Weira-Dosha SSIP Irrigation Project Method Statement
Weira-Dosha SSIP Irrigation Project Method Statement
Butajira WWCE
Contents
1. INTRODUCTION....................................................................................................................1
1.1 PURPOSE.............................................................................................................................1
1.2 SCOPE..................................................................................................................................1
1.3 MAJOR COMPONENTS OF THE PROJECT....................................................................2
1.4 CONSTRUCTION PERIOD................................................................................................2
1.5 Construction plan and Schedules..........................................................................................2
1.6 Construction Material...........................................................................................................2
1.7 Tools & Equipment...............................................................................................................2
1.8 Personnel...............................................................................................................................3
2. Work Methodology for Major Activities.................................................................................3
2.1 General and Preparatory works............................................................................................3
2.1.1 Mobilization......................................................................................................................3
2.1.2 Temporary diversion.........................................................................................................4
2.2 Head Work & Appurtenant Structure...................................................................................4
2.2.1 Site Preparation.................................................................................................................4
2.2.2 Excavation.........................................................................................................................5
2.2.3 Concrete works.................................................................................................................6
3. Safety........................................................................................................................................6
Weira-Dosha Small Scale Irrigation Project
1. INTRODUCTION
1.1 PURPOSE
This Construction Method Statement (CMS) sets out the program and Methodology for the
construction of Weira- Dosha SSIP. It describes a proper work procedure that would be carried
out during construction of headwork & appurtenant Structure as per specification and contract
drawings.
1.2 SCOPE
This Work Method Statement covers the full scope required for the construction of headwork &
appurtenant Structure and covering all key stages in the construction |diversion Weir
2.1.1 Mobilization
To commence the construction activities all required personnel’s, materials, tools and
equipment’s required to set up the camp facilities will be mobilized starting from the site
possession dates. Preliminary activities include the setting up of the contractor’s compounds and
offices for the Contractor and Engineer. After selecting suitable sites for camp facilities in
consultation with stake holders the construction of the camp facilities will commence as per the
standard and specification on the contract documents. Preparatory works for the temporary site
establishments will involve some site clearance work, minor earthworks operations to level the
site, drainage and pavement works for the car park and service installation. Then personnel’s,
materials, tools and equipment’s required for the first phase of construction activities will be
mobilized to the project site as per the approved schedules.
2.2.2.6 All excavated material shall be kept a minimum of 1.0 meter from the edge of
excavation or shall be stockpiled to the area designated by the Engineer.
2.2.2.7 For all excavation activities, adequate safety barriers, sign boards, advance warning
signs would be used.
2.2.2.8 For foundation, as soon as the excavation reaches the required depth/elevation the
surface shall be leveled and shall be compacted to 95 % of maximum dry density or
MDD.
2.2.2.9 Before the compaction starts, it shall make sure that the excavated level is free from
standing water or excessive moisture content.
2.2.2.10 Inspection would be conducted during compaction for checking and approval of
the Engineer.
2.2.2.11 Anti-termite treatment would be conducted prior to start blinding works but make
sure the anti-termite material is approved by the Engineer.
2.2.2.12 Constructing masonry and concrete works
2.2.2.13 Back filling for the first reach of the canal excluding top soil and compacting
accordingly
2.2.2.14 Replace topsoil as soon as all the spoil has been back-filled. Roll out a heavy
geotextile barrier over the soil first to prevent topsoil from mixing with gravel in the
trench. Then replace the topsoil in the trench. This will ensure fertile soil and easy re-
vegetation without having to resort to costly fertilizer
2.2.3 Concrete works
The construction methods for concrete works would be as per the standard procedure and quality
of material and workmanship specified on the contract documents.
3. Safety
3.1 All works shall comply with safety procedure or instruction as set in out in project Safety
Plan and Municipality rules and regulation.
3.2 Basic Personal Protective Equipment ( PPE ) shall be worn by all staff or laborers.
3.3 Trained operator or banks man shall be engaged to control or operate heavy equipment
machine.