Guinea Dasheng Railway Signal System Project

Project Background

Dasheng Railway is located in the Bokai and Jindia districts in northwestern Guinea. The
starting point of the line is at the port of Dabilon in the Bokai region and ends at the
Shengtu mining area in the Jindia district. It is 112 kilometers in length and has 6 stations,
which is an important infrastructure for bauxite mining enterprises along the way
Project Organisation Structure

Project Manger: Commercial Manager: Configuration Manager: Risk Manager: Quality Manager:
Financial Controller:
Peibin Li Chuyue Ding Yiyang Wang Qizhi Ying Yifeng Sun
Bo Shi
Responsible for the Responsible for selecting and Responsible for various Responsible for formulating
Responsible for cost manage- Responsible for organising the establish-
planning and execution negotiating with suppliers, risks identification and quality implementation
ment, spend control, bank ment of quality management system,
of purchase contracts signing, analysation , developi standard, inspecting the
accounts setup, customers product quality inspection standard setup.
project , supervising odered items tracking and ng risk management project quality in process and
the work of other payment ensurment
checking, supervising inventory controls and
members contingency plans making solutions for quality
accidents
Project Cycle Division

Compile Complete
WBS and material
responsibility procurement
distribution and material
matrix delivery

Initiation Designing Construction

Planning Purchasing
Complete Construction safety
Determine procurement training,
equipment
the scope and technical
installation,
specifications and
time of the commissioning , trial
construction operation and
project drawings acceptance.