You are on page 1of 32

Production Stoping Chapter 9

Contents
Stope Design 127
Drilling 127
Measurement 127
Preparation 129
Priming 130
Charging 131
Initiation 133

Slot Excavation 134


Design 134
Drilling 134
Priming 135
Charging 135
Initiation 135

Narrow Vein Stoping 136


Design 137
Drilling 137
Priming 138
Charging 138
Initiation 139

Bench Stoping 139


Design 139
Drilling 141
Priming 141
Charging 141
Initiation 141

Chapter 9 Production Stoping 125


Longhole Open Stoping 142
Design 142
Drilling 142
Priming 144
Charging 144
Deck Charging 145
Initiation 146

VCR Stoping 146


Design 146
Drilling 147
Priming 148
Charging 148
Initiation 148
Perimeter Blasting 149
Common Problems 149

Initiation Procedure for Stoping Applications 149


Stripping and stoping 149
Longhole Stoping 150
Mass Blasting 152

Overbreak Control 154


Production Blasts 154
Line Drilling 154
Presplitting 154
Trim Blasting 155

126 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Production Stoping Chapter 9

Many diverse drilling and blasting techniques


are used for production stope blasting to
Drilling
suit various underground mining methods, Selection of blasthole diameter, orientation and
including those listed below: length should be based on analysis of many
interrelated factors, including those listed below:
• Bench stoping, using vertical downholes.
• Mining method, stope geometry and extraction
• Block caving, using blastholes to undercut the ore. sequence.
• Cut & fill stoping, using upholes. • Intact rock properties and geological structure.
• Open stoping, using rings of inclined blastholes. • Location of access development for drilling
• Slot stoping, using upholes and downholes. and charging.
• Sublevel caving, using upholes. • Fragmentation required for loading and
• VCR (Vertical Crater Retreat) stoping, using large transport system.
diameter downholes. • Drilling equipment and skills available.
This chapter includes information to assist with • Explosives, charging equipment and skills available.
designing, drilling, priming, charging, and initiating • Cost of various alternatives and combinations.
longhole stope blasts. Drilling and blasting techniques
for benching, ring blasting, Narrow Vein Stoping, and In small stopes where short blastholes are drilled,
VCR stoping are discussed, as these can be adapted the cost of each hole is relatively small. However,
to suit other less common longhole stoping methods. long large diameter blastholes in open stopes are
The cost-effective use of emulsions and non-electric a significant investment of time and money. In any
detonators is emphasised. situation, the position of each blasthole can have a
large effect on overall mining efficiency and costs.
Many unusual words and expressions have evolved This highlights the need for careful design, markup,
to describe specific aspects of longhole stope drilling alignment, collaring, drilling and flushing of each
and blasting; some of the terms commonly used blasthole. After drilling, blasthole collars should be
in underground metal mines are summarised in marked to ensure that they can be easily relocated
Figure 9.1. for charging. Blasthole collars may also need to be
protected or sealed, to prevent the entry of drill
cuttings, rocks or cement grout.
Stope Design
Stopes are designed to suit specific mining conditions,
including local geology, mine geometry, mining Measurement
sequence, production rates, and the skills, equipment All blastholes should be measured after drilling, to
and services available. Stope designs are usually check their condition, length, and the presence of
influenced by drilling and blasting technology, any water or obstructions. This information should be
including equipment, products, techniques and recorded on the drilling plan, with relevant comments
skills. It is essential to ensure that stope design and about geology, penetration rates, broken ground
extraction plans are based on proven drilling and or breakthroughs encountered. If any obstructions
blasting capabilities. This requires people with drilling are encountered inside blastholes, they should be
and blasting experience to be involved with all stages removed by a charging hose, tamping stick or suitable
of planning, design and scheduling. Technology may tool, before charging commences. If any blastholes
change during the planning and development of large are blocked or drilled short, it may be necessary
stopes, but it is unwise to design stopes based on to redrill them. This emphasises the need to check
equipment, products or techniques which are not yet blastholes immediately after drilling, before the
available or proven. drilling equipment is moved out.

Chapter 9 Production Stoping 127


a) Section b) Cross-section

Sub level
drill drive Rings

Drill drive Silled drive

Downholes

Undercut Orebody
Upholes

Extraction drive Undercut drive

c) Plan

Raise

Figure 9.1 Longhole Stope Section

128 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Where blastholes intersect an opening, it is essential
to accurately measure the length at “breakthrough”. a) b)
Several techniques have been developed for doing
this efficiently, including those listed below:
• In short blastholes, it is usually possible to accurately
estimate the length by using a flexible hose with
suitable markings. The hose is attached to a source
of compressed air and the free end pushed into the
blasthole. The sound of the compressed air leaving
the end of the hose will change noticeably when
it passes out of the breakthrough position
(Figure 9.2a).
Figure 9.2 Measuring Breakthrough Blasthole Depth
• In longer blastholes, a short length of flexible pipe (by plastic bag)
or a rolled plastic bag can be pushed or lowered to
the breakthrough position. The blasthole length can
be estimated by pulling the pipe or bag back into
Preparation
contact with the rock, then withdrawing it back After downholes are measured and cleaned out,
through the blasthole (Figure 9.2b). they may need to be sealed to prevent the entry of
drill cuttings, rocks, or cement before charging. This
• In long, large diameter downholes, more accurate
is especially important where mobile equipment is
measurements can often be made by using a short
driven over or near the collars of downholes. In many
rod attached by one of its ends to a strong, flexible
mines, it will be sufficient to place a tapered timber or
tape. The tape is weakly attached to the rod at a
plastic plug in the blasthole collar, to mark its position
second place near its centre, using a short length
and prevent large objects from falling in. However,
of soft wire (Figure 9.3a). The tape is then gently
if downholes will remain uncharged for an extended
pulled up to measure the breakthrough depth,
time and equipment will be driven over them, it may
allowing for the short length of tape laying along
be necessary to seal the collars with special plugs to
the rod (Figures 9.3b and c). The rod is retrieved by
prevent blockages.
jerking the tape to break the soft wire, allowing the
rod to hang vertically in the blasthole. Breakthrough downholes must be blocked off at the
toe, and should be partly backfilled with stemming
Downholes that do not breakthrough will usually
material to confine explosion energy. Several
need to be washed out, to remove drill cuttings and
techniques have been developed for efficiently
sludge. If required, water can be blown out, using
blocking breakthrough holes, including:
compressed air and a flexible hose. When blowing
out blastholes, it is essential to wear eye protection • In small diameter blastholes, an adequate plug may
and stand aside to avoid being struck by drill cuttings be provided by a rolled plastic bag that fits tightly
and muddy water. after being pushed into place by a charging hose.
Blastholes may also be surveyed by in-hole • Small and medium diameter blastholes can be
instruments that accurately plot the position at blocked at the toe by using stiff bottlebrushes,
intervals from the collar. This will identify any collaring tapered plastic cups, or commercial plastic
errors and quantify in-hole deviation, which can be “spider” retainers.
significant in long blastholes.

(a) (b) (c) (d)


Figure 9.3 Measuring Breakthrough Blasthole Depth (by rod)

Chapter 9 Production Stoping 129


• Large diameter downholes may be sealed by The choice of primer will generally depend on the
suspending a wooden block on stiff rope, which is factors summarised below:
secured at the collar (Figure 9.4). In long blastholes, • sensitivity of main explosives charge;
the rope may stretch and allow the block to drop,
unless the rope is very stiff. • blasthole diameter and length;

• Large diameter downholes may also be sealed by • groundwater conditions and effect on explosives;
split wedge blocks that are secured in place near • “Sleep time” between charging and firing;
the toe. The split wedge is lowered into position by • number and location of Boosters required; and
a rope, and then locked into place by dropping a
rock onto it (Figure 9.5). Alternatively the bottom • spacing and orientation of blastholes.
wedge can be lowered into position and then the Packaged emulsion or cast PETN-TNT Boosters
top wedge dropped onto it. (e.g. Pentex™) are generally used for priming stope
Large diameter upholes may require collar plugs to production blastholes. “Multiple-priming” is common
keep some explosives in place. Where the charge is practice in relatively long blastholes, to provide
almost self-supporting, bottlebrushes, tapered plastic insurance against misfires from ground movement,
cups, or plastic “spider” retainers may provide the explosives contamination, charge separation, or
required resistance. If necessary, stronger plugs can be downline damage (refer Chapter 4). “Reverse
secured near the collar by wedging or grouting them priming” is generally recommended, with the base of
in place (Figure 9.6). This technique is relatively slow the detonator pointing towards the blasthole collar.
and costly, and can usually only be justified for special Detonators and explosives should always be kept
applications. separate until they are assembled into Boosters.
The charging area should be cleaned up, and all Boosters should be assembled at the face or collar,
unnecessary tools and equipment removed, before and then immediately placed inside blastholes.
any explosives are brought in. When explosives and Assembled Boosters are a sensitive and powerful
detonators are delivered, they should be stored combination, which must never be lying about as
separately in approved containers until required an unnecessary hazard. Boosters should only be
for charging. assembled as required, and detonators should be
removed from unwanted Boosters.
Where electric detonators are used for stope blasting
Priming relatively close to the surface, all work with explosives
Booster must be long enough to completely enclose should stop if a thunderstorm approaches the area.
the longest detonators being used, and of sufficient Everyone should leave the charging area until the
mass to reliably initiate the main explosives charge. storm has passed, as electrical energy from lightning
The Booster diameter should generally be the largest strikes may be conducted underground and initiate
that will easily fit inside the blasthole; this will ensure electric detonators inside blastholes.
that the maximum amount of energy is available to
quickly accelerate the detonation in the main charge
to its maximum VOD.

