and independent
learning activities at their own pace and time. Further, this also aims to help learners
acquire the needed 21st century skills especially the 5 Cs, namely: Communication,
Collaboration, Creativity, Critical Thinking, and Character while taking into
consideration their needs and circumstances.

In addition to the material in the main text, you will also see this box in the
body of the module:

As a facilitator you are expected to orient the learners on how to use this
module. You also need to keep track of the learners' progress while allowing them to
manage their own learning. Moreover, you are expected to encourage and assist the
learners as they do the tasks included in the module.

4
For the learner:

Welcome to the Electrical Installation and Maintenance Grade – 9 Self-Learning


Module on Board Wiring no.1- Installing Two Lamp Controlled by Two Surface Type
SPST using Knobs and Tube.

This module was designed to provide you with fun and meaningful
opportunities for guided and independent learning at your own pace and time. You
will be enabled to process the contents of the learning material while being an active
learner.

This module has the following parts and corresponding icons:

Expectations - This points to the set of knowledge and skills


that you will learn after completing the module.

Pretest - This measures your prior knowledge about the lesson


at hand.

Recap - This part of the module provides a review of concepts


and skills that you already know about a previous lesson.

Lesson - This section discusses the topic in the module.

Activities - This is a set of activities that you need to perform.

Wrap-Up - This section summarizes the concepts and


application of the lesson.

Valuing - This part integrates a desirable moral value in the


lesson.

Posttest - This measure how much you have learned from the
entire module.

5
EXPECTATIONS
Upon completion of this lesson, you are expected to:

• Establish the step-by-step procedures in Board Wiring no.1- Installing


Two Lamp Controlled by Two Surface Type SPST using Knobs and Tube;

• Justify the step-by-step procedures in Board Wiring no.1- Installing Two


Lamp Controlled by Two Surface Type SPST using Knobs and Tube; and

• Observe the protection precaution in step-by-step procedures in Board


Wiring no.1- Installing Two Lamp Controlled by Two Surface Type SPST
using Knobs and Tube

PRETEST
Directions: Lists down all the possible electrical materials needed to complete the
Board Wiring no.1- Installing Two Lamp Controlled by Two Surface Type SPST using
Knobs and Tube.

Materials
1.

2.

3.

4.

5.

6.

7.

8.

9.

6
RECAP

Do you still remember our last lessons? Can you Explain the importance of
procedures in installing the two Lamp controlled by two surface type SPST using
knobs and tube wiring method? Write your answer on the space provided.

__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________

LESSON

BOARD WIRING NO. 1- INSTALLING TWO LAMP CONTROLLED BY


TWO SURFACE TYPE SPST USING KNOBS AND TUBE
1. Prepare your drawing plan

7
2. Prepare and put near beside you all the materials, tools, equipment and PPE’s
need for the works.

3. Prepare your wiring board or working area by layout all measurement given
on your job sheet plan and drawing plan using pencil, meter square and frame
square

4. In measurement, always consider finding the center of conduit, raceways and


devices as references for layout design.

8
5. Always level the position of layout vertically and horizontally.

6. For final marking layout of conduit, raceways, boxes and devices always
used chalk.

7. Always mounted or install first all boxes after that connector and adopter
then if you need to tighten it follow the standard torque specification.

8. Mount all box type lighting fixture and surface type receptacle according to
given measurement and locations but don’t forget when lighting material like
incandescent bulb used flush type receptacles use junction box for mounting
receptacle.

9
9. Put the standard wire inside the service panel, and all boxes based on the
Philippine Electrical Code (PEC) and strip the wire carefully then connect it
to the terminal of service panel as sources, switches and to incandescent lamp
then attach it to knobs ready for wiring connections.

10. Splices all joints and connect it according to wiring connections standards
do not forget that you must carefully tape all joints with electrical tape.

10
Safety Precaution
1. Always provide tube in the two wires crossing each other to avoid contact
between the two wires

2. All the connections in lighting circuit must base on the standard

3. Always conduct continuity check to know and identify the possible wiring
defects

4. When wiring installation is finish always ask your teacher assistance to


evaluate your works

ACTIVITIES
DRAWING: Complete the circuit of Two Lamp Controlled by Two Surface Type SPST
using Knobs and Tube in a Pictorial Diagram as ACTIVITY NO. 2 and labelled the
parts of the complete circuit as ACTIVITY NO. 2

Note: Do not change the position of electrical materials

11
WRAP-UP
1. Make a short write up that response on what did you learn from the lesson.

__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________

VALUING

1. Give the safety precaution that you need to consider in doing electrical wiring
connections?

__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________

12
POSTTEST

Directions: Read each item carefully and choose the letter that corresponds to the
correct answer. Write your answer in the space provided before each number.

_____ 1. What is the meaning of switch acronym SPST?

A. Single Pole Single Throw C. Single Pole Single Tap

B. Single Pin Single Throw D. Single Pin Single Test

_____ 2. What type of switch is attach to the exposed surface of utility box wherein
the utility box in not part of the switch?

A. Floral Type Switch C. Floor Type Switch

B. Flush Type Switch D. Flow Type Switch

_____ 3. What is the meaning of wires acronym THHN?

A. Thermoplastic, High Heat, Nylon coated

B. Thermal plasma, High Heat, Nylon coated

C. Thermostat, Heat, Nylon coated

D. Thermostatic, High Heat, Nylon coated

_____ 4. What is a non-metallic materials that is use to insulated the two wires that

pass through to each other?

A. knobs C. THHN

B. Flush Type Switch (SPST) D. Tube

_____ 5. Which of the following is about the number of switch that is present in one

plate which is control the lamp?

A. Gang C. Moldflex Conduit

B. Flush Type Switch D. THHN

13
KEY TO CORRECTION

References

Author Marino C. Cueto and Roman A. Cabusora Jr, book title: Technology &
Livelihood Education–Grade 9 Learner’s Material (DepEd – IMCS First Edition, 2013)
pp. 88 – 120.

14