Professional Documents
Culture Documents
OR1840 SEB Man Ch09
OR1840 SEB Man Ch09
Contents
Stope Design 127
Drilling 127
Measurement 127
Preparation 129
Priming 130
Charging 131
Initiation 133
126 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Production Stoping Chapter 9
Sub level
drill drive Rings
Downholes
Undercut Orebody
Upholes
c) Plan
Raise
128 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Where blastholes intersect an opening, it is essential
to accurately measure the length at “breakthrough”. a) b)
Several techniques have been developed for doing
this efficiently, including those listed below:
• In short blastholes, it is usually possible to accurately
estimate the length by using a flexible hose with
suitable markings. The hose is attached to a source
of compressed air and the free end pushed into the
blasthole. The sound of the compressed air leaving
the end of the hose will change noticeably when
it passes out of the breakthrough position
(Figure 9.2a).
Figure 9.2 Measuring Breakthrough Blasthole Depth
• In longer blastholes, a short length of flexible pipe (by plastic bag)
or a rolled plastic bag can be pushed or lowered to
the breakthrough position. The blasthole length can
be estimated by pulling the pipe or bag back into
Preparation
contact with the rock, then withdrawing it back After downholes are measured and cleaned out,
through the blasthole (Figure 9.2b). they may need to be sealed to prevent the entry of
drill cuttings, rocks, or cement before charging. This
• In long, large diameter downholes, more accurate
is especially important where mobile equipment is
measurements can often be made by using a short
driven over or near the collars of downholes. In many
rod attached by one of its ends to a strong, flexible
mines, it will be sufficient to place a tapered timber or
tape. The tape is weakly attached to the rod at a
plastic plug in the blasthole collar, to mark its position
second place near its centre, using a short length
and prevent large objects from falling in. However,
of soft wire (Figure 9.3a). The tape is then gently
if downholes will remain uncharged for an extended
pulled up to measure the breakthrough depth,
time and equipment will be driven over them, it may
allowing for the short length of tape laying along
be necessary to seal the collars with special plugs to
the rod (Figures 9.3b and c). The rod is retrieved by
prevent blockages.
jerking the tape to break the soft wire, allowing the
rod to hang vertically in the blasthole. Breakthrough downholes must be blocked off at the
toe, and should be partly backfilled with stemming
Downholes that do not breakthrough will usually
material to confine explosion energy. Several
need to be washed out, to remove drill cuttings and
techniques have been developed for efficiently
sludge. If required, water can be blown out, using
blocking breakthrough holes, including:
compressed air and a flexible hose. When blowing
out blastholes, it is essential to wear eye protection • In small diameter blastholes, an adequate plug may
and stand aside to avoid being struck by drill cuttings be provided by a rolled plastic bag that fits tightly
and muddy water. after being pushed into place by a charging hose.
Blastholes may also be surveyed by in-hole • Small and medium diameter blastholes can be
instruments that accurately plot the position at blocked at the toe by using stiff bottlebrushes,
intervals from the collar. This will identify any collaring tapered plastic cups, or commercial plastic
errors and quantify in-hole deviation, which can be “spider” retainers.
significant in long blastholes.
• Large diameter downholes may also be sealed by • groundwater conditions and effect on explosives;
split wedge blocks that are secured in place near • “Sleep time” between charging and firing;
the toe. The split wedge is lowered into position by • number and location of Boosters required; and
a rope, and then locked into place by dropping a
rock onto it (Figure 9.5). Alternatively the bottom • spacing and orientation of blastholes.
wedge can be lowered into position and then the Packaged emulsion or cast PETN-TNT Boosters
top wedge dropped onto it. (e.g. Pentex™) are generally used for priming stope
Large diameter upholes may require collar plugs to production blastholes. “Multiple-priming” is common
keep some explosives in place. Where the charge is practice in relatively long blastholes, to provide
almost self-supporting, bottlebrushes, tapered plastic insurance against misfires from ground movement,
cups, or plastic “spider” retainers may provide the explosives contamination, charge separation, or
required resistance. If necessary, stronger plugs can be downline damage (refer Chapter 4). “Reverse
secured near the collar by wedging or grouting them priming” is generally recommended, with the base of
in place (Figure 9.6). This technique is relatively slow the detonator pointing towards the blasthole collar.
and costly, and can usually only be justified for special Detonators and explosives should always be kept
applications. separate until they are assembled into Boosters.
The charging area should be cleaned up, and all Boosters should be assembled at the face or collar,
unnecessary tools and equipment removed, before and then immediately placed inside blastholes.
any explosives are brought in. When explosives and Assembled Boosters are a sensitive and powerful
detonators are delivered, they should be stored combination, which must never be lying about as
separately in approved containers until required an unnecessary hazard. Boosters should only be
for charging. assembled as required, and detonators should be
removed from unwanted Boosters.
Where electric detonators are used for stope blasting
Priming relatively close to the surface, all work with explosives
Booster must be long enough to completely enclose should stop if a thunderstorm approaches the area.
the longest detonators being used, and of sufficient Everyone should leave the charging area until the
mass to reliably initiate the main explosives charge. storm has passed, as electrical energy from lightning
The Booster diameter should generally be the largest strikes may be conducted underground and initiate
that will easily fit inside the blasthole; this will ensure electric detonators inside blastholes.
that the maximum amount of energy is available to
quickly accelerate the detonation in the main charge
to its maximum VOD.