(a) (b)

Primer
Air tube

Explosives

Plug
Charging
hose

Figure 9.4 Blocking Figure 9.5 Split Wedge Block Figure 9.6 Collar Plug

130 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Charging ANFO can be safely and efficiently “blow-loaded”
into small and medium diameter blastholes by
Stope production blasts may be charged with a wide compressed air. Enclosed pressure vessels are
range of explosives, depending on specific mine generally used for charging stope production blasts
conditions. Packaged or bulk blasting agents and (refer Chapter ‘5’). Semi-conductive charging hose
detonator-sensitive explosives are now available with should always be used when blow-loading ANFO,
diverse characteristics to meet different requirements. to dissipate electrostatic charges generated by the
Selecting the most suitable type of explosives and stream of moving particles.
charging system for blasting in a particular stope will
The ANFO charger should also be effectively
require analysis of the factors listed below:
“earthed”, to drain away electrostatic charges,
• intact rock properties and geological structure; and the operator should always wear eye protection
• presence and type of ground water (i.e. static when charging.
or flowing); Some guidelines for “blow-loading” ANFO with a
• blasthole diameter, length and orientation; pressure vessel are summarised below:
• “Sleep time” between charging and firing; • Check the condition of the pressure vessel,
and ensure that the inside is clear and free
• rock fragmentation and displacement required;
of obstructions.
• size and frequency of blasts;
• Effectively “earth” the charger by placing it in direct
• explosives, equipment and skills available; contact with a wet surface, or by means of an earth
• overbreak or ground vibration constraints; strap which is attached to a rockbolt or placed in a
• ventilation system effectiveness; pool of water.

• rock temperature and chemical reactivity; and • Set the recommended operating air pressures, and
check that the pressure relief valve is functional.
• relative cost of various alternatives.
• Fill the tank with ANFO and pressurise it.
Blasting agents are generally safer than detonator-
sensitive explosives, although modern detonator- • Gently push the primer to the toe of the hole, and
sensitive emulsions are insensitive to initiation by then retract the hose 100 to 300 mm.
impact, flame or friction. Explosives energy output • Stand to one side of the blasthole collar, and then
and cost usually increase with density, and packaged turn on the ANFO supply and steadily retract the
explosives always cost more per tonne than bulk charging hose.
products. Bulk delivery systems can increase charging • As the end of the hose approaches the design
rates and productivity, but usually require a significant blasthole collar, turn off the ANFO supply.
investment in equipment and facilities at the mine.
• When all blastholes are charged, empty the
Bulk delivery systems have been widely used at
remaining ANFO from the tank into a suitable
surface mines for many years, and are growing in
bag, then thoroughly clean out the tank with
popularity in underground operations particularly with
compressed air.
the availability of customer-operated systems.
In wet conditions, packaged emulsions are used in
In stope blasting, results are often determined more
small or medium diameter blastholes. Bulk emulsion
by rock properties than explosives characteristics.
explosive delivery systems may be used for charging
Where conditions are consistently dry, ANFO and
stope blasts if facilities and equipment are available
Impact® can be used to produce reliable results in
at the mine. Emulsion explosives have excellent water
a wide range of rock types. These products can
resistance, and bulk charging produces a relatively
be handled and stored in bulk, then poured into
high-energy output per metre of blasthole. The
downholes or blow-loaded into horizontal blastholes
latter can enable blasthole burden and spacing to be
or upholes.
increased, thus reducing overall costs; alternatively,
ANFO and the Impact® SF Series are not suitable for the increased energy can be used in smaller patterns,
use where blastholes are wet, or if they may become to produce finer fragmentation and thus improve
wet between charging and firing. A small amount of loading rates. Bulk emulsions can be charged in
water can dissolve or desensitise a large amount of a range of densities to suit the prevailing ground
ANFO, causing misfires or poor blast performance. conditions and desired result.
Thus large stope blasts are often charged with water-
Packaged explosives should easily fit inside blastholes,
resistant explosives to avoid poor results caused by
with adequate clearance available for minor
gradual water seepage or unexpected inflows.
obstructions and detonator tails. In short blastholes,

Chapter 9 Production Stoping 131


packages should be charged using a suitable tamping Rough blastholes usually require more clearance
stick which is long enough to reach the bottom of around packages, and it may be necessary to
each blasthole, has square ends, and is approximately charge each package individually to avoid jamming.
the same diameter as the packaged explosives. In Packaged explosives should never be forced past
long blastholes, packages may be dropped into obstructions. If blastholes are very rough or partly
position, pushed into place by a flexible hose, or blocked, it may be necessary to use smaller diameter
effectively charged to a higher in-hole density by a packages to enable safe charging.
cartridge charger (refer Chapter ‘5’). If a package becomes jammed inside a blasthole, an
The primer should be carefully placed by lowering or attempt should be made to gently move it by using
gently pushing with the tamping stick or charging the charging hose to push it into or blow it out of
hose, but never tamped. Other packaged explosives the hole. (However, if a primer becomes stuck inside
can then be charged individually, or several at a a blasthole, no attempt should be made to move
time. These packages may be tamped into place, to it by force.) If a jammed package cannot be easily
increase charging density and reduce the probability removed, the blasthole should be re-primed and the
of ejection by charges that fire on earlier delays. open portion charged to the design collar. It may be
Effective tamping is achieved by gently but firmly possible to compensate for the uncharged portion by
pressing the end of the charge. Packaged explosives increasing the charges in surrounding blast holes.
should never be tamped roughly, as this rarely Where blastholes contain a small amount of water
increases the charging density and may cause damage from drilling, it can either be blown out with
to detonator tails. The plastic packaging around compressed air, or pumped from large diameter
emulsion explosives will burst as the contents are downholes. This will usually leave a small amount of
squeezed to fill almost the entire blasthole. residual water at the toe, which can desensitise an
Where maximum explosives energy is required, it is ANFO charge. If there is no seepage of water into the
recommended that packages are inserted and tamped blasthole, packaged explosives may be used to “step
individually. When several packages are inserted up” above the water level (Figure 9.7a and b). ANFO
before tamping, only the last portion of the charge is or Impact can then be charged into the top portion
deformed to fill the hole, and the energy per metre of of the blasthole. This technique can produce reliable
charge will be less than the maximum possible. results when blastholes are fired soon after charging,
and conditions are very dry. Alternatively, blastholes

a) b) c) d)

Misfires

Gap

Figure 9.7 Charging Packaged Explosives

132 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
may be completely charged with water-resistant
explosives, to ensure that groundwater will not
Initiation
cause problems. The result of stope production blasts depends on
complex interactions between adjacent blastholes.
If packaged explosives are dropped into blastholes
Blasthole charges must be detonated in a controlled
that contain some water, the package may deform
sequence, with suitable intervals between successive
and spread out when it hits the water (Figure 9.7c).
detonations. Initiation sequence and delay timing
This may cause the package to sink very slowly, or
affect the resulting fragmentation, throw, ground
jam in the blasthole and leave an uncharged section.
vibrations, overbreak and damage to the
To avoid this problem, the package diameter should
surrounding rock.
be chosen to leave adequate clearance inside the
blasthole, a relatively stiff product should be used The best initiation sequence and delay timing for any
if available, and packages should not be slit before blast will depend on many factors, including those
dropping into water. listed below:
During charging it is essential to ensure that • rock properties, including strength, structure,
explosives do not become jammed, fall out of density,
breakthrough holes, or enter cavities. Thus it is • blast geometry, including burden, spacing and
important to regularly measure the position of the free faces,
top of the charge, and compare it to plan. Any
inconsistencies should be immediately investigated, • blasthole diameter and uncharged collar lengths,
to avoid gaps in the explosives column, wasting • explosives characteristics and degree of coupling,
explosives, or overcharging.
• Boosters and initiation system used,
If rock or drill cuttings fall into a blasthole during
• ground vibration restrictions, and
charging, a gap or barrier may be created in the
explosives column. To avoid misfires from this cause, it • rock fragmentation and throw required.
is essential to clear loose material away from blasthole There will always be several different ways to
collars before charging, and take care when handling successfully fire a stope blast, but generally a delay
charging hoses. interval of a few milliseconds per metre of spacing
An uncharged collar is usually left on each blasthole should be used between adjacent blastholes in a
in a stope firing. The uncharged length should ring. This enables each charge to detonate whilst the
generally be at least 18 blasthole diameters, and surrounding rock is pre-stressed but not disrupted
is often made equal to the burden at the collar. by the effects of charges that have already fired.
This avoids unnecessary overcharging near the Adjacent blastholes thus interact positively, and
collar where the rock will be already be damaged explosives energy is applied to rock more effectively.
by blasting. An uncharged collar will also reduce The best delay interval between adjacent charges in
backbreak, which may damage or cut off blasthole a production blast is usually slightly less than 5 ms/m
collars in the next ring of blastholes. The “cratering” of blasthole spacing. Instantaneous and very short
effect at the end of the blasthole charge will usually delay blasts tend to produce more forward throw, but
break the rock in this area, unless the uncharged fragmentation may be coarser and ground vibrations
collar is longer than the burden. higher; longer delays make each blasthole work more
Inert stemming material can be placed into blasthole independently, and may cause adjacent charges to be
collars, to confine explosion gases and improve dislocated by ground movement during the blast.
blasting efficiency. Crushed rock stemming is In a multi-ring blast, it is necessary to progressively
often used to stem large diameter downholes, but develop a sequence of free faces during the blast.
stemming is rarely used in other stope blastholes This ensures that blastholes in successive rows or
because it is difficult to place and keep in position. rings have an effective free face to break towards.
Moist clay plugs can be tamped into small and For stope production blasts fired to free face, 8 to 15
medium diameter uphole and horizontal holes. The ms/m of blasthole burden is usually appropriate. Long
best material for stemming downholes is screened delays between rings will usually increase forward
rock aggregated in the 6 mm to 12 mm size range; throw, minimise overbreak and reduce ground
explosion gases cause this material to jam against the vibrations. Short delays tend to produce the opposite
blasthole walls, producing more confinement than effects, because blastholes do not have an effective
fine sand or drill cuttings. free face when they detonate.
When charging or stemming blastholes, care should In stope blasting, it is essential to use in-hole delays
be taken to avoid damaging detonator downlines by that ensure no charges detonate before the initiation
impact or abrasion. signal is transmitted to each blasthole. This is required

