1 Earthworks R 136,045.00
3 Masonry R 441,644.00
4 Waterproofing R 97,190.00
7 Ironmongery R 23,277.15
10 Metalwork R 483,114.22
11 Plastering R 271,112.50
12 Tiling R 210,237.25
13 Glazing R 18,739.25
14 Paintwork R 229,527.00
Sub-Total R 3,712,089.44
VAT R 754,293.77
Page 1 of 32
Item DESCRIPTION UNIT QTY - AMOUNT
SECTION 1
ELEMENT 01
Page 2 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
SECTION 2
ELEMENT 01
EARTHWORKS (PROVISIONAL)
Entire Building
Basement
GARAGE
9 Excavate for bulk exceeding 2m deep m3 167 R 105.00 17,535.00
10 Extra over Soft rock m3 8 R 350.00 2,800.00
11 Extra over hard rock m3 8 R 850.00 6,800.00
12 Risk of collapse to the sides trenches m2 146 R 60.00 8,760.00
Hobby Room
13 Excavate for bulk exceeding 2m deep m3 73 R 105.00 7,665.00
14 Extra over Soft rock m3 4 R 450.00 1,800.00
15 Extra over hard rock m3 4 R 850.00 3,400.00
16 Risk of collapse to the sides trenches m2 81 R 60.00 4,860.00
Page 3 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 02
BASEMENT FLOOR
1 Garage
2 Blinding 25mm m2 49 133.00 6,517.00
3 Surface bed 25MPa/19mm (100mm) m2 49 215.00 10,535.00
4 RC Slab 250mm m2 49 1,089.00 53,361.00
5 Formwork propping m2 49 580.00 28,420.00
6 Reinforcement mesh + bars m2 49 66.00 3,234.00
7 Test Cube Sets 2 2,000.00 4,000.00
Hobby Room
8 Blinding 25mm m2 19 133.00 2,527.00
9 Surface bed 25MPa/19mm (100mm) m2 19 215.00 4,085.00
10 RC Slab 250mm m2 19 1,089.00 20,691.00
11 Formwork propping m2 19 580.00 11,020.00
12 Reinforcement mesh + bars m2 19 66.00 1,254.00
13 Test Cube Sets 2 2,000.00 4,000.00
GROUND FLOOR
14 Surface bed 25MPa/19mm (100mm) m2 114 215.00 24,510.00
15 RC Slab 250mm m2 165 1,089.00 179,685.00
16 Formwork propping m2 165 580.00 95,700.00
17 Reinforcement mesh + bars m2 165 66.00 10,890.00
18 Test Cube Sets 4 2,000.00 8,000.00
Page 4 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 03
MASONRY
BRICKWORK
BASEMENT FLOOR
Garage
1 280mm brick cavity wall - Superstructure m2 84 643.00 54,012.00
2 Lintel one brick wall m 6 161.00 966.00
3 150mm Wide reinforcement built in horizontally - In Superstructure m 988 9.00 8,892.00
Hobby Room
4 280mm brick cavity wall - Superstructure m2 54 643.00 34,722.00
5 280mm brick cavity wall m2 50 643.00 32,150.00
6 Lintel one brick wall m 3 161.00 483.00
7 150mm Wide reinforcement built in horizontally - In Superstructure m 1224 9.00 11,016.00
GROUND FLOOR
8 280mm brick cavity wall - foundation m2 125 643.00 80,375.00
9 280mm brick cavity wall m2 125 643.00 80,375.00
10 One brick walls - foundation m2 3 625.00 1,875.00
11 One brick walls m2 35 625.00 21,875.00
12 Half brick walls m2 35 188.00 6,580.00
13 Lintel one brick wall m 2 161.00 322.00
14 Lintel half brick wall m 3 89.00 267.00
15 150mm Wide reinforcement built in horizontally - In Superstructure m 2008 9.00 18,072.00
16 75mm Wide reinforcement built in horizontally - In Superstructure m 137 9.00 1,233.00
FIRST FLOOR
17 280mm brick cavity wall m2 94 643.00 60,442.00
18 One brick walls m2 12 625.00 7,500.00
19 Half brick walls m2 10 188.00 1,880.00
20 Lintel one brick wall m 5 161.00 805.00
21 Lintel half brick wall m 1 89.00 89.00
22 150mm Wide reinforcement built in horizontally - In Superstructure m 1247 9.00 11,223.00
23 75mm Wide reinforcement built in horizontally - In Superstructure m 118 55.00 6,490.00
Page 5 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 04
WATERPROOFING
BASEMENT FLOOR
Garage
1 Waterproofing to walls m2 84 233.00 19,572.00
2 Waterproofing to floor m2 43 233.00 10,019.00
3 Waterproofing to floor slab m2 43 604.00 25,972.00
Hobby Room
4 Waterproofing to walls m2 50 233.00 11,650.00
5 Waterproofing to floor m2 15 233.00 3,495.00
6 Waterproofing to floor slab m2 15 604.00 9,060.00
GROUND FLOOR
Covered Porch
7 Waterproofing to floor slab m 11 604.00 6,644.00
