Professional Documents
Culture Documents
GROUP TECHNLOGY
PART CLASSIFICATION AND CODING
OPTIZ
MICLASS
Grouping of operations
8
Part Families
A part family is a collection of parts which are similar based on design
attributes (such as geometric shape and size) or manufacturing attributes
(the sequence of processing steps required in their manufacture)
It possible for parts in the same family to be very similar in design yet radically
different in the area of production requirements. The opposite may also be true.
The parts, which are similar in their design characteristics, are grouped in a
family referred to as a design part family.
The part, which are similar in their manufacturing characteristics, are groped in
a family referred to as a manufacturing part family.
1. Visual inspection.
2. Route sheet analysis.
3. Parts classification and coding system.
1. Visual inspection
• Simplest method.
• Least sophisticated method.
• Least accurate method.
• Especially for grouping parts by design attributes.
• Classification of parts by physical parts or photographs.
Visual Inspection Method
• The most widely used method for grouping parts is the parts
classification and coding method.
• Parts similarities
1. Design Attributes
2. Manufacturing Attributes
Part Classification and Coding
• Reasons are…
Design retrieval:
“A simple change in an existing part would take much less
time than designing a whole new part from scratch.”
• Difficult to construct.
Mechanical
321X 323X
322X Transmission
UNF thread
• One advantage of a poly code over a mono code is that parts with a
specific characteristics can be readily identified.
Material Handling
Reduction in work part move and waiting time
Production and inventory control:
Production scheduling is simplified.
Grouping of parts into families and machines into cells reduces the
complexity.
Reduction in production lead time (70%), work in process (62%)
and late deliveries (82%).
Employee Satisfaction
Machine cell allows parts to be processed from raw material to finished
state by small group of workers.
Cultivate an improved worker attitude and higher level of job
satisfaction.
The next problem is to organize the machines into the most logical arrangement.
Let us describe two simple yet effective methods suggested by Hollier.
Both methods use data contained in From-To charts and are intended to arrange the
machines in an order that maximizes the proportion of in-sequence moves within the
cell.
Hollier Method 1
The first method uses the sums of flow "From" and "To" each
machine in the cell.
1. Develop the From-To chart from part routing data. The data contained in the
chart indicates numbers of part moves between the machines (or workstations) in the
cell. Moves into and out of the cell are not included in the chart.
2. Determine the "From" and "To" sums for each machine. This is
accomplished by summing all of the "From" trips and "To" trips for each
machine (or operation). The "From" sum for a machine is determined by
adding the entries in the corresponding row, and the "To" sum is found by
adding the entries in the corresponding column.
4. Reformat the From-To chart. After each machine has been selected,
restructure the From-To chart by eliminating the row and column
corresponding to the selected machine and recalculate the "From" and "To"
sums.
Repeat steps 3 and 4 until all machines have been assigned.
Group Technology Machine Sequence using Hollier Method 1
1. Develop the From-To chart. This is the same step as in Hollier Method 1.
Flow diagram for machine cell in Examples. Flow of parts into and out of
the cells has also been included.
Two performance measures can be defined to compare solutions to the machine
sequencing problem:
(1) percentage of in-sequence moves and
(2) percentage of backtracking moves.
The percentage of in-sequence moves is computed by adding all of the values
representing in-sequence moves and dividing by the total number of moves.
The percentage of backtracking moves is determined by summing all of the
values representing backtracking moves and dividing by the total number of
moves.
Computer-Aided Process Planning (CAPP)
What is Process planning?
• Process planning is concerned with determining the machine tools and the
sequence of manufacturing operations involved in the manufacture of the part
or product.
• The process planner to be familiar with the shop practice and equipment
capabilities.
95
PROCESS PLAN OR ROUTE SHEET
Examples of process plan (route sheet)
Route Sheet by: T.C. Chang
97
Traditional process planning
Process planning procedure is dependent on the experience and
judgment of manufacturing engineers or industrial engineers
98
Computer Aided Process Planning (CAPP) can be defined as the
functions which use computers to assist the work of process planners
Two approaches to CAPP are
CAPP System
• Retrieval-type (or variant systems) CAPP systems
• Generative type CAPP systems
Standard plans are then stored in a data base and indexed by family
matrices.