Chapter 9 Production Stoping 133


to prevent flyrock, airblast and rock movement from Slot excavation requires a raise to be developed
damaging downlines or parts of the initiation system between sublevels, to provide a free face for initial
outside blasthole collars. An exception to the general blasts to “open up” the slot. This “cutoff raise” may
rule is the use of a sequential “bridge” initiation be developed by conventional hand-held techniques,
system, where blastholes detonate before the entire longhole drilling and blasting, or raiseboring. A
initiation system has fired. conventional raise can be used to follow irregular
Stope production blasts are usually fired using orebodies, but it must be straight enough to enable
Millisecond (MS) delay detonators, which allow effective longhole drilling around it. Longhole raising
sufficient time for progressive relief of burden during can be used where the orebody is relatively straight
the blast. Long Period (LP) delays can be used if it between sublevels, but care should be taken during
is essential to minimise forward throw, but the very blasting to avoid damaging the surrounding rock.
long delay intervals can cause blasthole charges to be Raiseboring is only practical for regular, planar
dislocated by ground movement during the blast. For orebodies which extend for sufficient height to justify
large blasts, it may be necessary to use a combination the time and cost of setting up equipment.
of surface and in-hole delays to sequence blastholes. For blasted raises, a minimum size of 2 m x 2 m is
This enables blasthole firing times to be “split” recommended to provide an adequate free face and
between nominal detonator firing times, to control breakout angles for initial blasthole firings. Bored
ground vibrations and maintain short inter-hole delays raises should be as large as possible, as small diameter
for optimal fragmentation. circular openings are very stable and relatively
Detonator lead lengths should be selected to allow difficult to break into. Blastholes around the raise
each primer to be placed in the required location must be drilled close enough to produce realistic
without the need to extend downlines. For large breakout angles, but avoid intersecting the raise
stope blasts, a range of lead lengths may be required when deviation occurs. More information on raising is
to suit varying blasthole depths. presented in Chapter 8.

Slot Excavation Drilling


Slot excavation requires closely spaced blastholes to
Slot excavation is required before the commencement overcome the tight geometry of a narrow free face.
of production blasting in any stoping area. The term Thus overall drilling efficiency is usually low, and
refers to the opening up of a “void” which can then more explosives energy is required per tonne of rock
be used to fire “rings” into. broken, i.e. higher “powder factors” are required.
Blasthole diameter is usually determined by the need
to minimise hole deviation, and thus depends on the
Design sublevel interval. Where sublevels are 10 m to 20 m
The sublevel interval for slot excavation will have apart, 64 mm to 76 mm diameter blastholes may be
been previously determined by mine design factors used. For cutoff slots for open stopes, 89 mm to 115
including the following: mm diameter blastholes are generally used to ensure
• orebody dip, regularity and width; sufficient drilling accuracy between sublevels 30 m to
50 m apart.
• rock properties of ore and surrounding rock;
Drilling patterns for slot excavation must be designed
• access development available; to suit specific rock types, stope geometry, sublevel
• drilling equipment available; and interval, blasthole diameter and deviation. A typical
• stope wall support requirements. Slot design is shown in Figure 9.8. Rings should be at
least 3 blastholes wide to maximise break out angles
Sublevels may need to be developed at relatively
as previously discussed.
small intervals (e.g. 10 m), to define the orebody
position and install rock support. In competent rock In a 3 m wide slot, 64 mm to 76 mm diameter
with regular ore-waste contacts, it may be possible to blastholes can be drilled on a square 1.5 m x 1.5 m
space sublevels further apart; the maximum practical pattern. The burden for larger diameter blastholes is
sublevel interval will often be determined by drilling restricted by geometry, and should not exceed the
equipment capabilities and drilling accuracy. A slot width. In larger slots (5 - 6 m wide), 89 mm or
sublevel interval of up to 40 m may be possible in a 102 mm holes may be drilled on a 2 m x 2 m pattern.
regular orebody, if blastholes can be accurately drilled
over this distance.

134 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
blasthole conditions. Poor, wet and jointed ground
usually requires more Boosters than competent, dry
ground to ensure complete column initiation.

Charging
Slot blastholes that are dry can be charged with ANFO
or Impact® mixtures, by blow loading into upholes
and pouring or blow loading into downholes. The
perimeter blastholes may be charged with Impact,
to reduce overbreak and damage to the surrounding
rock. Blastholes in the centre of the slot may also be
charged with Impact, if ANFO charges cause damage
to the walls or dislocation of perimeter charges.
If blastholes are wet, it may be necessary to charge
water-resistant bulk emulsion, or packaged explosives.
Packaged explosives with a relatively small diameter
may be required in perimeter blastholes, to reduce
over break and damage to the slot walls. Charging
will be slower and more expensive than ANFO,
Emulsion or Impact®, especially where upholes are
drilled. Packaged explosives must be tamped to
ensure retention in upholes, which is difficult unless
a pneumatic cartridge charger is available. Tamping
Figure 9.8 Slot Stoping
will produce a high in-hole charging density, which
may cause damage to the surrounding rock. For these
Blastholes drilled close together in slots must be reasons, it is preferable to drill downholes which
carefully marked up, aligned and drilled, to minimise breakthrough into the sublevel below, to maximise
deviation from design. Incorrect alignment or in-hole the use of ANFO, Emulsion and Impact® mixtures.
deviation may cause blastholes to intersect each other Breakthrough blastholes must be blocked off
or deviate outside stope boundaries. This can result and stemmed at the toe, to support and confine
in poor fragmentation, dilution, misfires, or failure to the explosives charge. All downholes should be
break the burden. stemmed at the collar, to improve blasting efficiency
Where possible, slot excavation should be designed and prevent backbreak that may damage collars
to allow blastholes to breakthrough into the sublevel in the next ring. Upholes are rarely stemmed, but
above or below. This enables blasthole positions to an uncharged collar should be left to minimise
be determined at the collar and toe, without the backbreak. An uncharged collar length equal to the
need for in-hole surveys. If blastholes have deviated burden should be adequate in most situations, but in
excessively, they may be redrilled or fired in a weak or fractured rock it may be necessary to increase
sequence that allows for their actual positions. the collar to reduce overbreak.

Priming Initiation
The close spacing of blastholes in slots can result Slot excavation is commenced by firing blastholes
in explosives charges being damaged or cutoff by around the cutoff raise, to form the initial void, and
adjacent blastholes. This can be a major problem then proceeding from the void in a logical sequence.
if the ore is wet and weak or fractured. Therefore, Figure 9.9 illustrates a typical slot excavation and
multiple Boosters should generally be used in each the sequence in which it should be initiated, once
blasthole, to provide insurance against misfires the raise has been opened to full slot width. Note
caused by ground movement or dynamic pressure numbers shown are sequence numbers and not
desensitisation. Blastholes should usually be primed delay numbers.
near the middle, with additional Boosters above and In all firings, the first blasthole to fire should have
below for security. A general rule of thumb is one the widest break out angle available. Thus the
primer per 10m of blasthole length, however more centre blasthole in the front ring should fire first (1),
or less may be used depending on specific ground/

Chapter 9 Production Stoping 135


followed by the perimeter holes (2 & 3). Perimeter The issue with MS delays is that as firing of each ring
holes in the same ring are usually fired on separate progresses, it becomes more difficult to maintain
delays to minimise ground vibrations and ensure that appropriate delays between holes and rings as per
the broken rock does not become “choked” in the the rules of thumb given above. The more rings that
narrow slot. All blastholes in each ring should be fired are fired at any on time, the higher the likelihood that
before the first hole in the next ring, to ensure an delays will need to be doubled up increasing the risk
effective free face. of cut offs due to the increased time between delays.
General rules for slot initiation: For this reason, slots fired with MS delays should be
generally limited to less than 10 rings.
• 25-100 ms between adjacent holes (depending
on hole length).
• 100-300 ms between rings (depending on width,
or number of rings in slot).
Narrow Vein Stoping
Narrow vein stoping involves the extraction of narrow,
Use of these principles ensures adequate hole steeply dipping orebodies by longhole drilling and
interaction between the 3 holes, and provides enough blasting techniques, or alimak methods. The orebody
relief between rings to allow for confinement. For must have regular boundaries that can be followed
long (or wide) slots relief between rings can be by long blastholes and the surrounding rock must
increased as the firing progresses away from the void, be competent enough to stand unsupported over
to allow for the increased confinement. relatively large spans.
Electronic blasting systems are a very effective Narrow Vein Stoping is most effective in steeply
and flexible tool for slot excavation as they allow dipping tabular orebodies that have well-defined
consistent and accurate sequencing of blastholes ore-waste contacts. Narrow Vein Stoping can be
preventing cutoffs and out of sequence firings. Figure successfully used in orebodies as narrow as 1 m,
9.10 illustrates a typical slot, 3 holes wide with 10 if the orebody contacts are very regular and the
rings. In this case a delay of 25 ms has been chosen surrounding rock is competent. In thinner or irregular
between the holes in a ring and 100 ms between the orebodies, drilling control is more difficult, blasting is
first 5 rings, increasing to 200 ms in subsequent rings. “tighter”, and overbreak can cause excessive dilution.
In most hard rock conditions underground this will
give good results The particular challenges faced with narrow vein
stoping are:
Exel™ Millisecond (MS) delay detonators can also be
effective in slot blasts depending on the size of blast • A low ratio of stope tonnage per metre developed.
being undertaken. The delay sequence must provide • High dilution from stope sidewalls.
adequate time for burden relief but ensure that • The conflicting drilling and blasting requirements of
charges fire before they are disrupted by adjacent minimising damage to sidewalls and breaking the
blastholes. In most slot blasts, consecutive millisecond ore adequately and efficiently.
delays (i.e. #1, #2, #3, etc) can be used in sequence,
because burdens are very small. However, if large • Low efficiencies in bogging relatively small tonnages
diameter blastholes are used in dense, massive rock, it of ore per blast.
may be better to use alternate delays (i.e. #1, #3, #5) • The effects of stress concentration ahead of the
to provide more time for burden movement. Figure stope faces and in abutment areas.
9.11 shows a typical slot initiation sequence using In general the narrower the veins, the more severe
MS delays. these problems become.

