You are on page 1of 1

P.W.

Ghana Limited
P W GHANA
Civil Engineering and Mining Contractors
Site Offices
Tema Port Stacking & Marshalling Area B
Ghana

METHOD STATEMENT – SECTION 2 (GENERAL)


PW/MS/10
Work Section: Pavement Structure
Activity: Construction of Pavement Quality Concrete – Dangerous Cargo Area
Prepared By: Solomon Adjasoo
Date: 10th February 2007

1. All work, materials and plant must be in accordance with the Employers Requirements.
2. All drawings in use for site work must be clearly marked ‘ISSUED FOR CONSTRUCTION’
3. All works must be within the tolerances stated in the Employer’s requirements.
4. All Works Must be carried out in accordance with the Method Statement – Section 1
5. All personnel should be suitably qualified and competent to carry out the work for which they are
employed.
6. The work must be carried out in accordance with the following approved I.F.C drawings: -
 PW/ABC/200
 PW/ABC/202
 PW/ABC/332
 PW/ABC/339
 PW/ABC/349
7. All concrete work must be in accordance with Section 10 of the Employers Requirements
8. The QC Management shall be in accordance with the Employers Requirements.

Signed……………………………………………. Project Manager

Page 1 of 1

You might also like