Name : PCK1 Price List

Supp Ref Code Item Description Unit Mark Rate Last


Code Up % Updated
Trade Heading: O - Labour Rates
0.00 JADUAL KADAR HARGA UPAH BURUH
2002
O001 Labourer (Unskilled) Day 45.00 05/07/2005
O001A Semi-skilled labour Day 70.00 26/04/2011
O001B Skilled labour Day 100.00 26/04/2011
O002 Drainlayer Day 60.00 05/07/2005
O003 Concrete Leveller and Screeder Day 65.00 05/07/2005
O004 Mason Day 65.00 05/07/2005
O005 Bricklayer Day 65.00 05/07/2005
O006 Carpenter and Joiner Day 65.00 05/07/2005
O007 Steel Barbender and Fixer Day 65.00 05/07/2005
O008 Pneumatic Tool Operator Day 65.00 05/07/2005
O009 Fitter Day 70.00 05/07/2005
O010 Welder Day 70.00 05/07/2005
O011 Plumber Day 65.00 05/07/2005
O012 Painter Day 60.00 05/07/2005
O013 Roofer Day 65.00 05/07/2005
O014 Glazier Day 65.00 05/07/2005
O015 Ironworker Day 70.00 05/07/2005
O016 Pavior/Plasterer Day 65.00 05/07/2005
O017 Tile Fixer Day 70.00 05/07/2005
O018 Watchman Day 50.00 05/07/2005
O019 Labour (Skilled) Day 65.00 05/07/2005
O020 Pipelayer Day 60.00 05/07/2005
O021 Fence Fixer Day 60.00 05/07/2005
O022 Labour to erect formwork m2 22.00 26/04/2011
O023 Labour to cut, bend & fix steel bar tonne 550.00 26/04/2011
O024 Labour to cast concrete m3 35.00 26/04/2011
O025 Labour to lay bricks; 115 mm thick m2 8.50 26/04/2011
O026 Labour to install lintol 100m x 100mm m 9.00 26/04/2011
O027 Labour to lay damp proof course, 230mm wide m 0.30 26/04/2011
O028 Labour to lay cement & sand acreed to floor;
25mm thick, steel trowel
m2 5.50 26/04/2011
O029 Labour to plaster wall; cement & sand; 28mm
thick; 3 coats; external
m2 12.50 26/04/2011
Page : 1 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O030 Labour to plaster wall; cement & sand; 28mm
thick; 3 coats; internall
m2 8.50 26/04/2011
O031 Labour to lay tiles; homogeneous m2 16.00 26/04/2011
O032 Labour to fix corner beading m 2.30 26/04/2011
O033 Labour to install timber door frame for single
leaf door including sub-frame
no 36.00 26/04/2011
O034 Labour to install timber door frame for double
leaf door including sub-frame
no 39.00 26/04/2011
O035 Labour to install timber door; single leaf no 50.00 26/04/2011
O036 Labour to install timber door; double leaves no 70.00 26/04/2011
Skilled And General Workers
O037 Concretor day 50.00 18/12/2008
O038 Concretor 'Kepala' day 62.00 18/12/2008
O039 Steel bar bender & fixer day 53.00 18/12/2008
O040 Bar bedber 'Kepala' day 66.00 18/12/2008
O041 Formwork carpenter day 54.00 18/12/2008
O042 Formwork carpenter 'Kepala' day 68.00 18/12/2008
O043 Bricklayer day 52.00 18/12/2008
O044 Bricklayer 'Kepala' day 65.00 18/12/2008
O045 Blocklayer day 57.00 18/12/2008
O046 Blocklayer 'Kepala' day 71.00 18/12/2008
O047 Roofer day 55.00 18/12/2008
O048 Roofer 'Kepala' day 71.00 18/12/2008
O049 Joinery carpenter day 57.00 18/12/2008
O050 Joinery carpenter 'Kepala' day 82.00 18/12/2008
O051 Structural steel worker day 65.00 18/12/2008
O052 Structural steel worker 'Kepala' day 94.00 18/12/2008
O053 Welder day 71.00 18/12/2008
O054 Welder 'Kepala' day 101.00 18/12/2008
O055 Plumber day 61.00 18/12/2008
O056 Plumber 'Kepala' day 83.00 18/12/2008
O057 Plasterer day 57.00 18/12/2008
O058 Plasterer 'Kepala' day 75.00 18/12/2008
O059 Tiler day 61.00 18/12/2008
O060 Tiler 'Kepala' day 85.00 18/12/2008
O061 Painter day 55.00 18/12/2008
Page : 2 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O062 Painter 'Kepala' day 70.00 18/12/2008
O063 General worker (Male) day 40.00 18/12/2008
O064 General worker (Female) day 35.00 18/12/2008
Piling
OO01 Sheet pile
OO01A Handle, pitch and drive
O065 FSP 3A, 12m lenght pcs 80.00 16/12/2008
O066 FSP 3A, 9m lenght pcs 70.00 05/11/2008
OO02 Extracting
O067 FSP 3A, 12m lenght pcs 70.00 05/11/2008