(a) (b)
Primer
Air tube
Explosives
Plug
Charging
hose
Figure 9.4 Blocking Figure 9.5 Split Wedge Block Figure 9.6 Collar Plug
130 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Charging ANFO can be safely and efficiently “blow-loaded”
into small and medium diameter blastholes by
Stope production blasts may be charged with a wide compressed air. Enclosed pressure vessels are
range of explosives, depending on specific mine generally used for charging stope production blasts
conditions. Packaged or bulk blasting agents and (refer Chapter ‘5’). Semi-conductive charging hose
detonator-sensitive explosives are now available with should always be used when blow-loading ANFO,
diverse characteristics to meet different requirements. to dissipate electrostatic charges generated by the
Selecting the most suitable type of explosives and stream of moving particles.
charging system for blasting in a particular stope will
The ANFO charger should also be effectively
require analysis of the factors listed below:
“earthed”, to drain away electrostatic charges,
• intact rock properties and geological structure; and the operator should always wear eye protection
• presence and type of ground water (i.e. static when charging.
or flowing); Some guidelines for “blow-loading” ANFO with a
• blasthole diameter, length and orientation; pressure vessel are summarised below:
• “Sleep time” between charging and firing; • Check the condition of the pressure vessel,
and ensure that the inside is clear and free
• rock fragmentation and displacement required;
of obstructions.
• size and frequency of blasts;
• Effectively “earth” the charger by placing it in direct
• explosives, equipment and skills available; contact with a wet surface, or by means of an earth
• overbreak or ground vibration constraints; strap which is attached to a rockbolt or placed in a
• ventilation system effectiveness; pool of water.
• rock temperature and chemical reactivity; and • Set the recommended operating air pressures, and
check that the pressure relief valve is functional.
• relative cost of various alternatives.
• Fill the tank with ANFO and pressurise it.
Blasting agents are generally safer than detonator-
sensitive explosives, although modern detonator- • Gently push the primer to the toe of the hole, and
sensitive emulsions are insensitive to initiation by then retract the hose 100 to 300 mm.
impact, flame or friction. Explosives energy output • Stand to one side of the blasthole collar, and then
and cost usually increase with density, and packaged turn on the ANFO supply and steadily retract the
explosives always cost more per tonne than bulk charging hose.
products. Bulk delivery systems can increase charging • As the end of the hose approaches the design
rates and productivity, but usually require a significant blasthole collar, turn off the ANFO supply.
investment in equipment and facilities at the mine.
• When all blastholes are charged, empty the
Bulk delivery systems have been widely used at
remaining ANFO from the tank into a suitable
surface mines for many years, and are growing in
bag, then thoroughly clean out the tank with
popularity in underground operations particularly with
compressed air.
the availability of customer-operated systems.
In wet conditions, packaged emulsions are used in
In stope blasting, results are often determined more
small or medium diameter blastholes. Bulk emulsion
by rock properties than explosives characteristics.
explosive delivery systems may be used for charging
Where conditions are consistently dry, ANFO and
stope blasts if facilities and equipment are available
Impact® can be used to produce reliable results in
at the mine. Emulsion explosives have excellent water
a wide range of rock types. These products can
resistance, and bulk charging produces a relatively
be handled and stored in bulk, then poured into
high-energy output per metre of blasthole. The
downholes or blow-loaded into horizontal blastholes
latter can enable blasthole burden and spacing to be
or upholes.
increased, thus reducing overall costs; alternatively,
ANFO and the Impact® SF Series are not suitable for the increased energy can be used in smaller patterns,
use where blastholes are wet, or if they may become to produce finer fragmentation and thus improve
wet between charging and firing. A small amount of loading rates. Bulk emulsions can be charged in
water can dissolve or desensitise a large amount of a range of densities to suit the prevailing ground
ANFO, causing misfires or poor blast performance. conditions and desired result.
Thus large stope blasts are often charged with water-
Packaged explosives should easily fit inside blastholes,
resistant explosives to avoid poor results caused by
with adequate clearance available for minor
gradual water seepage or unexpected inflows.
obstructions and detonator tails. In short blastholes,
a) b) c) d)
Misfires
Gap
132 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
may be completely charged with water-resistant
explosives, to ensure that groundwater will not
Initiation
cause problems. The result of stope production blasts depends on
complex interactions between adjacent blastholes.
If packaged explosives are dropped into blastholes
Blasthole charges must be detonated in a controlled
that contain some water, the package may deform
sequence, with suitable intervals between successive
and spread out when it hits the water (Figure 9.7c).
detonations. Initiation sequence and delay timing
This may cause the package to sink very slowly, or
affect the resulting fragmentation, throw, ground
jam in the blasthole and leave an uncharged section.
vibrations, overbreak and damage to the
To avoid this problem, the package diameter should
surrounding rock.
be chosen to leave adequate clearance inside the
blasthole, a relatively stiff product should be used The best initiation sequence and delay timing for any
if available, and packages should not be slit before blast will depend on many factors, including those
dropping into water. listed below:
During charging it is essential to ensure that • rock properties, including strength, structure,
explosives do not become jammed, fall out of density,
breakthrough holes, or enter cavities. Thus it is • blast geometry, including burden, spacing and
important to regularly measure the position of the free faces,
top of the charge, and compare it to plan. Any
inconsistencies should be immediately investigated, • blasthole diameter and uncharged collar lengths,
to avoid gaps in the explosives column, wasting • explosives characteristics and degree of coupling,
explosives, or overcharging.
