Revised Connection Plan

Multi Bintang Sampang Agung


20th March 2024
Rev00
Contents

● Background Findings
● Engineering Proposal
● Mechanical Proposal
● Alteration of Breaker Setting
● Projection Timeline
Background Findings
Background Finding

Issue:
During the testing energization of the system, it is found that while
the main breaker at Bottling Hall is rated at 1600A. The transformer
rating is capped at 1375A at 420V, or 1443A at 400V.
Interconnection point
at Botting Hall Consequences:
Deployment of system at full capacity is not allowed

Proposed Solution:
To split the LV interconnection point.
Engineering Proposal
Previous Injection Point Configuration

PV System
Injection Level: LV at Bottling Hall
No of inverters: 9
Maximum Current output: 1571.84A @400V
ACB Rating: 1600A

All 9 inverters connected to single injection


point
SYSTEM
PV
Revised Injection Point Configuration
PV System
Injection Level: LV at Engineering
Room
No of inverters: 2
Maximum Current output: 348.8@400V
Proposed MCCB Rating: 400A

Split connection: 2 inverters output


connected to LV MSB of Engineering
Room

SYSTEM
PV
PV System
Injection Level: LV at Bottling Hall
No of inverters: 7
Maximum Current output: 1220.8A @
400V
Proposed ACB Rating: 1280A

Split connection: 7 inverters output


connected at LV MSB of Bottling Hall
SYSTEM
PV
Re-set Solar Breaker Rating

Current Solar Breaker Setting: 1600A, Ir = 1


Revised Solar Breaker Setting: 1280, Ir = 0.8
Engineering Summary
Single Injection Point Previous Configuration

Injection Point Location LV Botting Hall

Transformer Rating @ 400V 1000kVa, 1443

Existing Breaker Rating 1600A

Solar Breaker Rating 1600A

Maximum Current of inverter @ 400V 1571.84A

Split Injection Point Revised Configuration

Injection Point Location LV Botting Hall Engineering Room

Transformer Rating @ 400V 1000kVa, 1443 1600kVa, 2300A

Existing Breaker Rating 1600A 2500A

Solar Breaker Rating 1280A 400A


(To remain installed breaker, only
change at tap setting)

Maximum Current of Inverter @400V 1220.8A 348.8


Mechanical Proposal
Revised Routing for Split LV Injection Point
Legend:
• 9 inverters will remain as per previous LV MSB – Engineering Room
location (In front of Bottling Hall)
LV MSB – Bottling Hall
• 7 inverters will be interconnected to PV Inverter Room
Bottling Hall, sets of cable to reduce from
4 sets per phase to 3 set per phase Additional Solar AC Routing (~160m)

• 2 inverters will be interconnected to the Existing Solar AC Routing


Engineering Room, to pull cable from
inverter station to the LV MSB of
Engineering Room

• To add 1 more ACDB inside Engineering


Room
Equipment Plan inside Engineering Room
Proposed second ACDB Location
Transformer Rating

Main Breaker Rating


Projection Timeline
Projected Duration
Item Duration
Procurement
AC Cable 6 weeks
Cable Tray 2.5 weeks
LV Current Transformer (0.2s) 4 weeks
2nd Switchboard Fabrication 4 weeks
GI Conduit Pipe 2.5 weeks
Communication Cable 2 weeks
Construction
Dismantling of Existing AC Cable 0.5 week
Cable Tray Installation 2.5 weeks
(Roof, Gantry, Building Exterior) *Subject to HNK permitting working on gantry.
2nd Switchboard Installation & Assembly 3 days
AC Cabling Laying 1.5 weeks
AC Cable Crimping & Termination 3 days
Communication Cabling & Conduit 1 week
Breaker Coordination Setting & Relay Configuration 1 day
Energization 1 day