LOTO
PROGRAM
2013 - Rev1
CONTENT
1. Objectives
2. Applicable reference documentation
3. Definitions and responsibilities
4. Preparation of LOTO process on site
5. Specific LOTO areas
6. LOTO process
7. Obligations
8. Authorized material
9. Manual of ‘Permit To Work in LOTO Area’
Objectives and
applicable reference
documentation
1 – OBJECTIVES OF LOTO PROGRAM
This program was designed to prevent injuries and damages caused by energization,
unexpected start-up or release of hazardous energy during all the steps of a project
(construction, pre-commissioning, commissioning or maintenance).
2 – APPLICABLE REFERENCE
DOCUMENTATION
GE LOTO Procedures: GE Energy – Construction EHS Plan – Module 7 Rev.2
Definitions
&
Responsibilities
3 – DEFINITIONS ET RESPONSIBILITIES
3.1 – Remind of some definitions and rules of LOTO Program
(cf. GE Energy - Construction EHS PLAN – Module 7 – Rev2 / 2. Definitions)
Dissipation
The process of removing stored energy from a machine, equipment, process or circuit. The energy source steadily
declines to a zero value after the energy source has been shut off and locked.
De-energization
Physical isolation from all energy sources and not containing residual or stored energy. A zero energy state is
verified as existing.
Site Manager
Has overall responsibility for site safety within GE Scope of the project, and for all GE/contractor personnel on site
Will order stoppage of any work performed in an unsafe manner
Will order corrective actions for any unsafe condition
Approved roles and responsibilities
Will order the review and issuance of revised LOTO procedures.
Will assign the responsibility for weekly LOTO inspections of the LOTO log and procedures.
EHS Manager
He shall be knowledgeable in the specific plant systems that they have responsibility for.
He may physically operate all necessary devices to isolate the equipment or system and attach all locking devices and
tags to the systems and equipments that have been assigned to him .
He Employee is trained in the practice of LOTO. The System Authorized Employee shall ensure that all Affected
Employees are notified of activities within their respective areas or on equipment under their scope of control/operation.
He can be the LOTO officer.
LOTO Officer
LOTO Administrator
He shall be responsible for maintenance of LOTO documentation including, the Logbook, the LOTO index, active and
inactive LOTO Work Permit. He shall monitor active LOTOs for compliance with the procedure.
He received all LOTO Program Trainings.
LOTO Trainer
He shall create and develop specific LOTO training template under control of Commissioning Manager.
He shall train Affected, Authorized, Lead Authorized, System authorized workers to the site specificities.
He updates training files.
Lead Authorized Employee
Authorized Employee
Affected Employee
An Affected Employee is an employee whose job requires him/her to be in an area where work is being performed
under LOTO. Any site personnel who even work in the general vicinity of equipment or systems under LOTO must be
trained as an Affected Employee.
Reference
Step Appendix Documentation Link
1 A LOTO Protocol
A site map that identifies all high risk areas is updated and posted.
Example: this site map carte represents all high risk areas.
All these areas including forbidden areas and dangers associated are
clearly identified with pictograms.
If an area is not defined as “high risk area”, no LOTO procedure are
required.
If change, a daily update of this plan is done with a written
acknowledgment signed by GE (Commissioning Manager and EHS
Manager)
Each entry of a person in high risk area requires a LOTO work permit.
All implicated persons in a LOTO work permit are named and their trainings/certifications verified.
Support function persons (quality, EHS…) who want an access to all areas are named by the Site Manager after
completing all required trainings.
LOTO Process
Tasks 1 Task planning with risk assessment
+ Risk assessment associated by Lead authorized employee (GE
supervisor) and the performer.
1
2 If the task is located in specific high risk
Task must be LOTO area, a request of LOTO work permit is
realized in specific high risk
LOTO area ? done by the Lead authorized employee.
IMPORTANT !!!
On activity location:
Work permit and risk assessment are available and directly accessible.
• Weekly LOTO/EHS inspection will be done during the pre-comissioning and the commissioning.
Obligations
7 – Obligations
A One only key per padlock. A padlock refers to one permit only.
B One tag per padlock indicating the lock number, the permit number, the reference of
equipment locked, its lock position (open/closed) and the name of the System Authorized
Employee.
C Copies of “LOTO work permit” and risk assessment are directly available in the concerned
work places and the original is in the LOTO Administrator office.
D All parts of the permit are correctly and clearly fulfilled and all requirements are respected.
E The “LOTO work permit” are required for all activities which take place in high risk area
(energy…). The oral instructions are forbidden (lock and tag, remove padlock and tag,
startup…)
F The presence of employees and the equipments are checked/controlled after the work
completion. The work completion confirmation on permit is signed by all concerned
employee and all copies have to be transferred to the LOTO Administrator before the
authorization of removing padlock and tags.
G Traceability of LOTO work permit and padlocks including their location on equipment.
(Logbook is permanently updated)
H If LOTO Program can’t be applied, works can’t be authorized. EHS and Commissioning
department must be informed as soon as possible in order to find and validate an
alternative.