8 Waterproofing to vertical wall m2 27 233.00 6,291.00
FIRST FLOOR
Covered Porch
11 DPC to vertical and horizontal wall m2 5 54.00 270.00
Page 6 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 05
ENTIRE BUILDING
BASEMENT FLOOR
Garage
Frame
2 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden door frame No 1 R 3,047.50 3,047.50
Door
3 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden semi- No 1 R 3,047.50 3,047.50
hollow core door frame
Hobby Room
Skirting and Architraves
5 Allow a Prime Cost of R 65.00 excluding VAT for install wooden skirting m 17 R 118.74 2,018.54
GROUND FLOOR
Laundry Room
Frame
6 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden door frame No 1 R 3,047.50 3,047.50
Door
7 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden semi- No 1 R 3,047.50 3,047.50
hollow core door frame
Entrance
Skirting and Architraves
9 Allow a Prime Cost of R 80.00 excluding VAT for install wooden skirting m 31 R 136.85 4,242.35
Foyer
Frame
10 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden door frame No 1 R 3,047.50 3,047.50
Door
11 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden semi- No 1 R 3,047.50 3,047.50
hollow core door frame
Page 7 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
Laundry
Frame
13 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden door frame No 1 R 3,047.50 3,047.50
Door
14 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden semi- No 1 R 3,047.50 3,047.50
hollow core door frame
Bathroom
Frame
16 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden door frame No 1 R 3,047.50 3,047.50
Door
17 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden semi- Sum 1 R 3,047.50 3,047.50
hollow core door frame
Boardroom 1
Frame
19 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden door frame Sum 1 R 3,047.50 3,047.50
Door
20 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden semi- Sum 1 R 3,047.50 3,047.50
hollow core door frame
Boardroom 2
Frame
22 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden door frame Sum 1 R 3,047.50 3,047.50
Door
23 Allow a Prime Cost of R 2 000.00 excluding VAT for install wooden semi- . 1 R 3,047.50 3,047.50
hollow core door frame
FIRST FLOOR
Roof Construction
25 Wooden roof structure to mono pitched, consisting of truss No. 1 R 61,875.00 61,875.00
Page 8 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
Scullery
28 Allow a Prime Cost of R 895.00 excluding VAT for install wooden door frame Sum 1 R 1,713.21 1,713.21
Door
29 Allow a Prime Cost of R 895.00 excluding VAT for installing wooden semi- No 1 R 1,713.21 1,713.21
hollow core door frame
Dresser
Frame
31 Allow a Prime Cost of R 895.00 excluding VAT for install wooden door frame Sum 1 R 1,713.21 1,713.21
Door
32 Allow a Prime Cost of R 895.00 excluding VAT for install wooden semi-hollow . 1 R 1,713.21 1,713.21
core door frame
E-suite Bathroom
Frame
34 Allow a Prime Cost of R 895.00 excluding VAT for install wooden door frame Sum 1 R 1,713.21 1,713.21
Door
35 Allow a Prime Cost of R 895.00 excluding VAT for install wooden semi-hollow . 1 R 1,713.21 1,713.21
core door frame
Main Boardroom
37 Roof construction mono pitched Sum 1 R 154,275.00 154,275.00
Frame
38 Allow a Prime Cost of R 895.00 excluding VAT for install wooden door frame Sum 1 R 1,713.21 1,713.21
Door
39 Allow a Prime Cost of R 895.00 excluding VAT for install wooden semi-hollow . 1 R 1,713.21 1,713.21
core door frame
Page 9 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 06
ROOF COVERING
1 Construction of IBR roof covering including flashing mono pitched roof not Sum 1 R 61,875.00 61,875.00
exceeding 25 degrees angle
Page 10 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 07
IRONMONGERY
BASEMENT
Hinges
