Project Name & No.: 132/11KV, SRAYATST SS MEP No. & Amount:
Objections or insistence by NOC stake holders on fulfilment of unanticipated Delays in obtainment of NOC & ensuing delays in Ensure meeting of all the statutory requirements for NOC &
PT‐143‐09 preconditions for processing of NOC. planned schedule. External Approvals 3 3 9 keep suitable float in the project schedule. Contractor
Inadequacy in PQ process & selection of non‐competent contractor for works Improper execution, failure in execution & Restricting pre‐qualification to DEWA registered & pre‐qualified
consequent non fulfilment of project objectives contractors. DEWA/
PT‐143‐05 Pre‐Contract 2 4 8
in time & requirements. Contractor
Inadequate data /Non‐availability of data Major changes in Tendered scope & associated Obtain the data from DEWA & counter verify the obtained
PT‐143‐01 time and commercial impacts. Pre‐Contract 2 4 8 data with Asset owner's work site staff and asset owner's Client/
contractors involved in related works. Consultant
Design not meeting or deviating the overall project requirements or charter Jeopardize all the associated substation work Develop conceptual design in close collaboration& association
with other projects and related stake holders. Consultant /
PT‐143‐02 Design Stage 2 4 8
Client
Wrong design of material & associated non‐acceptance by Asset Owner and Delays in planned schedule due to revised Ensure material Designs as per materials which were pre‐ DEWA/Consulta
PT‐143‐10 subsequent re‐design & re‐order. engineering & procurement Design Stage 2 4 8 approved by DEWA nt/Contractor
Flaws in construction design & subsequent non‐acceptance of work by other Denial of approvals for As built & final Ensure design & installations to be approved by DEWA Authorities/
stake holders (DM,RTA etc.) clearances with associated non‐acceptance by
PT‐143‐11 Design Stage 2 4 8 Consultant/
DEWA.
Contractor
Delays in manufacturing or rejection of materials owing to failure in FAT Delays in planned schedule due to requirement Ensure manufacturing & FAT procedures to be approved by
of re‐manufacturing & minor impact on costs DEWA and also allow necessary float between procurement & Consultant/
PT‐143‐12 Material Delivery 2 4 8
due to requirements of reinspection. installation. Contractor
Delay during installations or failure of any equipment during testing Non‐completion of work &associated delay in Ensure the installation works are supervised by approved and
project schedules. competent staff of consultant & contractor. Ensure the Consultant/
PT‐143‐15 Construction Stage 2 4 8 suppliers/vendors of material are part of project stake holders. Contractor
Modification works in the existing remote end substations Impact on project time & costs due to delay of Ensure work complies with accepted method statements and DEWA/
PT‐143‐16 outage certificate by DEWA Construction Stage 2 4 8 DEWA work procedures. Consultant/
Contractor
Delay in nomination of SCS contractor or in SCS contractor works Impact on project time & costs due to delay of Ensure delivery of SCS system on time and also installation and
SCS work SCS relay testing to be done as per project scheduale . DEWA/SCS
PT‐143‐17 Pre‐Contract 2 4 8
Contractor
Delay in 132 KV cable feeder laying and termination works Impact on project time & costs due to delay of Ensure cable laying on time and also termination and cable DEWA/Cable
PT‐143‐18 132 KV cable laying and termination work Construction Stage 2 4 8 testing to be done as per project scheduale . Contractor
Delay in DEWA acceptance for substation commissioning Impact on project time & costs due to DEWA Ensure all systems are tested and ready for energization and
reediness for substation commissioning ensure all snag points are cleared and signed by DEWA DEWA/Consulta
PT‐143‐19 Handover Stage 2 4 8
engineers nt/Contractor
Major snag items in the works, which warrants non‐issuance of TOC Delays in project close out. Ensure TOC issuance as per Asset Owner's clearance & DEWA/Consulta
PT‐143‐20 Handover Stage 2 3 6 acceptance of works. nt /Client
Denial or Delay of Approvals (Construction NOC, Permits) Delays in planned project time schedule Ensure compliance to submission & mode of submission as per Contractor/
PT‐143‐22 External Approvals 2 3 6 requirements of Authorities concerned. Consultant
Minor unforeseen flaws which can surface later on Delays in validation during execution stage & Allow necessary resource provisions to meet impacts of time
associated time and cost impacts /costs Consultant /
PT‐143‐04 Construction Stage 2 3 6
Contractor
Delays in delivery due to shipping delays & delays of site inspections after Non‐availability of materials as per planned Ensure delivery on time and also allow necessary float
receipt. schedule & associated delay in project between procurement & installation.
PT‐143‐13 Material Delivery 2 3 6 Contractor
completion schedules.
Deviations in survey levels or coordinates for the civil work items (Duct Banks, Non‐acceptance of work or non‐suitability of Ensure compliance to survey levels & coordinates as per
HDD) work for Electrical installation and associated Construction NOC and ensure compliance of Asset owners Consultant/
PT‐143‐14 delays in project schedule. Construction Stage 2 3 6 stage wise check lists to ensure civil works meet the Contractor
requirement of electrical works.
Surfacing of defects in work & associated NODs (Notification of defects) Delays in project close out. Ensure issuance of DLCs will be in consultation with Asset
PT‐143‐21 Handover Stage 2 2 4 DEWA/Consulta
owner.
nt/Client
Denial or Delay of Internal Approvals Delays in planned project time schedule Discuss with concerned parties/departments to pre‐empt any Client/Consultan
PT‐143‐23 Internal Approvals 2 2 4 objections or denials/delays etc. t/Contractor
Short comings in Technical & associated commercial evaluation process Non‐acceptance of works, materials by Asset Employ/engage an Asset Owner's listed and experienced
owner or price quotes with higher/ non‐market consultancy agency for Tender evaluation process
PT‐143‐06 Pre‐Contract 1 4 4 Client
prices by Bidder.
Supervision by un‐experienced agency & associated non‐meeting of Asset Non‐acceptance of works by Asset Owner & Employ/engage an Asset Owner's listed and experienced
Owner's required work quality . associated impacts on planned project schedule. consultancy agency for post contract services & Supervision. Client/
PT‐143‐07 Construction Stage 1 4 4
Consultant
Green
78%
LEGEND
CATASTROPHIC
5 Risk Likelihood
REMOTE Less than 5% probability
MINOR
2 Risk Impact
NEGLIGIBLE Insignificant impact on Project
NEGLIGIBLE
1 MINOR Some impact on the Project
REMOTE UNLIKELY POSSIBLE PROBABLE CERTAIN MODERATE Significant impact on the success of the Project
1 2 3 4 5
0‐5% 5‐25% 25‐50% 50‐80% >80%
MAJOR Major impact on achievement of the project deliverables
Likelihood
High
CATASTROPHIC Effects impact on project performance
Medium
Low