2nd Quarterly Presentation

MENTOR PRESENTED BY
Sri. SANTANU BATSHAV BHUYAN KAMAL SINGH BISHT
DGM OGPS (S/R) Sr.Engg. (OGPS)
Departments Covered

Commissioning and Workover Section


WSS and ALP Section
COMMISSIONING & WORKOVER SECTION
08th August- 07th October
Activities Witness at C&WO Section:

Activity Locations Activity Locations

Spool Testing HZH,HZE Well Kiling NHK#340,135,


WBM#01,HXO,
NHK#619,DIK
Casing Integrity HZE Packer Unsetting NHK#207,579,36
WBM#01
Test
Packer Setting HW-TNL#07, Fluid Level NHK#207,036
TML#01,MKL#01
HYD-DIK,DBY#820
Measurement

Well Testing & TAG,MKL#01, Well Activation TINALI#07,DBY#


HZH,NHK#340,394, 820
Well Control 407, WBM#01
(NPU, Gas Shot)
WELLHEAD
Wellhead and
X-mass tree
Spool Test
Spool Testing:
Well no.: HZH (5000psi)

Procedure:

1 ●
Final cut of 4¼ʺ is given to 5½ʺ casing.

2 ●
Primary seal and ring gasket is placed.

3 Tubing spool is placed and studs are


Space between primary


● tightened.
and

4 secondary seal is pressurised


up to 80% (4000psi) of rated
capacity.
Casing Integrity Test (Hermetical Test):
Casing integrity test refers to closed cycle pressure
testing of casing.
It is carried out by pumping fluid to detect leakage in
production casing.
Well no.:HZH (5000 psi)
Procedure:
1 ●
Line testing is done at a pressure of 3500 psi.

2 ●
Topped up the annulus of 9 ⅝ʺ and 5½ʺ casing and tubing.

3 ●
Pressurised the 5½ʺ casing up to 3000 psi.

4

No displacement is observed in the annulus
and no pressure drop is detected in the
recorder chart .Test completed successfully.
WELL KILLING:

It is an operation to place a column of fluid inside the


well bore which has a hydrostatic head equal to or
greater than the formation pressure to prevent any
inflow to the well bore.

NEED FOR KILLING:


 For the work over of the well if the well falls sick.
 On safety consideration , due to damage of well head
by miscreants.
 For abandonment of the well.
 For any other well intervention involving work over.
WELL KILLING

BULL Pumping the kill fluid directly down the wellbore


HEADING forcing the well bore fluids back into the reservoir.

FORWARD Kill fluid is pumped into the production tubing and


CIRCULATION circulating out through the annulus.

REVERSE Pumping the kill fluid down the annulus of the well and
CIRCULATION circulating out through tubing.

LUBRICATION Kill fluid pumped into well bore in small quantities


AND BLEED after some time migrated fluids bleed from tubing.
Oil well killing setup

X-MASS TREE

Pump

CHECK VALVE

Suction
Tank
RETURN LINE
GROUND
XMT EFFLUENT PIT
Gas Flare OCS

STORAGE TANKS
10K Well Head Isolation Valve

Kill Manifold

Heat Exchanger

Kill Pump

Choke Manifold

Salt Solution/
Mud Tank

Test Separator

Pilot/ Returns Tank

Gas Well Killing Schematic


Gas Flare
FIELD VISIT: GAS WELL KILLING
(Loc.: HXO)

SITP = 2400 psi SICP = 400psi


Kill Fluid –70 pcf NaCl solution
Steps:
1. The kill line was hydraulically pressure tested at 3000psi.
2. Tried to bleed tubing and casing pressure to zero but was unsuccessful.
3. Started pumping operation by pumping water(18 bbls) and take return to
attank via steam jacket.
4. Then kill fluid was pumped through casing (reverse circulation) @1000 psi.
5. After pumping 208 bbls (190+18), same weight solution was found to return.
6. Tubing and casing pressure down to zero after pumping was stopped.
7. Well was observed for half an hour & found no displacement.
WSS & ALP Section
08th October- 07th November
Coiled Tubing Unit

A well servicing unit comprising of a continuously spooled high fatigue


strength steel tubing that is spooled onto a reel and can be injected or
pulled out of a well under high pressure through a stripper.
Coiled Tubing Unit

CONTROL CABIN COILED TUBING CRANE GUIDE ARC

INJECTOR

STRIPPER

BOP
REEL
Applications of CTU

Sand Removal

Well Activation with NPU

Acidization

Dewaxing with Hot Oil Unit

Fish Removal

Perforation, Logging, Well Killing

Setting of Packer , Bridge Plug (Advanced Application)


Artificial Lift

 Artificial lift is a technique used to bring oil from the reservoir to the surface
because of decreasing reservoir pressure.

 In order to be able to produce the fluids to surface, energy must be


introduced or transported downhole to the fluids, to help lift them to the
surface and overcome the flowline pressure.
SURFACE PUMPING UNIT FOR SUCKER ROD PUMP
Walking
Beam

Horsehead
Equalizer and
Equalizer Bearing
Saddle
Briddle wire Bearing Counterweight Balance
Pitman
Arm

Carrier Bar + Rod


Crank
Rotator Hanger
Gear
Assembly
Box Wrist Pin

Polished Rod
Belt

Stuffing Box Samson


Post

Wellhead
Setup
Surface Pumping Unit

Wellhead Setup
Polished Rod

Tubing

Sucker Rod String

Sucker Rod Pump


Inside Tubing
SUCKER ROD

PLUNGER
Basic Components of
the Sucker Rod Pump TRAVELING VALVE

BARREL TUBE

STANDING VALVE

HOLD DOWN
THANK YOU