You are on page 1of 2

GENERAL NOTES: STANDARD SPECIFICATIONS

AND PRECAUTIONS: UNIT


1. ALL MECHANICAL WORKS HEREIN INCLUDED SHALL
BE DONE ACCORDANCE WITH THE LATEST 1. WHEN INSTALLATION MADE EQUIPMENTS CHECK FOR THEIR LOAD OF
NO. DESCRIPTION HP WATTS
REQUIREMENTS OF THE PHILIPPINE BUILDING CODE REFRIGERANT.
AND LOCAL RELATION. 2. INSTALLATION SHOULD BE PROVIDED ON PIPES THE LIQUID PIPES AND SUCTION
PIPES IN ORDER TO MINIMIZE THE HEAT TRANSFER AND ELIMINATE
CONDENSATION,
2. THE LOCAL SCOPE OF WORKS SHALL INCLUDE WORKS
DESCRIBED IN THE GENERAL PROVISIONS OF THE
3. WRONG WIRING CONNECTION OCCUR IN POWER RTS-RTS, SCROLL COMPRESSOR IN
REVERSE CREATES NOISE,CHECK TO AVOID DAMAGES. 1 AIRCONDITIONING UNIT 2 1492
TECHNICAL SPECIFICATIONS FOR MECHANICAL WORKS. 4. CONSULT PROFESSIONAL MECHANICAL ENGINEER IN SYMBOLS OF OPERATION,
REMOTE CONTROL WITH THE WIRING
3. ALL WORKS SHALL BE EXECUTED IN CLOSE 5. DUCT SYSTEM ALLOW MOTOR SPECIFICATION DRIVES CARRIES PULLEY ON
COORDINATION WITH THE WORKS OF OTHER TRADES
COORDINATE WITH THE ARCHITECTURAL AND 6.
MAGNETIC WITH CONTRACTOR.
MOTOR PERFORMANCE TEST SHOULD IN ACCORDANCE WITH ASH-57 2 AIRCONDITIONING UNIT 2.5 1865
INSTALLED CAPACITY
ELECTRICAL THE EXACT LOCATION OF FANS. PIPE AND
AIR CONDITIONING UNIT. A.) COOLING CAPACITIES ON 27°C DB AND 19.5°C NB (INDOOR UNIT).

4. CONTRACTORS SHALL SUBMIT SHOP DRAWING,


7.
B) CONDENSING TEMPERATURES IS 50°C AND EVAPORATING TEMPERATURE IS 72°C.

ALWAYS CHECK INDICATED LOAD, ENTRANCE CONDUCTOR/SERVICE EQUIPMENT ON


3 AIRCONDITIONING UNIT 3T 3500
MANUFACTURED EQUIPMENT, SPECIFICATIONS,
INSULATIONS, FILTERS. ETC. BEFORE EXECUTION OF MODELS HAS ACT ON SIZING OF PIPES.
8. ALWAYS CONDUCT ON RECORD OF REFRIGERANT APPLICATION AND SHOULD FREE
WORKS.