1 Allow a Prime Cost of R 275.00 excluding VAT for supply and installation Sum 1 R 372.31 372.31
hinges
Handles
2 Allow a Prime Cost of R 650.00 excluding VAT for supply and installation Sum 1 R 922.88 922.88
handles
Door stoppers
4 Allow a Prime Cost of R 105.00excluding VAT for supply and installation door Sum 1 R 184.29 184.29
stopper
GROUND FLOOR
Hinges
5 Allow a Prime Cost of R 275.00 excluding VAT for supply and installation Sum 5 R 372.31 1,861.56
hinges
Handles
6 Allow a Prime Cost of R 650.00 excluding VAT for supply and installation Sum 5 R 922.88 4,614.38
handles
Door stoppers
8 Allow a Prime Cost of R 105.00 excluding VAT for supply and installation door Sum 5 R 184.29 921.44
stopper
FIRST FLOOR
Hinges
9 Allow a Prime Cost of R 275.00 excluding VAT for supply and installation Sum 3 R 372.31 1,116.94
hinges
Handles
10 Allow a Prime Cost of R 650.00 excluding VAT for supply and installation Sum 3 R 922.88 2,768.63
handles
Door stoppers
12 Allow a Prime Cost of R 105.00 excluding VAT for supply and installation door Sum 3 R 184.29 552.86
stopper
Bathroom fittings
13 Allow a Prime Cost of R 350.00 excluding VAT for supply and installation Sum 3 R 480.13 1,440.38
toilet holder
Page 11 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
Page 12 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 08
ENTIRE BUILDING
BASEMENT FLOOR
Garage
1 Suspended plasterboard ceiling m2 43 R 623.88 26,826.63
2 Shadoline m 28 R 112.99 3,163.65
3 Optional Allowance for trap door No 1 R 897.00 897.00
Hobby Room
4 Suspended plasterboard ceiling m2 15 R 623.88 9,358.13
5 Shadoline m 17 R 112.99 1,920.79
6 Optional Allowance for trap door No 1 R 897.00 897.00
GROUND FLOOR
Covered Porch
7 Suspended plasterboard ceiling m2 27 R 623.88 16,844.63
8 Shadoline m 26 R 112.99 2,937.68
Entrance Lobby
9 Suspended plasterboard ceiling m2 35 R 623.88 21,835.63
10 Shadoline m 31 R 112.99 3,502.61
11 Optional Allowance for trap door No 1 R 897.00 897.00
Laundry Room
12 Suspended plasterboard ceiling m2 10 R 623.88 6,238.75
13 Shadoline m 14 R 112.99 1,581.83
14 Optional Allowance for trap door No 1 R 897.00 897.00
Passage
15 Suspended plasterboard ceiling m2 3 R 623.88 1,871.63
16 Shadoline m 8 R 112.99 903.90
Bathroom
17 Suspended plasterboard ceiling m2 9 R 623.88 5,614.88
18 Shadoline m 11 R 112.99 1,242.86
19 Optional Allowance for trap door No 1 R 897.00 897.00
Bedroom 1
20 Suspended plasterboard ceiling m2 14 R 623.88 8,734.25
21 Shadoline m 15 R 112.99 1,694.81
22 Optional Allowance for trap door No 1 R 897.00 897.00
Bedroom 2
23 Suspended plasterboard ceiling m2 16 R 623.88 9,982.00
24 Shadoline m 16 R 112.99 1,807.80
25 Optional Allowance for trap door No 1 R 897.00 897.00
FIRST FLOOR
Covered Porch
26 Suspended plasterboard ceiling m2 R 623.88 623.88
27 Shadoline m R 112.99 112.99
28 Optional Allowance for trap door No R 897.00 897.00
Page 13 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
Foyer
32 Suspended plasterboard ceiling m2 9 R 623.88 5,614.88
33 Shadoline m 12 R 112.99 1,355.85
Scullery
34 Suspended plasterboard ceiling m2 6 R 623.88 3,743.25
35 Shadoline m 10 R 112.99 1,129.88
36 Optional Allowance for trap door No 1 R 897.00 897.00
Dresser
37 Suspended plasterboard ceiling m2 11 R 623.88 6,862.63
38 Shadoline m 13 R 112.99 1,468.84
39 Optional Allowance for trap door No 1 R 897.00 897.00
E-suite Bathroom
40 Suspended plasterboard ceiling m2 12 R 623.88 7,486.50
41 Shadoline m 14 R 112.99 1,581.83
42 Optional Allowance for trap door No 1 R 897.00 897.00
Main Bedroom
43 Suspended plasterboard ceiling m2 18 R 623.88 11,229.75
44 Shadoline m 18 R 112.99 2,033.78
45 Optional Allowance for trap door No 1 R 897.00 897.00
Page 14 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 09
STRUCTURAL STEELWORK
GROUND FLOOR
1 Structural I - Column 152x 152 x 5.8mm and 23kg/m m 13 R 1,451.01 18,863.16