O068 FSP 3A, 9m lenght pcs 60.00 05/11/2008
OO03 600mm diameter pretensioned spun concrete
pile
O069 Allow for the provision of all necessary injection
piling equipment, plant, tools and ancillary
equipment (for the execution of all piling work
in this contract) and for their transportation to
site handling, assembling, erecting, dismantling
and removal on completion of the work for any
idle standing time
Item 42,250.00 04/03/2009
O070 Allow for moving and handling piling
equiment, plant, tools, and ancillary equipment
about the site as often and whenever necessary
for the execution of the whole piling operation
(as covered under this contract) including any
excavation and filling required for moving the
plant, tools and ancillary equipment from
differing places and levels of the site, erection
of any staging required and dismantling and
removal on completion.
Item 9,833.33 04/03/2009
O071 Handle, transport and pitch 600mm Diameter
spun pile; 12.00m long
No 44.00 04/03/2009
O072 Drive only by injection method 600mm
Diameter spun pile; 12.00m long (In No. 766)
M 45.67 04/03/2009
O073 12.70mm (overall) Butt weld connection
1884mm girth between edges of mild steel
extension head and base cap plates including
coated heavily with bituminous compound.
No 58.00 04/03/2009
O074 Cut off 600mm diameter pre-tensionedspun
concrete pile to be required level and roughen
the inner surface to detail.
No 59.25 04/03/2009
O075 Allow for Pile Dynamic Analysis (PDA) test and
submission of analysis.
No 1,700.00 04/03/2009
OO04 500mm diameter prestressed spun concrete
pile
Page : 3 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O076 Allow for mobilisation of labour, plants and
hydraulic hammer piling equipment to site,
moving around and demobilisation from site
Item 18,000.00 16/12/2008
O077 Handle, sling and pitch initial and extension
vertical piles not exceeding 12m long
no 64.00 16/12/2008
O078 Handle, sling and pitch initial and extension
raked 1:4 piles not exceeding 12m long
no 80.00 16/12/2008
O079 Drive vertical pile to the required depth m 45.00 16/12/2008
O080 Drive raked 1:4 piles to the required depth m 60.00 16/12/2008
O081 Fillet weld vertical extension pile joints no 97.50 16/12/2008
O082 Cut off piles to the required level and roughen
inner surface of pile
no 120.00 16/12/2008
O083 Provide labours, plants, temporary staging,
kentledge, testing equipment and load 500mm
diameter test pile to 1200KN
no 15,000.00 10/12/2008
O084 Subsequent load test no 10,000.00 10/12/2008
OO05 350mm diameter prestressed spun concrete
pile
O085 Allow for mobilisation of labour, plants and
hydraulic hammer piling equipment to site,
moving around and demobilisation from site
Item 14,666.67 23/12/2008
O086 Handle, transport and pitch initial and extension
pile not exceeding 12m long
no 33.20 23/12/2008
O087 Drive initial and extension pile to the required
depth
m 13.93 23/12/2008
O088 Fillet weld pile joint no 36.00 23/12/2008
O089 Cut off pile head, strip concrete and exposed
reinforcement to a length of 600mm including
bending and binding exposed reinforced rods to
the reinforcement in the pile cap
no 39.00 23/12/2008
O090 Supply and fix 'concrete plug' no 70.00 23/12/2008
O091 Provide all equipments, hydraulic jack,
deflection gauge, kentledge and other related
items for initial load testing to a vertical load of
130 ton or 1300KN
no 13,333.33 23/12/2008
O092 Subsequent load test no 6,933.33 23/12/2008
OO06 300mm diameter prestressed spun concrete
pile
O093 Allow for mobilisation of labour, plants and
jacked -in piling equipment to site, moving
around and demobilisation from site
Item 40,000.00 23/12/2008
O094 Handle, transport, pitch and drive initial and
extension pile to the required depth