• Boosters and initiation system used,
If rock or drill cuttings fall into a blasthole during
• ground vibration restrictions, and
charging, a gap or barrier may be created in the
explosives column. To avoid misfires from this cause, it • rock fragmentation and throw required.
is essential to clear loose material away from blasthole There will always be several different ways to
collars before charging, and take care when handling successfully fire a stope blast, but generally a delay
charging hoses. interval of a few milliseconds per metre of spacing
An uncharged collar is usually left on each blasthole should be used between adjacent blastholes in a
in a stope firing. The uncharged length should ring. This enables each charge to detonate whilst the
generally be at least 18 blasthole diameters, and surrounding rock is pre-stressed but not disrupted
is often made equal to the burden at the collar. by the effects of charges that have already fired.
This avoids unnecessary overcharging near the Adjacent blastholes thus interact positively, and
collar where the rock will be already be damaged explosives energy is applied to rock more effectively.
by blasting. An uncharged collar will also reduce The best delay interval between adjacent charges in
backbreak, which may damage or cut off blasthole a production blast is usually slightly less than 5 ms/m
collars in the next ring of blastholes. The “cratering” of blasthole spacing. Instantaneous and very short
effect at the end of the blasthole charge will usually delay blasts tend to produce more forward throw, but
break the rock in this area, unless the uncharged fragmentation may be coarser and ground vibrations
collar is longer than the burden. higher; longer delays make each blasthole work more
Inert stemming material can be placed into blasthole independently, and may cause adjacent charges to be
collars, to confine explosion gases and improve dislocated by ground movement during the blast.
blasting efficiency. Crushed rock stemming is In a multi-ring blast, it is necessary to progressively
often used to stem large diameter downholes, but develop a sequence of free faces during the blast.
stemming is rarely used in other stope blastholes This ensures that blastholes in successive rows or
because it is difficult to place and keep in position. rings have an effective free face to break towards.
Moist clay plugs can be tamped into small and For stope production blasts fired to free face, 8 to 15
medium diameter uphole and horizontal holes. The ms/m of blasthole burden is usually appropriate. Long
best material for stemming downholes is screened delays between rings will usually increase forward
rock aggregated in the 6 mm to 12 mm size range; throw, minimise overbreak and reduce ground
explosion gases cause this material to jam against the vibrations. Short delays tend to produce the opposite
blasthole walls, producing more confinement than effects, because blastholes do not have an effective
fine sand or drill cuttings. free face when they detonate.
When charging or stemming blastholes, care should In stope blasting, it is essential to use in-hole delays
be taken to avoid damaging detonator downlines by that ensure no charges detonate before the initiation
impact or abrasion. signal is transmitted to each blasthole. This is required
134 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
blasthole conditions. Poor, wet and jointed ground
usually requires more Boosters than competent, dry
ground to ensure complete column initiation.
Charging
Slot blastholes that are dry can be charged with ANFO
or Impact® mixtures, by blow loading into upholes
and pouring or blow loading into downholes. The
perimeter blastholes may be charged with Impact,
to reduce overbreak and damage to the surrounding
rock. Blastholes in the centre of the slot may also be
charged with Impact, if ANFO charges cause damage
to the walls or dislocation of perimeter charges.
If blastholes are wet, it may be necessary to charge
water-resistant bulk emulsion, or packaged explosives.
Packaged explosives with a relatively small diameter
may be required in perimeter blastholes, to reduce
over break and damage to the slot walls. Charging
will be slower and more expensive than ANFO,
Emulsion or Impact®, especially where upholes are
drilled. Packaged explosives must be tamped to
ensure retention in upholes, which is difficult unless
a pneumatic cartridge charger is available. Tamping
Figure 9.8 Slot Stoping
will produce a high in-hole charging density, which
may cause damage to the surrounding rock. For these
Blastholes drilled close together in slots must be reasons, it is preferable to drill downholes which
carefully marked up, aligned and drilled, to minimise breakthrough into the sublevel below, to maximise
deviation from design. Incorrect alignment or in-hole the use of ANFO, Emulsion and Impact® mixtures.
deviation may cause blastholes to intersect each other Breakthrough blastholes must be blocked off
or deviate outside stope boundaries. This can result and stemmed at the toe, to support and confine
in poor fragmentation, dilution, misfires, or failure to the explosives charge. All downholes should be
break the burden. stemmed at the collar, to improve blasting efficiency
Where possible, slot excavation should be designed and prevent backbreak that may damage collars
to allow blastholes to breakthrough into the sublevel in the next ring. Upholes are rarely stemmed, but
above or below. This enables blasthole positions to an uncharged collar should be left to minimise
be determined at the collar and toe, without the backbreak. An uncharged collar length equal to the
need for in-hole surveys. If blastholes have deviated burden should be adequate in most situations, but in
excessively, they may be redrilled or fired in a weak or fractured rock it may be necessary to increase
sequence that allows for their actual positions. the collar to reduce overbreak.
