Dhofar Power Company SAOG

7.7.8 Quality Control after Erection


]111
The Contractor shall be responsible for checking that the supports are complete and that all bolts have
been cOlTectly tightened before conductor stringing commences. A record of this work shall be kept by
the Contractor and made available to the Owner/Engineer on request.
Critical bolts are to be marked after erection with red paint to ensure priority checking during
maintenance.
Where appropriate, tests on the aircraft obstruction lighting shall be undertaken to provide compliance of
the systeill. Records of the tests shall be made available to the Owner/Engineer upon request.
After complete erection and stringing the live line washing installation shall be demonstrated by the
Contractor. All insulators shall be thoroughly washed before carrying any electrical tests.
7.8 Packaging, Protection and Despatch Marking
The Contractor shall adopt packing methods that are enumerated in Section 15 as a minimum requirement
under this Contract.
7.9 Health Safety and Environmental Requirements
Contractor's attention is drawn to the fact that the location of the work is mostly mountains, with access
difficulties, communication difficulties etc. The Contractor shall take stringent measures to ensure safety
of men and material. Health, Safety and Environmental plan of the Contractor shall be specifically
devised to meet the special needs of the site and the activities undertaken.
Construction of 132kV Overhead line between Awqad GSS &SFZ GSS
Rev. No. :A
and Associated Works (Package-1)
Volume 2 Overhead Line Specification Date : December 2010
Section 7 Supports Page :Page 25 of 38