2 Structural I - Beam 152x 152 x 5.8mm and 23kg/m m 12 R 1,451.01 17,412.15
FIRST FLOOR
3 Structural I - Beam 152x 152 x 5.8mm and 23kg/m m 17 R 1,451.01 24,667.21
4 Structural I - Beam 152x 152 x 5.8mm and 23kg/m m 15 R 1,451.01 21,765.19
Page 15 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 10
METALWORK
Page 16 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 11
ENTIRE BUILDING
External Wall
1 External Plaster - Garage m2 61 R 161.00 9,821.00
Basement
2 External Plaster - Garage m2 53 R 161.00 8,533.00
3 External Plaster - Hobby m2 53 R 161.00 8,533.00
First Floor
5 External Plaster m2 153 R 161.00 24,633.00
BASEMENT FLOOR
Garage
6 Internal plaster m2 129 R 155.25 20,027.25
7 Screed m2 43 R 155.25 6,675.75
8 Skim on ceiling m2 43 R 120.75 5,192.25
Hobby Room
9 Internal plaster m2 45 R 155.25 6,986.25
10 Screed m2 15 R 155.25 2,328.75
11 Skim on ceiling m2 15 R 120.75 1,811.25
GROUND FLOOR
Covered Porch
12 Screed m2 26 R 155.25 4,036.50
Entrance Lobby
13 Internal plaster m2 93 R 155.25 14,438.25
14 Skim on ceiling m2 36 R 120.75 4,347.00
Laundry Room
15 Internal plaster m2 42 R 155.25 6,520.50
16 Skim on ceiling m2 10 R 120.75 1,207.50
Foyer
17 Internal plaster m2 60 R 155.25 9,315.00
18 Screed m2 10 R 155.25 1,552.50
19 Skim on ceiling m2 10 R 120.75 1,207.50
Bathroom
20 Internal plaster m2 27 R 155.25 4,191.75
21 Screed m2 9 R 155.25 1,397.25
22 Skim on ceiling m2 9 R 120.75 1,086.75
Bedroom 1
23 Internal plaster m2 48 R 155.25 7,452.00
24 Screed m2 16 R 155.25 2,484.00
25 Skim on ceiling m2 16 R 120.75 1,932.00
Bedroom 2
26 Internal plaster m2 45 R 155.25 6,986.25
Page 17 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
FIRST FLOOR
Covered Porch
29 Screed m2 26 R 155.25 4,036.50
30 Skim on ceiling m2 26 R 120.75 3,139.50
Scullery
34 Internal plaster m2 30 R 155.25 4,657.50
35 Screed m2 6 R 155.25 931.50
36 Skim on ceiling m2 6 R 120.75 724.50
Dresser
37 Internal plaster m2 39 R 155.25 6,054.75
38 Screed m2 11 R 155.25 1,707.75
39 Skim on ceiling m2 11 R 120.75 1,328.25
E-suite Bathroom
40 Internal plaster m2 42 R 155.25 6,520.50
41 Screed m2 12 R 155.25 1,863.00
42 Skim on ceiling m2 12 R 120.75 1,449.00
Main Bedroom
43 Internal plaster m2 54 R 155.25 8,383.50
44 Screed m2 18 R 155.25 2,794.50
45 Skim on ceiling m2 18 R 120.75 2,173.50
Page 18 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 12
TILING
BASEMENT FLOOR
Garage
1 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 43 R 566.38 24,354.13
tiles
Hobby Room
2 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 15 R 566.38 8,495.63
tiles
GROUND FLOOR
Covered Porch
3 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 26 R 566.38 14,725.75
tiles
Entrance Lobby
4 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 36 R 531.88 19,147.50
tiles
Laundry Room
5 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 10 R 531.88 5,318.75
tiles
6 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install wall m2 4 R 566.38 2,265.50
tiles
Foyer
7 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 10 R 566.38 5,663.75
tiles
Bathroom
8 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 9 R 566.38 5,097.38
tiles
9 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install wall m2 18 R 566.38 10,194.75
tiles
Bedroom 1
10 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 16 R 566.38 9,062.00
tiles
Bedroom 2
11 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 14 R 566.38 7,929.25
tiles
FIRST FLOOR
Covered Porch
12 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 26 R 566.38 14,725.75
tiles
Scullery
Page 19 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
15 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 6 R 566.38 3,398.25
tiles
Dresser
16 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 11 R 566.38 6,230.13