Priming Initiation
The close spacing of blastholes in slots can result Slot excavation is commenced by firing blastholes
in explosives charges being damaged or cutoff by around the cutoff raise, to form the initial void, and
adjacent blastholes. This can be a major problem then proceeding from the void in a logical sequence.
if the ore is wet and weak or fractured. Therefore, Figure 9.9 illustrates a typical slot excavation and
multiple Boosters should generally be used in each the sequence in which it should be initiated, once
blasthole, to provide insurance against misfires the raise has been opened to full slot width. Note
caused by ground movement or dynamic pressure numbers shown are sequence numbers and not
desensitisation. Blastholes should usually be primed delay numbers.
near the middle, with additional Boosters above and In all firings, the first blasthole to fire should have
below for security. A general rule of thumb is one the widest break out angle available. Thus the
primer per 10m of blasthole length, however more centre blasthole in the front ring should fire first (1),
or less may be used depending on specific ground/
136 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Figure 9.10 Typical delay sequence with Electronic Detonators
138 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
If blastholes are wet, it will be necessary to charge
water-resistant emulsion explosives or alternatively Bench Stoping
use ANFO with hole liners. Packaged explosives can Bench stoping utilises rows of long, parallel
be used for downholes. For upholes, hole liners with downholes to create an open stope in steeply
ANFO are an option or preferably bulk emulsion. dipping orebodies (Figure 9.13). The orebody and
Charging with packages will be slower and more surrounding rock must be competent, or capable
expensive than for ANFO or Impact®, especially of being supported over broad spans. The orebody
where upholes are drilled. Packaged explosive must boundaries should be planar, as the stope outline will
be tamped to ensure retention in upholes, which be defined by long, straight blastholes. Bench stoping
is difficult unless a pneumatic cartridge charger can be used to extract orebodies of varying widths,
is available. Tamping will produce a high in-hole and becomes “Narrow Vein Stoping” in very narrow
charging density, which may cause damage to the orebodies. The maximum practical width is usually
surrounding rock. For these reasons, it is preferable to
determined by the need to sill out the orebody.
drill downholes which breakthrough into the sublevel
below, to maximise the use of ANFO and Impact
mixtures or charge with low-density bulk emulsion.
Design
Breakthrough blastholes must be blocked off
The height of a bench stope will be determined by
and stemmed at the toe, to support and confine
the following factors:
the explosives charge. All downholes should be
stemmed at the collar, to improve blasting efficiency • orebody dip, regularity and width;
and prevent backbreak that may damage collars • rock properties of ore and surrounding rock;
in the next ring. Upholes are rarely stemmed, but
• access development available;
an uncharged collar should be left to minimise
backbreak. An uncharged collar length equal to the • drilling equipment available; and
burden should be adequate in most situations, but in • stope wall support requirements.
weak or fractured rock it may be necessary to increase
Bench stopes are often restricted to approximately
the collar to reduce overbreak.
20 m height, to limit unsupported rock exposures
and ensure that blasthole lengths are not excessive.
Initiation Taller stopes may be developed using longer large
diameter blastholes, if the surrounding rock is
Blast initiation is a crucial area in narrow vein stoping. competent enough.
It is essential that each hole goes off in the planned
sequence without fail. Bench stoping requires a cutoff slot to be extracted
across the orebody over the full stope height, to
If any part of the hole fails to initiate the result is provide a free face for initial blasts. This cutoff slot is
inevitably a bridge which has to be redrilled and
usually developed from a longhole raise, using slot
fired (if indeed possible) causing delays and
excavation techniques.
potentially lost ore.
Where an orebody is mined upwards by a series of
Detonators should be placed inside Boosters, charged
bench stopes, each completed stope is filled before
into blastholes, and hooked up according to the
the next is commenced. Thus the extraction drive
procedures outlined in Chapter ‘2’.
of each stope is completely silled out, and loaders
Because of the confined geometry, relatively slow work on a floor of fill material. To ensure that
timing between holes will provide increased relief and loaders operate efficiently, it is essential to produce a
reduced overbreak damage. consistently loose, well fragmented muckpile. This is
Exel™ Goldet™ detonators with surface delays of 100 especially important where remote-controlled loaders
or 200 ms have successfully been used to provide the are required to extract ore (Figure 9.13a and b).
required timing and reduce projection of the broken
dirt to limit remote bogging requirements.
Alternatively, use of the Exel™ MS range is common
practice, skipping numbers in the series as required to
provide the appropriate delay interval.