5. CONTRACTOR/SUPPLIER SHALL INSTALL ALL 9.


BLOW OF AIR-COOLING SYSTEM BE ACCOMMODATED THE ENTIRE AREA AND
CAPACITY BE ACCUMULATED THE ENTIRE PLACE
THE AHU AND ACCU SHALL BE FIRMLY SECURED TO THE BASE FOUND.
4 AIRCONDITIONING UNIT 2 1492
EQUIPMENT IN ACCORDANCE WITH THE MANUFACTURER 10. ALL ACCU's INSTALLED ON THE SIDE OF THE BUILDING AND ELEVATED NO LESS
RECOMMENDATIONS COMPRESSOR SHALL PROVIDED THAN 5 FT. ABOVE THE GROUND LEVEL, SHALL BE PROVIDED SERVICE ACCESS
WITH DUAL PRESSURE CUT-OUT SWITCH TIME DELAY FROM WITHIN THE BUILDING OF SERVICE LADDER OUTSIDE THE BUILDING.
RELAY, THERMAL OVERLOAD PROTECTION AND ALL 11. FOR THOSE EXPOSED TO THE WEATHER, INSULATION SHALL HAVE AN ADDITIONAL
PLASTIC TAPE COVERING OR METAL CLADDING ALL COPPER TUBES SHALL BE
REQUIRE ACCESSORIES.
BRAND NEW AND FREE FROM DEEP SCRATCHES, DENTS, KINKS AND BURNS, HARD
DRAWN TYPE K OR L IS RECOMMENDED REFRIGERANT LINES LARGE THAN 3/4
6. ALL FLOOR SLAB MOUNTED VIBRATING EQUIPMENT DIAMETER.
SHALL BE PROVIDED WITH VIBRATION ISOLATORS TO 12. AIR SHALL NOT BE RETICULATED IN AREAS OR SPACES WHERE THERE ARE
PREVENT VIBRATION AND NOISE TRANSMISSION. OBJECTIONABLE QUANTITIES OF TOXIC WASTE GASES FLAMMABLE VAPORS
BACTERIA AND DUST AND FOR UNDERGROUND PIPING, BOTH SUCTION AND
7. PIPE ALL EQUIPMENT CONDENSATE DRAIN UNDER TO DISCHARGES LINES SHALL BE ADEQUATELY PROTECTED AGAINST DAMAGES FROM
WATER AND OTHER FOREIGN MATERIALS THAT MAY HAVE A HARMFUL EFFECT ON
THE NEAREST FLOOR CATCH BASIN. USE MAX. 3/4 0 PVC
THE PERFORMANCE OF THE UNIT.
PIPE DRAIN LINE. 13. A SAFETY SWITCH AND OR CIRCUIT BREAKER SHALL BE INSTALLED BETWEEN THE
POWER SOURCE AND THE UNIT ALL CONDUCTOR SHALL ADEQUATELY PROTECTED
8. PITCH ALL HORIZONTAL REFRIGERANT LINE A MINIMUM AGAINST PHYSICAL DAMAGES AND WHEN RUN UNDERGROUND SHALL BE
1/2" IN FEET IN THE DIRECTION OF REFRIGERANT FLOW. INSTALLED IN A DUCT OF RIGID METALLIC CONDUITS SUITABLE FOR THE CONDITION,
DUCTS AND CONDUITS MADE ORDINARY STEEL BE COATED ON CORROSION
9. PROVIDE 20 MM THICK ELASTOMERIC RUBBER RESISTANCE.
14. ALWAYS INSTALL A DOUBLE-THROW CIRCUIT BREAKER WITH 500 AMPERES.
INSULATION TO ALL LINES WITH BLUE FILM TAPE FINISH
AS FINISHED.

10. PROVIDE AND INSTALL CONTROL WIRING FOR ALL PVC


AND VENTILATION EQUIPMENT.

11. THE EVAPORATORS SHOULD BE INSTALLED WITH STEEL


SUPPORT FREE FROM MY VIBRATION A RUBBER SHOULD
BE PROVIDED AND INSTALLED PROPERLY.

12. PROPER INCLINATION FOR DRAIN PIPE SHOULD BE


INSTALLED AT LINES TO PREVENT BACK FLOW.

13. ARMAFLEX AND AEROFLEX INSULATION SHOULD BE


INSTALLED AT LINES TO PREVENT.

14. 14. ELECTRICAL LINES FOR CONTROL AND SWITCHES


SHOULD NOT BE VISIBLE AND SHOULD BE IMBEDDED IN
CONCRETE WALL.
15. DRAIN SHOULD PAN AND BE COATED WITH WEATHER
INSULATIONS.
16. HE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL
TESTING, ALSO BALANCING AND COMMISSIONING OF
THE ENTIRE INSTALLATION.

AS-BUILT PLAN OF 2-STOREY WAREHOUSE MR. & MRS. ANDREW NG M-1


WAREHOUSE

CR. CONFERENCE
ROOM 3T
ACU

CR.

1 1
OFFICE
OFFICE

2.5HP 2.0HP 2.0HP


ACU ACU ACU

STAIRS STAIRS

1 GROUND FLR. LAYOUT 2 SECOND FLR. LAYOUT


ME 02 SCALE NTS ME 02 SCALE NTS

AS-BUILT PLAN OF 2-STOREY WAREHOUSE MR. & MRS. ANDREW NG M-2

You might also like