tiles
E-suite Bathroom
17 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 12 R 566.38 6,796.50
tiles
18 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install wall m2 28 R 566.38 15,858.50
tiles
Main Bedroom
19 Allow a Prime Cost of R 250.00/m2 excluding VAT for supply and install floor m2 18 R 566.38 10,194.75
tiles
Page 20 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 13
GLAZING
SHOWER
1 Allow a Prime Cost of R 4 500.00 excluding VAT for Shower enclosure No 2 R 7,446.25 14,892.50
2 Allow a Prime Cost of R 450.00 excluding VAT for soup holder 10mm clear No 4 R 641.13 2,564.50
toughed glass fixed to shower wall with fixings and glue
Page 21 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 14
PAINTWORK
ENTIRE BUILDING
External Wall Plaster
1 External Wall Plaster - Garage m2 61 R 123.00 7,503.00
Fibre cement boards m 51 R 46.00 2,346.00
Basement
2 External Wall Plaster - Garage m2 53 R 123.00 6,519.00
3 External Wall Plaster - Hobby m2 53 R 123.00 6,519.00
4 Ceiling
First Floor
6 External Wall Plaster m2 102 R 123.00 12,546.00
On Metal
7 Steel Beams and Columns m2 53 R 123.00 6,519.00
On Roof Slabs
Garage m2 45 R 123.00 5,535.00
8 Hobby room m2 16 R 123.00 1,968.00
BASEMENT FLOOR
9 Garage
10 Internal Wall Plaster m2 129 R 123.00 15,867.00
11 Screed m2 43 R 123.00 5,289.00
12 Ceiling m2 43 R 123.00 5,289.00
Hobby Room
13 Internal Wall Plaster m2 45 R 123.00 5,535.00
14 Screed m2 15 R 123.00 1,845.00
15 Ceiling m2 15 R 123.00 1,845.00
GROUND FLOOR
Covered Porch
16 Ceiling m2 26 R 123.00 3,198.00
17 Polish floor m2 26 R 123.00 3,198.00
Entrance Lobby
18 Internal Wall Plaster m2 93 R 123.00 11,439.00
19 Ceiling m2 36 R 123.00 4,428.00
Laundry Room
20 Internal Wall Plaster m2 42 R 123.00 5,166.00
21 Ceiling m2 10 R 123.00 1,230.00
22 Door and frame m2 2 R 123.00 246.00
Foyer
23 Internal Wall Plaster m2 60 R 123.00 7,380.00
24 Screed m2 10 R 123.00 1,230.00
25 Ceiling m2 10 R 123.00 1,230.00
26 Door and frame m2 2 R 123.00 246.00
Page 22 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
Bathroom
27 Internal Wall Plaster m2 27 R 123.00 3,321.00
28 Screed m2 9 R 123.00 1,107.00
29 Ceiling m2 9 R 123.00 1,107.00
30 Door and frame m2 2 R 123.00 246.00
Bedroom 1
31 Internal Wall Plaster m2 48 R 123.00 5,904.00
32 Screed m2 16 R 123.00 1,968.00
33 Ceiling m2 16 R 123.00 1,968.00
Bedroom 2
34 Internal Wall Plaster m2 45 R 123.00 5,535.00
35 Screed m2 14 R 123.00 1,722.00
36 Skim on ceiling m2 14 R 123.00 1,722.00
37 Door and frame m2 2 R 123.00 246.00
FIRST FLOOR
Covered Porch
38 Screed m2 26 R 123.00 3,198.00
39 Ceiling m2 26 R 123.00 3,198.00
Scullery
43 Internal Wall Plaster m2 30 R 123.00 3,690.00
44 Screed m2 6 R 123.00 738.00
45 Ceiling m2 6 R 123.00 738.00
46 Door and frame m2 2 R 123.00 246.00
Dresser
47 Internal Wall Plaster m2 39 R 123.00 4,797.00
48 Screed m2 11 R 123.00 1,353.00
49 Plasterboard ceiling m2 11 R 123.00 1,353.00
50 Door and frame m2 2 R 123.00 246.00
E-suite Bathroom
51 Internal Wall Plaster m2 42 R 123.00 5,166.00
52 Screed m2 12 R 123.00 1,476.00
53 Ceiling m2 12 R 123.00 1,476.00
54 Door and frame m2 2 R 123.00 246.00
Main Bedroom
55 Internal Wall Plaster m2 54 R 123.00 6,642.00
56 Screed m2 18 R 123.00 2,214.00
57 Ceiling m2 18 R 123.00 2,214.00
58 Door and frame m2 2 R 123.00 246.00
Page 23 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 15
ENTIRE BUILDING
FITTINGS
MUNICIPAL CONNECTIONS
1 Allow a budget of R 13 800.00 excluding VAT for municipal bulk supply and Sum 1 R 13,800.00 13,800.00
waste connections
WATER HEATER
2 Water 150 Litre, complete with valves, tray, and drip pipe No 1 R 19,596.00 19,596.00
GROUND FLOOR
SANITARYWARE
Bath
3 Allow a Prime Cost of R 4 500.00 excluding VAT for PVC built-in bath tub No 1 R 6,066.25 6,066.25