m 40.00 23/12/2008
O095 Fillet weld pile joint no 27.67 23/12/2008
O096 Cut off and remove surplus length and strip off
pile head, bend back reinforcement for
connection
no 37.50 23/12/2008
O097 Initial pile test to 1100KN no 14,500.00 23/12/2008
Page : 4 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O098 Subsequent load test no 7,166.67 23/12/2008
O099 PDA test no 1,450.00 23/12/2008
OO07 350 x 350mm R.C Pile
O100 Allow for the provision of necessary hydraulic
hammer piling equipment, plant and tools and
for their transportation to the site, handling,
assembling and removal after the completion of
operation
Item 15,000.00 19/02/2009
O101 Allow for moving and handling piling
equipment about the site
Item 3,000.00 19/02/2009
O102 Allow for submission of records of all piles Item 3,700.00 19/02/2009
O103 Allow for the provision of necessary testing
equipment, plant and tools and for their
transportation to the site, handling, assembling
and removal after completion including all
idling and standing time
Item 4,750.00 19/02/2009
O104 Handle, transport, pitch and drive initial and
extension pile to the required depth
m 16.50 19/02/2009
O105 Fillet weld pile joint no 34.00 19/02/2009
O106 Cut off pile head to required level, strip off
concrete to expose reinforcement, bend the pile
reinforcement excess length to dispose to
Contractor's own dump site
no 35.80 19/02/2009
O107 Initial pile test to twice working load of 1500KN no 29,030.00 19/02/2009
O108 Subsequent load test no 18,720.00 19/02/2009
O109 PDA test including preparation of pile head,
submission of test report
no 960.00 19/02/2009
OO08 300 x 300mm R.C Pile
O110 Mobilisation & Demobilisation of hydraulic
hammer piling frame and equipment
Item 13,666.67 16/12/2008
O111 Moving and handling piling equipment, plant
and tools about the site
Item 4,000.00 16/12/2008
O112 As built survey Item 4,000.00 16/12/2008
O113 Submission of piling record Item 1,500.00 16/12/2008
O114 Handle, transport and pitch only, 12m long
initial/extension pile
no 43.00 16/12/2008
O115 Drive only initial/extension pile m 14.50 16/12/2008
O116 Filler weld pile joint no 30.00 16/12/2008
O117 Cut off pile head and cart away surplus length
from site
no 35.00 16/12/2008
O118 Preliminary load test 2 x 1000KN no 14,166.67 16/12/2008
O119 PDA test no 1,333.33 16/12/2008
OO09 250 250mm R.C Pile
Page : 5 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O120 Allow for moving and handling jacked-in piling
equipment, plants, tools at the site as often and
whenever necessary for the operation of the
whole piling operation including for moving the
plants, tools and ancillary equipment from
different levels of the site and all necessary
staging, platform and any idling standing time.
no 42,500.00 23/12/2008
O121 Handle, transport, pitch and drive initial and
extension pile to the required depth
m 29.50 23/12/2008
O122 Fillet weld pile joint no 22.75 23/12/2008
O123 Cut off and remove surplus length and strip off
pile head, bend back reinforcement for
connection
no 29.50 23/12/2008
O124 Initial load test to 660KN no 10,350.00 23/12/2008
O125 Subsequent load test no 8,750.00 23/12/2008
O126 PDA test no 1,187.50 23/12/2008
OO10 200 x 200mm R.C pile
O127 Handle, transport and pitch, 6m long
initial/extension pile
no 9.00 16/12/2008
O128 Drive initial/extension pile to the required depth m 4.50 16/12/2008
O129 Fillet weld pile joint no 8.00 16/12/2008
O130 Cut off pile head and cart away surplus length
from site
no
OO11 150 x 150mm R.C pile
O131 Allow for the provision of necessary hydraulic
hammer piling equipment, plant and tools and
for their transportation to the site, handling,
assembling and removal after the completion of
operation
