You are on page 1of 1

Hazardous Spray Exercise

Initial Conditions: Thursday, January 3, 10:35 control room and talked to the Shift Both rinsed the fluid off their skin.
AM. Normal plant operations. Removal and Supervisor. He gave them permission to
The Unit Operator notified the Shift
replacement of Line “A” pressure detector install the new A2 detector and told them to
Supervisor of the problem who had the two
number 2 on Tank G1036 was in progress. inform the Unit Operator about the
pipefitters report to the site first-aid station.
replacement.
Description of Incident: Two pressure The pipefitters were referred to the county
detectors (to provide a redundant capacity) are They then went to the unit, found the Unit hospital where they were observed overnight
available on each of three feed inlet lines. Operator (making hourly reading checks) and released the next morning.
Pressure detector number 2 on Line “A” failed and informed him that they were there to
Both pipefitters were wearing safety glasses
low at 10:15 PM on Wednesday, January 2. replace detector A2. The Unit Operator said
but not full face shields nor protective gloves
Maintenance and Operations management that he told them the off-going shift had
as required by SDS. One received first
decided to replace the detector with a pre- drained the system and that it was ready for
degree burns to his face and hands. The
calibrated spare during the day shift on work. The Unit Operator did not go to the
other received a first degree burn to one
Thursday. work site and review the work with the
hand. Both returned to work the next day on
pipefitters (required by plant policy).
The midnight-shift Unit Operator prepared the a restricted work basis.
work request and tagout for detector A2 and had The pipefitters then went to the detector
Further investigation showed that the
it authorized by the midnight-shift Shift platform (an elevated platform that provides
detectors were not within sight of the locked-
Supervisor. The midnight-shift Unit Operator easy access to the detectors which are
out isolation valves (isolation valves were at
says that on Thursday, she isolated detector A2, approximately 10 feet above floor level) and
floor level underneath the platform), there
drained the hazardous fluid into an approved began to loosen the detector's connecting
were no equipment identification labels on
container, and placed appropriate isolation tags flange bolts. They did not hang their own
the detectors, and the senior pipefitter, who
and locks on the A2 isolation valves. She then locks or tags on the isolation valves or trace
was familiar with this type of unit, said he
called the Shift Supervisor and informed him the lines (required by plant policy). When
thought he was disconnecting detector A2
that detector A2 was ready for removal and the third bolt was about three turns loose
because he believed the detector
replacement. (they had already removed two of four bolts),
arrangement was the same as the "identical
hazardous material began spraying from the
At 8:00 AM shift turnover occurred. The day-shift units" he was used to working on. However,
flange onto the pipefitters. They re-
Unit Operator and Shift Supervisor were told he disconnected detector A1 instead of A2
tightened the third bolt, but the spray
detector A2 was ready for removal and because the arrangement is backward to the
continued until one of the previously
replacement. The day-shift Shift Supervisor other "identical units". The company’s line
removed bolts was inserted and tightened.
contacted the Maintenance Foreman to get the break policy requires pipefitters to loosen all
Overall, the spray lasted about one to two
work started. The Maintenance Foreman bolts and break the line away from them
minutes.
assigned two pipefitters to the job. before they remove any bolts.
The Unit Operator, who had just come by,
At 10:00 AM, the two pipefitters arrived at the
took them to a nearby eyewash and wash
down station.

You might also like