Professional Documents
Culture Documents
L3-019-HSE-02 Control of Floor Openings
L3-019-HSE-02 Control of Floor Openings
: L3-019-HSE-02
AZN Procedure
Rev. Date: 25-Dec-2018
Issue No Issue Date Revalidation
Control of Floor Openings
3 28-Jun-2015 24-Dec-2020 Page 2 of 8
Distribution List
Department/Section Recipient Department/Section Recipient
Management GM Stores All staff
Operations All staff Chemistry All staff
H.R. & Administration All staff Electrical All staff
I.T. All staff Mechanical All staff
Finance All staff Instrumentation & Control All staff
Procurement All staff Engineering All staff
H.S.E. All staff Performance All staff
Security All staff
Doc. No.: L3-019-HSE-02
AZN Procedure
Rev. Date: 25-Dec-2018
Issue No Issue Date Revalidation
Control of Floor Openings
3 28-Jun-2015 24-Dec-2020 Page 3 of 8
Revision Record
Revision
Issue No. Description of Change Effective date
No.
1 0 First issue 28/06/2015
2 1 Routine review 22/03/2018
3 2 Format Change 31/12/2018
Doc. No.: L3-019-HSE-02
AZN Procedure
Rev. Date: 25-Dec-2018
Issue No Issue Date Revalidation
Control of Floor Openings
3 28-Jun-2015 24-Dec-2020 Page 4 of 8
Contents
1.0 PURPOSE.................................................................................................................. 5
2.0 PRINCIPLE ................................................................................................................ 5
3.0 SCOPE....................................................................................................................... 5
4.0 RESPONSIBILITY ..................................................................................................... 5
5.0 DEFINITIONS/ ABBREVIATIONS ............................................................................. 5
6.0 REFERENCES ........................................................................................................... 5
7.0 HSE AND BUSINESS RISK....................................................................................... 5
8.0 PROCEDURE ............................................................................................................ 5
8.1 Flooring .................................................................................................................................. 5
8.2 Inspection ............................................................................................................................. 5
8.3 Permanent Floor Openings................................................................................................... 6
8.4 Temporary Floor Openings................................................................................................... 6
8.5 Temporary Floor Openings Lasting More Than One Working Day .................................... 7
8.6 Barriers .................................................................................................................................. 7
9.0 AUDIT / REVIEWS ..................................................................................................... 7
10.0 ATTACHMENTS ........................................................................................................ 7
CONTROL OF FLOOR OPENING CHECK LIST ......................................................................8
Doc. No.: L3-019-HSE-02
AZN Procedure
Rev. Date: 25-Dec-2018
Issue No Issue Date Revalidation
Control of Floor Openings
3 28-Jun-2015 24-Dec-2020 Page 5 of 8
1.0 PURPOSE
This procedure defines the requirements for the maintenance of floors and the control of floor
openings at AZN.
2.0 PRINCIPLE
Maintenance of floors, and control of openings in floors, roads and pathways so that risks to persons
are minimised. Handrails or guardrails permanently fitted to prevent access to machinery are not
included. Such rails or fencing must not be removed unless a Permit for Work is held.
3.0 SCOPE
Floor inspections will be carried out on all open mesh floor panels and all other types of floors,
passages and gangways during monthly safety walks. Loose, unsecured or missing sections and
broken, badly fitting or distorted sections must be replaced.
4.0 RESPONSIBILITY
It is the responsibility off all staff and contractors to report promptly any defects or issues associated
with flooring.
The Planning Engineer is responsible for ensuring a routine annual inspection of walkways, fixed
stairways and handrails is carried out.
6.0 REFERENCES
None
8.0 PROCEDURE
8.1 Flooring
Chequer plate and other metal sectional floors must have every section properly
supported and securely fastened to the supports and where necessary to adjacent
sections.
8.2 Inspection
The inspection of all plant flooring, grating and handrails on site is managed via the
site MMI system via Planned Maintenance WOCs.
Doc. No.: L3-019-HSE-02
AZN Procedure
Rev. Date: 25-Dec-2018
Issue No Issue Date Revalidation
Control of Floor Openings
3 28-Jun-2015 24-Dec-2020 Page 6 of 8
Any floor plates and gratings lifted should be refitted at every opportunity during the work,
to minimise exposure to the hazard.
On completion of work, the floor section will be replaced and all bolts and clips refitted
and checked by the work planner to ensure that it is safe before authorising the removal
of the barriers and notices. The temporary barriers and notices must be dismantled and
returned to their correct storage area.
The work planner will then inform the Shift Engineer of the safe replacement of the floor
opening.
Note - Where there is a temporary opening, the adjacent gratings must be clipped
down to ensure that they do not move to avoid creating a potential hazardous opening.
Doc. No.: L3-019-HSE-02
AZN Procedure
Rev. Date: 25-Dec-2018
Issue No Issue Date Revalidation
Control of Floor Openings
3 28-Jun-2015 24-Dec-2020 Page 7 of 8
8.5 Temporary Floor Openings Lasting More Than One Working Day
In addition to the requirements described in the previous section, if the Temporary Floor
Opening lasts more than one day the Control of Floor Openings Check List should be
used.
The checklist will be initiated and controlled by the work planner with records maintained
in the register. The register will consist of a unique number index (WOC number), an
active section and a completed section.
The work planner will complete Control of Floor Openings Check List and file it in the
active section of the register which will be maintained by the Main Control Room. The
work planner will be responsible for routine inspection of the barriers, notices and the floor
opening for as long as the floor opening exists and will record the inspections on the
Control of Floor Openings Check List kept in the register.
On the completion of the work, the work planner will then inform the Shift Engineer of
the safe replacement of the floor opening, complete part C of the Control of Floor
Openings Check List and file the form in the completed section of the register.
The Control of Floor Openings Check List should be completed at each stage and
signed off by the Shift Engineer.
8.6 Barriers
Barriers must be physically strong enough to restrain persons from falling into the
opening. Hazard warning tape should only be used to indicate the presence of a hazard,
never as a barrier or guard. Barriers must be erected as close as is practicable to the
edge of the opening so that there is no accessible floor area within the barrier. Approved
barriers must be used wherever possible, or a scaffolding barrier may be erected by
Competent Persons.
10.0 ATTACHMENTS
AZN/HSE/PROC/019 F1 Control of Floor Openings Check List
Issue: 1
Form
Ref: AZN/HSE/PROC/019 F1
Date 05/06/2015
Control of floor openings Page Page 8 of 8
Revalidation 05/06/2017
CONTROL OF FLOOR OPENING CHECK LIST
PART A (To be completed by person requesting a floor opening).
__________________________________________________________________________
PART B Inspection record. (To be completed by Technical Officer at a frequency decided with the
Shift Engineer at time of issue of the unique number- see part A).
I have reinstated the floor, cleared the barriers, returned the signs and informed the Shift Engineer.