The operation stage occurs when the
system is ready for production.
Then, a standard process plan can be shared by the entire family. Minimum
modification on the standard plan will be required for such family members.
There are three approaches to construct a data base: hierarchical, network, and
relational.
(iii) Search Procedure
The principle of a variant system is to retrieve process plans for similar
components.
The search for a process plan is based on the search of a part family to which the
component belongs.
When, the part family is found, the associated standard plan can then be
retrieved.
A family matrix search can be seen as the matching of the family with a given
code.
Family matrices can be considered as masks. Whenever, a code can pass through
a mask successfully, the family is identified.
There are two types of plan editing: One is the editing of the standard plan itself
in the data base, and the other is editing of the plan for the component.
For editing a standard plan, the structure of the data base must be flexible enough
for expansion, additions, and deletions of the data records.
Cont..
Disadvantages
• The components to be planned are limited to previously planned similar
components.
• Experienced process planners are still required to modify the standard
plan for the specific component.
• Details of the plan cannot be generated.
• Variant planning cannot be used in an entirely automated
manufacturing system, without additional process planning.
106
Example of Retrieval type process planning systems
CAM-I CAPP-Retrieval type
Generative Approach for computer aided process planning
Generative process planning is a system that synthesizes process
information in order to create a process plan for a new component
automatically.
Upon receiving the design model, the system can generate the required
operations and operation sequences for the component.
112
To generate a universal process planning system, variables such as process
limitations, and capabilities, process costs, must be defined at the planning stage.
The path taken represents the sequence of processes. For example, the
initial state is the raw material and the final state is the component
design.
In forward planning, the steps to obtain the final surface with the desirable
attributes must be carefully planned to guarantee the result.
On the other hand, backward planning starts with the final requirements
and searches for the initial condition.
Geometry based, defines all the geometric features, feature sizes and
locations and tolerances.
Using a CAD model as input to a process planning system can eliminate the human effort
of translating a design into code and other descriptive form.
Additional code is needed to convert the machined surface shape from raw material shape.
Several other systems such as GENPLAN, AUTOPLAN, etc., also use a CAD database
interactively for tool and fixture selection.
The decision logic determines how a process or processes are selected. The
major function of the decision logic is to match the process capabilities with the
design specification.
(v) CAPP BASED ON ARTIFICIAL INTELLIGENCE (AI)
On the other hand, the knowledge of processes defines how the component can
be changed by processes (procedural knowledge).
Procedural knowledge can be represented by IF (condition), THEN
(action) statements which are similar to decision trees or decision tables. In
AI such rules can be called production rules.
Even after the descriptive and procedural knowledge have been represented,
conclusions cannot be deduced, because we do not have mechanism to apply
the appropriate rules to the problem.
125
Production planning and control
All manufacturing and service operations require planning and controlling
• To ensure that manufacturing run effectively and efficiently and
produces products as required by customers.
Forecasting Purchasing
Production planning Machine loading and scheduling
Process planning Dispatching
Estimating Expediting
Master Scheduling Quality control
Requirements planning Shipping and inventory control
Forecasting
Projecting or predicting the future sales activity of the firm’s products
• Long-range forecasts – Plant construction and equipment acquisition
- Appropriate amount of capacity to meet the market demand in the future
- Provides human resource capabilities, technology and plant locations.
• Intermediate-range forecasts – Long lead materials and components
- Matching supply and demand in terms of both volume and product
mix
- Planning for the right logistics.
• Short-term forecasts – Decisions on personal, purchasing and production
scheduling
- Involves time, people, material, equipment and facilities.
- Involves people working on the right things.
- Involves tracking the use of resources and execution results.
- Provide problem-solving support.
Cont..
Production planning (Aggregate production planning)
• Technique of foreseeing every step in a long series of separate operations, each
step to be taken at the right time and in the right place and each operation
to be performed in maximum efficiency.
• Fully load facilities and minimize overloading and under loading, make sure
enough capacity available to satisfy expected demand.