Item 4,500.00 19/02/2009
O132 Allow for moving and handling piling
equipment about the site
Item 1,000.00 02/01/2009
O133 Allow for submission of records of all piles Item 2,000.00 02/01/2009
O134 Allow for the provision of necessary testing
equipment, plant and tools and for their
transportation to the site, handling, assembling
and removal after completion including all
idling and standing time
Item 10,000.00 02/01/2009
O135 Handle, transport, pitch and drive initial and
extension pile to the required depth
m 4.38 19/02/2009
O136 Fillet weld pile joint no 8.83 19/02/2009
O137 Cut off pile head to required level, strip off
concrete to expose reinforcement, bend the pile
reinforcement, excess length to dispose to
Contractor own dump site
no 16.83 19/02/2009
O138 Subsequent load test to twice working load of
400KN
no 5,250.00 19/02/2009
Page : 6 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O139 PDA test including preparation of pile head,
submission of test report
no 958.33 19/02/2009
Concretor
O140 Concretor m3 16.00 13/02/2009
O141 Lean Concrete m3 16.00 26/02/2009
OO12 Lean concrete, 50mm thick including
necessary trimming base of excavation
03/12/2008
O142 To underside of pile cap, footing, ground beam,
apron slab, ground floor slab, trench beam,
trench slab, pit slab and the like
m2 1.50 17/02/2009
OO13 Reinforced concrete including vibrating and
trowelling to a smooth and uniform level in
O143 Pile cap, footing, column stump, ground beam,
trench beam and lift pit
m3 19.00 03/12/2008
O144 Column m3 20.00 03/12/2008
O145 Stiffener and lintol m3 21.00 03/12/2008
O146 Roof beam m3 20.00 03/12/2008
O147 150mm thick ground floor slab and apron slab m3 19.00 03/12/2008
O148 150mm thick suspended floor slab and
suspended floor beam
m3 19.00 03/12/2008
O149 150mm thick roof slab m3 19.00 03/12/2008
O150 200mm thick wall m3 20.00 03/12/2008
Bar Bender
O151 Bar-Bender tonne 330.00 13/02/2009
O152 Fabric BRC m2 1.35 24/10/2008
OO14 Rods, 12mm, 16mm, 20mm, 25mm, 32mm and
40mm diameter
O153 In foundation kg 0.33 03/12/2008
O154 In column kg 0.33 03/12/2008
O155 In beam kg 0.33 03/12/2008
O156 In wall kg 0.33 03/12/2008
OO15 Strirrups and Links
O157 6mm, 10mm and 12mm diameter kg 0.33 03/12/2008
OO16 BRC Fabric
O158 In ground floor slab, apron slab, trench slab,
suspended floor slab and roof slab
m2 1.30 03/12/2008
Formwork
O158A Formwork m2 13.00 13/02/2009
Page : 7 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
OO17 Timber formwork fabrication, fixing and
striking not exceeding 3.50m high
O159 To sides of pile cap, footing, column stump,
ground beam, trench beam and lift pit
m2 13.00 03/12/2008
O160 To sides of column and stiffener m2 13.00 03/12/2008
O161 To sides and soffits of suspended floor beam and
roof beam
m2 13.00 03/12/2008
O162 To sides and soffits of suspended floor slab m2 13.00 03/12/2008
O163 To sloping soffit of staircase m2 13.00 03/12/2008
Precast prestressed hollow core slab, plank
and precast beam
Installation & Grouting Works
OO18 Installation (Labour Only NOT inclusive
cranage)
O164 Hollow core slabs & planks in thickness 300mm
& below
m2 3.43 26/02/2009
O165 Hollow core slabs & planks in thickness 300mm
& above
m2 5.00 26/02/2009
O166 Hollow core slabs & planks in thickness 325mm m2 3.80 26/02/2009
O167 Hollow core slabs & planks in thickness 360mm m2 4.60 26/02/2009
O168 Precast beams, L < 10m no 103.13 26/02/2009
O169 Precast beams, 10m < L < 15m no 178.00 26/02/2009
O170 Precast column, 1 tier in one length no 152.50 26/02/2009
O171 Precast column, 2 tiers in one length no 200.00 26/02/2009
O172 Precast staircase flight no 108.80 26/02/2009
O173 Precast landing slab no 132.00 17/02/2009
O174 Precast wall, 2400 x 1800 x 150mm thick no 100.00 31/12/2008