Figure 9.9 Typical Firing Sequence for a Slot

136 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Figure 9.10 Typical delay sequence with Electronic Detonators

Design equipment capabilities and drilling accuracy. A


sublevel interval of up to 40 m may be possible in a
Conventional mining methods are still in use in some regular orebody, if blastholes can be accurately drilled
mines. In steeper veins these include hand held over this distance.
jackhammer mining methods for benching, shrinkage
and various cut and fill configurations. Longwall and
room and pillar are preferred methods in shallower Drilling
dipping veins. Maintenance of support of the back
Both development and production drilling equipment
and sidewalls of headings and work areas is a
is available in the “narrow” ranges from all of the
continual challenge.
major drilling equipment suppliers.
Developments in equipment towards straighter
In the narrow vein long hole stoping operations,
drill holes and remote control LHD operation have
dilution is a major concern. Increased drill hole
made narrow vein long hole stoping more viable
diameters give straighter holes, improved blasting
with benefits in reduced production costs and
efficiency and improved fragmentation but also result
increased safety.
in increased powder factors leading to blast damage
The sublevel interval for Narrow Vein Stoping will be and increased dilution.
determined by the following factors:
The main variants in longhole methods are downhole
• Orebody dip, regularity and width; benching, uphole retreat and Alimak Vein Mining. In
• Rock properties of ore and surrounding rock; all methods it is desirable to drill to breakthrough so
that the accuracy of holes can be checked with holes
• Access development available;
abandoned and redrilled as required.
• Drilling equipment available; and
Alimak Vein mining has the advantage of permitting
• Stope wall support requirements. shrinkage drawing of the ore that may be an
Sublevels may need to be developed at relatively advantage where weak hanging wall and footwall are
small intervals (e.g. 10 m), to define the orebody encountered.
position and install rock support. In competent rock Narrow vein stope blasting requires closely spaced
with regular ore-waste contacts, it may be possible to blastholes to overcome the tight geometry of a
space sublevels further apart; the maximum practical narrow free face. Thus overall drilling efficiency is
sublevel interval will often be determined by drilling

Figure 9.11 Showing typical delay sequence with MS detonators

Chapter 9 Production Stoping 137


usually low, and more explosives energy is required
per tonne of rock broken.
Priming
The close spacing of blastholes in narrow vein stopes
Hole diameters are typically limited to the range
can result in explosives charges being damaged or
57mm to 76mm depending on stope width, to
cut off by adjacent blastholes. This can be a major
control damage and dilution.
problem if the ore is wet and weak or fractured.
The maximum length that a hole can be drilled will Therefore, multiple Boosters should generally be
depend on a number of factors including ground used in each blasthole, to provide insurance against
conditions, accuracy required, the type of drill string misfires caused by ground movement or dynamic
being used and the stiffness of the system in general. pressure desensitisation. Blastholes should usually
For stope widths less than 2 m a single row of holes be primed near the middle, with additional Boosters
or two row staggered pattern can be utilised. For above and/or below for security.
stope widths in excess of 2 m, a dice five pattern may
be more appropriate (Figure 9.12).
Drilling accuracy is vital to the economic success of
Charging
narrow vein stoping. Care must be taken with drill Blastholes that are dry can be charged with ANFO,
set up as a misaligned hole will prevent all following emulsion or Impact® mixtures, by blow loading into
holes from firing out or may break the hanging upholes and pouring or blow loading into downholes.
wall or footwall causing over break and consequent Blastholes may be charged with “Impact®” products
dilution. or low-density bulk emulsion, to reduce powder
factor and limit overbreak and damage to the
surrounding rock.

Figure 9.12 Drill Patterns for Narrow Stope Widths

138 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
If blastholes are wet, it will be necessary to charge
water-resistant emulsion explosives or alternatively Bench Stoping
use ANFO with hole liners. Packaged explosives can Bench stoping utilises rows of long, parallel
be used for downholes. For upholes, hole liners with downholes to create an open stope in steeply
ANFO are an option or preferably bulk emulsion. dipping orebodies (Figure 9.13). The orebody and
Charging with packages will be slower and more surrounding rock must be competent, or capable
expensive than for ANFO or Impact®, especially of being supported over broad spans. The orebody
where upholes are drilled. Packaged explosive must boundaries should be planar, as the stope outline will
be tamped to ensure retention in upholes, which be defined by long, straight blastholes. Bench stoping
is difficult unless a pneumatic cartridge charger can be used to extract orebodies of varying widths,
is available. Tamping will produce a high in-hole and becomes “Narrow Vein Stoping” in very narrow
charging density, which may cause damage to the orebodies. The maximum practical width is usually
surrounding rock. For these reasons, it is preferable to
determined by the need to sill out the orebody.
drill downholes which breakthrough into the sublevel
below, to maximise the use of ANFO and Impact
mixtures or charge with low-density bulk emulsion.
Design
Breakthrough blastholes must be blocked off
The height of a bench stope will be determined by
and stemmed at the toe, to support and confine
the following factors:
the explosives charge. All downholes should be
stemmed at the collar, to improve blasting efficiency • orebody dip, regularity and width;
and prevent backbreak that may damage collars • rock properties of ore and surrounding rock;
in the next ring. Upholes are rarely stemmed, but
• access development available;
an uncharged collar should be left to minimise
backbreak. An uncharged collar length equal to the • drilling equipment available; and
burden should be adequate in most situations, but in • stope wall support requirements.
weak or fractured rock it may be necessary to increase
Bench stopes are often restricted to approximately
the collar to reduce overbreak.
20 m height, to limit unsupported rock exposures
and ensure that blasthole lengths are not excessive.
Initiation Taller stopes may be developed using longer large
diameter blastholes, if the surrounding rock is
Blast initiation is a crucial area in narrow vein stoping. competent enough.
It is essential that each hole goes off in the planned
sequence without fail. Bench stoping requires a cutoff slot to be extracted
across the orebody over the full stope height, to
If any part of the hole fails to initiate the result is provide a free face for initial blasts. This cutoff slot is
inevitably a bridge which has to be redrilled and
usually developed from a longhole raise, using slot
fired (if indeed possible) causing delays and
excavation techniques.
potentially lost ore.
Where an orebody is mined upwards by a series of
Detonators should be placed inside Boosters, charged
bench stopes, each completed stope is filled before
into blastholes, and hooked up according to the
the next is commenced. Thus the extraction drive
procedures outlined in Chapter ‘2’.
of each stope is completely silled out, and loaders
Because of the confined geometry, relatively slow work on a floor of fill material. To ensure that
timing between holes will provide increased relief and loaders operate efficiently, it is essential to produce a
reduced overbreak damage. consistently loose, well fragmented muckpile. This is
Exel™ Goldet™ detonators with surface delays of 100 especially important where remote-controlled loaders
or 200 ms have successfully been used to provide the are required to extract ore (Figure 9.13a and b).
required timing and reduce projection of the broken
dirt to limit remote bogging requirements.
Alternatively, use of the Exel™ MS range is common
practice, skipping numbers in the series as required to
provide the appropriate delay interval.

Chapter 9 Production Stoping 139


Silled drive

Stope

Extraction drive

a) Long section b) Cross section

8 4
Silled drive
6 2

Stope 6 4 2 3 5
5 1
Back-up delays

7 3

5 3 1 2 4
c) Plan
Primary delays

10 7 5 2
9 3
6 4 2 3 5
1
6
Extraction drive
4
8

10 7 5 2 e) Initiation sequence

d) Plan
Figure 9.13 Bench Stoping

140 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Drilling Charging
The drill drive and extraction sublevel in a bench Breakthrough blastholes must be blocked off and
stope are usually silled out across the full width of stemmed at the toe, to support and confine the
the orebody. This enables rows of parallel downholes explosives charge. At the toe of each blasthole, an
to be drilled to breakthrough, which increases the uncharged length approximately equal to the burden
tonnes broken per metre drilled, and allows blastholes should generally be used, to avoid backbreak and
to drain clean for charging. In wide orebodies, the damage to the back of the extraction drive.
burden and spacing may be relatively large, because Blastholes that are dry can be charged with ANFO
blastholes are not tightly constrained by geometry. or Impact®; these products are generally poured into
However, conservative drilling patterns are often downholes, but may be blow-loaded if higher
used, to provide good fragmentation and minimise in-hole densities are required. Perimeter blastholes
overbreak. may be charged with low-density Impact series
Blasthole diameters for bench stoping are usually explosives, to reduce overbreak and damage to the
determined by the need to minimise in-hole deviation, surrounding rock.
and thus depend on the length required. Where the In bench stopes that are undercut, all blastholes
distance between the floor of the drill drive and the should breakthrough. Any blastholes that contain
back of the extraction drive is 10 m to 20 m, 5 7 mm water can be said therefore, either to be drilled short,
to 76 mm diameter blastholes may be used. For taller or to have deviated outside the stope boundary; any
stopes, larger diameter blastholes may be required necessary redrilling should be done before charging
to ensure drilling accuracy. As blasthole toes break begins. If blastholes are wet, it may be necessary
through, it is possible to accurately locate positions to charge water-resistant emulsion explosives. In
and redrill if necessary. perimeter holes, small diameter packages may be
Drilling patterns for bench stopes must be designed required to reduce overbreak and damage to the
to suit specific rock types, sublevel interval, blasthole stope walls.
diameter, deviation, and the fragmentation required. An uncharged collar length equal to the burden
Square drilling patterns are often used for simplicity, should generally be left on each blasthole, to
especially in narrow orebodies (Figure 9.13c). In very minimise backbreak. All blastholes should be
wide orebodies, it may be practical to drill a more stemmed, to improve blasting efficiency and reduce
efficient staggered pattern, with additional “easer” damage to blasthole collars in the next row.
holes adjacent to perimeter blastholes. Where
the surrounding rock is relatively weak, it may be
necessary to drill closely spaced blastholes along the Initiation
walls, and lightly charge them to minimise overbreak
Bench stope blasts are generally restricted to one or
(Figure 9.13d).
two rows, to minimise forward throw and reduce the
amount of remote loading required. It is desirable to
Priming produce a muckpile that rests against the free face,
to maximise the amount of ore that can be loaded
Blastholes in bench stopes should usually be primed from under the brow (Figure 9.13a). This ore is then
near the middle, to ensure maximum confinement extracted to clear the face before the next firing.
and prevent Boosters from being damaged or torn
out by ground movement near the toe and collar. Complete rows of blastholes should be fired together,
In weak or fractured rock, explosives charges can with short delays between blastholes in each row. The
be damaged or cut off by adjacent blastholes. Thus centre blasthole in the front row should fire first, and
multiple Boosters should generally be used in each initiation should progress towards the perimeter holes
blasthole, to provide insurance against misfires caused (Figure 9.13c). The delay between adjacent blastholes
by ground movement. in a row should usually be as short as possible, but
not instantaneous; thus, consecutive Millisecond (MS)
Packaged explosives or Pentex boosters may be used delay numbers are most suitable, with blastholes fired
to initiate explosives charges in bench stopes. Where on separate delays if necessary to reduce ground
ANFO or Impact® are charged, Pentex™ boosters are vibrations. If several rows are fired in a blast, it is
the most efficient. The primer should be large enough usually best to completely initiate each row before
to quickly initiate a stable detonation in the main starting on the next; this will ensure that blastholes
charge, and long enough to completely enclose the in successive rows have an effective free face and
longest detonator being used. acceptable breakout angles when they fire.