Stope
Extraction drive
8 4
Silled drive
6 2
Stope 6 4 2 3 5
5 1
Back-up delays
7 3
5 3 1 2 4
c) Plan
Primary delays
10 7 5 2
9 3
6 4 2 3 5
1
6
Extraction drive
4
8
10 7 5 2 e) Initiation sequence
d) Plan
Figure 9.13 Bench Stoping
140 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Drilling Charging
The drill drive and extraction sublevel in a bench Breakthrough blastholes must be blocked off and
stope are usually silled out across the full width of stemmed at the toe, to support and confine the
the orebody. This enables rows of parallel downholes explosives charge. At the toe of each blasthole, an
to be drilled to breakthrough, which increases the uncharged length approximately equal to the burden
tonnes broken per metre drilled, and allows blastholes should generally be used, to avoid backbreak and
to drain clean for charging. In wide orebodies, the damage to the back of the extraction drive.
burden and spacing may be relatively large, because Blastholes that are dry can be charged with ANFO
blastholes are not tightly constrained by geometry. or Impact®; these products are generally poured into
However, conservative drilling patterns are often downholes, but may be blow-loaded if higher
used, to provide good fragmentation and minimise in-hole densities are required. Perimeter blastholes
overbreak. may be charged with low-density Impact series
Blasthole diameters for bench stoping are usually explosives, to reduce overbreak and damage to the
determined by the need to minimise in-hole deviation, surrounding rock.
and thus depend on the length required. Where the In bench stopes that are undercut, all blastholes
distance between the floor of the drill drive and the should breakthrough. Any blastholes that contain
back of the extraction drive is 10 m to 20 m, 5 7 mm water can be said therefore, either to be drilled short,
to 76 mm diameter blastholes may be used. For taller or to have deviated outside the stope boundary; any
stopes, larger diameter blastholes may be required necessary redrilling should be done before charging
to ensure drilling accuracy. As blasthole toes break begins. If blastholes are wet, it may be necessary
through, it is possible to accurately locate positions to charge water-resistant emulsion explosives. In
and redrill if necessary. perimeter holes, small diameter packages may be
Drilling patterns for bench stopes must be designed required to reduce overbreak and damage to the
to suit specific rock types, sublevel interval, blasthole stope walls.
diameter, deviation, and the fragmentation required. An uncharged collar length equal to the burden
Square drilling patterns are often used for simplicity, should generally be left on each blasthole, to
especially in narrow orebodies (Figure 9.13c). In very minimise backbreak. All blastholes should be
wide orebodies, it may be practical to drill a more stemmed, to improve blasting efficiency and reduce
efficient staggered pattern, with additional “easer” damage to blasthole collars in the next row.
holes adjacent to perimeter blastholes. Where
the surrounding rock is relatively weak, it may be
necessary to drill closely spaced blastholes along the Initiation
walls, and lightly charge them to minimise overbreak
Bench stope blasts are generally restricted to one or
(Figure 9.13d).
two rows, to minimise forward throw and reduce the
amount of remote loading required. It is desirable to
Priming produce a muckpile that rests against the free face,
to maximise the amount of ore that can be loaded
Blastholes in bench stopes should usually be primed from under the brow (Figure 9.13a). This ore is then
near the middle, to ensure maximum confinement extracted to clear the face before the next firing.
and prevent Boosters from being damaged or torn
out by ground movement near the toe and collar. Complete rows of blastholes should be fired together,
In weak or fractured rock, explosives charges can with short delays between blastholes in each row. The
be damaged or cut off by adjacent blastholes. Thus centre blasthole in the front row should fire first, and
multiple Boosters should generally be used in each initiation should progress towards the perimeter holes
blasthole, to provide insurance against misfires caused (Figure 9.13c). The delay between adjacent blastholes
by ground movement. in a row should usually be as short as possible, but
not instantaneous; thus, consecutive Millisecond (MS)
Packaged explosives or Pentex boosters may be used delay numbers are most suitable, with blastholes fired
to initiate explosives charges in bench stopes. Where on separate delays if necessary to reduce ground
ANFO or Impact® are charged, Pentex™ boosters are vibrations. If several rows are fired in a blast, it is
the most efficient. The primer should be large enough usually best to completely initiate each row before
to quickly initiate a stable detonation in the main starting on the next; this will ensure that blastholes
charge, and long enough to completely enclose the in successive rows have an effective free face and
longest detonator being used. acceptable breakout angles when they fire.
142 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
a) Hanging wall b) Foot wall c) Twin drill drive
drill drive drill drive
Ring 2, 4, 6
Ring 1, 3, 5
11 10 9
9
11
7
7
5
4
6
1 4
6
2
3 1
144 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
usually can be charged faster, are less expensive, • avoid placing explosives in soft or cracked rock.
and produce more energy per metre of blasthole The most effective inter-deck stemming material is
than packaged explosives. The increased energy screened rock aggregated in the 6 mm to 12 mm
output may be utilised by drilling larger blasthole size range. Explosion gases cause this material to
patterns, or used in standard patterns to produce jam against the blasthole walls, producing more
finer fragmentation. If bulk water-resistant explosives confinement than sand or drill cuttings.
are not available on site, it will be necessary to use
packaged explosives. These can be quickly and easily The length of inter-deck stemming must be sufficient
charged into downholes, but charging rates for flat to prevent explosives being affected by sympathetic
and upholes will be slow unless a pneumatic cartridge detonation, dynamic pressure desensitisation, or
charger is used (refer to Chapter ‘5’ for more details). physical dislocation when adjacent charges are fired
on different delays. In wet blastholes, the inter-deck
Breakthrough blastholes must be blocked off and stemming length must be increased, because shock
stemmed at the toe, to support and confine the waves may be transmitted through the inert deck.
explosives charge. An uncharged collar should be left
on all blastholes, and stemming placed in downhole The effects of one deck charge or another will
collars. The minimum stemming length required is depend on many variables, including the following:
approximately 18 blasthole diameters, and screened • blasthole diameter;
rock aggregate is the best material to confine • explosives sensitivity and diameter;
explosion gases and increase blasting efficiency.