O175 Precast wall, 2250 x 1800 x 150mm thick no 132.00 26/02/2009
OO19 Grouting Works to Precast System (Labour &
Materials)
O176 Grouting to beam dowels connection no 52.56 26/02/2009
O177 Grouting to beam & column gap including
formwork
no 104.99 26/02/2009
O178 Grouting to BSF connection gap including
formwork
no 102.74 26/02/2009
OO20 Grouting to HCS/Plank shearkey joint
(E.mix) to
O179 AV5 - 265 m 9.13 26/02/2009
O180 EV4-325 m 14.30 26/02/2009
O181 EV4-460 m 19.60 26/02/2009
O182 Plank 110 m 5.90 17/02/2009
Page : 8 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O183 WV6 - 205 m 5.00 31/12/2008
OO21 Grouting to column base, 50mm in gap in
between; column to pile cap & column to
column
O184 500 x 500mm no 97.90 26/02/2009
O185 450 x 600mm no 100.10 17/02/2009
O186 300 x 700mm no 68.33 26/02/2009
O187 300 x 300mm no 82.50 17/02/2009
OO22 Grouting to column corrugated connection
O188 4 dowels (300 x 300) no 138.60 17/02/2009
O189 6 dowels no 156.25 26/02/2009
O190 8 dowels (500 x 500) no 278.30 26/02/2009
OO23 Grouting to column corrugated connection at
beam top rebar
O191 2 tiers no 55.00 17/02/2009
O192 Grouting to staircase flight no 121.00 17/02/2009
O193 Grouting to landing slab no 121.00 17/02/2009
O194 Grouting to wall no 69.75 26/02/2009
OO24 Associated Works On Site
O195 Concrete G30 to topping, 75mm thick m3 310.00 17/02/2009
O196 Concrete G40 to beam infill & beam top m3 340.00 31/12/2008
O197 Concrete G40 to beam-column junction m3 340.00 31/12/2008
O198 Rebar to beam top, span & support kg 3.25 17/02/2009
O199 Rebar to topping, EB/PB kg 3.25 17/02/2009
O200 RD6 mesh to topping, 4.44kg/m2, measure nett,
allow lap in rate
m2 13.00 17/02/2009
O201 Formwork to underside of hcs at perimeter beam
end
m 18.00 31/12/2008
O202 Formwork to edge of topping m 18.00 31/12/2008
Bricklayer
O203 Bricklayer pcs 0.15 24/10/2008
O204 Hoisting brick pcs 0.02 15/11/2008
OO25 Lay cement and sand brick
O205 110mm thick wall m2 8.05 03/12/2008
OO26 Lay clay brick
O206 115mm thick wall m2 8.05 03/12/2008
OO27 Lay hollow concrete block
Page : 9 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O207 200mm thick wall m2 8.50 13/01/2009
Plasterer
O208 External m2 7.53 13/02/2009
O209 Internal m2 6.99 13/02/2009
OO28 Plaster including mortar mixer, wheel barrow
and trowelling tools and erection of working
platform to a working height of not more than
3.0m high
OO29 19mm thick with wood float or sponge finish
in two (2) coats
O210 Brickwall and concrete surface; externally m2 8.00 04/12/2008
OO30 19mm thick with steel trowelled finish in two
(2) coats
O211 Brickwall and concrete surface; internally m2 7.00 04/12/2008
Door
O212 Lintol Small no 5.00 27/11/2008
O213 Lintol Big no 15.00 27/11/2008
O214 Lintol Arch no 100.00 27/11/2008
OO31 Timber/Metal Frame
O215 Door Frame, SL no 10.00 24/10/2008
O216 Door Frame, DL no 15.00 24/10/2008
OO32 Timber window frame fixing
O217 Overall size 300mm x 300mm high no 10.00 04/12/2008
O218 Overall size 1200mm x 1200mm high no 13.00 04/12/2008
OO33 Timber door frame fixing
O219 Overall size 900mm x 2100mm high no 13.00 04/12/2008
O220 Overall size 1800mm x 2100mm high no 19.00 04/12/2008
OO34 Metal door frame fixing
O221 Overall size 900mm x 2100mm high no 13.00 04/12/2008
O222 Overall size 1800mm x 2100mm high no 19.00 04/12/2008
OO35 Timber Leaf Including Ironmongery
O223 Door Leaf including ironmongery, SL no 15.00 24/10/2008
O224 Door Leaf including ironmongery, DL no 30.00 24/10/2008
OO36 Fire Leaf Including Ironmongery
O225 Door Leaf including ironmongery, SL no 40.00 24/10/2008
O226 Door Leaf including ironmongery, DL no 80.00 24/10/2008
Page : 10 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