Authorized material
&
Keys management
8.1 – Authorized Material
Usual LOTO material Specific material
HASP
Breakers
LockBox
8.2 – Keys management
LOTO keys are always under supervision.
The Commissioning Manager has the final responsibility of the keys.
Once the Padlocks are placed on site, the associated keys are immediately placed in LockBox that is in
accordance with GE requirements.
Either LockBoxes are given to the Commissioning Manager or the keys of LockBoxes (in that
case be careful of traceability in LogBook)
Or the padlock keys are given to Commissioning Manager who stores them in a specific LOTO
cabinet. The Commissioning Manager is the only person who has the only key of this LOTO
cabinet (possibly his deputy can have the key in case of team working (day/night)).
It is STRICTLY forbidden for anybody (including LOTO Officer, System Authorized Employee
and Commissioning Manager) to move with keys which are not in a LockBox in accordance with
GE requirements.
Presentation of Permit to
Work in LOTO Area
9 – Presentation of work permit g Permit to Work
in LOTO Are a
Site :
Unit :
for Work
for Te st
Date / Time :
Expiry date of the permit Number
Permit Re que st
Fluid No Yes : Pre ssure No Yes : 0 EHS Manage r Approval
Heading Voltage
Fire
No
No
Yes :
Yes :
Chimical No
Mechanica l No
Yes :
Yes :
Initials + Visa
Pe rmits
Confined S. Yes - n° Yes - n°
Identification of companies impacte d by work
Hot Work Yes - n° Yes - n°
Repre sentant of
Impa cte d : 1 Approval for be ginning the LOTO process
Compa ny the company Function Visa
YES / NO
(name) LOTO re quire d YES NON
Commissioning
Initia ls Date /Time Visa
Ma nage r
Permit request If your activity is impacted, ple ase list all the what lockout device s are
require d
S ys te m
Autho rize d
Em plo ye e
Initia ls Date /Time Visa
Da te / Time
Identification of dangers
Coactivity Nom / Initials
Da te / heure
Nom / Initiales
Visa
g Pe rmit to Work
in LOTO Are a
Site :
Unit :
for Work
for Te st
Expiry date of the pe rmit
Date / Time :
Number
Fill date and time of permit request (not the beginning of work)
Fill the foreseeable duration of work
Fill the name of companies and the number of workers who will carry out the task concerned by this permit
Indicate the name of Lead Authorized person of each team (day and night)
Indicate the name of the execution responsible (usually the subcontractor supervisor) of each team.
Indicate the number of JSA ‘Job Safety assessment” (risk assessment) associated to the work.
Indicate the system and/or the equipment impacted or that can impact on the work to be performed.
Describe shortly and clearly what work will be performed.
Identification of dangers To be filled by the Commissioning
Coactivity
Lockout devices Manager and the System Identification of dangers
If several companies are responsible of equipment or system, they have to If your activity is impacted, please list all the what lockout devices are
indicate if they will be impacted by the work associated to this permit. required
Details of lockout devices and intructions
Otherwise, the companies have to lock and tag or give instructions so that
N° Ide ntifica tion Condition/state Padlock N°
the wok can be performed safely.
Remind: The oral instructions are forbidden. They have to be
communicated following the LOTO Process.
Initia ls + Visa
P e r m it s
0/ The EHS managers of each team verify the validation of risk assessment and Confine d S. Ye s - n° Ye s - n°
work permits associated, then they give their approval for their respective team. Hot Work Ye s - n° Ye s - n°
1 Approval for be ginning the LOTO proce ss
1/ The commissioning Manager and the System Authorized Employee indicate if LOTO re quire d YES NON
lockouts devices are required, define them (cf previous page), then authorize the Commissioning
Initia ls Da te / Time Visa
Ma na ge r
activation of LOTO to LOTO Officer and the start of work; S ys te m
Autho rize d Initia ls Da te / Time Visa
Em plo ye e
2/ The LOTO Officer locks out systems and equipments indicated by the System 2 LOTO applie d by LOTO Office r
Authorized Employee and the Commissioning Manager. LOTO Office r 1 Initia ls Da te / Time Visa
An other LOTO Officer check if lockout and tag are correctly installed. LOTO Office r 2
(in c ha rge o f Initia ls Da te / Time Visa
c he c k)
3/ When the 3 previous parts of the LOTO Permit are validated, the Lead Authorized 3 Pe rmit re ce ption by Le ad Authorize d Employe e
Employee can get the copy of work permit associated to his team. Da te / Time
Nom / Initia ls
4/ When work has been completed, each Lead Authorized Employee indicates it on
the permit and signs the declaration of work completion associated to his team. Visa
Visa
6/ The LOTO Officer removes all lockout devices and validates it on the permit.
5 Re moval of LOTO de vice s authorization
Commissioning
Initia ls Da te / Time Visa
7/ The LOTO Administrator closes the permit. Ma na ge r
S ys te m
Autho rize d Initia ls Da te / Time Visa
Em plo ye e
6 Re moval of LOTO de vice s done by LOTO Office r