Professional Documents
Culture Documents
TABLE OF CONTENTS
Page No.
LIST OF FIGURES
1.0
PURPOSE
2.0
INTRODUCTION
3.0
TERMINOLOGY
3.1
3.2
3.3
3.4
Safety
Operation
Maintenance
Economics
4
4
4
5
4.0
4.1
4.2
6
6
5.0
5.1
5.2
5.3
O:\WINWORD\3DG\P22\001-00.DOC
8
8
9
Page No.
PAGE 1 OF
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
Reflux Nozzle
Instrument Nozzles
Preferred Component Locations
Miscellaneous Nozzle Considerations
Tray Details
Packed Bed Sections
Platform Details
Optimizing Tower Layout
Reboiler and Pipe Support Considerations
9
9
10
10
11
12
12
13
13
6.0
REFERENCE DRAWINGS
14
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 2 OF
LIST OF FIGURES
Figure 1
Figure 2
Figure 3
Figure 4
Feed Nozzles
Figure 5
Manway Locations
Figure 6
Figure 7
Figure 8
Figure 9
Reflux Nozzle
Figure 10
Instrument Nozzles
Figure 11
Figure 12
Figure 13
Tray Details
Figure 14
Figure 15
Platform Details
Figure 16
Figure 17
Figure 18
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 3 OF
1.0
PURPOSE
To provide a layout designer with the guidelines to develop a comprehensive
fractionation tower design which considers safety, operation, maintenance and
economics.
2.0
INTRODUCTION
The philosophy addressed in this guide primarily deals with trayed fractionation
towers. It is the responsibility of the Plant Design and Piping group to develop
a layout based upon a combination of certain specific rules and logic. The
optimum tower design is achieved through a trial and error approach when not
governed by specific industry codes and regulations. This includes striking a
balance between setting tray orientations, use of internal piping, and proper
grouping of valves and instruments to minimize platforming requirements.
3.0
TERMINOLOGY
3.1
Safety
Design of towers must give proper attention to safety for all plant personnel
who will be required to work within its confines. As one travels from grade to
the upper most platform, the area must be free of dangerous obstructions when
attempting to gain access to values, instruments or exit the tower in an
emergency.
3.2
Operation
Modern technology rarely requires constant attention on trayed towers. When
required, access to valve handwheels and instrumentation should be placed in
such a way that a minimum amount of time is required to perform the function.
3.3
Maintenance
Features to be considered for towers include providing davits at the top of
towers for handling large relief valves, placing manways in a way to facilitate
removal of internals to grade, locating davits or hinges on manway covers in a
way it does not obstruct other required maintenance or access, provide
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 4 OF
Economics
Financial impact of one design over another is one feature that is often
overlooked when engaged in development of a tower layout. Setting the
bottom tangent line at the true minimum elevation; arranging internal and
external piping in such a way that platforming can be minimized and weighing
the cost of increasing the vessel wall thickness to directly support a vertical
reboiler over a support from grade requiring foundations, steel structure, etc.
4.0
4.1
a.
b.
c.
Establish tray orientation based upon review of all governing criteria (see
4.2).
d.
Start layout by working from the top of tower downward (see 5.0).
e.
f.
g.
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 5 OF
The two primary piping circuits which normally impact tray orientation are
the feed nozzle and reboiler connection.
b.
The feed nozzle may have one or a multiple of external connections with
an array of internal piping configurations. See Figure 4. Three typical
feed arrangements are:
(1)
(2)
(3)
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 6 OF
c.
For Bechtel preferred internal piping and tray details see Drawings B501, 502, 503 and 504.
d.
Should the feed nozzle not be a deciding factor, refer to the reboiler
piping requirements in paragraph e.
e.
Since the preferred reboiler piping arrangement is the most direct route,
coming off the bottom tray downcomer now comes into play in setting
tray orientations. A stress engineer should approve the proposed layout
before assuming the selected nozzle location will work for the piping.
Scheme (A) in Figure 2 is an example of an optimum design for the
reboiler inlet line. Scheme (B) shows one of a number of arrangements
for the reboiler return line. Tray orientations are unaffected by draw-off
nozzles located in the bottom head of the tower. These nozzles may be
located at any orientation to suit.
f.
g.
5.0
5.1
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 7 OF
The first order of business is to select the routing of the vapor overhead line.
This line is normally run to a condenser located in an adjacent structure or over
the piperack directly in front of the tower. Consideration for flexibility will most
likely determine what segment of the tower facing the piperack the line will be
located. See Figure 6. The most direct route may apply if no flexibility concern
exists, assuming the line can span the horizontal distance from the tower to the
condenser header. Locating the line along the 0 axis would provide a
moderate "leg" for stress while routing the line away from the condenser would
allow greater flexibility should it be necessary. This issue must be worked with
a stress engineer as the design is developed. The vapor overhead line may
exit the tower in one of two general locations. The most common is shown in
scheme (A) off the top head. A variation of this design would be the elimination
of the flanged nozzle for a butt weld connection for very large O.D. lines. This
would most likely require client approval, but should be considered for
economic reasons. The second approach, scheme (C), utilizes an internal pipe
exiting the top side of the vessel just below the tangent line. This design may
eliminate the need for a top head platform. As with all lines at similar
equipment, the piping will be supported as close to the top tangent or nozzle as
possible. Additional items normally found on vapor overhead lines may
include, temperature connections, inhibitor injections, relief valves and vents.
