Project Description

o Number of Stories: B+ G+3 Floors


o Covered Area: 234,000 sft
o Retrofitting Designer: Dr. Qaiser Ali
o Design Consultancy Fee: 900,000/- PKR
o Retrofitting Execution Cost: 26,603,990/-PKR
o Project Duration: 07 Months
o Retrofitting Execution Start: 10-09-2018
o Retrofitting Execution End: 10-04-2019
Retrofitting Structural Elements

o RCC Columns Jacketing: 193 No.


o RCC Shearwall Jacketing: 85 No.
o CFRP Column Wrapping: 10 No.
Existing Layout Plan
Block-A Layout Plan
o 78 no. columns to be retrofitted by RCC Jacketing.
o 10 no. of columns to be retrofitted by CFRP.
o All shear walls (45) to be retrofitted by 6" RCC Jacketing.
Block- B Layout Plan
o 115 no. columns to be retrofitted by RCC Jacketing.
o All shear walls (40) to be retrofitted by 6" RCC Jacketing.
Cutting of Columns And Shear Walls
Cutting of Shear Walls
Steel Grouting of Column and Shear Wall
Dr. Qaiser Ali Inspection
Dr. Qaiser Team Checks Admixture For Mix
Design
Dr. Qaiser Team Checks Mix Design
Arrangements
Dr. Qaiser Team Checking Concrete Slump
Dr. Qaiser Team Visit & Checking Mix
Design Slump