• presence of water;
• rock type;
Deck Charging • location and type of Boosters;
The explosives charge in each blasthole may be • delay between decks and adjacent charges; and
separated into several isolated “decks” with inert
stemming material placed between adjacent charges • length and type of inert material used.
(Figure 9.15). Deck charging may be used to achieve Because of the large number of variables, it is not
one or more of the objectives summarised below: possible to precisely define the type and length of
• reduce the mass of explosives initiated on an inert deck that will guarantee an optimum
each delay; blasting result. A deck length of approximately
15-20 blasthole diameters is a good starting point.
• reduce the overall amount of explosives used; and/or
146 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Drill drive
Stope Stope
Stemming
Charge
Stope
craters or chambers will result, and humps of to all explosive charges at the same horizon in most
unbroken rock will remain. If blasthole deviation is cases; this may involve small firings of one or two
excessive, the actual depths of burial and location correcting charges to trim up the face before large
of charges may not coincide with designed values, firings proceed.
and reduced rock displacement and remnant humps
of rock may result. The effect of unbroken rock
humps is cumulative and if not recognised and dealt Drilling
with, major problems can occur including the virtual The larger the blasthole diameter, the greater
freezing up of whole portions of the stope. Once the mass of explosives that can be used while
irregularities predominate the free face, it becomes still maintaining an efficient degree of charge
difficult to get explosives charges down to their compactness. The greater the mass of explosives,
designed depth of burial, and frequently blastholes the greater the optimum depth of burial and volume
become blocked or cut off. The solution is to carefully of rock that can be displaced. In practice blastholes
monitor blast progress and deal with irregularities as in the diameter range 150 mm to 165 mm are
soon as they appear. It is desirable to keep the tops most common, however blastholes of diameter
148 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Perimeter Blasting to produce good fragmentation. For large blasts,
the Extended Range of MS Delays 16 to 30 may
In VCR blasting, explosives charges are designed to be used. Exel™ Long Period (LP) detonators are
break outwards and downwards to the free face. rarely used for stripping or stoping, because the
Thus VCR blasting can be expected to produce relatively long delay intervals tend to produce
rougher stope walls than might be achievable using coarser fragmentation. However, LP detonators are
blastholes designed to break inwards to a pre-blasted sometimes used to reduce the throw from a blast,
void. It is seldom appropriate to charge perimeter where this is more important than fragmentation.
holes with lower energy explosives, as high-energy
• A trunkline of detonating cord is used to initiate
explosives are essential for cratering.
the in-hole non-electric detonators (Figure 9.17b).
It is possible that perimeter holes can be allowed to Cordtex™ 5 and Cordtex™ 3.6 detonating cords
lag behind the development of the centre of a stope, reliably initiate Signal Tube, using standard J-Hook
then fired as stripping holes using ANFO or decoupled connections.
charges. In doing this there is always the risk of holes
• For large blasts, non-electric delay detonators
being damaged or cut off, thus some ore would
can also be used outside blastholes, as bridges to
remain on the walls and be lost.
link several detonating cord trunklines together.
This enables many rows of blastholes to be fired
Common Problems in a single blast, using short delays to produce
good fragmentation. The in-hole detonators are
The following problems have a significant influence connected to several separate detonating cord
on the effectiveness of VCR mining: trunklines, which are initiated in sequence by the
• blasthole deviation; bridge detonators (Figure 9.17c).
• inaccurate measurement of hole depth and location • Two instantaneous #8 strength electric detonators
of the free face; are used to initiate the detonating cord trunkline.
• insufficient explosives energy and density; Initiating explosives used in stripping and stope
• insufficient explosives quantities for each blasting should be charged and connected together
individual hole; according to standard procedures that include the
following recommendations.
• inadequate blocking-off of holes;
• Each in-hole detonator is inserted into a packaged
• the free face becomes very irregular; or cast explosives primer that completely encloses
• excessive slice thickness attempted; the detonator shell.
• rocks fall into the collars of blastholes and • Semi-conductive charging hose is used when
block them; blow-loading ANFO over non-electric detonators
• stemming above the charge freezes and prevents inside blastholes. Packaged explosives are carefully
charge placement; and inserted and gently tamped, to avoid damaging the
Signal Tube.
• blastholes shift with ground movement.
• A closed-loop detonating cord trunkline is used,
to provide two paths of initiation to each in-hole
Initiation Procedure for detonator. Several separate cord trunklines
may be used, linked together by non-electric
Stoping Applications detonator bridges.
• Each in-hole detonator is connected by its J-Hook
to the nearest part of the detonating cord trunkline.
Stripping and stoping All connections between cord and Signal Tube are
made at right angles, with the Tube pulled taut
Stripping and stope blasts are now usually fired
but not stretched. Connections are made at least
by an initiation system that includes the products
200 mm away from detonating cord knots or
listed below:
branch lines.