4 Allow a Prime Cost of R 2 000.00 excluding VAT for bath mixer and sprout No 1 R 3,047.50 3,047.50
Sink
7 Allow a Prime Cost of R 2 100.00 excluding VAT for Stainless steel double No 1 R 3,168.25 3,168.25
sink cut in counter top (counter top elsewhere measured)
8 Allow a Prime Cost of R 1 800.00 excluding VAT for Stainless steel single sink No 1 R 2,806.00 2,806.00
cut in counter top (counter top elsewhere measured)
9 Allow a Prime Cost of R 1 800.00 excluding VAT for sink mixer No 2 R 2,806.00 5,612.00
Water-Closet
14 Allow a Prime Cost of R 3 500.00 excluding VAT for Water-Closet complete No 1 R 4,858.75 4,858.75
with seats and flush mechnism
Basin
17 Allow a Prime Cost of R 4 500.00 excluding VAT for vanity tops with No 2 R 5,836.25 11,672.50
countersunk basin
Page 24 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
External works
25 Bib tap, including gulley complete with grating, pre-cast concrete casing No 1 R 2,558.75 2,558.75
FIRST FLOOR
SANITARYWARE
Bath
26 Allow a Prime Cost of R 4 500.00 excluding VAT for PVC built-in bath tub No 1 R 6,066.25 6,066.25
27 Allow a Prime Cost of R 1 800.00 excluding VAT for bath mixer and sprout No 1 R 2,806.00 2,806.00
Sink
30 Allow a Prime Cost of R 2 100.00 excluding VAT for Stainless steel double No 1 R 3,168.25 3,168.25
sink cut in counter top (counter top elsewhere measured)
31 Allow a Prime Cost of R 1 800.00 excluding VAT for sink mixer No 1 R 2,806.00 2,806.00
32 Sink waste, and grating, and water stopper No 2 R 537.63 1,075.25
33 Gate valve No 1 R 477.25 477.25
34 P/S double trap No 1 R 1,193.13 1,193.13
Water-Closet
35 Allow a Prime Cost of R 3 500.00 excluding VAT for Water-Closet complete No 1 R 4,858.75 4,858.75
with seats and flush mechnism
Basin
38 Allow a Prime Cost of R 4 500.00 excluding VAT for vanity tops with No 1 R 5,836.25 5,836.25
countersunk basin
Page 25 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
Page 26 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
ELEMENT 16
Electrical Works
FITTINGS
ENTIRE BUILDING
DISTRIBUTION BOARD
1 Allow a Prime Cost of R 15 000.00 excluding VAT for construction of Sum 1 R 20,412.50 20,412.50
Distrubution Board including all sockects
WATER HEATER
2 Electrical Geyser 150 litre complete with tray, valves etc. (electrical works Sum 1 R 2,722.63 2,722.63
elsewhere measured)
TEST
3 Testing and issues of Certificate of compliance for electrical works Sum 1 R 11,125.00 11,125.00
LIGHT FITTINGS
4 Allow a Prime Cost of R 650.00 excluding VAT to install light Sum 8 R 1,106.88 8,855.00
5 Allow a Prime Cost of R 1 500.00 excluding VAT for construction of Sum 1 R 2,121.75 2,121.75
Distrubution Board including all sockects
BASEMENT FLOOR
Garage
LIGHT FITTINGS
6 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
7 Allow a budget of R 15 410.00 consruction of double door garage motor Sum 1 R 15,410.00 15,410.00
8 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Hobby Room
LIGHT FITTINGS
9 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
10 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
GROUND FLOOR
Covered Porch
LIGHT FITTINGS
Page 27 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
11 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
12 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Entrance Lobby
LIGHT FITTINGS
13 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
14 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Laundry Room
LIGHT FITTINGS
15 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
16 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Foyer
LIGHT FITTINGS
17 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
18 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Passage
LIGHT FITTINGS
19 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