• Stabilize production over the production horizon and allow for launching of
new products into the company product line.
Estimating
•Determining prices, predicting costs and preparing schedules.
• Estimates manufacturing lead times and production costs.
Master scheduling
• Aggregate production plan translated into master schedule.
• Specific schedule (master production schedule) of the quantities of
individual models in each major product line.
• Listing of the products to be produced, quantity and quality of the
product
• Purchase orders of raw materials, order of components from outside
vendors and production schedule for parts made in the shop.
• Must be consistent with the plant’s production capacity.
Cont..
Requirements planning
• Based on the master schedule- raw materials, components and sub
assemblies requirements are planned
• MRP
Purchasing
• For components made in-house, raw materials have to be acquired
• Developing and purchasing components from the vendors and suppliers.
Dispatching
• Involves issue of production orders for starting the operations.
• An important step as it translates production plans into production.
• The dispatching function is performed by the shop foreman or by a
person called a dispatcher.
• Involves in giving out order tickets, route sheets, part drawings
and job instructions.
Cont..
Expediting
• Compare the actual progress of the order against the production
schedule.
• Recommends corrective action.
• Adjusting the route, rescheduling of work changing the workloads,
repairs and maintenance of machinery or equipment, control over
inventories.
Quality control
• Assuring the quality of the product and its components.
• Inspection at various levels.
Large amount of data are supplied with the use of electronic computers
and data communication devices to handle and process.
MRP,
Shop floor control,
Capacity planning,
Cost planning and
control,
inventory management
are new.
Master Production Schedule
• A master production schedule (MPS) is a product wise plan for
manufacturing products.
• MPS determines what quantities of which product types should be
produced, taking into account the market demand and the limited
capacity of resources, in order to maximize profit over the planning
horizon.
• For this planning task, information about product demand and
resource deployment are relevant:
Product Demand:
(1) In case of market oriented production: Information about
demand quantities and prices can be provided by forecasts.
(2) In the case of customer order driven production: Demand is
directly specified by the customers.
Resource deployment:
Capabilities and capacity of the production system and the demand
capacity of each product type have to be known as well as cost of
production.
Cont..
MPS relies on the following information:
The production plan conveyed by the top management
Long term forecasts of the individual items
Actual orders received from the customers for the plan period
Present inventory levels of the individual items
Resource constraints
Based on the above frame work, develop a preliminary MPS. Then check this
MPS against the capacity constraints. Then final MPS should be arrived as:
Best use of all the resources in all the plan periods.
The cost incurred is not in excess including overtime payment, sub
contracting, additional man power.
All the due dates for the orders can be met with.
Relationship of MPS to other manufacturing planning and control activities
Example: Aggregate Forecast and MPS
Forecast of demand for the next four months is 70 units per month
Committed customer orders for the next four months are 80, 50,
30, and 10, respectively. Order size is 100 units. Beginning
inventory is 100. Prepare MPS
Capacity planning
Capacity
Limiting capability of a productive unit to produce within a stated
time period, normally expressed in terms of output units per unit of
time.
Capacity is related to the intensity with which a facility is used.
Example: Policy to work a plant five days per week, one shift per day, to
produce a maximum of 1000 units per week.
Capacity can be increased by overtime of 1150 units.
By adding second shift capacity can be pushed to 1800
units per week.
Subcontracting is another way to increase.
These alternative sources of capacity can provide managers with important
flexibility in making capacity plan.
Measure of capacity
Auto plants - Number of autos, Beer plant – cases of beer
Nuclear plant- megawatts of electricity
Cont..
The successful execution of a material requirement plan (MRP) is
dependent on a complete understanding of the required capacity for the
plan.
Strategic Planning
The highest level of capacity planning is based on the long range
business plan that extends out as much as 5 years.
The time period is necessary for planning cash requirements,
additional plants, capital equipment.
The capacity management technique at this level is resource
requirement planning and will be based on the analysis of total
planned sales.
The projection of requirements at this level may be based on the
extension of critical resources.
This technique is known as CPOF (capacity planning using overall
factors).