Chapter 9 Production Stoping 141


It is especially important to delay perimeter blastholes drill drives on different sublevels, to limit blasthole
to ensure that they have the maximum possible lengths and enable wall support to be installed.
breakout angle. However, delays between adjacent Rings of blastholes are always fired to a free face,
blastholes should be short enough to avoid charges which requires a cutoff slot to be extracted over the
being cutoff by ground movement. Long Period (LP) full stope height. The cutoff slot may be developed
delays are, therefore, rarely used in bench stope from a blasted or bored raise, using slot excavation
blasts, unless it is essential to minimise forward techniques.
throw; these long delay intervals may cause poor
fragmentation or misfires, especially in highly-jointed In longhole open stopes drilled from several sublevels,
rock. Where blastholes are multiple primed the upholes may be drilled from drives on the extraction
“insurance” delays should generally be one number level. These ‘undercut’ rings intersect the main
higher than the primary delays (Figure 9.13e). rings, and form a trough to funnel broken rock into
drawpoints (Figures 9.1a and b).

Longhole Open Stoping Drilling


Longhole stoping techniques can be used in
Ring drilling can incorporate upholes, downholes,
orebodies of varying widths and dips, but is most
full 360º rings or partial fans, drilled in vertical or
effective for bulk mining in broad stopes with vertical
horizontal planes. As blastholes are divergent, the
or steeply dipping walls.
overall tonnes broken per metre drilled is lower than
Longhole stoping in wide orebodies generally involves for rows of parallel blastholes. The burden is usually
drilling long blastholes at various angles from drill constant, because rings are drilled in planes parallel
drives that are not “silled out” across the orebody to the cutoff slot. However, the blasthole spacing
(Figures 9.14a and b). These “rings” or “fans” of reduces from the toe towards the collar, and rings are
blastholes can enable a large volume of rock to be usually designed on the basis of maximum acceptable
drilled and blasted from relatively small drill drives. toe spacing. The design toe spacing is usually 1.5
Ring drilling is also used in block caving and pillar to 2.0 times the burden, which is a compromise
“mass blasts”. For block caving, rings of blastholes between excessive spacing at the toe, inefficient
are drilled and blasted to undercut the ore block. drilling, and the requirement for acceptable blasthole
For pillar recovery, rings may be drilled in vertical or breakout angles.
horizontal planes, from drill drives or raises. In open
Blasthole diameters used in ring drilling typically range
stoping techniques, rings are usually drilled in vertical
from 57 mm to 115 mm diameter, but downholes
planes to blast the ore in slices.
may be as large as 200 mm diameter. Smaller
This section will emphasise ring drilling techniques for diameter blastholes may produce more consistent
longhole open stoping, as pillar recovery involves the fragmentation in some rock types, but they are less
same general principles. productive and prone to in-hole deviation. Large
diameter blastholes usually result in higher drilling and
blasting productivity, and can be drilled straighter over
Design longer distances. However, large diameter blastholes
Ring drilling has been used to successfully extract are usually drilled on relatively conservative burdens
open stopes and pillars that vary from approximately and spacings, because of geometrical constraints and
5 m to 100 m wide, and from 10 m to 250 m high. the need for relatively fine fragmentation to enable
In narrow, squat stopes, all drilling may be done efficient extraction from drawpoints.
from a single drill drive. If the orebody dips from the Blasthole burdens and spacing for ring drilling
vertical, the drill drive should generally be located vary widely, because of rock properties, geological
on the hangingwall side to minimise damage to structure, stope geometry, required fragmentation,
the overhanging rock (Figure 9.14a). If blastholes blasthole diameter, and explosives used. Some
are drilled to the hangingwall from a drive located examples of blasthole burdens and toe spacings
elsewhere, damage and overbreak may be caused that have been successfully used are summarised
by the effect of blasthole toes or over drilling (Figure in Table 9.1.
9.14b). In wide orebodies, multiple drill drives may
The results of ring blasting are greatly influenced by
be used to reduce the length of blastholes required,
drilling accuracy, especially for long, flat blastholes. In-
increase drilling efficiency, and cleanly define the
hole deviation depends on geology, diameter, length,
footwall and hangingwall by perimeter blastholes
orientation, equipment and drilling rates. Thus ring
(Figure 9.14c). Tall stopes will usually require several
designs should be based on realistic blasthole lengths,

142 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
a) Hanging wall b) Foot wall c) Twin drill drive
drill drive drill drive

Ring 2, 4, 6
Ring 1, 3, 5
11 10 9

9
11

7
7

5
4
6

1 4

6
2

3 1

d) Staggered pattern and initiation sequence


Figure 9.14 Ring Drilling

Chapter 9 Production Stoping 143


to avoid excessive deviation. Blasthole positions Detonating cord “tracer” lines should only be used
should be accurately marked up in drill drives, and in blastholes after giving careful consideration to the
detailed ring sections will be required by the driller. core load and effects on the explosives column.
Drilling accuracy depends on correct collaring and
alignment, which cannot be achieved unless the
correct equipment is used. Charging
The toes of breakthrough blastholes may be located Ring-drilled blastholes converge from toe to collar,
to determine their actual positions. Blastholes that which makes it impossible to evenly distribute
do not breakthrough can also be surveyed, using in- explosives energy within the rock. The explosives
hole instruments; these instruments will identify any energy per tonne of rock will be greater near
alignment errors, and quantify in-hole deviation. the collars than at the toes, unless lower energy
explosives are used towards the collar. However, as
the burden is constant and breakout angles reduce
Priming towards the collars, the use of varying energies is
Long blastholes usually require multiple Boosters, to itself a compromise. Common practice is to charge
provide insurance against downline cutoffs, charge blastholes to a collar position where adjacent charges
dislocation or desensitisation of the explosives are separated by a distance equal to the toe spacing
column. The position and number of Boosters used (Figure 9.14d).
will depend on many factors, but it is common to use Dry blastholes are usually charged with ANFO or
Boosters at 10 m to 15 m spacings in blasthole rings. Impact®, by pouring into downholes or blow loading
Boosters should not be placed too close to blasthole into upholes and flat holes. For large blasts, or if there
toes or collars, as they may be damaged or dislocated is a risk of water entering blastholes before firing,
by adjacent charges. This is especially important water-resistant explosives may be preferred for security.
where the toes of blastholes from different drill drives In hard rock types or if there is a need to expand
“interlock” together (Figure 9.14d). For a double- drilling patterns, slit cartridges of packaged emulsion
primed blasthole, the Boosters should generally be may be used to provide more energy per metre of
placed approximately one third of the charge length blasthole. Perimeter blastholes are often charged with
from either end. Impact®, to reduce overbreak and damage to the
Packaged explosives or Pentex™ boosters may be used surrounding rock. In relatively weak or highly jointed
to initiate ANFO or Impact® in dry blastholes. Full rock types, Impact® may even provide adequate
columns of packaged explosives should be primed by fragmentation when used in the entire blast.
a package of the same product, or a Pentex™ booster If blastholes are wet, or may become wet before
if charges may be affected by dynamic pressure in firing, water-resistant explosives should be used. For
weak, saturated rock. Bulk emulsion explosives should large blasts, bulk explosives may be used if equipment
be initiated by Pentex™ boosters. and facilities are available on site. Bulk explosives

Blasthole Diameter Ring Burden Toe Spacing


Explosives
(mm) (m) (m)
57 ANFO Blow Loaded 1.8-2.1 2.7-3.0
64 Impact ®
1.25-1.5 2.0-2.2
64 ANFO Blow Loaded 2.0 3.0
70 Impact ®
2.0-2.4 3.0-3.6
70 ANFO Blow Loaded 2.1-2.5 3.0-3.6
115 Impact ®
2.0 4.0
115 ANFO Poured 3.0-3.2 5.0-6.5
115 Bulk Subtek ™
4.5 7.0
140 Impact® 2.0-3.0 4.0-6.0
140 ANFO Poured 3.0-3.7 5.5-7.5
165 Impact ®
2.0-3.0 4.0-6.0
165 ANFO Poured 2.5-4.1 6.0-8.0
165 Bulk Subtek ™
4.0 6.0
200 ANFO Poured 4.0-5.0 6.0-8.0
Table 9.1 Ring Drilling Burdens and Toe Spacings

