CONTRACTORS: M/s.

GDC LTD
Sr. No. DATE LOCATION OBSERVATION / DEVIATION REMEDIAL ACTION SUGGESTED

DATE :- 16.02.2013
PHOTOS

16.02. 2013

OPAL BLOCK (BLOCK VIII)

First floor it has been observed that


the column bar coupler is not tightened properly, in pour 1area.

Mr.Ramar / Mr.Pandey

16.02. 2013

OPAL BLOCK (BLOCK VIII)

First floor it has been observed that


the column lateral ties spacing is provided 210mm instead of 170mm, in pour 1 area. GDC to revert with corrective & Remedial measures
Mr.Ramar / Mr.Pandey

16.02. 2013

OPAL BLOCK (BLOCK VIII)

Stilt roof slab it has been observed


that the column concrete is casted high in the beam bottom level, in pour 2 area.
Mr.Ramar / Mr.Pandey

"This report is established in line with our service proposal no : IN/CHN/IND/20110155 dot 16.11.2011 and your WO No : AP/CHN/OS/TECH/VSN/WO-10/2011 DT 21.12.11

DATE :- 16.02.2013
STATUS OF COMPLIANCE

Rectified

"This report is established in line with our service proposal no : IN/CHN/IND/20110155 dot 16.11.2011 and your WO No : AP/CHN/OS/TECH/VSN/WO-10/2011 DT 21.12.11