OO37 Partition Leaf Including Ironmongery
O227 Door Leaf including ironmongery, SL no 10.00 24/10/2008
O228 Door Leaf including ironmongery, DL no 20.00 24/10/2008
OO38 PVC Leaf
O229 Door Leaf, SL no 7.00 27/11/2008
OO39 Timber hollow core door fixing with hinges
and normal/standard lockset
O230 Standard hollow core flush door faced both sides
with plywood; overall size 900mm x 2100mm
high x 40mm thick
no 17.00 04/12/2008
O231 Standard double leaf hollow core flush door
faced both sides with plywood; overall size
1800mm x 2100mm high x 40mm thick
pair 28.00 04/12/2008
OO40 Timber solid core door fixing with hinges and
normal/standard lockset
O232 Standard solid core flush door faced both sides
with plywood; overall size 900mm x 2100mm
high x 42mm thick
no 30.00 04/12/2008
O233 Standard double leaf solid core flush door faced
both sides with plywood; overall size 1800mm x
2100mm high x 42mm thick
pair 54.00 04/12/2008
OO41 Timber fire door fixing with hinges and
normal/standard lockset
O234 Standard one (1) hour fire-rated door; overall
size 1070mm x 2100mm high x 50mm thick
no 42.00 04/12/2008
O235 Standard double leaf one (1) hour fire-rated
door; overall size 1800mm x 2100mm high x
50mm thick
pair 74.00 04/12/2008
OO42 Ironmongery fixing
O236 Door closer no 9.00 04/12/2008
O237 Lockset no 5.00 18/02/2009
Pavior
OO43 Mason
O238 Rendering, 25mm thick m2 5.38 13/02/2009
O239 Rendering, 50mm thick m2 5.92 13/02/2009
OO44 To floor
O240 25mm thick cement and sand render with steel
trowelled finish to a smooth and level surface
m2 5.40 04/12/2008
O241 20mm thick cement and sand base screed with
steel trowelled finish to a smooth and level
surface to receive finishing
m2 5.40 04/12/2008
Tiling
Page : 11 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
OO45 Wall tile including preparation and laying of
cement and sand backing screed
OO46 To wall
O242 200mm x 200mm ceramic tile m2 17.00 04/12/2008
O243 450mm x 450mm granite slab m2 54.00 04/12/2008
O244 450mm x 450mm marble slab m2 43.00 04/12/2008
OO47 Floor tile including preparation and laying of
cement and sand backing screed
OO48 To floor
O245 300mm x 300mm ceramic tile m2 17.00 04/12/2008
O246 300mm x 300mm homogeneous tile m2 17.50 04/12/2008
O247 600mm x 600mm granite slab m2 48.00 04/12/2008
O248 600mm x 600mm marble slab m2 43.00 04/12/2008
OO49 Wall & Floor Finishes
O249 Power float m2 3.60 24/10/2008
O250 Wall tile m2 17.22 06/01/2009
O251 Floor tile m2 17.76 06/01/2009
O252 Skirting m 5.25 06/01/2009
O253 Wall tile menara TM Melaka m2 34.43 24/10/2008
O254 Floor tile Menara TM Melaka m2 34.43 24/10/2008
O255 Floor tile skirting Menara TM Melaka m 2.40 24/10/2008
O256 Carpet tile m2 9.70 26/11/2008
O257 Carpet roll m2 14.00 26/11/2008
Roofer
OO50 Structural steelwork fabrication, erection and
fixing including cranage
OO51 Heavy section
O258 Universal beam and universal column kg 0.90 04/12/2008
OO52 Hollow section
O259 Square, rectangular and circular hollow sections kg 1.00 04/12/2008
OO53 Attached connection
O260 Cleats, stiffeners and plates and the like kg 0.90 04/12/2008
OO54 Roof truss
O261 Up to 10.0m span kg 0.90 04/12/2008
O262 Above 10.0m span kg 0.90 04/12/2008
OO55 Roofer
Page : 12 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O263 Lay aluminium foil m2 2.38 29/10/2008
O264 Lay chicken wire netting m2 1.81 26/04/2008
O265 Fix fascia board m 6.29 26/04/2008
O266 Fix valley gutter m 5.58 18/02/2009
O267 Lay concrete roof tile pc 0.50 24/10/2008
O268 Lay concrete roof tile to pitch not exceeding 30
degree
m2 6.00 03/12/2008
O269 Lay metal deck to pitch not exceeding 30 degree m2 5.00 03/12/2008
O270 Lay 50mm thick fibre wool insulation & wire
mesh netting to slope
m2 1.50 03/12/2008
