86 PEFS

Process Engineering Flow Scheme

87 PFS

Process Flow Scheme

88 E/R

Engineering Requisition (= Material Requisition)

89 MSD

Material Selection Diagram (MM Preparation, PR Review)

90

(+ /) * 95%(?)

91 PMSA

Progress Measuring System Application

92 Project Tool

P3, PMSA (MS Acess), Project Space(EDMS),

Project

ITB -> -> -> KOM (Launch Meeting) -> ->


-> PD Sign

93 Work Flow

-> -> -> (10 , )


( M/H , (Project Highlight ))

94 P-code

95

M/H (PM), ( ),

96 Work package

Cost Breakdown Structure ( , )

97 Insulation(LIM)

Insulation Limit

98 EDIS

Engineering Data Information System

99

LDM

Line Data Management

100

NDM

Nozzle Data Management

101

ELM

Equipment List Management

102

ELD

Equipment Loading Data


(BBJN )

6 Package

PD, PM PE , ITB
, (Where-What)
, (Purpose, Contents)
, (Emphasis)

103

, (Safty, Layout - Requirement)


.

(20 binders ) 2 ,
2 2 .
104 BEDD

Basic Engineering Design Data

105 Engineering Portion

3~5%(??)

106 NPC

Notification of P&ID Change

107 NEC

Notification of ELP Change

108 DCN/FCN

Design/Field Change Notice

109 MDR

Master Document Register ( ? : )

110 IFA

Issued for Approval ( )

111 IFC

Issued for Construction

112 As Built

113

P&ID, Equipment Layout Plan(ELP), Underground(U/G) Composite Drawing

114

Preliminary (Pre.) : PA, PB, ---

, ,

115

Issued for Information (IFI) : A, B, C, ---

"IFI" or "AFC" "0"

116

Issued for Review (IFR) : A, B, C, ---

"IFI" or "AFC" "0"

117

Issued for Approval (IFA) : A, B, C, ---

"IFI" or "AFC" "0"

118

Approved for Design (AFD) : 0, 1, 2, ---

P&ID, EQ list, Process Data Sheet,


etc.

119

Issued for Construction or Approved for Construction (IFC or AFC) : 0, 1, 2, ---

120

Issued for Purchase or Approved for Purchase (IFP or AFP) : 0, 1, 2, ---

121

Issued for Fabrication or Approved for Fabrication (IFF or AFF) : 0, 1, 2, ---