Hierarchy of Capacity planning
Capacity adjustments for the short term
• Inventory stockpiling
This tactic might be used to maintain steady employment
levels during slow demand periods.
• Order backlogs
Deliveries of the product to the customer could be delayed
during busy periods when production resources are
insufficient to keep up with demand.
• Subcontracting
This involves the letting of jobs to other shops during busy
periods or the taking in of extra work during slack periods
Capacity planning adjustments for the long term include
• New equipment Investments. This involves investing in more
machines or more productive machines to meet increased future
production requirements, or investing in new types of machines to match
future changes in product design.
• Plant closings. This involves the closing of plants that will not be needed
in the future,
Cost planning and control
This is useful for financial executive and provides techniques whereby the
information created and maintained for manufacturing purposes can be
used for managing cost and accounting data and budgeting.
Objective of the cost planning and control system are to help to answer the
following questions:
What are the expected costs to manufacture and sell each of the
company’s products?
What are the actual cost to manufacture and sell?
What are the difference between?
The main aim of cost planning and control is to minimize the costs of
manufacturing the firm’s products.
Process route sheets- lists the manufacturing operations used for each
component in the product.
Time standards – specify the operation times for each operation listed
on the route sheets.
Machine breakdown
Job priorities might change after the job order is issued to the
shop.
The accuracy and correctness of the work order status report are
dependent on the correctness and timeliness of the basic data
collected in shop.
1. Order release
2. Order scheduling
3. Order progress
1. Order release
The order release phase of shop floor control provides the documentation
needed to process a production order through the factory.
(3) Job cards or other means to report direct labour time devoted to the
order and to indicate progress of the order through the factory.
The first is the authorization to produce that derives from the master
schedule.
The second input to the order release module is the engineering and
manufacturing data base which provides the product structure and process
planning information needed to prepare the various documents that accompany
the order through the shop.
2. Order Scheduling
The order scheduling module follows the order release module and assigns the
production orders to the various work centres in the plant.
The order scheduling module prepares a dispatch list, which indicates which
production orders should be accomplished at the various work centres.
It also provides information about relative priorities of the different jobs,
for example, by showing due dates for each job.
The term shop loading is also used, which refers to the loading of all
machines in the plant.
• Earliest due date: Orders with earlier due dates are given higher
priorities.
• Least slack time: Slack lime is defined as the difference between the
time remaining until due date and the process time remaining. Orders
with the least slack in their schedule are given higher priorities.
• Critical ratio: The critical ratio is defined as the ratio of the time
remaining until due date divided by the process time remaining.
Orders with the lowest critical ratio are given higher priorities.
The relative priorities of the different orders may change over time.
(4) Defective raw materials that delay an order. The priority control
function reviews the relative priorities of the orders and adjusts the
dispatch list accordingly.
3. Order Progress
The order progress module in shop floor control monitors the status of the
various orders in the plant.
Work order status reports. These reports indicate the status of production
orders. Typical information in the report includes the current work centre where
each order is located, processing hours remaining before completion of each
order, whether the job is on-time or behind schedule, and priority level.
Data collection equipment can be taken to that place -to collect the data.
This requires automatic or direct data collection from the shop floor.
2. MACHINES - STATUS
3. PARTS/RAW MATERIALS LOCATION
a: Idle
a: Raw Stores
b: Setup
b: Transit
c: Production
c: On-machine
d: Delay
d: Waiting
e: Downtime
e: Finished stores
f: Assembly
g: Missing
SHOP FLOOR DATA COLLECTION
Data collection techniques.
Some data by the employees
the rest are recorded automatically.
In an on-line system, the data are directly entered to the computer and are
available to the order progress module.
The advantage lies in the fact that the data file representing the status of the shop is
always at the current state.
In this the data are collected temporarily in a storage device or a stand alone
computer system in a batch mode.
In this mode there is delay in the entry and processing of the data.
So this system cannot provide real time information of shop floor status. The
advantage of this system is that it is easier to install and implement.
DATA INPUT TECHNIQUES
The data collection techniques include manual procedures and computer
terminals located on the shop floor.