O271 Lay sisalation to slope m2 1.00 03/12/2008
Ceiling Installer
O272 Ceiling board and frame m2 6.50 13/02/2009
O273 Skim coat m2 2.00 24/10/2008
OO56 Ceiling framing & finishing fixing
non-suspended ceiling
O274 1200mm x 600mm x 3.2mm thick ceiling board m2 6.00 04/12/2008
O275 1200mm x 600mm x 4.5mm thick ceiling board m2 6.50 04/12/2008
Sanitary
O276 Squatting w.c complete set no 52.50 02/01/2009
O277 Closed coupled sitting w.c complete set no 52.50 02/01/2009
O278 Table top wash basin complete set no 42.50 02/01/2009
O279 Wall hung handicap wash basin complete set no 45.00 24/12/2008
O280 Sink no 40.00 02/01/2009
O281 Urinal no 50.00 02/01/2009
O282 Wall mounted pillar tap no 15.00 24/12/2008
O283 Hand bidet with flexible hose complete set no 20.00 24/12/2008
O284 Surface mounted stainless steel paper holder no 15.00 24/12/2008
O285 Stainless steel vertical liquid soap dispenser
complete set
no 25.00 24/12/2008
O286 Single robe hook with door stopper no 15.00 24/12/2008
O287 Stainless steel floor trap complete with insect
cage, size 150mm x 150mm
no 10.00 24/12/2008
O288 40mm diameter stainless steel grab rail for OKU no 35.00 24/12/2008
Page : 13 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O289 On completion of the installation of sanitary
fittings, test all fittings, make good any defects
and leave in perfect working order to the entire
satisfaction of the Architect
Item 500.00 24/12/2008
WATER TANK
OO57 Approved FRP water storage tank square
type as described complete with cover and all
necessary fixing accessories
O290 3520 Gallons; Ditto; overall size 4000mm x
2000mm x 2000mm high approximately 20m
above ground level
No 400.00 02/03/2009
O291 2200 Gallons; Ditto; overall size 5000mm x
2000mm x 1000mm high approximately
600mm above ground level
No 340.00 02/03/2009
Scaffolder
O292 Erect frame including cross braces, base plate
and joint pin
frame 6.00 27/11/2008
O293 Dismantle frame, cross braces, base plate &
joint pin including stacking up properly directed
on site
frame 3.00 27/11/2008
O294 Fix 6.0m g.i pipe bracing including all
accessories and coupler
no 6.00 27/11/2008
O295 Dismantle 6.0m g.i pipe bracing & accessories
and coupler including stacking up properly as
directed on site
no 4.00 27/11/2008
O296 Fix 3.0m g.i pipe bracing including all
accessories and coupler
no 3.00 27/11/2008
O297 Dismantle 3.0m g.i pipe bracing & accessories
and coupler including stacking up properly as
directed on site
no 2.00 27/11/2008
O298 Fix wall tie including drilling hole for anchor
bolt (bolt by Main Contractor)
no 4.00 27/11/2008
O299 Dismantle wall tie including making good bolt
hole
no 2.00 27/11/2008
O300 Fix netting size 6'0"x17'0" including tying in
position by wires
pc 10.00 27/11/2008
O301 Dismantle netting including rolling up properly
and return to store as directed
pc 6.00 27/11/2008
Drainage
OO58 Surface Water
O302 Concrete base & P.C half round drain m 18.00 27/11/2008
O303 230mm thick brickwall & plastering m2 23.50 27/11/2008
O304 R.C Strut no 10.00 27/11/2008
O305 Brickwall sump including R.C base no 150.00 27/11/2008
Page : 14 CHEW FU KEONG Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
of 15
Name : PCK1 Price List
Supp Ref Code Item Description Unit Mark Rate Last
Code Up % Updated
Trade Heading: O - Labour Rates (Continued)
O306 600mm diameter pipe culvert m 75.00 27/11/2008
O307 225mm SGW pipe no 5.00 27/11/2008
O308 Precast road kerb no 5.00 27/11/2008
OO59 Rain Water Down Pipe
O309 100mm diameter m 10.66 23/12/2008
O310 150mm diameter m 10.66 23/12/2008
OO60 Gutter
O311 Galvanised iron m 18.05 23/12/2008
Road furniture
O312 Install single beam highway guardrail m 8.50 10/12/2008
Page : 15 CHEW FU KEONG Date of Printing: 21/Jul/11