144 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
usually can be charged faster, are less expensive, • avoid placing explosives in soft or cracked rock.
and produce more energy per metre of blasthole The most effective inter-deck stemming material is
than packaged explosives. The increased energy screened rock aggregated in the 6 mm to 12 mm
output may be utilised by drilling larger blasthole size range. Explosion gases cause this material to
patterns, or used in standard patterns to produce jam against the blasthole walls, producing more
finer fragmentation. If bulk water-resistant explosives confinement than sand or drill cuttings.
are not available on site, it will be necessary to use
packaged explosives. These can be quickly and easily The length of inter-deck stemming must be sufficient
charged into downholes, but charging rates for flat to prevent explosives being affected by sympathetic
and upholes will be slow unless a pneumatic cartridge detonation, dynamic pressure desensitisation, or
charger is used (refer to Chapter ‘5’ for more details). physical dislocation when adjacent charges are fired
on different delays. In wet blastholes, the inter-deck
Breakthrough blastholes must be blocked off and stemming length must be increased, because shock
stemmed at the toe, to support and confine the waves may be transmitted through the inert deck.
explosives charge. An uncharged collar should be left
on all blastholes, and stemming placed in downhole The effects of one deck charge or another will
collars. The minimum stemming length required is depend on many variables, including the following:
approximately 18 blasthole diameters, and screened • blasthole diameter;
rock aggregate is the best material to confine • explosives sensitivity and diameter;
explosion gases and increase blasting efficiency.
• presence of water;
• rock type;
Deck Charging • location and type of Boosters;
The explosives charge in each blasthole may be • delay between decks and adjacent charges; and
separated into several isolated “decks” with inert
stemming material placed between adjacent charges • length and type of inert material used.
(Figure 9.15). Deck charging may be used to achieve Because of the large number of variables, it is not
one or more of the objectives summarised below: possible to precisely define the type and length of
• reduce the mass of explosives initiated on an inert deck that will guarantee an optimum
each delay; blasting result. A deck length of approximately
15-20 blasthole diameters is a good starting point.
• reduce the overall amount of explosives used; and/or

Figure 9.15 Deck Charging

Chapter 9 Production Stoping 145


Initiation free face at the bottom of each hole. The technique
is often used to recover pillars from between filled
Rings of blastholes may be fired one at a time, in stopes, where it is necessary to minimise the area of
small groups, or as large “mass blasts” of multiple walls exposed at any time (Figure 9.16 a, b).
rings. Rings which contain blastholes with interlocking
The VCR method involves firing short explosives
toes are usually fired together, to retain a straight
charges in blastholes drilled perpendicular to a
free face (Figure 9.1), However, it may occasionally be
(horizontal) free face. The explosives energy is utilised
necessary to “undercut” or “overhand” the stope,
to form an inverted crater and to eject fragmented
or fire the toes off blastholes, to meet grade control,
rock downwards (Figure 9.16c). Testing and analysis
scheduling or rock mechanics requirements.
has shown that there is a definite relationship
Each firing must be individually designed to suit between:
specific stope requirements, but some general
• the energy of the explosives;
rules are:
• the shape of the charge;
• all in-holes delays are activated before any
charge fires; • the “depth of burial” (location) of the charge;
• rings fire from the bottom, proceeding upwards; • the properties of the rock; and
• the first hole to fire has the widest breakout angle; • the volume of rock fragmented and dislodged.
• the longest holes in a ring fire as early as possible; The explosives charge shape would be spherical for
ideal blast results, but experiments in various rock
• perimeter or hangingwall holes fire last
types have shown that good VCR blasting can be
(Figure 9.14d);
achieved when explosives charges with a length to
• interlocking blasthole toes fire together; diameter ratio of not more than 6:1 are used.
• minimum expansion void required is 35%; The thickness of ore removed by a pattern of
• allow 3 ms to 5 ms/m of spacing within rings; VCR charges placed at optimum depth is largely
determined by the rock type and geological structure
• allow 12 ms to 15 ms/m of burden between rings;
present. Generally the effective horizon of breakage
and
is at or above the level of the top of each explosives
• the maximum charge fired per delay may charge, and this is verified when the free face is
be restricted. measured for the next round. Some rock, especially
Exel™ MS delay detonators or Electronic Blasting when influenced by in-situ stresses, may break or
Systems should always be used in preference to Exel™ cave-in to a depth well above the charge location.
LP detonators for ring blasting, to allow adequate However, if geometry varies from the design because
time for burden relief but ensure that charges fire of deviating, blocked or unchargeable blastholes, the
before they are disrupted by adjacent blastholes. actual thickness of ore removed may be significantly
For large blasts, a combination of in-hole and collar less than optimum.
delays may be used to control ground vibrations
and maintain short inter-hole delays for optimal
fragmentation (refer Chapter ‘2’). Design
Detonator lead lengths should be selected to allow The correct depth of burial is critical to the success of
each primer to be placed in the required location VCR blasting, and is best determined by tests on-site.
without the need to extend downlines. For ring The depth of burial is the distance from the effective
blasting, a range of lead lengths is usually required for free face to the centre of the explosives charge (Figure
varying blasthole depths. 9.16c). Ideally the optimum depth of burial should be
determined by drilling a series of short blastholes of
Detonators should be placed in Boosters, charged
the proposed VCR diameter, with the depth of these
into blastholes, and hooked up according to the
holes increasing in small steps. A standard (spherical)
procedures outlined in Chapter ‘2’.
explosives charge is fired in each, and the volumes
of the resulting craters are measured and compared

VCR Stoping to determine the most efficient depth of burial. In


practice however, crater tests are usually conducted
Vertical Crater Retreat (VCR) Stoping involves the in blastholes of a diameter smaller than that of
drilling of large vertical blastholes on a regular production blastholes.
pattern, and charging them with short explosives If charges are placed too far from the free face
charges at carefully determined distances from the (excessive depth of burial), then long, bell-shaped

146 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Drill drive

Stope Stope

a) Long section b) Cross section

Stemming
Charge

Stope

c) VCR blasting principle


Figure 9.16 Vertical Crater Retreat Stoping

craters or chambers will result, and humps of to all explosive charges at the same horizon in most
unbroken rock will remain. If blasthole deviation is cases; this may involve small firings of one or two
excessive, the actual depths of burial and location correcting charges to trim up the face before large
of charges may not coincide with designed values, firings proceed.
and reduced rock displacement and remnant humps
of rock may result. The effect of unbroken rock
humps is cumulative and if not recognised and dealt Drilling
with, major problems can occur including the virtual The larger the blasthole diameter, the greater
freezing up of whole portions of the stope. Once the mass of explosives that can be used while
irregularities predominate the free face, it becomes still maintaining an efficient degree of charge
difficult to get explosives charges down to their compactness. The greater the mass of explosives,
designed depth of burial, and frequently blastholes the greater the optimum depth of burial and volume
become blocked or cut off. The solution is to carefully of rock that can be displaced. In practice blastholes
monitor blast progress and deal with irregularities as in the diameter range 150 mm to 165 mm are
soon as they appear. It is desirable to keep the tops most common, however blastholes of diameter

Chapter 9 Production Stoping 147


114 mm up to 200 mm have been used successfully. Before charging, each blasthole must be checked
Factors influencing blasthole diameter will include to determine whether it breaks through, the
drilling accuracy, drill rig costs, site accessibility, blast breakthrough depth, and the approximate shape of
vibration or wall damage constraints, and the overall the breakthrough position.
dimensions of the stope. Breakthrough blastholes must be blocked, and
VCR blastholes should be drilled in such a way that stemming placed to the design bottom of each
the craters formed after firing, actually intersect and charge. Packaged explosives should be slit before
remove a horizontal slab of rock. Blastholes drilled too dropping into blastholes to maximise the amount
far apart will leave humps of unbroken material that of “slumping” and hence in-hole density. In any
cause major problems as mining proceeds upwards. blastholes that are blocked and contain water, care
Blasthole spacings that are much too small can result must be taken to avoid packages deforming and
in interference of adjacent charges and misfires, cut jamming at the water interface (Figure 9.7c).
offs or blocked holes. Although blasthole pattern Each blasthole should be stemmed to confine
size is best determined from on-site crater test shots, explosion energy. Below the charge, screened rock
Table 9.2 gives an indication of the expected range aggregate maybe used, but it is best to use 1.5 m to
of blasthole spacings and diameters when a slumped 2.0 m of sand above the charge, to avoid blastholes
high energy packaged emulsion or bulk emulsion becoming blocked.
is used in rock of medium strength. However, such
estimates are no substitute for detailed crater testing
to optimise VCR geometry! Initiation
VCR blasthole charges ideally function independently
Priming of adjacent charges, so the initiation sequence may
not require special design. However it is common for
Because of the short charges in VCR blasting, the the free face to become irregular rather than flat and
location of the primer is not critical. It is common in these circumstances it is important to gain a clear
to place the booster near the top of the charge. As impression of the shape of the backs and the location
the explosives are generally not detonator sensitive, of charges and to fire the lowest charges first.
Pentex™ or emulsion Boosters are used.
There is some benefit in firing those charges nearest
the stope walls last, so that they can also break
Charging towards the slightly fractured zone of material on the
fringe of previously displaced craters.
In VCR blasting, it is desirable to use explosives that
exert maximum pressure in the blasthole. Initially Where VCR excavation is proceeding smoothly, it
all VCR work was carried out using high density, may be possible to blast two or more rounds in a
TNT-based Packaged Watergels. More recently, single firing by placing separate decked charges
VCR blasting has been carried out using packaged within each blasthole, and placing them on different
emulsions. A greater concentration of explosives delays. The main benefit of this technique is that the
energy (in a “spherical charge”) will permit greater time-consuming task of measuring and logging all
depths of placement, with resulting increases in hole depths and blocking off blastholes has to be
blasthole spacings and achieved advance per round. done only once for each blasthole, regardless of the
Attempts have been made to apply ANFO, but number of decks. However, the risk of choking up the
the need to reduce blasthole spacings make this round, dislodging charges, sympathetic detonation
uneconomical. and/or desensitisation generally make multiple
rounds unpopular.

