Professional Documents
Culture Documents
Permit To Work System PI Training V3
Permit To Work System PI Training V3
Introducing:
• Sue – who has come to repair the toilet at Z Mana
• Fred – who has come to install new electrical socket
Authority:
• All Z employees, site representatives, contractors and workers, are
authorised to stop the work if there is a HSSE concern.
For example non-routine work is a work activity that is, but not limited to,
any of the below:
• Performed infrequently
Site Representative - the site person who confirms the site environment is
safe for the contractor to work; sign contractor on and off site via the
Work Clearance Form (WCF) e.g. Retail Site member, Z office member,
Construction Site Manager
Non-permitable:
• Medium Risk activities,
• Low Risk activities, and
• Deliveries
• Restricted Space
• Erection structures
Low Risk:
• Any other activity deemed low risk using Z’s risk matrix
• E.g. changing the washer on the tap
Deliveries:
• Delivery only services – drop off and pickup standard deliveries of
stock
• For example:
- Coca cola delivery to retail store or
- construction material to a stock pile on site
Certificates:
• A – Hot Work Certificate
• B – Confined Space Certificate
• C – Work at Height - roofs, canopies and temporary structures
• D – Excavation Certificate
• E – Isolation Certificate
• F – Tank Removal / Installation Certificate
• G – Demolition Certificate
• H – Overhead Crane Certificate
LIKELIHOOD A B C D E
Reporting and Mitigation Actions Injuries with severity up to first aid Medical treatment case , Lost work day cases resulting in Life-threatening consequences; Fatality or multiple or
cases. restricted work case, & lost work up to 21 days away from work. Permanent total disability (PTD) widespread long-term health
Health and
CRITICAL HIGH day cases resulting in up to 7 or injury with irreversible health impacts.
injury
Further treatment should be Further treatment should be days away from work. problems resulting from injury or
considered immediately. Consider considered. High risks must Little damage or threat to Minor health effect, fully Diagnosed occupational illness occupational illness.
ceasing operations created by the be reported to the Executive health. reversible in the short term case, irreversible damage to
risk or revise the strategy to increase as soon as possible after it health; long-term disabilites.
the opportunity for treatment. has been identified.
Loss of containment (LOC) or loss Loss of containment (LOC) or loss Loss of containment (LOC) or loss Loss of containment (LOC) or loss
Critical risks must be reported to the
of primary containment (LOPC) of primary containment (LOPC) of primary containment (LOPC) of primary containment (LOPC)
Environmental impact
Report Medium residual risks up be accepted. Acceptable $100K except when process - $1M (except when process $10M (except when process - $50M (except when process $50M
through the management chain to risks do not require treatment; safety related) safety related) safety related) safety related)
the appropriate Operational however the controls,
Manager. Risk mitigation actions are procedures and practices will Tier 2 process safety incident Tier 1 process safety incident
to be developed or introduce need periodic monitoring to Incident results in temporary Temporary loss of local Loss of major infrastructure for Loss of major infrastructure for a Loss of major infrastructure for a
sufficient controls to lower risk level as ensure that the level of the shutdown of infrastructure for less infrastructure (less than a week) period of 1 month. period of greater than 1 month period greater than 3 months
soon as possible. risk has not changed. than 4 hours. and less than 3 months.
SWMS/JSA Hierarchy of Controls
Self Permits
• No one is allowed to issue a Permit to themselves
Remote Permits
A remote Permit can ONLY be issued if ALL of the following criteria
is satisfied:
- The PI has knowledge of the site or has reliable drawings
and site data
- The PI has a detailed knowledge of the task and activities
to be permitted
- The PI has experience working with the Contractor and
individual PH.
- The Z senior permit issuer or delegate confirms remote
permitting is appropriate and the above criteria have
been met.
Contractor Permitting
• A PI may issue a Permit to another person in the same Contractor
organisation.
Blanket Permits
• Blanket Permits are not permitted.
Derogations and standard operating procedure approval
• SOP more appropriate for repetitive, routine activities.
• Refer to PTWS Manual for procedure to obtain derogation approval
Changes in Conditions
PTWS Training
• www.z.co.nz/ptwinfo
Contacts
• Neil.Moon@z.co.nz
• Tracy.evans-tracy@z.co.nz
Introducing:
• Sue – who has come to repair the toilet at Z Mana
• Fred – who has come to install new electrical socket