20 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Bathroom
LIGHT FITTINGS
21 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
Page 28 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
SWITCH
22 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Bedroom 1
LIGHT FITTINGS
23 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
24 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Bedroom 2
LIGHT FITTINGS
25 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
26 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
FIRST FLOOR
Covered Porch
LIGHT FITTINGS
27 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
28 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Dining Room
LIGHT FITTINGS
29 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
30 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Kitchen
LIGHT FITTINGS
31 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
Page 29 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
32 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Foyer
LIGHT FITTINGS
33 Allow a Prime Cost of R 5 000.00 excluding VAT to install light including Sum 1 R 6,359.50 6,359.50
backplate built-in wall
SWITCH
34 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Passage
LIGHT FITTINGS
35 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
36 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Scullery
LIGHT FITTINGS
37 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
38 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 744.63 744.63
backplate built-in wall
Dresser
LIGHT FITTINGS
39 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
40 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
E-suite Bathroom
LIGHT FITTINGS
41 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
42 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Page 30 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
Main Bedroom
LIGHT FITTINGS
43 Allow a Prime Cost of R 1 500.00 excluding VAT to install light including Sum 1 R 2,133.25 2,133.25
backplate built-in wall
SWITCH
44 Allow a Prime Cost of R 350.00 for for supply and install switch including Sum 1 R 733.13 733.13
backplate built-in wall
Page 31 of 32
Item DESCRIPTION UNIT QTY RATE AMOUNT
SECTION 3
ELEMENT 17
ENTIRE BUILDING
ELECTRICAL WORKS
1 Allow a budget of R 149 600.00 for construction of internal electrical works Sum 1 149,600.00 149,600.00
specialist contractor (motor and electrical works elsewhere measured)
2 Allow a budget of R 45 375.00 for construction of external electrical works Sum 1 45,375.00 45,375.00
specialist contractor (motor and electrical works elsewhere measured)
PLUMBING WORKS
4 Allow a budget of R 149 600.00 for construction of internal supply and waste Sum 1 149,600.00 149,600.00
drainage works (sanitaryware fitting elsewhere measured)
5 Allow a budget of R 45 375.00 for construction of external supply and waste Sum 1 45,375.00 45,375.00
drainage works (valves and fitting elsewhere measured)
6 Allow profit and attendance of 10% Sum 10% 194,975.00 19,497.50
BUILT IN CUPBOARD
7 Allow a budget of R 275 000.00 for construction of Built in Cupboards garage Sum 1 275,000.00 275,000.00
door specialist contractor (motor and electrical works elsewhere measured)
BASEMENT FLOOR
Garage
8 Allow a budget of R 65 000.00 for construction of double garage door specialist Sum 1 65,000.00 65,000.00
contractor (motor and electrical works elsewhere measured)
9 Allow profit and attendance of 10% Sum 10% 65,000.00 6,500.00
External Works
10 Allow a budget of R 74 800.00 for landscaping Sum 1 74,800.00 74,800.00
11 Allow a budget of R 181 800.00 for construction of boundry fence Sum 1 181,800.00 181,800.00
12 Allow a budget of R 243 100.00 for construction of leveling and paving Sum 1 243,100.00 243,100.00
Page 32 of 32