• Exel™ detonators, with MS (Millisecond) delays 1 to
• The hookup is thoroughly checked, to ensure
15, are used for all types of stripping and stoping
that all J-Hooks are connected and that no Signal
including benching, uphole stoping and flatback
Tubes cross over or lie close to any detonating cord
(Figure 9.17a). Short delay times are used between
between the J-Hook and the blasthole collar
blastholes, to ensure that they interact effectively
(Figure 9.17c).
8 7 6 7 8
5 3 3 5
4 2 1 2 4
1 2 3 4 5 6 7 8 3 4 5 6 7 8 3 4
75 ms
200 ms 225 ms
Det cord
150 ms
6
Det cord #2
6
Starter det Bridge det
150 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
downlines are generally used because they do not • Each Signal Tube downline is secured by its J-Hook
disrupt explosives charges or stemming material, to the nearest part of the detonating cord network.
and are available with a larger range of delays. All connections are made at right angles, at least
• A Trunkline of detonating cord is used to initiate 200 mm from detonating cord knots, with the tube
the in-hole non-electric detonators, Cordtex™ 5, pulled taut but not stretched.
and Cordtex™ 3.6 detonating cords reliably initiate • The hookup is thoroughly checked to ensure that
Signal Tube, using standard J-Hook connections. all J-Hooks are connected and that no Signal Tubes
For large blasts, the overwrapped cords are cross over or lie close to any detonating cord
often preferred because their superior knot-tying between the J-Hook and the blasthole collar.
characteristics are an advantage when making
• Two detonating cord lead-in lines are used to
multiple branch line connections.
initiate the trunkline network in each drill drive. The
• Non-electric detonators can also be used outside lead-in lines are long enough to locate the starter
blastholes, as additional collar (piggyback) delays detonators at least 2 m away from any Signal Tube.
to control sequencing. This enables blasthole firing
• Two instantaneous #8 strength electric detonators
times to be split between nominal detonator firing
are attached to the lead-in lines, just before clearing
times, to control ground vibrations and maintain
the area for firing. These two starters are securely
closely spaced inter-hole delays for optimal
fragmentation. Non-electric Exel™ Connectadet™ taped to the lead-in lines, approximately 150 mm
detonators are often used as collar delays, to from the cut ends. Both detonators point towards
sequentially initiate downlines in large blasts. The the blast, and are covered to protect all Signal Tubes
use of collar delays is discussed in Chapter ‘2’. from shrapnel.
• At least two instantaneous #8 strength electric • For procedures used in firing electronic blasting
detonators are used to initiate the detonating cord systems, refer to Chapter 3.
trunkline in each drill drive. Where collar delays are used, the following additional
• The i-kon electronic blasting system is being
™ recommendations apply:
routinely used for the firing of production blasts in • In-hole and collar delays are selected to ensure
many mines in Australia. that all collar detonators have fired before any
Initiating explosives used in longhole stoping should in-hole detonators fire, to prevent the surface
be charged and connected together according to initiation system being disrupted by airblast,
standard procedures which include the following flyrock or rockfalls.
recommendations: • Each downline or group of downlines is initiated
• Each in-hole detonator is secured inside a packaged either directly by the detonating cord trunkline,
or cast explosives primer that completely encloses or by two Exel™ Connectadet™s that are located
the detonator shell. outside the blasthole collar.
• Semi-conductive charging hose is used when blow- • Pairs of Exel™ Connectadet™ detonators are
loading ANFO over non-electric detonators inside attached to downlines with the plastic block
blastholes (refer Chapter ‘5’). ensuring that outgoing downlines do not loop
• Large diameter packaged explosives should be around in front of or over the block.
lowered on top of Boosters in downholes, rather • Each Exel™ Connectadet™ is secured by its J-Hook to
than dropped from the blasthole collar. the nearest part of the detonating cord network. All
• Downlines are held taut during charging and connections made at right angles, at least 200 mm
stemming, to prevent damage and minimise from detonating cord knots, with the Signal Tube
abrasion. pulled taut but not stretched.
• A closed-loop detonating cord trunkline is used, • Downlines that have collar delays are not connected
to provide two paths of initiation to each in-hole directly to the trunkline, as this would by-pass the
or collar detonator. Where a single ring or row of piggybacked Connectadet delay time.
blastholes is to be fired, one loop of detonating • Downlines without collar delays are secured by their
cord is laid out across or around the drill drive J-Hooks to the nearest part of the detonating cord
(Figure 9.18a). For initiating several strings or rows network. All connections are made at right angles,
of blastholes, a network of cord is laid out with at least 200 mm from detonating cord knots, with
trunklines along each side of the drill drive, and the Signal Tube pulled taut but not stretched.
branch lines across the drive (Figure 9.18b). The
cord network is secured in position by attaching it • The hookup is thoroughly checked, to ensure that
to rockbolts, eyebolts or mesh. all necessary J-Hook connections have been made,
Stope
Det cord
a) Single ring of upholes
152 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Delay
Sequence In-hole Delay Collar Delay Total Delay
Interval
Between
Number No. Time (ms) No. Time (ms) Time
Holes (ms)
1 3 75 – – 75 17
2 3 75 Connectadet ™
17 92 8
3 4 100 – – 100 17
4 3 75 Connectadet ™
42 117 8
5 5 125 – – 125 17
6 4 100 Connectadet ™
42 142 8
7 6 150 – – 150 17
8 6 150 Connectadet™ 17 167 8
9 7 175 – – 175
Note:
This is an extract from a more comprehensive list of combinations. It shows only the first nine sequences of more than 100 possible sequences.