Blasthole diameter Blasthole Spacing Depth of Burial Typical Charge


(mm) (m) (m) (m)
100 1.1-1.4 1.1-1.4 5 to 6
115 1.3-1.7 1.4-1.9 6 to 9
130 1.6-2.6 1.6-2.2 10 to 15
165 2.6-3.6 2.0-2.8 20 to 30
200 3.2-4.0 2.6-3.8 30 to 40
Table 9.2 VCR Blast Design

148 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Perimeter Blasting to produce good fragmentation. For large blasts,
the Extended Range of MS Delays 16 to 30 may
In VCR blasting, explosives charges are designed to be used. Exel™ Long Period (LP) detonators are
break outwards and downwards to the free face. rarely used for stripping or stoping, because the
Thus VCR blasting can be expected to produce relatively long delay intervals tend to produce
rougher stope walls than might be achievable using coarser fragmentation. However, LP detonators are
blastholes designed to break inwards to a pre-blasted sometimes used to reduce the throw from a blast,
void. It is seldom appropriate to charge perimeter where this is more important than fragmentation.
holes with lower energy explosives, as high-energy
• A trunkline of detonating cord is used to initiate
explosives are essential for cratering.
the in-hole non-electric detonators (Figure 9.17b).
It is possible that perimeter holes can be allowed to Cordtex™ 5 and Cordtex™ 3.6 detonating cords
lag behind the development of the centre of a stope, reliably initiate Signal Tube, using standard J-Hook
then fired as stripping holes using ANFO or decoupled connections.
charges. In doing this there is always the risk of holes
• For large blasts, non-electric delay detonators
being damaged or cut off, thus some ore would
can also be used outside blastholes, as bridges to
remain on the walls and be lost.
link several detonating cord trunklines together.
This enables many rows of blastholes to be fired
Common Problems in a single blast, using short delays to produce
good fragmentation. The in-hole detonators are
The following problems have a significant influence connected to several separate detonating cord
on the effectiveness of VCR mining: trunklines, which are initiated in sequence by the
• blasthole deviation; bridge detonators (Figure 9.17c).
• inaccurate measurement of hole depth and location • Two instantaneous #8 strength electric detonators
of the free face; are used to initiate the detonating cord trunkline.
• insufficient explosives energy and density; Initiating explosives used in stripping and stope
• insufficient explosives quantities for each blasting should be charged and connected together
individual hole; according to standard procedures that include the
following recommendations.
• inadequate blocking-off of holes;
• Each in-hole detonator is inserted into a packaged
• the free face becomes very irregular; or cast explosives primer that completely encloses
• excessive slice thickness attempted; the detonator shell.
• rocks fall into the collars of blastholes and • Semi-conductive charging hose is used when
block them; blow-loading ANFO over non-electric detonators
• stemming above the charge freezes and prevents inside blastholes. Packaged explosives are carefully
charge placement; and inserted and gently tamped, to avoid damaging the
Signal Tube.
• blastholes shift with ground movement.
• A closed-loop detonating cord trunkline is used,
to provide two paths of initiation to each in-hole
Initiation Procedure for detonator. Several separate cord trunklines
may be used, linked together by non-electric
Stoping Applications detonator bridges.
• Each in-hole detonator is connected by its J-Hook
to the nearest part of the detonating cord trunkline.
Stripping and stoping All connections between cord and Signal Tube are
made at right angles, with the Tube pulled taut
Stripping and stope blasts are now usually fired
but not stretched. Connections are made at least
by an initiation system that includes the products
200 mm away from detonating cord knots or
listed below:
branch lines.
• Exel™ detonators, with MS (Millisecond) delays 1 to
• The hookup is thoroughly checked, to ensure
15, are used for all types of stripping and stoping
that all J-Hooks are connected and that no Signal
including benching, uphole stoping and flatback
Tubes cross over or lie close to any detonating cord
(Figure 9.17a). Short delay times are used between
between the J-Hook and the blasthole collar
blastholes, to ensure that they interact effectively
(Figure 9.17c).

Chapter 9 Production Stoping 149


• If several detonating cord trunklines are to be fired Two instantaneous #8 strength electric detonators are
in sequence, they are linked together by non- attached to the lead-in lines, just before clearing the
electric detonator bridges. When using bridging area for firing. These two starters are securely taped
detonators in this way, it should be understood to the lead-in lines, approximately 150 mm from the
that there is a risk that trunklines and signal tubes cut ends.
in later firing bridged sections could be damaged
by flyrock or airblast from earlier firing sections.
To minimise the risk, the delay times of the bridge Longhole Stoping
detonators should be selected to provide a suitable Longhole stope blasts are now usually fired by an
buffer between detonating holes and exposed initiation system that includes products listed below:
trunklines. Trunklines in each separate bridged
• Exel™ detonators, with MS delays 1 to 15 plus the
section are linked by pairs of identical bridging
Extended Range of MS delays 16 to 30, are used
detonators taped to short lengths of detonating
for all types of longhole stope blasting. Heavy
cord. This enables the detonators to be placed
Duty (HD) Signal Tube is used where charged
at least 2m from any Signal Tube connections
blastholes are required to sleep for an extended
(Figure 9.17c).
time before firing. Slider Boosters and detonating
• Two detonating cord lead-in lines are used to cord downlines may be used where large diameter
initiate the trunkline system. The lead-in lines are blastholes contain multiple decked charges.
long enough to locate starter detonators at least However, non-electric detonators with Signal Tube
2 m away from any Signal Tube.

8 7 6 7 8

5 3 3 5

4 2 1 2 4

Stope Det cord

a) Millisecond delay sequence b) Standard Trunkline system

1 2 3 4 5 6 7 8 3 4 5 6 7 8 3 4
75 ms
200 ms 225 ms
Det cord
150 ms
6
Det cord #2
6
Starter det Bridge det

c) Trunkline “bridge” system


Figure 9.17 Stope Blast Initiation Systems

150 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
downlines are generally used because they do not • Each Signal Tube downline is secured by its J-Hook
disrupt explosives charges or stemming material, to the nearest part of the detonating cord network.
and are available with a larger range of delays. All connections are made at right angles, at least
• A Trunkline of detonating cord is used to initiate 200 mm from detonating cord knots, with the tube
the in-hole non-electric detonators, Cordtex™ 5, pulled taut but not stretched.
and Cordtex™ 3.6 detonating cords reliably initiate • The hookup is thoroughly checked to ensure that
Signal Tube, using standard J-Hook connections. all J-Hooks are connected and that no Signal Tubes
For large blasts, the overwrapped cords are cross over or lie close to any detonating cord
often preferred because their superior knot-tying between the J-Hook and the blasthole collar.
characteristics are an advantage when making
• Two detonating cord lead-in lines are used to
multiple branch line connections.
initiate the trunkline network in each drill drive. The
• Non-electric detonators can also be used outside lead-in lines are long enough to locate the starter
blastholes, as additional collar (piggyback) delays detonators at least 2 m away from any Signal Tube.
to control sequencing. This enables blasthole firing
• Two instantaneous #8 strength electric detonators
times to be split between nominal detonator firing
are attached to the lead-in lines, just before clearing
times, to control ground vibrations and maintain
the area for firing. These two starters are securely
closely spaced inter-hole delays for optimal
fragmentation. Non-electric Exel™ Connectadet™ taped to the lead-in lines, approximately 150 mm
detonators are often used as collar delays, to from the cut ends. Both detonators point towards
sequentially initiate downlines in large blasts. The the blast, and are covered to protect all Signal Tubes
use of collar delays is discussed in Chapter ‘2’. from shrapnel.

• At least two instantaneous #8 strength electric • For procedures used in firing electronic blasting
detonators are used to initiate the detonating cord systems, refer to Chapter 3.
trunkline in each drill drive. Where collar delays are used, the following additional
• The i-kon electronic blasting system is being
™ recommendations apply:
routinely used for the firing of production blasts in • In-hole and collar delays are selected to ensure
many mines in Australia. that all collar detonators have fired before any
Initiating explosives used in longhole stoping should in-hole detonators fire, to prevent the surface
be charged and connected together according to initiation system being disrupted by airblast,
standard procedures which include the following flyrock or rockfalls.
recommendations: • Each downline or group of downlines is initiated
• Each in-hole detonator is secured inside a packaged either directly by the detonating cord trunkline,
or cast explosives primer that completely encloses or by two Exel™ Connectadet™s that are located
the detonator shell. outside the blasthole collar.
• Semi-conductive charging hose is used when blow- • Pairs of Exel™ Connectadet™ detonators are
loading ANFO over non-electric detonators inside attached to downlines with the plastic block
blastholes (refer Chapter ‘5’). ensuring that outgoing downlines do not loop
• Large diameter packaged explosives should be around in front of or over the block.
lowered on top of Boosters in downholes, rather • Each Exel™ Connectadet™ is secured by its J-Hook to
than dropped from the blasthole collar. the nearest part of the detonating cord network. All
• Downlines are held taut during charging and connections made at right angles, at least 200 mm
stemming, to prevent damage and minimise from detonating cord knots, with the Signal Tube
abrasion. pulled taut but not stretched.

• A closed-loop detonating cord trunkline is used, • Downlines that have collar delays are not connected
to provide two paths of initiation to each in-hole directly to the trunkline, as this would by-pass the
or collar detonator. Where a single ring or row of piggybacked Connectadet delay time.
blastholes is to be fired, one loop of detonating • Downlines without collar delays are secured by their
cord is laid out across or around the drill drive J-Hooks to the nearest part of the detonating cord
(Figure 9.18a). For initiating several strings or rows network. All connections are made at right angles,
of blastholes, a network of cord is laid out with at least 200 mm from detonating cord knots, with
trunklines along each side of the drill drive, and the Signal Tube pulled taut but not stretched.
branch lines across the drive (Figure 9.18b). The
cord network is secured in position by attaching it • The hookup is thoroughly checked, to ensure that
to rockbolts, eyebolts or mesh. all necessary J-Hook connections have been made,

Chapter 9 Production Stoping 151


and that no Signal Tubes cross over or lie close to on different sublevels, and many blastholes that
the detonating cord between the J-Hook and the may have to be fired on individual delays. Thus blast
blasthole collar. design, charging and supervision are more complex
• Exel™ Connectadet™ blocks should have all than routine production blasts, although the basic
downlines secured and no tubes crossed over principles involved in selecting, charging and
in the block. hooking up the initiation systems are similar
to a single ring blast.
• Exel™ Connectadet™ detonators do not need
to be covered. Mass blast initiation systems may include different
levels of complexity, as summarised below:
• MS delay detonators are used inside blastholes,
Mass Blasting with Exel™ MS delays 1 to 15 plus the Extended
Large longhole stope and pillar mass blasts are Range of MS delays 16 to 36. A detonating
commonly fired using signal tube systems although cord trunkline network is used to initiate the
electronic blasting systems are rapidly becoming the in-hole detonators by J-Hook connections.
system of choice particularly for complex multilevel Trunklines in each drill drive are linked together
blasts. Mass blasts usually involve several drill drives by detonating cord branch lines (Figure 9.18b).

