AM/PM Conference
2016-17
1
MOU Achievement (Operations)
Parameter Unit Annual Tgt Prorata Tgt Ach Reason for Shortfall
2016-17 Apr-Mar17 Apr-Mar17
Third carousel works are under
progress. Civil and electrical
LPG Bottling Capacity
TMT 120 120 NIL works are under progress.
Augmentation Mechanical tender opened and
under finalization.
Out of circulation of LPG
cylinders - % of total % 0.15 0.14 0.09 )
cylinders bottled
Increase in Composite (Safety,
Security and M&I) Index of LPG No. >0.01 96.8 97.51
BPs
Rain water Harvesting at NIL
No. of
LPG BPs / Increase of RWH
Locations
Coverage
Star rating of LPG Bottling 100 100 100 Achieved L5
%
Plants
Cost per MT for LPG Bottling 5% 2017.39 1987.72 Reduction of 6.8 %
Rs./MT
Plants(ex R&M LPGC) reduction
Energy Audit of LPG Bottling NA
%
Plants
New In-house ST&P Facility Status of 1 1 1 Facility ready .PESO clearance
for Cylinders at LPG BPs Facility awaited.
6 RQC (Random Quality Check) 0.5% of bottling 0.5 0.768 0.5 1.152
3
KRA Performance
2015-16 Apr-March17
S.No. KRA Criteria Target Ach Target Ach
9 Training for the year 2016-17 As per OISD 154
4
Safety Index
Safety Index Major
S.No. Safety Index Action plan
achieved deviations
1 Ajmer BP 98.5
M&I Index
S. M&I Index Major
Plant Action plan
No. achieved deviations
1 Ajmer 96.02
5
Stock Loss
Apr16 to Mar
% of volume
Plant 17 cum. loss Reasons Action plan
handled (MTs)
(MT)
Ajmer 880.352 0.552% Gain
Scrap Disposal
Pending scrap
Plant Last disposal (Nos.) Date Value
disposal (Nos.)
6
PENDING INSPECTION POINTS OISD 3/70
SL Observations ESA Recommendations Original Present Status
Target
1 Yes, as per annexure, however 2 No. Hand gloves HSE ,HO is doing procurement of low
shortage of 2 Nos. low temp purchased. SAP indent temperature protective clothing
hand gloves and one no low
placed for low temp suit
temp suit have been found.
with HSE, HO. July 2017.
2 It has been observed that one Will be corrected / plugged July,2017 PT -technical bid opened and under
additional nozzle for draining during next Five Year testing evaluation(four bids)
has been provided on 2 Nos. which will be done during July
Above ground bullets in 2016, by advancing the hydro-
addition to liquid line nozzle testing dates to ensure
which is in contravention to compliance.
OISD144, Cl 6.2.2. These
additional nozzles have been
blinded with flange.
3 During audit in parking area, it Dedicated second crew should Dec-15 All the transporters have been advised to ensure
has been observed that Bulk be ensured with Bulk & packed dedicated second crew for their trucks vide letter
lorry drivers and packed lorry lorries and detail of drivers & no: AJM/LPG/SPM/11/04 dtd: 01.08.2018 and again
drivers are not having second crew should be entered vide letter dtd:24.08.2015,26.11.2015, 22.11.15 &
mandatory dedicated second in Gate register. 29.04.2016.. The transporters went on flash strike
crew. Details of driver & on 02.05.2016 but assured to provide cleaners
second crew is not being round the clock within 15 days.. after fervent follow-
entered at Gate register up by detaining trucks and withholding payments
six transporters have provided cleaners. Now no
truck being inducted/ replaced with dedicated
cleaner. Continuous follow-up is maintained.
PENDING INSPECTION POINTS MDT (9/24)
BM Available
Deployment
Category Strength Manpower Surplus/ Deficit Action Plan For Redeployment
Officers 14 14 14 0
PMCC 5 5 5 Nil
IN-HOUSE STP FACILITY
S. Item Status If No,
No. Target Date
Admin Approval
1 Yes
Obtained
Mechanically
5 Yes 31.03.2017
Completed
Trial of all the equipments
6 Commissioned Yes
done and commissioned.
16
NANO CUT FACILITY
Admin Approval
1 Obtained NA
2 Layout approval
3 PCB approval
3 Tenders Called
4 Order Placed
Mechanically
5
Completed
6 Commissioned
17
ENGG ACTIVITIES
S.
Item / Details Status Target
No.
Project Name
Commissioning of New
1 Commissioned on 13.03.2017.
LPG Pump 90 M3/Hr
Commissioning of New 6
2 Commissioned on 23.03.2017. -
bay TLD .
Commissioning of 100
3 CFM LPG Vapor Commissioned on 01.04.17 -
Compressor
18
ENGG ACTIVITIES
Civil Works Related To third carousel and Augmentation works
S Name Of The Site Status
No.
1 Paver Laying Job at TTPA a) Completed.
19
ENGG ACTIVITIES
Civil Works Related To Third Carousel and Augmentation Works
S Name Of The Site Status
No.
3 New Canteen Casting of footings up to plinth level has been completed. Bar
binding work is under progress.
4 New Engineering Excavation work for foundations has been completed. Bar
Store binding for footings and column is under progress.
5 50 KL U/G water Casting of PCC base of the tank is completed. RCC wall casting
collection sump. is under progress .
6 Associated utilities Two toilet blocks in licensed area are under construction.
7. Filling shed Contractor was advised to mark the column footings, Shifting
Extension of sprinkler riser pipe lines planned 14-16,April 17
8 Air comp Shed Excavation work for foundations done and base PCC has been
Extension laid.
20
ENGG ACTIVITIES
Civil Works Related To Third Carousel and Augmentation Works
S Name Of The Site Status
No.
9 750 KVA DG Drawing of the 750 KVA DG set has been given to party. The
foundation work of excavation is expected to start by 05.04.17.
10 New Entrance Soil filling work is under progress for leveling .
Gate
11 Service lane from The matter has been taken up with Ajmer DO for applying to
TTPA NHAI.
12
13
14
21
ENGG ACTIVITIES
Electrical Works Related To Third Carousel and Augmentation Works
1) Work Order for carrying out supply of electrical equipments and related electrical installation works
related to third carousel has been given to M/s Modern Electric vide WO: RSO/LPG-E/AJMBP/2016-17/PT-
01 Dated 19.12.2017.
2) So far M/s Modern Electric has obtained approvals on all GA / QAP/data sheets from consultant.
3) All the cables received at site on 17.03.2017. Party has been advised to start cable trenching job and cable
laying.
4) Excessive delay in commencing cable scanning works assured to start in 1st week of Feb'17 delayed by
more than 2 month. After repeated follow ups and reminders at last the one representative visited plant
on 03.03.2017 to carry out cable scanning survey. After that survey again the party is non responsive.
Foundation work for 750 KVA DG set etc are getting delayed due to this.
22
ENGG ACTIVITIES
(Details of uninstalled / non-commissioned procured equipments)
Target Date
S. Date of
Equipment of Action Plan
No. receipt
installation
Drawings of
foundation given to
1 750 KVA DG Set 23.02.2017 15.05.2017
work will start from
1st week of April,17
23
Energy audit done in March,16
25
ASSISTANCE REQUIRED
26