The entire trunkline network is initiated by several trunkline is used to initiate the Exel™ Connectadet™
instantaneous electric detonators on each sublevel. by their J-Hooks (Figure 9.19). The entire trunkline
Where suitable raises or service holes exist, network is initiated by several instantaneous electric
detonating cord may be used to link together detonators on each sublevel. Detonating cord links
the trunklines on each sublevel, for additional may also be used between sublevels, for additional
insurance. insurance.
• MS delay detonators are used inside blastholes, • i-kon™ electronic detonators used inside blastholes
with Exel™ MS delays 1 to 15 plus the Extended connected to a surface network of harness wire.
Range of MS delays 16 to 36. Non-electric Exel™ One or more loggers used to log detonators on
Connectadet™ detonators are used as additional each sublevel. Loggers on each level connected in
collar (Piggyback) delays outside blastholes parallel to a firing line.
to further extend the delay range. The collar • MS delay detonators are used to initiate separate
delays sequentially initiate downlines, enabling decked charges inside each blasthole. In-hole delays
blasthole firing times to be split between nominal are provided by Exel™ detonators with Signal Tube
detonator firing times (Table 9.3). Connectadet™s downlines. Downlines are sequentially initiated by
are connected to downline tails using the Exel™ piggybacked Exel™ Connectadet™ collar delays,
Connectadet™ block, and a detonating cord which are connected to detonating cord trunklines.
154 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Blasthole Charge er Suggested Presplit Trim Blasting Burden (Trim
Diameter Metre of Cartridge Blasthole Spacing Blasting Only)
(mm) Blasthole (kg) Diameter (mm) Spacing (m) (m) (m)
38* 0.15 25 0.4 0.6 0.9
51* 0.2 25 0.5 0.8 1.1
64 0.25 25 0.6 1 1.3
76 0.45 25 0.7 1.1 1.5
89 0.65 25** 0.9 1.3 1.8
102 0.8 29** 1 1.5 2
114 1 32** 1.1 1.7 2.1
152 1.8 45** 1.5 2.2 2.5
* A single strand of Cordtex™ 70P detonating cord (with an extra toe charge) can often be used successfully in these blasthole diameters.
** Continuous column charges of Senatel™.
production blast can then break. Firing of the presplit Disruption of the presplit face can also be minimised
charges will itself create overbreak if the presplit holes by careful design of the initiation sequence and delay
are too close together, or charged too heavily. timing of the production blast. Perimeter blastholes
The spacing between presplit blastholes normally must have adequate free faces to break towards,
increases with the blasthole diameter (Table 9.4). and be delayed to provide adequate relief of burden.
Because rock properties have an over-riding effect
on blasthole spacing and charge mass these figures
should be considered only as recommended starting Trim Blasting
values. The best spacing and charge for a particular Sometimes referred to as slashing, trim blasting
rock should be determined by field trails. involves drilling a row of closely spaced blastholes
Presplit holes are generally charged to within about 8 with a suitable burden: spacing ratio along the final
blasthole diameters of the collar and left unstemmed. excavation limit. All holes are charged with light,
If stemming is deemed necessary it can be achieved well-distributed charges and fired simultaneously,
by pushing down a wad of damp paper, hessian after the final production blast. To avoid loss of
or plastic film to the top of the charge and then blastholes through caving, trim blastholes should be
backfilling with drill cuttings. drilled AFTER firing the adjacent production blast.
A variation on trim blasting involves the charging
If the best possible presplitting action is to of the trim holes at the same time as the last
be obtained, presplit charges must be fired production blast and firing them simultaneously on
simultaneously. This is achieved most successfully the last delay.
by joining up all detonating cord downlines with a
detonating cord trunkline. Where ground vibrations Trim blastholes are charged and fired in the same
are likely to cause problems, millisecond delay firing of way as those for presplitting, so that the detonation
groups of holes may be used. The number of holes in tends to split the rock web between holes giving a
each group is made sufficient to obtain a satisfactory smooth wall with minimum overbreak. For 51 mm
splitting action while not exceeding the maximum to 89 mm diameter blastholes, the charge usually
allowable charge mass per delay. To enable the presplit consists of a string of small diameter packaged
fracture to develop to its fullest extent, the presplit explosives suspended at 0.3 m to 0.6 m intervals
holes should be initiated at least 100 ms before any on a detonating cord downline.
immediately adjacent production blast holes. In trim blasting burdens are always greater than
The presplit face will be damaged or even destroyed spacings. Stemming lengths are typically 0.6 m to
if production blastholes are drilled too close to it. If 1.0 m for 51 mm to 89 mm blastholes.
the distance between the presplit and the adjacent Trim blasting does not usually give the spectacular
production blastholes is too great, however, rock will type of result often produced by presplitting, but it
be left in front of the presplit face. The best distance does give a considerable reduction in overbreak. Trim
between the presplit and the adjacent production blasting tends to give better results than presplitting
blastholes should be determined by trial; it is in weak or highly jointed rocks.
usually 1/3 to 1/2 of the normal burden for
production blastholes.