Stope

Det cord Pin

Det cord
a) Single ring of upholes

b) Multiple ring of downholes


Figure 9.18 Longhole Stope Blast Initiation System

152 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Delay
Sequence In-hole Delay Collar Delay Total Delay
Interval
Between
Number No. Time (ms) No. Time (ms) Time
Holes (ms)
1 3 75 – – 75 17
2 3 75 Connectadet ™
17 92 8
3 4 100 – – 100 17
4 3 75 Connectadet ™
42 117 8
5 5 125 – – 125 17
6 4 100 Connectadet ™
42 142 8
7 6 150 – – 150 17
8 6 150 Connectadet™ 17 167 8
9 7 175 – – 175
Note:
This is an extract from a more comprehensive list of combinations. It shows only the first nine sequences of more than 100 possible sequences.

Table 9.3 In-hole and Collar Delay Combinations

The entire trunkline network is initiated by several trunkline is used to initiate the Exel™ Connectadet™
instantaneous electric detonators on each sublevel. by their J-Hooks (Figure 9.19). The entire trunkline
Where suitable raises or service holes exist, network is initiated by several instantaneous electric
detonating cord may be used to link together detonators on each sublevel. Detonating cord links
the trunklines on each sublevel, for additional may also be used between sublevels, for additional
insurance. insurance.

• MS delay detonators are used inside blastholes, • i-kon™ electronic detonators used inside blastholes
with Exel™ MS delays 1 to 15 plus the Extended connected to a surface network of harness wire.
Range of MS delays 16 to 36. Non-electric Exel™ One or more loggers used to log detonators on
Connectadet™ detonators are used as additional each sublevel. Loggers on each level connected in
collar (Piggyback) delays outside blastholes parallel to a firing line.
to further extend the delay range. The collar • MS delay detonators are used to initiate separate
delays sequentially initiate downlines, enabling decked charges inside each blasthole. In-hole delays
blasthole firing times to be split between nominal are provided by Exel™ detonators with Signal Tube
detonator firing times (Table 9.3). Connectadet™s downlines. Downlines are sequentially initiated by
are connected to downline tails using the Exel™ piggybacked Exel™ Connectadet™ collar delays,
Connectadet™ block, and a detonating cord which are connected to detonating cord trunklines.

Figure 9.19 Mass Blast Initiation System

Chapter 9 Production Stoping 153


• In-hole delays are provided by Exel™ non-electric separately. Alternatively, Impact® series of explosives
detonators. Downlines are sequentially fired by may be used in dry blastholes.
Exel™ Connectadet™ collar delays, which are • In wet blastholes, semi-rigid packaged emulsions
connected to several separate detonating cord can be used to give charges which build up as a
trunklines. The trunklines are fired in a delayed continuous column but which are a loose fit in the
sequence by non-electric detonator bridges blasthole. 25 mm diameter cartridges in a 45 mm
(Figure 9.17c). blasthole would be a suitably decoupled charge, as
would 55 mm cartridges in 90 mm blastholes.

Overbreak Control • Where bulk emulsion explosives are used, the


lowest density option should be used particularly
The intense energy from a normal stope production for hanging wall holes in weak ground providing
blast can destroy or, at least, reduce the structural burdens are adjusted accordingly.
strength of the wall rock; new fractures and planes of • The effective burden should not be greater than
weakness are created, and joints and bedding planes about 20 times the blasthole diameter.
which may have been tight before the blast are
• The spacing between perimeter blastholes should
opened up. As a result, there is an overall reduction lie between 25 and 40 times the blasthole diameter.
in the ability of the rock mass to hold together.
• For all blastholes except those in the last ring to be
Excessive overbreak results in greater ore dilution, fired, the length of the stemming column should be
increased material handling, the need for extra rock 18 to 25 blasthole diameters. To prevent overbreak
support, and a general reduction in safety it may be necessary to increase the stemming
and stability. length in perimeter holes.
Special blasting techniques such as presplitting can • The initiation sequence should be selected to
give rock walls of great smoothness and soundness. ensure that there are minimum numbers of
Before any attempt is made to apply presplitting or blastholes firing on the same delay, and perimeter
any other smoothwall technique, however, efforts holes are detonating in a delayed sequence.
should be made to find out to what extent modified
• Blastholes should be accurately aligned and collared
production blasts can reduce overbreak; if a high
to minimise deviation from design.
degree of success is achieved with redesigned
production blasts, then the need for smoothwall
blasting methods can be eliminated. The redesign
of a production blast to reduce overbreak does not
Line Drilling
necessarily reduce fragmentation or significantly Line drilling involves drilling a row of parallel
increase overall stoping costs. uncharged holes along the design excavation limit.
Hole diameter is usually 38-75 mm, and the spacing
Smoothwall blasting techniques are important
between holes is commonly 2-4 times the hole
methods of achieving stope walls that are smoother
diameter. These holes provide a plane of weakness to
and more sound than those that are left by
which the production blast can break. The distance
redesigned production blasts. These techniques are
between adjacent blastholes and the line-drilled holes
most successful in tough massive rocks and in tight
usually lies between 50% and 75% of the normal
horizontally bedded formations which are relatively
burden distance.
undisturbed by faults, etc. In unconsolidated,
weathered or highly fissured ground, problems in Because line drilling is a very costly and tedious
obtaining a consistently smooth wall are usually operation (as a consequence of the close hole
encountered. The very technique that produces the spacing required) it is used only where other blasting
desired effect in a tough massive rock may be entirely techniques are likely to cause too much overbreak.
unsuitable in weak, highly fissured ground. Blasthole
patterns and charge loads, therefore, will change
appreciably with the rock properties encountered. Presplitting
Presplitting involves drilling a row of closely spaced,
38-75 mm diameter blastholes along the design
Production Blasts perimeter. These blastholes are very lightly charged
Overbreak can be reduced by observing the following and then detonated simultaneously before the
guidelines in the design of production blasts: first production blastholes are fired. Firing of the
decoupled charges splits the rock just along the
• If a continuous column of ANFO is too powerful,
design limit, creating an internal surface to which the
deck charge the ANFO and initiate the charge decks

154 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines
Blasthole Charge er Suggested Presplit Trim Blasting Burden (Trim
Diameter Metre of Cartridge Blasthole Spacing Blasting Only)
(mm) Blasthole (kg) Diameter (mm) Spacing (m) (m) (m)
38* 0.15 25 0.4 0.6 0.9
51* 0.2 25 0.5 0.8 1.1
64 0.25 25 0.6 1 1.3
76 0.45 25 0.7 1.1 1.5
89 0.65 25** 0.9 1.3 1.8
102 0.8 29** 1 1.5 2
114 1 32** 1.1 1.7 2.1
152 1.8 45** 1.5 2.2 2.5
* A single strand of Cordtex™ 70P detonating cord (with an extra toe charge) can often be used successfully in these blasthole diameters.
** Continuous column charges of Senatel™.

Table 9.4 Presplit and Trim Blast Design

production blast can then break. Firing of the presplit Disruption of the presplit face can also be minimised
charges will itself create overbreak if the presplit holes by careful design of the initiation sequence and delay
are too close together, or charged too heavily. timing of the production blast. Perimeter blastholes
The spacing between presplit blastholes normally must have adequate free faces to break towards,
increases with the blasthole diameter (Table 9.4). and be delayed to provide adequate relief of burden.
Because rock properties have an over-riding effect
on blasthole spacing and charge mass these figures
should be considered only as recommended starting Trim Blasting
values. The best spacing and charge for a particular Sometimes referred to as slashing, trim blasting
rock should be determined by field trails. involves drilling a row of closely spaced blastholes
Presplit holes are generally charged to within about 8 with a suitable burden: spacing ratio along the final
blasthole diameters of the collar and left unstemmed. excavation limit. All holes are charged with light,
If stemming is deemed necessary it can be achieved well-distributed charges and fired simultaneously,
by pushing down a wad of damp paper, hessian after the final production blast. To avoid loss of
or plastic film to the top of the charge and then blastholes through caving, trim blastholes should be
backfilling with drill cuttings. drilled AFTER firing the adjacent production blast.
A variation on trim blasting involves the charging
If the best possible presplitting action is to of the trim holes at the same time as the last
be obtained, presplit charges must be fired production blast and firing them simultaneously on
simultaneously. This is achieved most successfully the last delay.
by joining up all detonating cord downlines with a
detonating cord trunkline. Where ground vibrations Trim blastholes are charged and fired in the same
are likely to cause problems, millisecond delay firing of way as those for presplitting, so that the detonation
groups of holes may be used. The number of holes in tends to split the rock web between holes giving a
each group is made sufficient to obtain a satisfactory smooth wall with minimum overbreak. For 51 mm
splitting action while not exceeding the maximum to 89 mm diameter blastholes, the charge usually
allowable charge mass per delay. To enable the presplit consists of a string of small diameter packaged
fracture to develop to its fullest extent, the presplit explosives suspended at 0.3 m to 0.6 m intervals
holes should be initiated at least 100 ms before any on a detonating cord downline.
immediately adjacent production blast holes. In trim blasting burdens are always greater than
The presplit face will be damaged or even destroyed spacings. Stemming lengths are typically 0.6 m to
if production blastholes are drilled too close to it. If 1.0 m for 51 mm to 89 mm blastholes.
the distance between the presplit and the adjacent Trim blasting does not usually give the spectacular
production blastholes is too great, however, rock will type of result often produced by presplitting, but it
be left in front of the presplit face. The best distance does give a considerable reduction in overbreak. Trim
between the presplit and the adjacent production blasting tends to give better results than presplitting
blastholes should be determined by trial; it is in weak or highly jointed rocks.
usually 1/3 to 1/2 of the normal burden for
production blastholes.

Chapter 9 Production Stoping 155


156 Orica Mining Services Safe and Efficient Blasting in Underground Metal Mines

You might also like