5.2
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 8 OF
device to clear the highest item to be handled. The lifted load of the heaviest
single component must be identified either from the vessel engineer or relief
valve vendor. The vessel vent should be located in the most convenient place
to accommodate operator maintenance and access on the top head platform.
5.3
5.4
Reflux Nozzle
Figure 9 shows variations of internal piping arrangements for the reflux nozzle.
Scheme A and B are fixed arrangements, while scheme C enables the reflux
nozzle to be oriented at any desired orientation within a 270 arc. This offers
multiple opportunities to develop an optimum layout for the reflux line.
5.5
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 9 OF
5.6
5.7
a.
Plan to run piping down the tower on the side facing the pipe rack, away
from manways, instrumentation, ladders, etc. for small diameter towers of
4'/1.2 or less, lines should be grouped for common support. (See Figure
17).
b.
Locate the manways toward the maintenance access area, away from
the piperack.
c.
d.
Ladders should be located between the main piping area and the
segment of platforming, manways, instruments, etc.
b.
Top head nozzles are set from the platform elevation (top of steel) to the
face of flange. The dimension varies with the nozzle rating.
c.
The maximum distance a nozzle can be set in the top head from the
vessel centerline is shown in detail "A".
d.
Platform penetrations for nozzles and lines are shown in Figure 15.
e.
Liquid outlet nozzle in the bottom head may have minimum dimensional
requirements. If a valve is bolted to the nozzle, a tower drain connection
is likely to be needed. Clearance between nozzles, and the drain nozzle
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 10 OF
10
5.9
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 11 OF
11
Tower platforms should enable plant personnel to work safely during normal
operations and maintenance, without being costly and excessive in size. The
minimum size for top head, crossover or normal operations can be seen in this
figure. Bracket spacing should be standardized whenever possible. Ladder
runs must adhere to certain industry and code regulations as shown in the
elevation view of the tower. No single ladder may not exceed 30'/10.0. Should
a ladder service more than one platform, the platforms must be set at an
elevation that is consistent with the rung spacing of 12"/.300. Dimension "A"
shall be in even increments or rung spacing. Avoid setting two platforms
serviced by one ladder at the same elevation for operator safety. Elevation
difference must be 2'/600 minimum.
Ladder cages are not needed for platforms whose elevation is under 20'/6.10.
Step through ladders are permitted. One rule to remember when designing
any platforming: never force plant personnel to go up a higher elevation, when
attempting emergency egress off a tower.
Platform penetration sizes should be consistent with the specifics of each case.
Clearance should be given to bare pipe, insulated pipe, and flanged
connections as necessary. It is not necessary to allow for clearance of
insulation on flanges, since it is likely the insulation will be removed prior to
removal of the flanged pipe.
5.11 Optimizing Tower Layout - Figure 16
Typical issues a designer must confront include such things as:
a.
A process suggested arrangement for a feed nozzle would put the block
valve away from any planned platforming. By employing one of the
alternate feed nozzle arrangements, the internal pipe can be set at any
desired orientation. This would put the block valve over the desired
platform layout.
b.
c.
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 12 OF
12
6.0
a.
b.
c.
REFERENCE DRAWINGS
The following Bechtel drawings should as reference material when engaged in
the layout of a fractionation tower.
Subject
- Feed and Vapor Overhead Nozzles
- Transition Section
- Bottom Section
- Drawoff Details
O:\WINWORD\3DG\P22\001-00.DOC
Dwg. No.
B-501
B-502
B-503
B-504
PAGE 13 OF
13
- Manway Davits
C-509
- Davit Details
- Circular Checker Plate Platforms
- Circular Grating Platforms
M-507
M-513
M-517
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 14 OF
14
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 15 OF
15
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 16 OF
16
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 17 OF
17
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 18 OF
18
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 19 OF
19
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 20 OF
20
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 21 OF
21
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 22 OF
22
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 23 OF
23
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 24 OF
24
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 25 OF
25
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 26 OF
26
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 27 OF
27
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 28 OF
28
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 29 OF
29
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 30 OF
30
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 31 OF
31
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 32 OF
32
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 33 OF
33
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 34 OF
34
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 35 OF
35
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 36 OF
36
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 37 OF
37
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 38 OF
38
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 39 OF
39
O:\WINWORD\3DG\P22\001-00.DOC
PAGE 40 OF
40