TYPES OF ESTIMATES ASAP

2. Detailed Estimate
Prepared for Tendering Purposes with almost 90%
accuracy of Project Cost
Detailed estimate should be accompanied with
i) Project Report
ii) Drawings (plans, elevation, sections)
iii) Specification
iv) Design charts and calculations
v) Standard schedule of Rates.
vi) Estimated Bill of Quantities
vii) Abstract of Costs

Dr. Bandana Jha, Professor, bjha@amity.edu 2


DETAILED ESTIMATES ASAP

Preparation of Detailed Estimate consists of :

i)Measurement & Calculation of Quantities of


materials

ii)Abstract of Estimated Cost

Dr. Bandana Jha, Professor, bjha@amity.edu 3


DETAILED ESTIMATES ASAP

Measurement & Calculation of Quantities of


materials requires:

i)Working Drawings with


- Detailed Dimensions
- Specifications

ii)Measurement Form
S.No Item Unit No. Length Breadth Height Total
Description Quantity

Dr. Bandana Jha, Professor, bjha@amity.edu 4


DETAILED ESTIMATES ASAP

Abstract of Estimate Calculation Requires:

i)Local Schedule of Item Rates based on


Specifications

ii)Abstract of Estimate Form Format:

Item Item Unit Quantity Rate Amount


No Description

Dr. Bandana Jha, Professor, bjha@amity.edu 5


TYPES OF ESTIMATES ASAP

Methods of Detailed Estimating

- Work Break Down / Bottom Up Method

- Final Abstract of Estimate

- Annual Repair Estimate

Dr. Bandana Jha, Professor, bjha@amity.edu 6


METHODS OF DETAILED ESTIMATES
ASAP

Work Break Down / Bottom Up Method

Work Breakdown Structure (WBS) is developed


during the planning stage of the project
Estimates are created for all tasks at the lowest level
of the WBS
These are accumulated to determine the estimates
for the whole project.
Bottom-up method is considered to be the most
accurate method for generating project estimates.
Determines budget or definitive estimates during the
planning phase and at the project start stage
Dr. Bandana Jha, Professor, bjha@amity.edu 7
SCHEDULE OF RATES ASAP

Dr. Bandana Jha, Professor, bjha@amity.edu 8


SCHEDULE OF RATES ASAP

Delhi Schedule of Rates 2018

Published by Central Public Works Department


The cost of each item of work is worked out from
the quantities that already computed in the details
measurement form at workable rate.
The total cost is worked out in the prescribed form
is known as abstract of estimated form.
10-15%of estimated Cost is allowed for Petty
Supervision, contingencies and Unforeseen items

Dr. Bandana Jha, Professor, bjha@amity.edu 9


METHODS OF DETAILED ESTIMATES
ASAP

Abstract Estimate

An Abstract summary of all estimates based on


WBS is prepared for generating final project
estimates.
Cost of each item of work is calculated from the
quantities that already computed in the detailed
measurement form at workable/published rate.
Total cost is worked out in a prescribed form known
as abstract of estimated form.
10-15%of estimated Cost is allowed for Petty
Supervision, contingencies and Unforeseen items
Dr. Bandana Jha, Professor, bjha@amity.edu 10
SCHEDULE OF RATES ASAP

Dr. Bandana Jha, Professor, bjha@amity.edu 11


ASSIGNMENT 2 ASAP

a) Make a list of 25 Construction items and


submit their unit of Measurement.
b) Draw the section of a Brick Wall of a single
storied building from “Foundation to Roof
Level”. Label the general specification of each
item of works in the section.

Dr. Bandana Jha, Professor, bjha@amity.edu 12


ASAP

REFERENCES
1. The Advanced Learner’s Dictionary of
Current English, Oxford, 1952, p. 1069.
2. L.V. Redman and A.V.H. Mory, The Romance
of Research, 1923, p.10. 3
3. The Encyclopaedia of Social Sciences, Vol.
IX, MacMillan, 1930.

Dr. Bandana Jha, Professor, bjha@amity.edu 13