The manual data collection methods require the production workers to fill out
paper forms indicating order progress data.
The manual data collection methods rely on the co-operation and clerical
accuracy of the employees to record a data property on a proper document.
The common forms of errors –wrong dates, incorrect order numbers and
incorrect operation numbers. These can be detected and corrected.
Another problem is that there may be a delay in submitting the order progress
for compiling.
The reason is that there will be always a time lapse between when occurrence of
events and recording of events.
VARIOUS TYPES OF INPUT SYSTEMS
1. CENTRALIZED TERMINAL
A single terminal is located centrally in the shop floor. This requires the
employees to go to the terminal and input the data. So employee’s time will be
wasted and in a big shop, this becomes inconvenient.
2. SATELLITE TERMINALS
These are multiple data collection centres located throughout the shop floor. In
this arrangement a balance is to be struck between the minimization of the
investment cost and maximization of the convenience of the employees in the
plant.
The most convenient arrangements to the employees are to have a data collection
terminal at each work centre.
This reduces the time to go to the central terminal. This can be applied when the
amount of data to be collected is very large.
AUTOMATIC DATA COLLECTION SYSTEM
A bar code reader is used to illuminate the bar code symbol and examine
successive segments of the symbol.
As the reader moves reader over the bar code symbol, due to reflectivity and
non reflectivity, alternate transitions from light to dark and dark to light
occur.
These are detected and the time it will take will be converted to digital
representations of ones and zeros of the bar code messages.
MOST COMMONLY USED BAR CODES ARE:
(i) Universal Product Code (UPC), (ii) Interleaved 2 of 5 (ITF) , (iii) Code 39
There are two types of bar code readers
(a) Fixed Beam Reader
(b) Moving Beam Reader
(a) FIXED BEAM READER
Bar code readers are either fixture mounted or
hand held.
Moving beam reader, as the name indicates, scans the symbol by a line of
light emitted from the reader.
A moving beam reader takes less time to scan the symbol depending on
the type of equipment.
(ii) OPTICAL CHARACTER RECOGNITION (OCR)
The optical character recognition (OCR) employs special fonts which can
be read by man and machine.
This is more reliable than key entry but less reliable compared to bar
code technology. The data is considered less secure than barcodes and 2D
symbols.
The fonts are printed with a magnetic ink to permit readability after being
overprinted or even smudged.
MICR is used to read smaller documents of size 7 to 20 cm. Like OCR, these
also require precise orientation and registration.
MICR code is printed on cheques and they let cheque processing easy.
The error rate for the magnetic scanning of a typical check is smaller than
with optical character recognition systems.
Moreover the training can be minimized and the key board entry can
be eliminated and hand and eye co-ordination is no longer needed.
The inventory control (IC) component must control the issue and
transfer of material and adjust inventory levels.
1. Inventory accounting –
It is concerned with inventory transactions and inventory records.
Creates audit trails with the exact time and operator for major files to
provide a record of additions, changes, and deletions.
Provides physical count tag support and cycle counting work sheets.
When the inventory level of an item falls to the reorder point, it is the
time to restock the item.
MRP accesses the data from the master production to determine what
products will be built during the planning period.
• Uses actual components planned for shop orders as a firm planned bill
of material to accurately reflect true material needs.
MANUFACTURING RESOURCE PLANNING (MRP II)
It became evident that MRP should be tied to other software packages to
create a more integrated production planning and control (PPC) system.
The PPC software packages that evolved from MRP became known as
manufacturing resource planning, or MRP II, to distinguish' it from the
original abbreviation and perhaps to suggest that it was second generation; that
is, more than "just" MRP.
Maintenance management
Warranty tracking
Marketing support
Distribution management
ERP is the next evolution of the MRP II system. While MRP helped companies
plan material purchases, and MRPII added in-plant scheduling and production
controls, ERP attempts to integrate the information flow from all
departments within a company: finance, marketing, production, shipping,
even human resources.
ERP systems are the software tools used to manage enterprise data.
Indirect Benefits
Better corporate image
Improved customer goodwill
Customer satisfaction
ERP - Softwares