SFAD TEAM WORKOVER RECOMMENDATION

NonOil
OilGain
GainJob
Job

Primary Job :
FIELD :

BANGKO

WELL :

DATE :

19-Aug-15

NUMBER :

SEQUENCE JOB

1265

PBTD:

Max Inc-BUR-KOP

1.
2.
3.
TD :

BO067 # O-W1-22
BNKO0006720150819LOG05

LOG05 - Pressure Survey

Swab
Water Shut Off
1900

Last WFL/FAP

Present

Off Reason (if any) :


Last Test

RT/GL : 40.42 ft/29.42 ft @

Proposed

LOG05 - Pressure Survey

GAS PRODUCER - VERTICAL


Status

Last Pump
Remarks

Normal
Normal

Priority :

:
:
:
:
:
:

Charge To:

ON

2500CP112012

1-Aug-2015 Rig Days

1 days

POT

:
0 BOEPD
: $ 3,500
0
:

Review

Oil Gain
0/302 MCFD/0% WC @1 August 2015

Cost

Field Rev

ALL DEPTH FROM MARKED LOG - ALL DEPTHS ARE IN MD

Estimated Maximum Zone Press.


Estimated Maximun Surface Press.
Required BOP Rating
Formation Fluid Expected
Weight Completion Fluid
Maximum Drilling Mud Weight
Est. Max. Zone Temperature

=
=
=
=
=
=
=

500
psi
110
psi
3000
psi
Gas/Condensate/Water
none
ppg
120
deg. F

240'-242'

Procedure Rig
1 Check master valves, swab valves, and wing valve before MIRU. Report to WSM.
2 MIRU. N/U Lubricator & BOPE and test.
3 RIH with dummy tool to PBTD. Move up and down along packer and
seal locator assy.
4 POOH with dummy tool.
5 RIH with pressure equipment to 448 ft.
6 Record flowing BHP for 60 minutes
7 Record flowing BHP for 60 minutes and gas rate as well (Please coordinate with
Operations to do gas rate measurement with DP meter).
8 Record pressure at the following depths :
- 50' interval for every 10 minutes from 448' to 200'.
9 POH w/ pressure equiptment
10 N/D Lubricator & BOPE. RDMO.
11 Open master valve and POP.

275'-277'
370'-372'
Petani sand
Arr Pkr @ 448'

530'-550'
Cmt Cup @ 1265'
TOS @ 1274'
LSP @ 1297'

Telisa 1480'sd
1516'-1528'
1528'-1543'
Duri 1600'sd
1656'-1688'
Duri 1680'sd
1728'-1736'
1736'-1747'
1760'-1780'

Justification
> Bangko #67 is a vertical gas poducer and status is ON
> Last test on 1 August-2015 was 302 MCFD.
> We propose to run SBHP survey for this well.
> The information obtained will be used to update bottom hole pressure to calculate P/Z
to estimate RR and to recognize if any liquid loading formed in the wellbore.

Surf. Casing

: 10.75 in - lb/ft, - J-55 - Surf. Csg @994 ft

Int. Casing1
Prod Casing
Liner
Tubing

:
: 7 in - lb/ft, - J-55 - Prod. Csg @1898 ft
: : 3.5 in - BadData - Tubing Set @437 ft

CCL

PE : Dimas Permana = hp : 081214002337; office : 42659


Arif Hilmi W = hp : 085731558779; office 42252
PE : on call = hp : 08117513134

PREPARED BY :
Petroleum Engineer

DMS/ARF/RH/JWID

(on weekdays)
(on weekdays)
(on weekend)

APPROVED BY:
Earth Scientist

Team Manager

KTB