A-36 Building

1. External Face Sandwich Panel / GI Sheet


Status: Gutters not Installed, Flashing not Installed, Leak Test remaining

2. MEP Works
Status: Ducting completed, Grills & Louvers remaining, Water supply network completed
only hose bibs remaining, AC Drain installed, AC Indoor units remaining, Drainage
completed

3. Installation of Doors, Windows, Furniture and Equipment


Status: Doors Installed, Windows remaining

Installation for 1st Stream (Ready for Operation)

1. GLS Tanks
Status: Completed

2. Cable Tray and Cable Pulling/Termination


Status: Electrical works remaining

3. Pretreatment Unit
Status: Pipe connections remaining, unit installed