Bright Wash Ltd.

U-2
CORRECTIVE ACTION PLAN ASPER FISH BONE METHOD.
Date : April-2024,

PROBLEM PROCESS ROOT CAUSE CORRECTIVE ACTION DEADLINE RESPONSIBLE PERSON

Awareness given to operator & Supervisor to Immediat action ProductionManager


Manager/Quality
Inconsistent Ignorance by Operator
make the process perfectly.

Production Manager/Quality
Less Low quality paper Using proper emery paper based on fabic composition Immediat action Manager

Started training with operators to develop their own Immediat action ProductionManager
Manager/Quality
Uneven Lack of Training skill.
Bright wash Ltd. Unit -2
CORRECTIVE ACTION PLAN ASPER FISH BONE METHOD.
Date : April-2024, ( 2nd 10- Days )

PROBLEM PROCESS ROOT CAUSE CORRECTIVE ACTION DEADLINE RESPONSIBLE PERSON

Awareness given to operator & Supervisor to Immediat action ProductionManager


Manager/Quality
Inconsistent Ignorance by Operator
make the process perfectly.

Production Manager/Quality
Less Low quality paper Using proper emery paper based on fabic composition Immediat action Manager

Started training with operators to develop their own Immediat action ProductionManager
Manager/Quality
Uneven Lack of Training skill.
Bright Wash Ltd. Unit -2
CORRECTIVE ACTION PLAN ASPER FISH BONE METHOD.
Date : April-2024, ( 3rd 10- Days )

PROBLEM PROCESS ROOT CAUSE CORRECTIVE ACTION DEADLINE RESPONSIBLE PERSON

Awareness given to operator & Supervisor to Immediat action ProductionManager


Manager/Quality
Inconsistent Ignorance by Operator
make the process perfectly.

Production Manager/Quality
Less Low quality paper Using proper emery paper based on fabic composition Immediat action Manager

Started training with operators to develop their own Immediat action ProductionManager
Manager/Quality
Uneven Lack of Training skill.